ILLINOIS POLLUTION CONTROL BOARD
March 17, 1971
MARBLEHEAD LIME COMPANY
v.
)
#PCB 70-52
ENVIRONMENTAL PROTECTION AGENCY
Opinion of the Board (by Mr.
Dumelle);
Marblehead Lime Company filed a petition for variance on December 28,
IJ)70 ~vith respect to Kiln No, 6 at its Thornton Plant. It filed a supplemental
petition on January 28, 1971. After a hearing
we
grant the request of the
petition subject to the conditions detailed below.
Kiln No,
6
operates
24 hours a day, seven days a week processing
dolomite (limestone), The end product is lime which is used in the steel
industry as a fluxing agent, and is also used
in
water treatment and other
industrial processes (B. 27—29),
In its petition the company was seeking a variance from the particulate
standards as set forth in the Rules and Regulations Governing the Control of
Air Pollution enacted by this Board~s predecessor, the Air Pollution Control
Board, The variance was requested
only
for Kiln No, 6 and not any
of
the
other three kilns, The variance was requested until March 15, 1971, a
date now passed. The company filed a
~letterof intentH on
July 20, 1967
which indicated that Kiln No, 6 was not
in
compliance and further said that
a firm program (ACERP) for bringing the kiln into compliance would be
filed
by April 15, 1968, In April 1968 the company proposed that the~control
equipment would he installed during 1970. The Technical Secretary of the
Air Pollution Control Board in May of 1968 advised the company that
its
program was
not acceptable because
it was
stretched too far into the
future, After the petitioner explained its proposed timetable,
the program
was
approved. The company
submitted
a progress report in December,
1968,
July
1969,
and September 1969, Very little progress was reported, One reason
for the lack of progress at this point appears to
be
that the company was observing
and evaluating
another producer~s
use
of an electrostatic precipitator. The
installation
on
which the petitioner planned
to make
its decision experienced a
fire
and
thus proved to be unsatisfactory because of the explosion and fire
hazard which it represented (R. 18-20). On January 5, 1970 the company
applied for a permit to install a baghouse. The permit was granted on
April 21, 1970. On December 3, 1970 the company advised the Environmental
Protection Agency that its contemplated completion date of December 31, 1970
could not be met, The letter requested an extension of the compliance date
to March 15, 1971, The instant petition followed.
Although the companyt s program to abate air pollution emissions was
approved by the old Air Pollution Control Board in July of 1968, nothing
tangible was accomplished until *ell into~l970, Such a delay appears to be
unnecessarily excessive and were the petitioner seeking a substantial further
delay and was not at the present acting in good faith, this factor would no
doubt weigh heavily against the grant of such a request. The company did,
however, seek a delay of very short duration and has stated that its installation
was probably 96
complete as of the date of the hearing (R. 41), The baghouse sys-
tem was to be completed by March
15,
1971 and Kiln No, 6 was not to be operated
without a baghouse after that date (R. 42). These facts point to the conclusion
that the pollutional problem
with
Kiln
No,
6 is very nearly solved.
We have been notified by letter, dated
March 15,
1971, that the petitioner
has shut down its operation of Kiln
No,
6, Apparently the baghouse
is cou:pletely
functional and ready to be put on
line
(R.
41-42),
With its baghouse abatement
system the company has stated that they will be controlling their emissions
from Kiln No. 6 with an efficiency
of 99,
9 (R.
42).
If the .kiln
were operating
with no abatement of emissions
it would
be
setting
airborne 2, 000
lbs
per
hour
of lime dust,
With the
use of the
baghouse the company anticipates that the
emissions
will be on the
order
of 2 lbs. per hour (B. 42-43), Before the
installation of the baghouse system
the emissions were estimated to cc 354
lbs. per hour
with the approximate 80 collection efficiency being effected by
a dry cyclone collection system (H.
43),
There
is
evidence
in this
record that
the company sought to interpose
the
non-delivery of the
abatement system both as a defense in a lawsuit
and
as proof
in the instant case of the existence of an arbitrary hardship,
The petitioner here has
met his
burden inasJnuch as
he has demonstrated
that
he
undertook reasonable measures to
insure delivery including the
dispatching of
an
expediter to
various subcontractors to examine the
contractorts work
and schedule (R. 22).
Other petitioners should,
however,
be on notice that
lack
of delivery,
when no efforts are made to effectuate
timely delivery, will not he looked
upon favorably by this Board. It would be
a foolish precedent for
this Board to establish that a variance petitioner
1 — 336
after having done little or nothing to effect delivery may simply transfer the onus
for non-completion of the job to his vendor.
That the company has been acting in good faith in recent months is beyond
question.
This is demonstrated by the program which the company’s chief
engineer,
Mr.
Charles Norton, outlined at our hearing and is demonstrated
from the record of the lawsuit styled People of the State of Illinois cx rel
William J. Scott vs. Marblehead Lime Company, No. 70 CH4443 in the
Circuit Court of Cook County, illinois which was introduced as an exhibit
in the instant hearing. Judge Nathan M. Cohen in fashioning an order at
the conclusion of the hearing in that case specifically found that the company
“is not guilty of any lack of good faith or willfulness in its failure to complete
the system’1.
This opinion constitutes the Board’s findings of fact and conclusions of
law.
ORDER
The Board, having considered the pleadings, transcript and exhibits
in this proceeding hereby grants the petition of Marblehead Lime Company
for a variance subject to the conditions detailed in the order entered by
Judge Nathan Cohen on March 15, 1971 in case No. 70 CH4443 captioned
People of the State of illinois cx rd William J. Scott vs. Marblehead
Lime Company in the Circuit Court of Cook County, Illinois.
I, Regina E. Ryan, Clerk of the illinois Pollution Control Board, certify
that the Board adopted the above opinion and order on~1_/7~f’dayof March, 1971.
I dissent:
Control Board
1
337