ILLINOIS POLLUTION CONTROL BOARD
    March 17, 1971
    MARBLEHEAD LIME COMPANY
    v.
    )
    #PCB 70-52
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion of the Board (by Mr.
    Dumelle);
    Marblehead Lime Company filed a petition for variance on December 28,
    IJ)70 ~vith respect to Kiln No, 6 at its Thornton Plant. It filed a supplemental
    petition on January 28, 1971. After a hearing
    we
    grant the request of the
    petition subject to the conditions detailed below.
    Kiln No,
    6
    operates
    24 hours a day, seven days a week processing
    dolomite (limestone), The end product is lime which is used in the steel
    industry as a fluxing agent, and is also used
    in
    water treatment and other
    industrial processes (B. 27—29),
    In its petition the company was seeking a variance from the particulate
    standards as set forth in the Rules and Regulations Governing the Control of
    Air Pollution enacted by this Board~s predecessor, the Air Pollution Control
    Board, The variance was requested
    only
    for Kiln No, 6 and not any
    of
    the
    other three kilns, The variance was requested until March 15, 1971, a
    date now passed. The company filed a
    ~letterof intentH on
    July 20, 1967
    which indicated that Kiln No, 6 was not
    in
    compliance and further said that
    a firm program (ACERP) for bringing the kiln into compliance would be
    filed
    by April 15, 1968, In April 1968 the company proposed that the~control
    equipment would he installed during 1970. The Technical Secretary of the
    Air Pollution Control Board in May of 1968 advised the company that
    its
    program was
    not acceptable because
    it was
    stretched too far into the
    future, After the petitioner explained its proposed timetable,
    the program
    was
    approved. The company
    submitted
    a progress report in December,
    1968,
    July
    1969,
    and September 1969, Very little progress was reported, One reason
    for the lack of progress at this point appears to
    be
    that the company was observing
    and evaluating
    another producer~s
    use
    of an electrostatic precipitator. The
    installation
    on
    which the petitioner planned
    to make
    its decision experienced a

    fire
    and
    thus proved to be unsatisfactory because of the explosion and fire
    hazard which it represented (R. 18-20). On January 5, 1970 the company
    applied for a permit to install a baghouse. The permit was granted on
    April 21, 1970. On December 3, 1970 the company advised the Environmental
    Protection Agency that its contemplated completion date of December 31, 1970
    could not be met, The letter requested an extension of the compliance date
    to March 15, 1971, The instant petition followed.
    Although the companyt s program to abate air pollution emissions was
    approved by the old Air Pollution Control Board in July of 1968, nothing
    tangible was accomplished until *ell into~l970, Such a delay appears to be
    unnecessarily excessive and were the petitioner seeking a substantial further
    delay and was not at the present acting in good faith, this factor would no
    doubt weigh heavily against the grant of such a request. The company did,
    however, seek a delay of very short duration and has stated that its installation
    was probably 96
    complete as of the date of the hearing (R. 41), The baghouse sys-
    tem was to be completed by March
    15,
    1971 and Kiln No, 6 was not to be operated
    without a baghouse after that date (R. 42). These facts point to the conclusion
    that the pollutional problem
    with
    Kiln
    No,
    6 is very nearly solved.
    We have been notified by letter, dated
    March 15,
    1971, that the petitioner
    has shut down its operation of Kiln
    No,
    6, Apparently the baghouse
    is cou:pletely
    functional and ready to be put on
    line
    (R.
    41-42),
    With its baghouse abatement
    system the company has stated that they will be controlling their emissions
    from Kiln No. 6 with an efficiency
    of 99,
    9 (R.
    42).
    If the .kiln
    were operating
    with no abatement of emissions
    it would
    be
    setting
    airborne 2, 000
    lbs
    per
    hour
    of lime dust,
    With the
    use of the
    baghouse the company anticipates that the
    emissions
    will be on the
    order
    of 2 lbs. per hour (B. 42-43), Before the
    installation of the baghouse system
    the emissions were estimated to cc 354
    lbs. per hour
    with the approximate 80 collection efficiency being effected by
    a dry cyclone collection system (H.
    43),
    There
    is
    evidence
    in this
    record that
    the company sought to interpose
    the
    non-delivery of the
    abatement system both as a defense in a lawsuit
    and
    as proof
    in the instant case of the existence of an arbitrary hardship,
    The petitioner here has
    met his
    burden inasJnuch as
    he has demonstrated
    that
    he
    undertook reasonable measures to
    insure delivery including the
    dispatching of
    an
    expediter to
    various subcontractors to examine the
    contractorts work
    and schedule (R. 22).
    Other petitioners should,
    however,
    be on notice that
    lack
    of delivery,
    when no efforts are made to effectuate
    timely delivery, will not he looked
    upon favorably by this Board. It would be
    a foolish precedent for
    this Board to establish that a variance petitioner
    1 — 336

    after having done little or nothing to effect delivery may simply transfer the onus
    for non-completion of the job to his vendor.
    That the company has been acting in good faith in recent months is beyond
    question.
    This is demonstrated by the program which the company’s chief
    engineer,
    Mr.
    Charles Norton, outlined at our hearing and is demonstrated
    from the record of the lawsuit styled People of the State of Illinois cx rel
    William J. Scott vs. Marblehead Lime Company, No. 70 CH4443 in the
    Circuit Court of Cook County, illinois which was introduced as an exhibit
    in the instant hearing. Judge Nathan M. Cohen in fashioning an order at
    the conclusion of the hearing in that case specifically found that the company
    “is not guilty of any lack of good faith or willfulness in its failure to complete
    the system’1.
    This opinion constitutes the Board’s findings of fact and conclusions of
    law.
    ORDER
    The Board, having considered the pleadings, transcript and exhibits
    in this proceeding hereby grants the petition of Marblehead Lime Company
    for a variance subject to the conditions detailed in the order entered by
    Judge Nathan Cohen on March 15, 1971 in case No. 70 CH4443 captioned
    People of the State of illinois cx rd William J. Scott vs. Marblehead
    Lime Company in the Circuit Court of Cook County, Illinois.
    I, Regina E. Ryan, Clerk of the illinois Pollution Control Board, certify
    that the Board adopted the above opinion and order on~1_/7~f’dayof March, 1971.
    I dissent:
    Control Board
    1
    337

    Back to top