1. the design criteria of SWB-l.

BEFORE
THE
POLLUTION
CONTROL
BOARD
OF THE STATE OF ILLINOIS
March
17,
1971
MALIBU VILLAGE LAND TRUST
#70-45
V.
ENVIRONMENTAL PROTECTION AGENCY
OPINION OF THE BOARD
(BY
MR.
LAWTON):
The Malibu Village Land Trust
(“Malibu”)
owns
a
trailer
park in Carbondale,
Illinois,
Since September
1,
1969,
this park has
contained 120 mobile homes, the sewage from which
is treated by
a
single-cell
lagoon.
A permit to operate this waste stablization
pond was issued to the previous owners in June,
1965 pursuant to
the
Rules
and Regulations Governing
the
Submission
of
Plan
Documents
and the Design
of
Sewage Works
(SWB-l,
continued
in
effect
by
Sec.
49 Cc)
of the Environmental Protection Act),
The design capacity
is
a population equivalent of 330
or
110
trailers computed on
a
square foot basis,
Malibu petitioned
for
a variance
on kecember
14,
1970,
seeking permission
to postpone compliance with the design
capacity requirement
“until
the summer of 1971”,
A varianco henring
was held on Fehruary
16,
1971,
Malibu~s chief
contentions
are as follows
(a)
That
when
it
purchased
the
trailer
park
in
August,
1969,
the
Sellers
represented
the
load
capacity
of
the
treatment
lagoon
to
be
125
trailers,
when,
in
fact,
the
nook
had
not
been
constructed
to
the
125
trailer
capacity
reflected
in
the
design
Zglans~
(b)
That
for
this
Board
to
deny
the
variance
would
impose unreasonable
hardship
on
the
tenants
of
the
park
and
~great
extra
expensed
to
Malibu~
(c)
That
delay
in
compliance
will
bring
no
harm
to
tIie
public
because
no
overflow
from
the
oxidation
pond
occurs.
1
325

Pursuant to the recommendation
of the Environmental
Protec-~
tion Agency, but with
some degree of reservation, we grant
the var-~
iance until July
31,
1971,
The difficulties of immediate compliance together
with
a
bit of undeserved good fortune constitute
the
core of the case
in
Malibu’s
favor,
The evidence is uncontradicted that the discharge from tee
treatment lagoon
(occasional flows of up to
20 gallons per minute,
EPA Recommendation,
p.1.)
is not pollutional.
This could mean
that the population equivalent
for 120 trailers
(360)
does not
live
in the park,
that the sanitary facilities were used less
than
average
during the
times the EPA ran water quality tests
on the effluent,
or that the sewage treatment facility is more effective
than antici~
pated.
In any event,
it
is by chance that no pollution has occurred.
We are impressed,
too,
with the showing of hardshi,
To Jung
the variance could disrupt considerably the Malibu villagers
(P26,
27),
7
to
10 families
of which would have
to relocate.
flse~ given
the already water—soaked earth
in which the construction of
improve~
ments
must
take
place
(P35),
the
spring
rains
might
threaten
the
effective
compaction
of
any
earth
excavated
in
late
winter
(R34)
.
In
light
of
the
apparent
absence
of
pollution,
these
burdens
are
too
great
either
to
deny
the
variance
or
to
reguine
immediate
construction
of
improvements.
These factors alone, not
the likelihood of “great extra ex~-
pense”
to Malibu
if construction of improvements were
‘to begin
this
winter
(P24,25)
(a self—induced hardshio)
cause
this Board
to
grant
the variance,
Could innocent residents
escane
disruption or were
the lagoon effluent pollutional,
our
iecision might well differ,
The Board’s reservation
in granting
this variance arises from
the casual indifference with
which
Malibu
approached
its
legal obli-
gation.
While
the
Seller
may
have
misreoresented
the
actual
sewage
capacity
of
the
lagoon,
it
was
Malibu’s
obligation
to
ascertain
the
facts
before
it
completed
the
purchase
and
assumed operation of the
facility.
Nor
does
it
appear
that
once
the
overloading
eas
known
to
Malibu
that
it
acted
with
the
dispatch
called
for
~v
the
circumstsnc~s.
By
July
31,
1970,
Malibu
knew
the
lagoon~
~
overloaded.
Tee
JPA
informed
Malibu
then
‘EPA
Exhibit
IJo.
1)
that
either
the
number of
house trailers served by
the
lagoon
should
be
decreased
or
the
capecitv
of
the
oxidation
pond
must
be
increased
to
accomodate
120
mobile hones.
At
this
point,
further
delay
could
serve
only
to
coaw~oued
the
error.
Malibu chose
the bureaucratic route.
kather then executing
one
of
the
only
two
options
it
could
legally
purses
(deleting
the
I
326

excess trailers or applying
for
a variance)
,
Malibu wrote to
the
EPA.
Given the Agency’s inexcusable delay
in responding
(2
to
3 months,
P21)
and another 1—1/2
to 2~l/2months
for Malibu to react,
4—1/2
months slipped by
from the time Malibu first learned of its overloaded
lagoon
to the
time of
filing
a
variance
request.
In
the
meantime,
unseasonal weather conditions,
adverse to an immediate undertaking
of the needed corrections,
had
set in.
Other
complications
exist,
inJuced
by
Malibu’s
dalliance,
halibu,
knowing
of
its
violation
after
mid—summer,
1970,
and
apply-
ing
finally
for
a
variance
in
mid-December,
1970,
failed
to
retain
a consulting engineer
until February
4,
1971,
less
than
two weeks
before the variance hearing.
(P43~’45)
In his testimony,
Malibu’s consultant could not
state
with
certainty which
type of sewage treatment system will be installed
(P32~33,4l,43) or when installation can be
completed
(P42,43).
Ar,
Achahon for
the EPA:
Q.
whssuming no
~eather problems once construction
is started,
how long will
it take until the
project
is completed?”
Mr.
kebe
ocn~ulting
engineer:
A.
~I
will
only
answer
this
in
a
qualified
manner,
because
I have
not had
time
to
complete
my en-
gineering studies
nor my engineering plans,
The nuanti ties of work involved are only
a vague
•r.stimate
in
my
own
mind.
I would
anticipate
that
the
mi~Jle
of
July
or
something
of
this
nature
would
be
the
soonest
that
you
could
reasonably
expect to complete
it.”
It
is
these errors of intifference,
the direct products
of
kalibu ‘a retter w~o~Jd:hen fling of
ins environmental obligations, which
rout. t
the koort
to
inpose
a
$150
nenaitu’
as
a
condition
to
granting
the varwhnce.
The
POP.
in nresentinq
its
case,
stressed
heavily the
met
thut the design criterro of nollutional control devices are
es tebiished
For
nub
hr
protection
C~’50
51)
and
must
be
taken
seriously.
A urtizen ‘s creup
the Committee for Ecological Action, Carbondale
trencim
rnvestigated
the lagoon situation and recommended that Malibu
be
“censured for negligence”
(P46-47)
n~l
rh
1
ar~
to r~ose
io, wwhhout
hozorts
to thu enviroument~ carcles~1y nurchase, operate

or enlarge facilities possessing pollution potential when extended
beyond their design capacity.
Those who purchase such facilities
rely on the representations of the seller at their peril.
When
operating a facility with the potential of pollution, one must defermine
for himself what is necessary for compliance.
This responsibility
cannot be shifted.
This opinion constitutes the findings of fact and conclusions
of law by the Board.
ORDER
The Board having considered the transcript an.~sxhibits in
this proceeding, hereby grants the petition of Malibu Villaga Land
Trust to operate with the present load of 120 trailers in violation
of SWB-l
(continued in effect by Sec. 49(c) EPA) until July 31,
1971,
subject to the following terms and conditions:
(1)
By April 15, 1971,
talibu Village Land Trust
shall submit to the ~PA plans and specifications
for
the
above
reç~uired iLprovemen~.
(2)
On
July
31,
1971,
;4aiibu
Village
Lani
..ru3t
shall
have completed constructic’..; of and h:tve in opara-
tion
a
three-’stage
lagoon
or
a
mechai~iica1 aeration
system for treating the sewage of 120 mobile homes.
(3)
No mobile homes shall be added to the pdrk until
Malibu Village Land trust is in compliance with
the design criteria of SWB-l.
(4)
Malibu Village Land Trust shall post with
the
EPA by April 15,
1971, a personal bon.3 or other
security in the amount of $5,000, which
sum
shall be forfeited to the State of Illinois in
the event the sewage treatment facility in rnns-
tion remains loaded beyond design capacity after
July 31, 1971 and Malibu Village Land Trust has
received no extension of this varianca.
(5)
Malibu Village Land Trust shall pay to the State
of Illinois, on or before April
22, 1971,
the
sum
of $100 as a penalty for violation of the statute
and
of the regulation with regard to the design
•capacity of sewage works.
1
—328

(6)
The failure of Malibu Village Land Trust
to ad-
here to any of the conditions
of this order
shall
be grounds
for revocation of the variance,
(7)
Petition for extension of this variance
or modifica-
tion of
this order shall
be filed no later than
May
31,
1971.
I~
£~i1~~L:
Ryan,
certify
that
the
Board
adopted
the
above
opinion
and
ordor
__________
,
1971.
I
329

Back to top