ILLINOIS POLLUTION CONTROL BOARD
August 2, 1971
NATIONAL GYPSUM COMPANY
V.
)
PCB #71—99
ENVIRONMENTAL PROTECTION AGENCY)
Donald Bomberry for National Gypsum Company
Roger C. Ganobcik
for Environmental Protection Agency
Opinion of the Board (by Samuel R. Aldrich):
On May
4, 1971, National Gypsum Company requested a variance
from air pollution regulations for its Waukegan, Illinois plant.
The request was made after the Company failed to comply with the
terms of an Air Contaminant Emission Reduction Program (“ACERP”)
approved by the Air Pollution Control Board in May of 1970. The
program set a completion date of April 15, 1971, for installation
of pollution control equipment. The Company failed to maet that
deadline, The petition asks for additional time in which to re-
duce dust emissions from a gypsum block grinder.
At the hearing, plant manager Donald Bomberry testified that he
misunderstood the terms of the Company~s ACERP, He geared the
installation operation for a completion date of July’ 1, 1971,
rather than April 15 (R. 5). When informed of
his
error he caused
the operation to be accelerated (R. 18). Installation was complete
by June 7, 1971 (Ex. F) and the Agency
states
that the Company is
now in compliance with the law, Therefore, notwithstanding the
Company~s inexcusable delay in achieving compliance, a variance
is no longer necessary. We find the question of whether a variance
should be granted is now moot, Consequently we will dismiss the
petition.
The block grinder in question grinds approximately 3000 pounds of
gypsum block per day used in the manufacture of wallboard (R.ll,37),
In its petition the Company indicated that the grinding process re-
sulted in
the
discharge of gypsum partioles at the rate of approxi-
mately five pounds per hour, This is on the order of 24 times the
rate allowed under the rules (F. 24). However, at the hearing
Donald Bomberry testified that the rate indicated in the petition
was
incorrect. He stated that it should have been five pounds per
~ay (F.
9),
The Environmental Protection
Agency could
neither
confirm nor
deny
the amended estimate since it had recognized the
original figure as being in violation of
the
standards and thus had
not conducted
any
tests at the site (F. 23). At the hearing
Donald Bomberry agreed to provide the Board with whatever documents
were available
concerning
emission rates. None was forthcoming,
however,
2—185
If the figure of five pounds of gypsum particles per day is cor-
rect, no violation of the air pollution regulations has occurred
(F. 23). We have already ruled the question of whether the variance
should be granted is moot. Consequently we need not consider
whether the emissions were in violation of applicable sections of
the Environmental Protection Act.
Apparently the Agency has not monitored emissions either prior to
or following installation of the control equipment. Counsel for
the Agency indicated that
the
equipment had been inspected and
judged capable of bringing emissions within the standard (R. 28).
But persons living near the plant testified that emissions did not
decline noticeably after June 7, 1971, when installation of the
equipment was completed (F. 39). The same persons indicated,
however, that emissions were reduced to zero during the week prior
to the hearing and claimed the plant had not been
operating
during
this interval. This was
denied
by Donald Bomberry who testified
the plant had been in complete operation
(F.
39). Under the
circumstances we must proceed on the assumption that if a problem
persists it will
be
brought to
the attention of the Agency or the
Board
in an appropriate manner.
The petition for
variance is hereby dismissed.
This opinion
constitutes the Board~s findings
of fact and
conclusions
of
law.
I dissent
I, Regina H. Ryan,~lerk of the Pollution Control Board,
hereby certif~rt at the Board adopted the above opinion and
order this
day of August, ~
2— 186