ILLINOIS
    POLLUTION
    CONTROL
    BOARD
    February 17, 1971
    MEDUSA-PORTLAND
    CEMENT
    CO.
    )
    )
    v.
    )
    170—27
    )
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    )
    OPINION
    OF
    TEE
    BOARD
    (BY
    ~1R.
    LAWTON):
    Medusa-Portland Cement Co. filed a petition for variance
    received by the Board on October 23, 1970.
    Waiver of the stat-
    utory provision requiring Board action within 90 days
    (Section
    38, Environmental Protection Act) has been filed.
    After hearing
    held on the petition, we grant a variance subject to the terms
    and conditions hereinafter set forth.
    Medusa-Portland Cement Co. manufactures and sells Portland
    cement at its plant in Dixon, Illinois.
    Portland cement is manu-
    factured by combining limestone, clay, sand and slag in predeter-
    mined proportions, which materials are then crushed and pulverized
    in grinding mills to produce lciln feed” (R-8).
    Approximately
    1900 tons of raw material are processed daily.
    This procedure
    is performed in a rotary kiln where the kiln feed is heated
    to 2800°F., which through chemical and physical changes produce
    cement
    clinker.
    The clinker
    is then pulverized in gr±nding
    mills to make the finished product known as Portland cement.
    Three of the Dixon kilns are preceded by pre-heaters whereby the
    kiln feed is brought into contact with hot gases for efficient
    transfer of heat.
    The kilns are fired with gas from April 15 to
    October 11 and coal between November 11 and April
    15.
    (See Peti-
    tion dated October 15,
    1970).
    The gases leaving the pre-heater
    kiln include the products of combustion of the fuel, carbon dioxide
    released through calcination of the limestone and dust particles
    entrained from the materials in the kilns by the gases passing
    through them.
    The total volume of gases is about 120,000
    SCFZ3.
    The
    particulate
    matter
    carried
    by
    the
    gases
    amounts
    to
    about
    8
    tons
    per hour
    (Pet., 10/15/70).
    The emissions reaching the ambient
    air amount to approximately 3500 pounds per hour, greatly in excess
    of particulate emissions set forth in Rule 3—3.111 of the Rules
    and Regulations governing the control of air pollution remaining
    in force and effect pursuant to Section 49c of the Environmental
    Protection Act.
    (See petitioner’s Exhibit 26, Page 2.)
    The evidence
    indicates
    that
    the
    operation
    emits
    a plume of 100
    opacity,
    500
    yards in length, which diffuses over a distance of up to five miles
    (R—201).
    1-237

    The Medusa plant
    at Dixon has four kilns, of which three
    are Fuller Humboldt pre-heater kilns xeferred to as Nos.
    1,
    2
    and
    3, installed
    in
    1957,
    and one conventional straight kiln,
    No.
    4.
    The pre—heater kilns
    are equipped with
    an electrostatic
    precipitator
    (“ESP”).
    The conventional straight kiln is equipped
    with
    a mechanical cyclone followed by
    a glass fabric dust collec-
    tor and
    is in compliance with the regulations.
    (See testimony of
    Charles Howlett
    (R-48-55) .Supplemental
    statement of Petitioner),
    The variance request is to obtain sufficient
    time
    to install
    specific abatement equipment on the three pre-heater kilns
    to
    achieve compliance with
    the emission regulations,
    in accordance
    with
    the time schedule hereinafter set
    forth.
    A detailed review
    of
    the events leading up to the present petition is necessary.
    On October
    12,
    1967,
    Petitioner filed
    a letter of intent
    with
    the Air Pollution Control Board relating to its entire Dixon
    operation
    noting that the precipitator
    installed in pre-heater kilns
    Nos.
    1,
    2 and
    3 was only
    90
    efficient.
    The letter stated that
    Medusa intended
    “to seek and add any technical improvements
    that
    could be incorporated with our present dust collection systems
    for these pre—heater kilns”.
    The record does not disclose what
    transpired
    during the next
    14
    months,
    On December 27,
    1968, Petitioner was advised by the Technical
    Secretary of the Air Pollution Control Board that the air contaminant
    emissions reduction program
    (Acerp)
    dated October
    12,
    1967,
    could
    not be recommended to the Board for
    ~pprova1
    because
    it specifically
    lacked specification of precisely what Petitioner proposed to do
    to abate pollution and failed to include any timetable to achieve
    compliance,
    On January
    20,
    1969,
    a new proposed air contaminant
    emission reduction program was submitted to the Air Pollution Con-
    trol Board,
    again,
    listing several alternatives that were under
    consideration by Petitioner but containing no specific program for
    compliance,
    This so-called air contaminant emission reduction pro-
    gram was again rejected by the Technical Secretary of the Air Pollu-
    tion Control Board for inadequacy,
    On June
    30,
    1969,
    a public hearing was authorized by the
    Illinois Air Pollution Control Board to consider appropriate action
    because of Petitioner~s failure to submit an adequate air contaminant
    emission reduction program,
    On July
    15,
    1969, Medusa wrote
    to the
    Air Pollution Control Board stating:
    ‘“We have been conducting the
    necessary tests and engineering on the most effective and practical
    method of reducing the emission of dust from our Dixon plant.
    From
    the information presently available on plant data
    and from engineering
    performed by suppliers of dust reduction equipment,
    we plan to reduce
    the emission of dust to an acceptable level in 1971,”
    1—238
    1

    On July
    18,
    1969,
    the Technical Secretary of the Air Pollu-
    tion Control Board answered stating that Petitioner was in violation
    of the Board~sRules and Regulations and advising Petitioner that
    the Board was proceeding with arrangements
    for
    a public hearing,
    but that upon receipt of an acceptable Acerp such hearing would be
    cancelled,
    On August
    6,
    1969,
    a revised dust emission control program
    was submitted
    to the Air Pollution Control Board,
    This proposal
    detailed the existence of the pre-heater kilns,the inadequacies
    of abatement procedures,
    and
    the installation’ of spray towers and
    automatic voltage control regulators
    to achieve partial abatement.
    The new proposal provided for the installation of
    a glass bag-type
    dust collector for kilns Nos,
    1 and
    3 and the continuation of the
    existing electrostatic precipitator for kiln No.
    2,
    coupled with
    the installation of
    a wet scrubber ahead of the ESP.
    These improve-
    ments were scheduled through 1970 and provided
    for completion by
    December of 1971, with field testing and measurement completed
    by March, 1970
    (Environmental Protection Agency Exhibit
    1).
    This
    Acerp was approved by the old Air Pollution Control Board on
    August
    28,
    1969,
    Progress reports on the status
    of the installation
    were required.
    The first progress report was submitted on July
    19,
    1970,
    indicating
    that engineering drawings had been received
    for the
    proposed installation
    and that negotiations were being conducted
    with Northern Illinois Gas Company for conversion to gas firing of
    kilns
    1,
    2 and
    3,
    during
    the period of April 15
    through’ November
    11,
    On July
    1,
    1970,
    the new Environmental Protection Act went
    into
    effect,
    On August
    3,
    1970, Petitioner wrote to
    the Director of the
    newly—created Environmental Protection Agency submitting
    a further
    status report indicating its expectation that the installation
    of the necessary emission abatement equipment would be completed
    by the dates originally proposed,
    On September
    17,
    1970,
    Petitioner
    wrote
    to the Environmental Protection Agency proposing
    a modifica-
    tion of its Acerp by the installation of
    a Dracco glass bag dust
    filter to supplement
    the existing electrostatic precipitator for
    all three pre-heater kilns.
    The new arrangement would be 99.7
    efficient,
    This program modified the earlier Acerp which had
    provided
    for the existing
    ESP to remain
    in conjunction with kiln
    No,
    2 alone and the new bag house to be installed on kilns
    1 and
    3
    only.
    The new plan called for one large bag house collector serving
    all three kilns with the retention of the ESP, producing
    a greater
    efficiency
    in removal of particulate matter; ,the coarse particles
    would be removed by
    the ESP
    and the super-fines removed by
    the bag
    house
    (See Petitioner~sExhibit
    28, Supplemental
    Statement of Medusa-
    Portland Cement’ Co.,
    Page
    6,)
    The modified plan would cost approx-
    imately $800,000.00 installed, being $200,000.00 more than the original
    Acerp proposed.

    On September
    30,
    1970,
    Petitioner was advised by the En-
    vironmental Protection Agency that the modification constituted
    a request
    for variance and that a new petition should be filed
    consistent with the Act,
    and Regulations of the Pollution Control
    Board.
    The Agency correctly interpreted the former Air Pollution
    Control Act and the present Act, both of which limit variances to
    a one—year period.
    Since an Acerp is
    a variance,
    one granted in
    August of
    1969, had expired prior to the September
    17,
    1970
    communication, which can only be construed as
    a new request for
    variance.
    (See Environmental Protection Agency
    v. Commonwealth
    Edison Co.,
    #70-4, decided thisday.)
    On October 15,
    1970, Petitioner sent
    a letter to the Environ-
    mental Protection Agency requesting
    “an extension of variance’
    granted by the Board
    on August
    28,
    1969.
    The letter contained
    a
    description of the operation of the pre-heater kilns,
    the daily
    processing of 1,907
    tons
    of raw material and
    a description
    of the
    existing equipment.
    The letter again proposed modification of
    the original Acerp by providing for the installation of
    a glass
    cloth bag-type filter
    to control all emissions from the three pre-
    heater kilns.
    The letter indicated that equipment orders had been
    placed,
    including an order with
    the Fuller Company for the bag house,
    in the amount of $246,000.00.
    The schedule provided for installation
    of all equipment and ducting with the ESP by December
    of 1971, which
    timing was consistent with that provided in the original Acerp,
    as
    approved.
    An additional period to March of 1972 was requested
    for field testing of the entire dust collection
    system.
    On October
    30, 1970,
    a letter supplementing the October 15,
    1970 letter was
    sent to the Agency stating that insistence on immediate
    compliance with the emission regulations would necessitate reducing
    the operation of the plant by two-thirds, resulting in the
    loss of
    2.2 million barrels of cement production
    and sales
    in the amount of
    $7,700,000,
    the income from which would be necessary to pay for
    the
    installation
    of proposed pollution abatement equipment.
    It was esti-
    mated that
    in excess of 180 employees would be unemployed and the
    loss
    to the community of Dixon and the State would be
    in excess
    of’
    several million dollars.
    Petitioner stated that the loss
    of such
    cement production would have
    a detrimental effect on the construction
    industry in the
    state,
    Pursuant
    to the Act,
    the Environmental Protection Agency
    filed its recommendation,
    urging that the petition be denied on
    the grounds that Petitioner could operate
    its plant at
    a “substan-
    tial production rate”
    in compliance with the Act,
    that Petitioner has
    engaged
    in
    a dilatory campaign and “is
    no closer
    to compliance today
    than it was
    in 1967”.
    The Agency contends that the evidence fails
    1
    240

    to show that Petitioner’s
    time schedule is the most expeditious
    possible and that there
    is substantial
    injury to the public as
    a
    result of Petitioner’s operation.
    The Agency’s investigation
    notes
    a substantial number of letters from citizens in the community,
    complaining of Petitioner’s
    emissions and indicating opposition
    to
    granting of
    the variance extension.
    However, persons contacted by the Agency in the area indi-
    cated their willingness
    to have the plant remain in operation
    until brought into compliance.
    The report noted that approximately
    750 people depend on Hedusa-Portland Cement Co.
    for their support.
    Hearing was held on the variance petit:~cnin the City Hall,
    Dixon,
    Illinois,
    on December
    1—,
    1970.
    The Board
    is asked to approve
    a program initiated
    in 1967
    which,
    according
    to the Petitioner, will
    not be completed until
    March of 1972,
    While the fault for this delay is principally that
    of
    the Petitioner,
    it must be shared by the old Air Pollution Control
    Board and
    its staff, which did not communicate a sense of urgency
    to Petitioner or take appropriate action to obtain and implement
    a definitive program.
    However, after inordinate procrastination,
    sparring and negotiation, Petitioner did submit an Acerp which
    was approved by the old Air Pollution Control Board.
    It now
    seeks to implement
    this program and the
    time schedule incorporated
    in
    it.
    This request we must
    now consider, not as an original
    proceeding, but within the framework of
    the events having already
    taken place
    and particularly,
    the steps taken by Petitioner in
    furtherance of
    its approved prog~m.
    Petitioner
    is seeking to adhere
    to
    the
    time schedule originally
    ~
    red, but to install facilities
    that will have improved capabiJ
    ~f pollution abatement beyond
    those originall contemplated,
    The evidence adduced at the hearing substantiated the character
    of Petitioner’s
    operation as above
    set forth, the ineffectiveness of
    the existing abatement facilities to adequately control the pre-
    heater kilns emission and the desire to pursue
    the pollutional abatement
    program as modified.
    The plant
    is
    located in
    a sparsely populated
    area east
    of Dixon,
    Evidence
    in the record details the magnitude
    of the emissions from Petitioner’s operation but the record is meager
    on the degree of impact produced by the emissions on the residential
    properties.
    The prevailing wind direction appears to be away from the
    populated area.
    The record contains some evidence as to the toxic
    effect of cement ~dust, both
    pro and con.
    (See testimony of Prince,
    R-205),
    (MPC Ex.
    27A-1).
    However, we find the evidence intro-
    duced by both parties on the subject of toxicity inconclusive and
    unpersuasive.
    At the hearing,
    the Agency reiterated its recommendation
    that the variance be denied, but that if it be allowed that
    it be only
    for
    a six-month’ periodS
    A representative
    of the Attorney General stated
    that his office concurred with the recommendation of the Environmental

    Protection Agency
    (R-32),
    While it is inexcusable for
    the company to have taken
    almost five years to reach its present proposal,
    the Board must
    consider the variance program in light of
    the current factual
    situation and determine whether Petitioner’s proposed program,
    or
    some modification thereof,
    is compatible with
    the statutory requisites
    for the allowance of
    a variance.
    The evidence supports
    the prin-
    cipal allegations of the variance request insofar as it details the
    nature of Petitioner’s operation,
    the inadequacies
    of the present
    abatement equipment,
    the proposed program for installation of
    a
    suitable bag house facility, and the time schedule calling for
    complete installation by the end of December,
    1971.
    The inability
    to operate
    in excess of 30
    capacity in event of
    a shut-down of the
    offending kilns is supported by
    the record
    (R-87~and
    177.)
    Furthermore,
    the desirability of the modification
    set forth in the September
    17,
    1970 letter
    is adequately demonstrated
    (R-59)
    Evidence introduced by the Petitioner included the purchase
    contracts, orders of
    the abatement equipment
    (Ex.
    1
    through
    23
    ),
    and the authorization by Petitioner’s
    corporate directors
    to spend $800,000,00 for
    the acquisition and installation of the
    equipment at the Dixon location.
    At the request of the Hearing
    Officer,
    a supplemental statement was submitted restating Petitioner’s
    intention to adhere to the time schedule proposed,
    describing the
    glass fabric dust filter to be obtained from the Fuller Company
    at
    a cost of $250,000.00
    and itemizing the additional purchase
    orders already issued exceeding $400,000,00.
    A photograph was
    included showing concrete footings already poured to accomodate
    the installation.
    Requests
    for bids
    on mechanical
    ahd structural
    erection will issue currently.
    The time schedule for specific
    erection of
    the equipment on the site provides
    for installation
    beginning in April,
    1971,
    and completion by October
    31,
    1971,
    with
    tie-in of the newly-erected equipment
    to ‘the existing kiln system
    and the present ESP completed by December 31,
    1971,
    The break-in
    and testing period will,
    according to Petitioner,
    require an addi-
    tional three months after final installation,
    William F,
    Troutman
    (R-148), Director of Corporate Development,
    stated that $800,000.00 had been allocated for this project,
    He
    asserted that elimination of production from kilns
    Nos,
    1,
    2 and
    3
    would reduce production to 30
    of capacity and result in operation
    costs double the revenue from such production.
    The alleged hard~hip
    included not only the asserted loss of revenue to the company, but
    the resulting unemployment of personnel,
    the inability to furnish
    needed concrete to customers and the significant impact on the economy
    of the immediate community and the State,
    This witness suggested
    that even partial cessation of operation would enable competitors
    ‘to move
    in on Petitioner’s market with the likelihood that such
    I
    242

    event would result in an ultimate shut—down of Petitioner’s entire
    Dixon operation
    (R-l57).
    One disturbing feature of this case does not appear in the
    record but must be noted.
    The recommendation of the Environmental
    Protection Agency states that the Agency had received numerous
    complaints concerning the impact of Petitioner’s
    operation on the
    community.
    Both the Agency and this Board have received communica-
    tions commenting on the unpleasant attributes
    of Petitioner’s par-
    ~iculate
    emissions.
    The hearing was publicized through the Board
    Newsletter and public newspaper notice,
    and received wide coverage
    in the local press,
    In excess of 100 people attended
    the Hearing.
    However,
    not
    a single person appeared to express opposition to the
    proposed variance
    or informed, the Board with regard to the impact,
    if any, produced by Medusa’s particulate emissions on personnel
    or residential areas.
    A representative of the local radio
    station,
    the president of the local bank and employees of the
    company all appeared
    in support of the proposed variance,
    A sugges-
    tion was made by one witness that
    the action of the Agency and the
    Board in seeking to bring Petitioner into compliance with the
    relevant statutory and regulatory provisions was “harassment”.
    (R—l32),
    While the Board does not draw any implications
    from the foregoing
    circumstances,
    it should be noted that the time and place to voice
    one’s concern in the matter of
    a specific operation should be at
    the Hearing,
    it
    is only through this procedure that the Board can
    be informed of the true factual situation
    in terms of the impact
    of the facility upon the community.
    The Board’s decision, however,
    can only be based on what
    is
    disclosed
    in the record,
    Failure to adequately inform the Board
    not only makes difficult the arrival at
    a
    just decision but con-
    stitutes
    a disservice
    to the community itself,
    Citizen concern and
    interest
    is meaningless
    if not communicated to the Agencies mandated
    to protect the public interest,
    It is the decision of the Board that while Applicant has been
    extremely dilatory in proposing and implementing a valid abatement
    program,
    it has,
    at last,
    embarked upon
    a schedule that will bring
    the Dixon operation into compliance with the
    law.
    The projected
    time schedule,
    in consideration of the present circumstances,
    is
    not unreasonable,
    The evidence indicates that shutting down the
    operation to the extent of 70
    would impose upon the applicant,
    the
    community,
    its employees,
    and the local economy hardships dispro-
    portionate with the benefit achieved by
    suc’h shut-down.
    This case
    differs from Marquette Cement Co. v.
    Environmental Protection Agency,
    #70-23
    (decided January
    6,
    1971)
    in which we imposed a $10,000 penalty
    as
    a condition
    of
    a variance,
    in that here,
    the delay in commencing
    a control program was essentially forgiven when the Air Pollution
    Control Board approved Medusa’s Acerp.
    We have
    not been asked to
    I
    243

    grant additional
    time beyond that allowed by the old Board.
    The Board has considered the character and degree of injury
    to the public health and general welfare of people in the immediate
    area
    and the social and economic value of the pollution source,
    It believes the proposed installation and abatement schedule
    to be practical and economically reasonable
    in eliminating the
    pollution
    source.
    While this proceeding
    is by way of variance
    and not an enforcement action,
    the foregoing
    facts must be cOnsidered
    in arriving at our decision.
    Failure to grant the variation would
    enable such enforcement action
    to be instituted where the fore-
    going matters would be the subject
    of consideration,
    This opinion
    constitutes the finding of fact
    and conclusions of
    law by the Board.
    ORDER
    The Board having considered the transcript and exhibits
    in this proceeding, hereby grants the petition of Medusa-Portland
    Cement Co.
    for
    a variance subject to the following terms
    and condi-
    tions:
    1.
    Medusa-Portland Cement Co. shall be allowed
    to operate
    its pre-heater kilns Nos.
    1,
    2 and
    3, thereby producing particulate
    emissions
    in excess of the relevant particulate emission limitations
    set forth in the Regulations of the Air Pollution Control Board for
    a period ending December
    31,
    1971.
    2.
    On December
    31,
    1971, Medusa-Portland Cement Co,
    shall
    have completely installed the new glass fabric dust collector
    in
    conjunction with the existing electrostatic precipitator
    so as
    to bring its operation into compliance with the relevant particulate
    emission regulations.
    Medusa-Portland Cement Co.
    shall adhere
    to the schedule
    of installation as set forth in its letters to the
    Environmental Protection Agency of October
    15,
    1970
    and October
    30,
    1970,
    as implemented by supplemental
    statement of Medusa-Portland
    Cement Co.
    filed herein,
    and shall file with the Agency and this
    Board reports, every two months, of
    its progress reflecting the
    status of all equipment ordered and received and the installation’
    of all facilities on the premises.
    3,
    Medusa-Portland Cement Co,
    shall post with the Environmen-
    tal Protection Agency,
    on or before March
    15,
    1971,
    in such form
    as the Agency may find satisfactory,
    a personal bond or other adequate
    security, in the amount of $100,000.00, which
    sum shall be forfeited
    to the State of Illinois
    in the event that the plant in question is
    operated after January
    1,
    1972 without
    an ewtension of this variance
    and without control equipment sufficient
    to reduce emissions
    to
    those permitted by the Regulations.

    4.
    Emissions
    shall not be increased
    above the levels
    disclosed in the form submitted by Medusa-Portland Cement Co.
    in connection with its
    let-ter of intent
    (Environmental Protection
    -
    Agency, Exhibit
    1)
    during the period of this variance.
    5,
    The failure of the company to adhere to any of the condi-
    tions of
    this order
    shall be grounds for revocation of the variance.
    6,
    Petition for variance or modification of
    this Order
    shall be filed no later than November
    1,
    1971,
    I, Regina
    E
    Ryan, certify that the Board adopted the above opinion
    and ~
    ,
    1971.
    f_fl
    ~
    ~
    //~
    I Concur
    I DissenL

    Back to top