ILLINOIS POLLUTION CONTROL BOARD
    February
    17,
    1971
    ENVIRONMENTAL PROTECTION AGENCY
    v.
    )
    #PCB
    70-8
    VILLAGE OF GLENDALE HEIGHTS
    Opinion of the Board
    (by Mr.
    Kissel):
    The Environmental Protection Agency filed its complaint against
    the Village of Glendale Heights
    on September
    16,
    1970,
    alleging that
    the Village sewage treatment plant was polluting the East branch of
    the DuPage River by the discharge
    of raw sewage,
    The complaint
    charged violations
    of the Sanitary Water Board Act, Section
    12
    of
    the Environmental Protection Act,
    and Regulation SWB-14 of the
    Illinois Sanitary Water Board and asked for the entry of
    a cease and
    desist order, and
    a $10,000
    fine plus
    $1000
    for each
    day such violation
    shall be shown
    to have continued,
    On the date of the hearing,
    the
    Agency moved
    to amend its complaint by dropping its request for
    penalties.
    This amendment,
    the Agency noted, was based on two
    circumstances:
    one,
    the Village’s confession
    of liability;
    two,
    the Agency’s belief
    that the principal issue
    in the
    case concerned
    the improvement of
    the Village’s sewage treatment works,
    The Agency directed its presentation in this case to the
    nature, design,
    and capacity of
    the proposed addition to the sewage
    treatment plant.
    The Village had received
    a permit to construct the
    plant on February
    27,
    1970.
    Carl
    T.
    Blomqren, environmental
    control
    engineer with
    the Environmental Protection Agency,
    described the
    proposed addition as follows:
    It
    is proposed to be
    a factory-built type of lift station,
    three pumps.
    Each one
    .
    .
    .
    has
    a 2100—gallon—per—minute
    capacity, which would give the lift station
    a capacity of about
    6,000,000 gallons with
    the largest unit out of service,
    in
    accordance with
    our rules.
    The flow
    is then pumped from the new lift station to
    each of the three package-type sewage treatment plants in
    parallel.
    These plants all ooerate in parallel.
    The flow would
    be split.
    Each
    package planti
    is
    an individual sewage treatment
    plant.
    It is the activated sludge process with an anaerobic
    digester
    as part of the unit of each plant
    .
    .
    .
    The effluent
    from the three plants then passes through the tertiary filters
    to an effluent disinfection before discharge to the ditch
    tributary to the East Branch of the DuPage River.
    (R. A18)*
    *The page references from the transcript from the Oct.
    15 hearing will
    be prefixed by an A;
    those from the Dec.2 hearino,
    by
    a
    B,
    1 —217

    The Agency permit issued for a plant
    in Glendale Heights capable
    of handling 3,000,000 gallons-mer-day with
    a discharge
    of 4,800 pounds
    of BOD
    (biochemical oxygen demand)
    per day.
    (R. A20)
    In order
    to
    meet the water quality standards for the receiving stream of
    4 mg/l
    of BOD
    and
    5 mg/l of suspended solids,
    the plant was designed to
    achieve an effluent of 3,2 mg/l of BOD and
    2 mg/l of suspended solids,
    (R. A20—l)
    Just released U.S.
    census figures showed Glendale Heights
    population in the vicinity of 18,000; based on population growth for
    the reasonably foreseeable
    future,
    the Agency projected
    a service
    area of 24,000 people.
    (R.
    A2l)
    At the rate
    of
    125 gallons per day
    per person,
    the Agency concluded that
    a
    3 mgd plant would be necessary.
    Blomgren indicated that
    a new plant is needed on the basis of
    (I)
    copulation growth,
    and
    (2)
    a wet weather peak load which has reached
    1.9 mgd.
    (R.
    A23)
    The third unit, he pointed out,
    is
    also necessary
    as
    a reserve unit,
    to be used when one of the other units is down for
    cleaning purposes.
    (R.
    A24)
    While
    the Village officials recognized
    a desnerate need for the
    expanded sewage treatment facility,
    its citizens
    did not.
    The voters
    defeated
    a referendum on May
    23,
    1970, which left the Village in the
    position of having inadequate treatment of its wastes
    today,
    and for
    sometime
    in the future.
    The Village sought
    a directive
    from this
    Board which would have given the Village the right to issue bonds in
    any amount permitted by
    the Environmental Protection Act in order
    to
    construct the
    new treatment facilities,
    After
    the original hearing,
    the Board considered
    the matter
    and ordered the Hearing Officer
    to reconvene the hearing
    to consider
    the followinq matters:
    (I)
    Whether the location of the proposed addition to the
    sewage treatment plant entails use of
    a flood plain;
    and,
    if
    so,
    if such location
    is detrimental;
    (2)
    The storm water infiltration of the sewer system;
    (3)
    The basis
    for the Agency’s dismissal
    of
    its request for
    money penalties;
    (4)
    Whether further connections
    to the sewer system should be
    allowed in
    the period between the entry of the Board’s order
    and the completion of the proposed addition to the sewage
    treatment plant;
    (5)
    How the orooosed Glendale Heights addition would conform
    with
    a regionalization of sewage treatment
    facilities
    in
    DuPage County.

    We will consider each of those matters:
    1)
    Money penalties
    -
    The Agency admitted that the money penalty
    request was dropped in consideraiton
    for the Village’s admission that
    it was
    in fact polluting
    the waters of the State of Illinois in
    violation of the Environmental Protection Act, Section
    12(a),
    We find
    that the compromise
    is
    a valid one for this
    case.
    It would indeed
    be shortsighted
    to require an already hard-pressed village
    to pay
    a
    money penalty
    to the
    State.
    The money
    is better used by
    the Village
    itself.
    In addition,
    the Village has demonstrated
    its good faith in
    submitti~ig to the voters bond issues for
    the improvement of the waste
    treatment plant not only once, but a second
    time after
    the first time it
    had
    failed.
    This good faith, along with
    the Village’s need
    for money
    and
    its admission of
    liability, is adequate basis for affirming the
    Agency’s decision to drop from the complaint the request for money
    penalties
    to be assessed against the Village,
    2)
    Storm water infiltration
    -
    While
    the letter of James Campion,
    an interested citizen, expressed some concern that the treatment
    facility would be overtaxed because of ‘~Leaky sewers”,
    the concern
    seems,
    from the evidence,
    to be overstated,
    The Village adequately
    demonstrated that by the use of television,
    smoke testing and visual
    inspection
    it has the problem under control for the moment.
    3)
    Location of the proposed plant
    in a flood plain
    -
    The inter-
    ested citizen, James Campion,
    testified that
    the sewage treatment
    plant lies below all of the construction within the Village.
    (R.
    B14)
    Campion stated that the
    1961 ditch flooding put the edges
    of the
    flooding at the doorstep to
    the sewage treatment plant and that the
    1954 flood reached 400
    feet from the proposed plant site.
    CR.
    Bl6,
    17)
    Campion stressed
    that additional development and resurfacing of land
    upstream and downstream since
    the flooding and
    in the future enhance
    the possibility of flooding on the oroposed exnansion site.
    (R.
    Bl7)
    The Village’s testimony showed that,
    though the proposed
    location
    is at
    a low point
    in the Village,
    it
    is not on
    a flood
    plain.
    The geological map offered into evidence showed that those
    areas which
    the map outlines within
    a shaded blue area are on a flood
    plain;
    the elevation of the new plant will be
    as high
    or higher than
    the present flood plain.
    CR.
    B46)
    Thus,
    as stated,
    the proposed site
    is outside of the flooded areas shown on the exhibit.
    Further, the
    plant would be raised about
    8 feet above, the present flood plain
    indicated in the USGS map.
    The elevation of the construction will
    be 708
    feet above sea level
    and the flood plain
    appears
    to be just
    under
    700
    feet.
    CR,
    B68)
    4)
    Regionalization
    -
    The Village has cooperated fully with other
    local officials in seeking some manner of county—wide sewage treatment
    plan.
    In the feasibility studies that have been undertaken by
    the
    County and its engineering consulting firms, both
    the 1962 and 1969
    reports contemplate additional facilities
    at the Glendale Heights
    1
    —~
    219

    treatment plant site--there
    to serve
    a larger area than that presently
    served,
    CR.
    B55,
    57)
    In other words, both renorts indicate that
    the county
    is proposing
    a regional facility be located adjacent to
    the present Village facility.
    CR.
    B59)
    The present county-wide plan
    calls
    for
    a larger treatment plant
    to be built at Glen Ellyn at some
    future date, with
    the Glendale Heiehts facility
    then being phased out.
    CR.
    B61)
    As the Village Engineer then explained,
    the Glendale Heights
    facility
    is
    to be used
    as
    an interim facility
    in the approximate
    10-
    year period before the county-wide plan is fully imolemented.
    CR.
    B62)
    The Agency,
    in its corroborative testimony,
    also stated that
    it con-
    sidered the regionalization of facilities
    in DuPaqe County when it
    originally approved the permit
    for the Glendale Heights facility.
    CR.
    B80)
    Thus,
    the present facility
    is compatible with any future
    plan
    for regionalization in DuPaqe County.
    5)
    Further connections
    to the sewer system
    -
    Admittedly,
    it will
    be some
    time before the expanded treatment plant of
    the Village will
    be in full operation,
    Before that happens
    the Village will not be
    able
    to handle
    the wastes of
    the citizens presently connected
    to
    the sewer system;
    therefore,
    it would follow that
    the Village should
    not be allowed to add any other connections
    to this system until it
    has adequately demonstrated
    that it has
    the capacity to handle such
    wastes.
    The Village was agreeable
    to that kind of condition being
    imnosed on it, but the Village seemed to make
    some kind of distinction
    between the new vs.
    old.
    lines,
    This Board will require that the
    Village disallow
    any additional connections
    to
    its sewer system and
    this Board will not,
    at this
    time, make any distinctions of the kind
    made in the record,
    Subsequent
    to the hearinq,
    the electorate of
    the Village approved
    a bond
    issue
    for the sewage treatment plant exoansion,
    That decision
    by the voters,
    although
    a welcome one,
    does not make this case moot.
    As the Village attorney has
    stated,
    the Village may need more
    funds
    because of the increasing costs of construction.
    There
    is no question
    in this case about pollution,
    The Villace admits that it
    is polluting
    the waters of this state.
    This Board must do everything within
    its
    power to abate
    that pollution and in this case
    it means that we must
    invoke Section
    46
    of the Environmental Protection Act.
    This section
    gives
    the Board the power,
    inter alia,
    to order
    a municipality or
    sanitary district to issue general obligation or revenue bonds
    for
    the purpose of raisinq money to abate
    the pollution.
    There need be
    no election or referendum for the issuance of the aforementioned bonds,
    We believe that the instant case
    is
    an appropriate one
    for the invoca-
    tion of Section 46.
    Although no amount need be soecified in the order
    at this
    time,
    the Board expects that
    a sufficient amount of bonds will
    be issued so that within the very near future the pollution will be
    abated.
    Specific attention
    is directed
    to
    the provision of Section
    46 which
    allows
    the bonds
    to be issued
    in such amounts
    as “would not
    raise the total outstanding bonded indebtedness of
    such municipality
    in excess
    of the limit imposed unon such indebtedness by
    the
    Constitution of the State of Illinois
    .
    .
    .
    ,“
    Since the new
    Constitution does
    nct. Impose any limit on the bonded indebtedness
    of municipalities o~. sanitary districts,
    it may be that the Board can
    require bonds
    to be .L~suedup to any amount.
    We need not decide that
    I
    220

    question
    here,
    but
    the
    Village
    should
    be
    guided
    by
    the
    direction
    that
    the
    Board
    will
    use
    all
    available
    legal
    means
    to
    end
    pollution
    of
    the
    waters
    of
    this
    State.
    The
    following
    order
    is
    hereby
    entered:
    (1)
    The
    Village
    of
    Glendale
    Heights
    is
    hereby
    ordered
    to
    cease
    and
    desist
    from
    pollutinq
    the
    waters
    of
    the
    east
    branch
    of
    the
    DuPage
    River
    to
    the
    extent
    reasonably
    possible
    until
    the
    construction
    of
    additional
    facilities,
    as
    required
    below;
    (2)
    The
    Village
    of
    Glendale
    Heights
    is hereby ordered
    to
    construct such additions to itsoresent waste treatment facilities
    as would bring the Village
    in compliance with
    all anolicable
    laws,
    rules
    and regulations governing the operation and maintenance of
    sewage
    treatment
    facilities;
    (3)
    The
    Village
    of
    Glendale
    Heights
    is
    ordered
    under
    Section
    46
    of
    the
    Environmental
    Protection
    Act to issue general obligation
    or revenue bonds
    in the amounts necessary
    to comnlete
    its prooosed
    sewage
    treatment
    plant
    expansion
    pursuant
    to
    permit
    No.
    l970-AB-98
    of the Environmental Protection Agency and to thereby abate its
    pollution of the east branch of the DuPage River,
    (4)
    No additional sewer connections
    to existino
    lines shall
    be
    made or new sewer
    lines
    connected
    until the pronosed addition
    to the sewage treatment plant is comoleted and certified
    as capable
    of operating within the Rules
    and Regulations
    of the Illinois
    Pollution Control Board.
    This order anplies
    to any sgwer connections
    or
    sewer
    lines which will
    feed
    into the Glendale Heights
    olant,
    whether or not such connections
    are within
    the coroorate limits
    of
    the Village of Glendale Heights.
    This moratorium is
    effective
    whether or not the Village of Glendale Heights chooses
    to avail itself
    of the funding procedures
    of Section
    46,
    C5)
    Within thirty days after the entry of
    this order,
    the Village
    of Glendale Heights shall confer with
    the Environmental Protection
    Agency and adopt
    a cormliance schedule
    for the comoletion of the sewage
    treatment facility.
    The compliance schedule agreed unon by the parties
    shall be submitted
    to
    the Board and,
    if no objection
    is made, shall
    be incorporated
    as part of the Board’s order.
    Thereafter,
    the Village
    of Glendale Heights shall furnish the Agency quarterly orogress reports
    as construction proceeds.
    I, Regina
    H.
    Ryan, Clerk
    of the Pollution Control Board,
    certify that the Board adopted the above opinion and order
    this
    17th
    day of
    F brua~y
    ,
    l97l~
    .
    .
    ..
    Regina
    E.
    Fyhn
    /
    Clerk of the Board

    Back to top