ILLINOIS POLLUTION CONTEOL BOARD
    July
    6,
    1971
    SPRAYING SYSTEMS,
    INC.
    V.
    )
    ~
    71~72
    ENVIRONMENTAL PROTECTION AGENCY
    PULTE
    LAND
    CORP.
    V.
    ~+
    71—7~
    ENVIRONMENTAL
    P ROTECTI ON
    AGENCY
    Opinion
    and
    Order
    of
    the
    Board
    (~y Mr.
    Currie)
    On
    February
    17,
    l~7l
    we
    entered
    an
    order
    in
    Environrnenta~
    Protection
    Agency
    v.
    Village ef
    °lenC~1~
    TTcithts,
    f
    70~R,
    findine
    the
    village
    was
    d.ischargi.ag
    inadc,Gnatelv
    trented
    sewage
    fren
    an
    overloaded
    plant
    and
    ordering
    the
    construction
    of
    facilities,
    which
    the
    village
    had
    airea~p
    begun,
    to
    ron’dr
    the~situation.
    One
    paragrach
    of
    our
    order
    banned
    additional
    rower
    connections
    tributary
    to
    the
    plant
    unti
    I.
    tho
    violation
    war
    corrected,
    on
    the
    ground
    that
    to
    permit
    then.
    wonl.d
    r~ounR the
    problem
    and
    in-
    crease
    pollution.
    The
    present
    pet.itions
    nook
    earl
    ances
    from
    that
    order
    to
    permit
    new
    cortnocti.onn
    be5ore
    cnm~-lnt.i
    on
    o~
    the
    new
    facilities
    Ye
    deny
    therr~
    Glend.ale fbi
    ght.s
    has
    a
    one—mi I lion—gal
    br
    —per—day
    (~‘
    2~
    25)
    secondary
    plant
    who~c
    effluent
    ~ft
    on.
    ernoeds
    the
    rtand~rd~
    for
    secondary
    treatment
    (P.
    12)
    hecans~
    it
    in.
    ~requontlv
    over—
    loaded.
    Rules
    arid
    Regulations
    P~’R~l4teouire
    a
    further
    stage
    of
    treatment
    for
    snail
    receiving
    streans
    such
    an
    this
    one,
    the
    East
    Branch
    of
    the
    DuPage
    Piver,
    The
    ~i
    11
    non
    is
    well
    on
    the
    way
    toward
    completion
    of its project,
    The tertIary cibters
    and
    chlorination
    facilities
    are
    expected
    to hc comeleted by
    July
    14,
    1971
    (R,
    46,
    40)
    so
    that
    dry—weather
    fbow~
    (which
    average
    about
    750,000
    to
    300,000 gpd
    (P.
    92))
    will by then he
    properly
    treated.
    The
    twin parallel primary
    and se~undary faeilities,
    which will give
    the system
    art additional
    2 ogd
    of car’acitv,
    are
    expected
    to be finished
    and
    in
    full operation
    by
    August
    1P
    (R.
    44,
    46,
    52).
    2
    73

    Thus if the petitioners have to wait
    to connect their new
    waste outlets
    to the village sewers they will
    not have to wait
    long~
    And indeed
    in the case of Spraying Systems there is no
    objection
    to
    waiting
    until Auaust
    15
    (P.
    119).
    That
    cornoany
    is
    about
    to
    move
    from
    a
    plant
    in
    Bellwood
    to
    its
    new
    plant
    in
    Glendale Heights
    (P.
    116).
    It will
    not
    he
    kent
    from
    doinci
    business by the denial of the variances
    Its reason for the re~
    quest
    is that to delay starting the move
    ~intil late September
    might cost
    it some orders since the move might
    then catch
    it
    in
    the middle of
    a rush buying period (P~ l2l~2?).
    There was also
    testimony that
    a delay might cause
    the company to pay
    for taxes
    and upkeep of the old
    and new plants at once
    (P~ 122), hut
    the
    e vidence
    is clear that this will he true until December even
    if the variance is granted since the move will he stretched out
    over
    that period
    (R,
    l23)~
    Since Spraying Systems will not he
    able
    to begin
    its move until after the Village expects to have
    its plant completed (P~ lii,
    118), we
    see no likelihood of hard~
    ship.
    If,
    on the other hand,
    the plant
    is considerably delayed,
    we think
    the
    facts that the company can continue operatina from
    its present plant and that it will be paying
    for both buildings
    until December anyway obviate any significant hardships that
    would justify allowing even the anticipated few
    thousand gallons
    per
    clay of extra wastes to
    a plant already overloaded,
    as we
    shall make clear below,
    Puite
    has planned
    to build 384 units
    of new housing
    (5,
    139)
    for more
    than
    800 people
    (P.
    162)
    in Glendale Heights,
    Except
    for model
    homes,
    it had
    net begun construction when our
    order
    came down,
    and
    it had not when
    the hearing was held June
    2
    (5,
    148)
    After
    an initial quick~huilciingperiod
    for the
    first units,
    a 60~dayconstruction period
    is anticipated
    (5,
    155)
    ,
    Puite
    asks
    to connect
    40 units per week
    (5,
    155)
    starting July
    15,
    adding an estimated
    125 gallons per capita per
    day
    (5,
    l63)~
    It argues
    (5,
    2fl~)
    that
    if
    it
    builds
    the houses
    now and leaves them idle until
    the treatment plant
    is done it
    must spend large
    sums
    for watchmen to prevent vandalism and pay
    interest on construction costs
    (P.
    155,
    157),
    while
    if it does
    not
    start construction until
    the olant
    is ready it will suffer
    from inflation
    in building costs
    (P~ 152,
    158)~
    These
    alternatives
    do not exhaust the possihilities~
    The first houses
    can he started
    in
    time for completion when
    the plant
    is to be done,
    and there
    will
    he neither
    a need
    for
    long vacancIes nor
    a
    long delay
    before building,
    since
    that dat~eis August
    15,
    Pulte put on several witnesses who had purchased
    its hones,
    whose testimony was not very tellinq~
    One said she needed
    to know
    when
    the new homes would he available
    so
    she
    could
    sell
    her
    present
    house
    (5,
    l79~81)
    ;
    a
    second,
    with
    no
    lease
    problem,
    a1 so
    had
    no pressing need
    to be in by July 15
    (5. l82~83)~ A
    third
    2
    74

    was getting
    married in late August and hoped to he able to move
    in by August
    28
    in
    order not to have
    to live with his parents
    (5, 174),
    A fourth had cancelled his order because of past de~-
    lays the company attributed to the sewer ban
    (5,
    177);
    there
    is nothing we can do about that now.
    As in the Spraying Systems case,
    therefore, we see no great
    hardship if Pulte must wait a month longer than it desires in
    order to avoid pollution.
    We note also that neither petitioner
    introduced any evidence as
    to efforts to make alternative
    arrangements
    such
    as renting package treatment plants
    (5.
    116)
    which
    as we noted in a related case were
    a possibility
    (League
    of
    Women Voters v.
    North Shore
    Sanitary
    District,
    * 70~7,March
    31,
    1971).
    Without such evidence
    there
    is inadequate proof of
    hardship,
    Moreover, Pulte was aware when
    it first investigated
    the
    land in question that
    the
    treatment plant was already
    dangerously loaded~(5,
    125);
    it
    cannot very well claim surprise.
    Further,
    it had not commenced construction when our order was
    handed down;
    not caught with nearly completed homes on its
    hand~,
    it
    seeks to start building now,
    to conduct business as
    usual without regard to the~pollutionthat would cause.
    It
    is argued that
    July and
    August were dry months
    in
    1970
    (5,
    17)
    and therefore that
    it
    is
    safe
    to allow
    an
    additional
    load
    until the plant
    is
    finished.
    But July
    in
    1968 and 1969
    was not so dry;
    flow exceeded
    a million gallons per day on six
    occasions in July 1968 and
    on seven
    in
    July 1969, with three
    July days
    in
    1969 over two million
    (5, l00’~02), Although
    the
    plant can put two mgd through without overflowing,
    it cannot
    give adequate treatment
    to more than
    one mgd
    (5.
    27); and flows
    over two mgd will cause
    an overflow of raw sewage
    (P.
    30,
    32,
    189),
    We cannot view these prospects with equanimity nor
    rely
    on
    1971
    to be
    as dry
    as 1970.
    While
    flows have been somewhat
    reduced by measures to control infiltration
    (5,
    105),
    that is
    not
    the big reason
    ~or
    the
    1969 high
    glows;
    the reason was heavy
    rainfall
    (5.
    102).
    It
    is argued that as soon as
    the
    tertiary filters are on
    line there will
    be
    adequate treatment even of excess f1ow~, Put
    there is
    no
    evidence to show what quality
    effluent
    would result
    from employing the filters on substantially undertreated sewage,
    except an unsupported and unexplained conclusion that the village
    believes the
    4
    ppm POD standard can
    he
    met with
    1
    1/2
    mgd
    (189),
    or
    to show the effect of such an effluent on the stream,
    The
    companies have not shown the addition of their wastes wo1h~d
    be harmless or that its adverse effects would he outwei4hed by
    the hardships they would suffer from denial of their petitions.
    That the quantities of sewage involved in Sprayj~qSvs~n~sare
    not huge
    (2000
    gpd)
    is relevant but not decisive.~ Any single
    source may appear insubstantial, but as we showed
    in the North
    Shore case it is the proliferation of small sources that can cause
    an overpowering pollution problem.
    And the amounts in issue in
    Pulte are not all that small; we are asked to allow the addition
    2
    75

    of 11,000 gpd each week,
    for
    a total
    of 104,000 gpd by October
    14
    (5,
    164),
    If something went seriously wrong with the
    Vil1age~sschedule, Pulte with a variance would add 10
    of the
    whole present capacity.
    The principle of this decision is very simple:
    New construction
    must wait for adequate sewage treatment.
    In this day and age
    it
    is
    inexcusable
    for
    new
    sources
    of
    waste
    to operate without
    pollution controls.
    We see no
    reason in thes& cases
    to depart
    from the salutary principle of the original Glendale
    Heiqhts
    case.
    In all probability the delay will be only until
    August
    15,
    The petitions for variance are denied.
    This opthion
    constitutes the Board’s findings of
    fact, conclusions of
    law,
    and order.
    I. Regina
    E.
    Ryan, Clerk of the Pollution Control
    Roam-I,
    certify
    that
    rd adopted
    the above Opinion
    and
    Order this~
    2—76

    Back to top