ILLINOIS POLLUTION CONTEOL BOARD
July
 6,
 1971
SPRAYING SYSTEMS,
 INC.
V.
 )
 ~
71~72
ENVIRONMENTAL PROTECTION AGENCY
PULTE
 LAND
 CORP.
V.
 ~+
71—7~
ENVIRONMENTAL
 P ROTECTI ON
 AGENCY
Opinion
 and
 Order
 of
 the
 Board
 (~y Mr.
 Currie)
On
 February
 17,
 l~7l
 we
 entered
 an
 order
 in
 Environrnenta~
Protection
 Agency
 v.
 Village ef
°lenC~1~
TTcithts,
 f
 70~R,
 findine
the
 village
 was
 d.ischargi.ag
 inadc,Gnatelv
 trented
 sewage
 fren
 an
overloaded
 plant
 and
 ordering
 the
 construction
 of
 facilities,
which
 the
 village
 had
 airea~p
 begun,
 to
 ron’dr
 the~situation.
One
 paragrach
 of
 our
 order
 banned
 additional
 rower
 connections
 tributary
 to
 the
 plant
 unti
 I.
 tho
 violation
 war
 corrected,
 on
 the
ground
 that
 to
 permit
 then.
 wonl.d
 r~ounR the
 problem
 and
 in-
crease
 pollution.
 The
 present
 pet.itions
 nook
 earl
 ances
 from
 that
order
 to
 permit
 new
 cortnocti.onn
 be5ore
 cnm~-lnt.i
 on
o~
the
 new
facilities
 Ye
 deny
 therr~
Glend.ale fbi
ght.s
 has
 a
 one—mi I lion—gal
 br
 —per—day
 (~‘
 2~
25)
 secondary
 plant
 who~c
 effluent
 ~ft
 on.
 ernoeds
 the
 rtand~rd~
for
 secondary
 treatment
 (P.
 12)
 hecans~
 it
 in.
 ~requontlv
 over—
loaded.
 Rules
 arid
 Regulations
 P~’R~l4teouire
 a
 further
 stage
of
 treatment
 for
 snail
 receiving
 streans
 such
 an
 this
 one,
 the
 East
 Branch
 of
 the
 DuPage
 Piver,
 The
 ~i
 11
 non
 is
 well
 on
 the
 way
toward
 completion
 of its project,
 The tertIary cibters
 and
chlorination
 facilities
 are
 expected
 to hc comeleted by
 July
14,
 1971
 (R,
 46,
 40)
 so
 that
 dry—weather
 fbow~
 (which
 average
about
 750,000
to
 300,000 gpd
 (P.
 92))
 will by then he
 properly
treated.
 The
 twin parallel primary
 and se~undary faeilities,
which will give
 the system
 art additional
 2 ogd
 of car’acitv,
 are
expected
 to be finished
 and
 in
 full operation
by
August
 1P
(R.
 44,
 46,
 52).
2
—
 73
Thus if the petitioners have to wait
 to connect their new
waste outlets
 to the village sewers they will
 not have to wait
long~
 And indeed
 in the case of Spraying Systems there is no
objection
 to
 waiting
 until Auaust
 15
 (P.
 119).
 That
cornoany
is
 about
 to
 move
 from
 a
 plant
 in
 Bellwood
 to
 its
 new
 plant
 in
Glendale Heights
 (P.
 116).
 It will
 not
 he
 kent
 from
 doinci
business by the denial of the variances
 Its reason for the re~
quest
 is that to delay starting the move
 ~intil late September
might cost
 it some orders since the move might
 then catch
 it
 in
the middle of
 a rush buying period (P~ l2l~2?).
 There was also
testimony that
 a delay might cause
 the company to pay
 for taxes
and upkeep of the old
 and new plants at once
 (P~ 122), hut
 the
e vidence
 is clear that this will he true until December even
if the variance is granted since the move will he stretched out
over
 that period
 (R,
 l23)~
 Since Spraying Systems will not he
able
 to begin
 its move until after the Village expects to have
its plant completed (P~ lii,
 118), we
 see no likelihood of hard~
ship.
 If,
 on the other hand,
 the plant
 is considerably delayed,
we think
 the
 facts that the company can continue operatina from
its present plant and that it will be paying
 for both buildings
until December anyway obviate any significant hardships that
would justify allowing even the anticipated few
 thousand gallons
per
 clay of extra wastes to
 a plant already overloaded,
 as we
shall make clear below,
Puite
 has planned
 to build 384 units
 of new housing
(5,
 139)
 for more
 than
 800 people
 (P.
 162)
 in Glendale Heights,
Except
 for model
 homes,
 it had
 net begun construction when our
order
 came down,
 and
 it had not when
 the hearing was held June
2
 (5,
 148)
 After
 an initial quick~huilciingperiod
 for the
first units,
 a 60~dayconstruction period
 is anticipated
 (5,
155)
,
 Puite
 asks
 to connect
 40 units per week
 (5,
 155)
starting July
 15,
 adding an estimated
 125 gallons per capita per
day
 (5,
 l63)~
 It argues
 (5,
 2fl~)
 that
 if
 it
 builds
 the houses
now and leaves them idle until
 the treatment plant
 is done it
must spend large
 sums
 for watchmen to prevent vandalism and pay
interest on construction costs
 (P.
 155,
 157),
 while
 if it does
not
 start construction until
 the olant
 is ready it will suffer
from inflation
 in building costs
 (P~ 152,
 158)~
 These
 alternatives
do not exhaust the possihilities~
 The first houses
 can he started
in
 time for completion when
 the plant
 is to be done,
 and there
will
 he neither
 a need
 for
 long vacancIes nor
 a
 long delay
before building,
 since
 that dat~eis August
 15,
Pulte put on several witnesses who had purchased
 its hones,
whose testimony was not very tellinq~
 One said she needed
 to know
when
 the new homes would he available
 so
 she
 could
 sell
 her
present
 house
 (5,
 l79~81)
 ;
 a
 second,
 with
 no
 lease
 problem,
 a1 so
had
 no pressing need
 to be in by July 15
 (5. l82~83)~ A
 third
2
—
 74
was getting
married in late August and hoped to he able to move
in by August
28
 in
 order not to have
 to live with his parents
(5, 174),
 A fourth had cancelled his order because of past de~-
lays the company attributed to the sewer ban
 (5,
 177);
 there
is nothing we can do about that now.
As in the Spraying Systems case,
 therefore, we see no great
hardship if Pulte must wait a month longer than it desires in
order to avoid pollution.
 We note also that neither petitioner
introduced any evidence as
 to efforts to make alternative
arrangements
 such
 as renting package treatment plants
 (5.
 116)
which
 as we noted in a related case were
 a possibility
 (League
of
Women Voters v.
 North Shore
Sanitary
District,
 * 70~7,March
 31,
 1971).
 Without such evidence
there
 is inadequate proof of
hardship,
 Moreover, Pulte was aware when
 it first investigated
the
land in question that
the
treatment plant was already
dangerously loaded~(5,
 125);
 it
cannot very well claim surprise.
Further,
 it had not commenced construction when our order was
handed down;
 not caught with nearly completed homes on its
hand~,
it
seeks to start building now,
 to conduct business as
usual without regard to the~pollutionthat would cause.
It
is argued that
July and
August were dry months
 in
1970
(5,
 17)
 and therefore that
it
is
safe
to allow
an
additional
load
until the plant
is
finished.
 But July
 in
1968 and 1969
was not so dry;
 flow exceeded
 a million gallons per day on six
occasions in July 1968 and
on seven
 in
July 1969, with three
July days
in
1969 over two million
 (5, l00’~02), Although
the
plant can put two mgd through without overflowing,
 it cannot
give adequate treatment
to more than
one mgd
 (5.
 27); and flows
over two mgd will cause
 an overflow of raw sewage
 (P.
 30,
 32,
189),
 We cannot view these prospects with equanimity nor
rely
on
1971
to be
as dry
as 1970.
 While
flows have been somewhat
reduced by measures to control infiltration
 (5,
 105),
 that is
not
the big reason
~or
the
1969 high
glows;
 the reason was heavy
rainfall
 (5.
 102).
It
is argued that as soon as
the
tertiary filters are on
line there will
be
adequate treatment even of excess f1ow~, Put
there is
no
evidence to show what quality
effluent
would result
from employing the filters on substantially undertreated sewage,
except an unsupported and unexplained conclusion that the village
believes the
 4
ppm POD standard can
he
met with
 1
 1/2
mgd
 (189),
or
 to show the effect of such an effluent on the stream,
 The
companies have not shown the addition of their wastes wo1h~d
 be harmless or that its adverse effects would he outwei4hed by
the hardships they would suffer from denial of their petitions.
That the quantities of sewage involved in Sprayj~qSvs~n~sare
not huge
 (2000
 gpd)
 is relevant but not decisive.~ Any single
source may appear insubstantial, but as we showed
 in the North
Shore case it is the proliferation of small sources that can cause
an overpowering pollution problem.
 And the amounts in issue in
Pulte are not all that small; we are asked to allow the addition
2
—
 75
of 11,000 gpd each week,
 for
 a total
 of 104,000 gpd by October
14
 (5,
 164),
 If something went seriously wrong with the
Vil1age~sschedule, Pulte with a variance would add 10
 of the
whole present capacity.
The principle of this decision is very simple:
 New construction
must wait for adequate sewage treatment.
 In this day and age
it
is
inexcusable
 for
 new
 sources
 of
waste
 to operate without
pollution controls.
 We see no
reason in thes& cases
 to depart
from the salutary principle of the original Glendale
Heiqhts
case.
 In all probability the delay will be only until
August
15,
The petitions for variance are denied.
 This opthion
constitutes the Board’s findings of
 fact, conclusions of
 law,
and order.
I. Regina
E.
 Ryan, Clerk of the Pollution Control
 Roam-I,
 certify
that
 rd adopted
the above Opinion
 and
Order this~
2—76