ILLINOIS
    POLLUTION
    CONTROL
    BOARD
    January
    6,
    1971
    MARQUEflE
    CEMENT
    MPG
    CO.
    )
    )
    v.
    )
    #70—23
    )
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    )
    Opinion
    of
    the
    Board
    (by
    Mr.
    Currie):
    Marquette
    Cement
    Manufacturing
    Co.
    filed
    a
    petition
    for variance October 1*,. 1970.
    After a hearing we grant
    the petition subject to several conditions enumerated be-
    low.
    Marquette operates in Oglesby, Illinois, a large and
    elderly cement manufacturing plant whose emission of cement
    dust concededly “far exceeds” the limits set by the particulate
    emission regulations adopted by the old Air Pollution Control
    Board in 1967.
    The regulations (Rule 2—2.31) required the
    submission by April 15, 1968, of afirin program (ACERP)
    for bringing emissions into compliance.
    On September 1,
    1967 Marquette filed a letter of intent (this and the
    following communications
    are
    combined in EPA Ex.
    3) stating
    that because the plant was “obsolete” the company was
    “studying feasibility of completely rebuIlding this plant
    or building at a new location” and promising
    that an ACERP
    would be filed on or before the date prescribed.
    Just be—
    tore that date, hcwever, the company requested an extension
    of time to study the alternatives, which had been “narrowed”
    to “five or six” and which now included “upgrading the existing
    plant to meet operating and air pollution requirements.”
    An extension was granted until December 15, 1968.
    In December of that year Marquette wrote that a committee
    of its Board of Directors
    had
    concluded that “the plant
    should
    be
    enlarged
    and
    modernized
    with
    the
    first
    phase
    to
    include
    completely
    new
    kiln
    department
    and
    a
    completely
    new finish grinding
    department,”and
    that
    the
    new design
    “will include the installation of the most modern and effective
    dust collection equipment available,” which would “be de—
    s~.gnedto fully meet the Illinois code.”
    This program was
    to
    be
    recommended
    to
    the
    company’s
    Board
    of
    Directors
    in
    February,
    and
    “it
    is
    expscted
    that
    approval
    will
    be
    given
    1
    145

    and
    an appropriation
    of funds made.”
    A letter
    a few weeks
    later listed five firms that had submitted proposals
    to
    build
    the new facilities,
    stated the belief that the
    company
    would
    “be in
    a position within the next week to make
    a final
    selection of an engineering firm for the Oglesby project”
    and would then “enter into
    a contract,”
    and included
    a
    schedule as follows:
    “(1)
    Detailed engineering
    to start
    not
    later than
    April
    30,
    1969.
    “(2)
    Construction to start May
    1,
    1970.
    “(3)
    Construction
    to be completed
    in September,
    1971.”
    On
    the basis of these assurances
    the Air Pollution Control
    Board approved the air contaminant emission reduction program
    January
    30,
    1969, requiring the filing of annual progress
    reports beginning July
    1,
    1969.
    Then the vacillations
    began.
    After obtaining
    state
    approval
    of
    the program the company’s Board of Directors,
    confronted
    by what Marquette described
    as
    “a sharp increase
    in the interest rates for
    long term capital borrowing,”
    voted only “conditional” approval of the plan the company
    had submitted,
    making
    the whole program contingent upon
    “arrangements
    to increase the company’s
    long term
    debt
    on a basis approved by
    the
    Administrative ,and Advisory
    Committee of this Board of Directors.”
    If
    no such arrange-
    ments could be made,
    the officers were authorized
    to install
    control equipment on the existing kilns,
    (Letter of March
    12,
    1969).
    Six weeks later
    a telegram informed
    the Air Board
    that
    the company
    had made the decision to install control
    equipment on exiting facilities and that
    a letter contain-
    ing
    a new program would be submitted the following week.
    But
    no letter was submitted,
    and neither was the pro-
    gress report required
    by the order approving the original
    program.
    On August 29,
    1969 the Board wrote
    to Marquette
    urging that
    the report
    be filed immediately to avoid en-
    forcement action.
    On September
    10
    the company responded
    that
    it regretted
    the “oversight”
    and placidly reported that
    after two years and a half of studying alternatives
    (and
    polluting the air)
    it was right back where
    it
    had started.
    This letter
    is
    so blatant
    in its assumption that
    the company
    could get away with whatever
    it pleased that
    I quote it rather
    extensively:

    “We are proceeding with detailed Oglesby en-
    gineering and financial studies along two
    lines,
    both of which would include satisfactory air pollution
    control.
    The
    first encompasses modernization
    of
    the present plant, and the second installing
    new
    air pollution control equipment on the present plant.
    “Discussions with the institutions from which
    we have secured
    our present
    long term debt indicate
    that financing the modernization of
    the present
    plant may become
    a problem,
    and this has raised
    the question about
    our ability to continue with
    this plan which your Board
    has approved.
    Should
    we find
    it necessary to take the alternative course
    of installing satisfactory air pollution
    control
    equipment
    on the present plant, we shall present
    to you and
    the Board for your consideration an
    amended Air Contaminant Emission Reduction Program
    and time schedule.”
    That was the
    last heard from Marquette Cement Manufacturing
    Company about fixing up its
    air pollution problems until
    the present petition for variance was
    filed
    in October, 1970——
    three and
    a half years after the regulations took effect.
    Pollution continues unabated.
    Now the company has presented
    a plan that,
    if
    it were
    not for the delay, would seem satisfactory.
    The new plan
    calls for replacement of the eight oldest kilns with
    a
    single
    new one (complete with electrostatic precipitator)
    to be completed by December
    31,
    1972, and
    for fitting the
    two other existing kilns with precipitator
    by March
    31,
    1972,
    The Environmental Protection Agency agrees that
    this
    program will bring Marquette into compliance with
    the
    particulate regulations.
    Moreover, although the Agency raised
    questions as
    to whether the timetable proposed could be
    expedited,
    the only evidence in the record supports
    the
    company~s schedule.
    Precipitator suppliers,
    the testimony
    shows, ar& presently overcommitted;
    substantial demolition
    work must
    be done to make room for the new installations
    in a crowded work area; provision must
    be made
    for
    a new
    electrical supply
    (R.
    29,
    ~I2,
    66, 71,
    82—83,
    88).
    On this
    record we accept the uncontradicted testimony that,
    given
    today as the starting date,
    the schedule is as tight as we
    can require.
    The statute provides
    for
    a variance to be granted only
    if the petitioner carries the burden of proving that
    to comply
    with the regulations would impose an “arbitrary or unreasonable
    1
    147

    hardship”
    (~35),
    The evidence as to hardship
    if the plant
    were closed during installation
    of the pollution control
    equipment
    is convincing,
    although one is tempted
    to say the
    hardship was self-~inflictedby the company’s long record
    of unnecessary delay.
    To close the plant would of course
    cause
    the loss of business for two
    years,
    and
    the company
    maintains that
    it would never be able to reopen the plant
    if the variance were denied
    (R.
    62).
    More importantly,
    the
    closing of the plant would deprive over
    400
    people
    of their
    jobs
    (R,
    17),
    in an area that has few obvious opportunities
    for reemployment
    (R,
    100).
    On the other side
    of the balance,
    while there have been a number
    of. complaints about dust
    emissions from the
    cement kilns
    (FL,
    8), there
    is
    no
    evidence
    that they are acutely
    toxic, and
    no one has asked us to
    shut
    down the plant while controls
    are being installed
    To the
    contrary, there was overwhelming community sentiment in
    favor
    of
    the
    grant
    of
    the
    variance.
    The
    manager
    of
    the
    regional
    chamber
    of
    commerce
    (R.
    97—101),
    the
    mayor
    of
    Oglesby
    (R,
    104),
    the
    local Roman
    Catholic
    priest
    (FL.
    112)
    and Protestant minister
    (FL,
    127), vice—presidents of
    a local
    bank
    (FL.
    115) and of
    a local savings and loan association
    (FL,
    125),
    the president
    (FL,
    149—50)
    and recording secretary
    of the union representing Marquette’s employees
    (FL.
    150)
    and another citizen
    (FL,
    153) all testified that they hoped
    the variance would be granted.
    Two other residents of Oglesby
    voluntarily
    testified
    that they objected
    to
    air
    pollution and
    noise
    from
    trucks
    serving
    the
    cement
    plant
    but that
    they did
    not
    object
    to
    the
    grant
    of
    the
    variance
    (f.
    139.,
    146).
    This community sentiment cannot
    be
    ignored.
    The
    people
    who
    will suffer most
    1.~rom continued pollution during the next
    two
    years
    while
    controls
    are
    being
    installed
    have
    told
    us
    in
    no
    uncertain
    terms
    that
    they
    would
    suffer
    much
    more
    if
    the
    plant
    were
    closed.
    We
    think
    hardship
    is
    amply
    shown and
    the
    variance
    must
    be
    granted.
    This does
    not, however, mean that we simply give
    the
    company what
    it asked for with no strings attached,
    To
    begin with,
    the
    s
    .~
    atute expressly limits any variance to
    one year
    (836
    (b)),
    in accord with
    the salutary ~policy of
    requiring the petitioner to come back within a reasonable
    time
    arid demonstrate that
    it
    has made satisfactory progress
    toward
    completing
    its program.
    We will grant
    the
    variance
    for one
    year, and Marquette may obtain an extension as the
    statute provides upon
    a timely petition and proof that
    it
    has made satisfactory progress
    and has complied with the
    conditions of today’s order.

    Moreover, today’s variance order does not authorize
    violations of
    anything
    other than
    the
    particulate regulations,
    or
    by
    any
    equipment
    other
    than
    that
    covered
    by
    the
    variance
    request.
    Questions
    were
    raised
    during
    the
    hearing
    con-
    cerning dust
    and
    diesel smoke
    (as well as
    nocturnal
    noise)
    from trucks entering and leaving the plant through a re-
    sidential area (e.g., R.
    l39—~I7),and concerning carbon monoxide
    and sulfur dioxide emissions as well (R.
    511—56).
    We urge
    the Environmental. Protection Agency to investigate whether
    Marquette’s operations cause violations other than those
    involved in the present case and to take appropriate action
    if such violations are found.
    While the present proceeding
    does not permit usb
    issue orders against such violations,
    we have not been asked to allow them, and
    our
    order today
    does not do
    so.
    Finally, the statute explicitly authorizes the Board ~o
    “impose such conditions as the policies of this Act
    may
    require” when granting a variance
    (~
    36 (a)).
    Several
    donditions are required here to further the purposes of
    the statute.
    First, we shall require Marquette to submit
    quarterly progress reports in order to assure that it is
    living up to its promised schedule and so that prompt
    corrective action can be taken if it is not.
    We do not
    wish
    to be in the position, a year from now, of discovering
    for the first time
    that
    there have been further delays.
    For
    the
    same
    reason,
    we
    shall
    insist
    not
    Only
    that
    the
    company
    aim
    toward
    ultimate
    compliance
    by
    the
    end of
    1972
    but
    that
    it
    meet
    several
    interim
    deadlines,
    in
    accord
    with
    its
    own
    variance proposal, in order to give, us intermediate
    checkpoints
    against
    which
    to
    measure
    progress.
    Third, since this is a case in which the hardship is
    temporary and the sole reason for the variance is the need
    for time in which to install control equipment, the statute
    (~
    36 (a)) requires the posting of security to assure that
    the company meets the dates it has set itself.
    There is
    some suggestion in the record that bonding companies
    may
    be reluctant to give security for this purpose, partly
    because the idea is a novel one with this statute and partly
    because the details of the required bond are
    not
    spelled
    out in the statute (R. 117—23, 128—31). There Ss even
    a suggestion that the security requirment maybe un9onstitutional
    (Petitioner’s summation,
    p.
    11), but no constitutional principle
    is cited in support of this contention, and the argument is
    patently without merit.
    We have required security in
    comparable past oases
    (e.g., Nestle Co. v. EPA, #70—22,
    decided December 22, 1970), and statutory bond requirements
    are in fact quite common and accepted in other fields.
    1-149

    As
    for
    the alleged reluctance
    of bonding companies,
    the
    statute
    and today’s order leave
    the Agency considerable
    flexibility in working out
    the details of the security;
    it may be that
    a commercial bond will not be required.
    The purpose of the bond requirement
    is
    to provide
    an additional
    incentive to the variance holder to meet his
    deadlines,
    by imposing the
    threat
    of forfeiture
    if he does
    not.
    The amount must
    be high enough to make
    it more
    unattractive
    to default than to spend the money
    for control
    equipment.
    While the cost of the equipment may be an
    adequate measure of this amount in some
    cases,
    it
    is not
    so
    here since much of the
    cost of the new installation
    is
    for
    new kilns,
    We think a security in the amount of $50,000
    will suffice,
    to be forfeited
    if the plant
    is operated
    without
    a further variance
    and without controls after
    January
    6,
    1972.
    Finally,
    the purposes
    of the statute require that we
    impose
    as
    a further condition
    of this variance the provision
    that Marquette pay to the
    State of Illinois
    the sum of
    $10,000 as
    a penalty for its inexcusable dilatory tactics,
    To
    let Marquette walk away without even
    so much as
    a slap
    on the wrist would suggest that
    the State does not mean
    business about pollution and would encourage other emitters
    to delay controlling their processes until
    the
    last possible
    moment.
    For Marquette, as
    amply
    shown by this record,
    publicly thumbed
    its corporate nose at the State of Illinois
    for at least
    one and
    a half years.
    After requesting and
    receiving
    a nine—month extension of a year’s grace period
    to devise
    a plan for compliance,
    the company received approval
    of
    its plan only
    to
    change its mind and procrastinate,
    It
    is
    not as
    if
    the
    old Board had granted
    approval
    of
    a program
    whereunder
    the company was to study the problem for another
    year
    or
    two;
    the
    ACEFLP
    submitted
    and
    approved
    in
    January
    1969 contemplated
    that Marquette
    would
    replace
    the
    old
    kilns with
    new
    ones equipped with adequate controls by
    September,
    1971.
    The failure
    of the company’s
    Board of
    Directors
    to endorse the program the State had approved
    put an end to that program,
    and the company did
    not submit
    another——or even request another time extension——for more
    than
    a year and
    a
    half thereafter,
    Rather the company kept
    putting off the Air Pollution Control Board wi~hassurances
    that
    it was still
    “studying”
    the problem.
    But the time
    for
    study had long passed.
    The Air Pollution Control Act did
    not grant people an indefinite period in which to make up
    their minds,
    Marquette was given plenty
    of time
    to decide
    how to bring its plant
    into compliance,
    and without leave
    it proceeded
    to take twice as long as was allowed.
    The re-
    sult
    is
    that
    the company was
    in clear
    and flat violation
    of the particulate regulations,
    from February
    1969, when
    the Board of Directors refused to endorse the ACERP that the
    State had approved, until the submission of the present
    1
    150

    plan and its approval today.
    The failure to live up to
    the
    ACER? and the failure to
    submit
    the progress report
    required
    in
    July,
    1969
    were
    additional
    violations
    for
    which
    penalties
    may
    be imposed.
    To ignore these violations would
    frustrate the purpose of the statute to “restore, maintain,
    and enhance the purity of
    the
    air”
    (8
    8), by encouraging
    delays
    that
    are
    prejudicial
    to
    the
    entire
    control
    program.
    As
    we
    said
    last
    month
    in
    Ozark—Mahoning
    Co.
    v.
    EPA
    (#70—19, decided December 22, 1970), the time may come when
    this Board refuses to accept a plea of hardship on behalf
    of one who has deliberately brought about his own plight
    by delaying the installation of control equipment.
    Today
    we choose not to deny the variance on this ground, but we
    think it necessary to impose a penalty as
    a
    condition
    of
    our variance order so that in the future people will under-
    stand that deligence in
    pursuit
    of
    a
    program
    of
    compliance
    is required.
    By
    dragging
    its feet Marquette
    has
    postponed
    for over a year and a half (since the original approval of the
    ACERP) the spending of the three million dollars it plans
    to invest in control equipment.
    The interest thus saved
    amounts to a pretty penny.
    While it is true that some of
    this saving is offset by rising construction costs, this
    could not necessarily have been foreseen at the time.
    It
    remains true that the company that
    delays
    making
    expenditures
    for air pollution control is likely to benefit financially
    at the expense of its innocent neighbors, and a penalty
    must be imposed as a deterrent.
    The
    sum
    of $10,000 is
    peanuts to a company undertaking a $15,000,000 construction
    program;
    I would be inclined to favor a penalty of $50,000.
    But
    the Board is of the opinion that a $10,000 slap will
    serve as adequate warning to those in similar positions
    in the future who might be tempted similarly to delay.
    Future penalties may not be so trivial, for the statute
    (8
    42) permits penalties of $10,000 plus an additional
    $1000 for each day a violation continues.
    Accordingly, the variance will be granted upon the
    conditions stated above, including the payment of $10,000
    to the State as a penalty for emitting particulate air
    contaminants in violation of the regulations promulgated
    by the Air Pollution Control Board and without pursuing a
    program of delayed compliance as authorized by those re-
    gulations.
    The ACERP approved by that Board is no defense,
    for the regulations
    plainly
    provide
    that
    there is such a
    de-
    fense
    only
    so
    long
    as
    the
    program
    is
    being
    implemented
    (Rule
    2—2.41).
    The protective mantle of that program expired
    1
    151

    when the company board refused to endorse it in February,
    1969.
    The violation continued at least until the filing
    of the present petition in October 1970,
    and the penalty
    assessed is easily within the amounts authorized
    over this ex-
    tended violation period by either
    the Environmental Protection
    Act
    or its predecessor.
    I conclude by quoting from the recommendation of the EPA:
    “The Agency can only conclude that petitioner
    was using
    the program to delay as long as possible
    the
    time when
    it must bring itself into compliance.
    .
    Petitioner’s only real progress,
    since submitting its
    January 1969 program,
    is to have finally decided what
    it
    is going to do,”
    This opinion constitutes the Board’s findings
    of
    fact
    and conclusions
    of
    law.
    ORDER
    The Board, having considered
    the transcript and exhibits
    in this proceeding,
    hereby grants the petition of Marquette
    Cement Mfg.
    Co.
    for
    a variance,
    subject to the following
    conditions.
    1.
    This order
    shall shield the company from proceedings
    for enforcement of
    the particulate emission regulatians
    adopted
    by the Air
    Pollution
    Control
    Board
    and preserved
    by section 49 of the Environmental Protection Act, with
    regard to emissions from the
    kilos for which control plans
    were submitted
    in the petition for variance filed in this
    proceeding,
    from the day of this order until January
    6,
    1972,
    provided that the other conditions of this order are complied
    with.
    2.
    Marquette shall adhere
    to the following schedule, as
    set
    forth in its petition for variance:
    Evaluation of bids and application for permits
    (for
    collection
    equipment)
    .
    .
    .
    February
    1,
    1971
    Start of construction work
    .
    .
    ,
    .April
    1,
    1971
    Completion of dust collection
    on two old kilos
    ...,.,...
    March 31,
    1972
    Completion
    of construction,
    total compliance
    .
    ,,,,,,,.
    December 31,
    1972

    3.
    Marquette
    shall file progress reports with the Board
    and with the Agency on April
    6,
    1971, and every three months
    thereafter, and shall apply for
    an extension of the variance,
    if necessary,
    no later than October
    6,
    1971.
    !4~
    Marquette
    shall
    post with the Environmental Protection
    Agency,
    on or before March
    1,
    1971, and
    in such form
    as
    the
    Agency may
    find satisfactory,
    a bond or other adequate security
    in the amount of $50,000, which sum shall be forfeited
    to
    the State of Illinois in the
    event
    that the plant
    in question
    is operated after January
    6,
    1972, without an extension
    of this variance and without control equipment sufficient
    to reduce emissions to those permitted by
    the regulations.
    5.
    Marquette
    shall pay
    to the State
    of Illinois,
    on or
    before
    March
    1,
    1971,
    the
    sum
    of $10,000
    as
    a penalty for
    continued
    violations
    of
    the
    statutes
    and
    of
    the
    regulations
    with
    regard
    to
    particulate
    emissions
    from
    the
    plant
    in
    question
    from
    Feb:ruary,
    1969
    until
    October,
    1970.
    6.
    Emissions
    closed
    in
    the
    its letter of
    variance.
    ~bal1 not he increased above
    the levels dis—
    forms
    submitted by Marquette in
    connection
    with
    intent
    (EPA Ex.
    3) during the period of this
    7.
    The failure of the
    company
    to
    adhere
    to
    any
    of
    the
    con-
    ditions
    of
    this
    order
    shall
    be grounds
    for revocation of
    the
    variance.
    ICQ~UR
    -~
    •-~
    _
    __-
    I,
    Regina
    E.
    Ryan,
    certify that
    the Board
    adopted
    the
    above
    soinion
    and
    order
    .January
    6,
    1971.
    /
    -
    ~2
    I
    DISSENT
    -
    L~
    A
    /
    ~
    ~
    1
    153

    Back to top