ILLINOIS POLLUTION CONTROL BOARD
    June
    12,
    1980
    ENVIRONMENTAL
    SITE
    DEVELOPERS,
    INC.,
    Petitioner,
    v.
    )
    PCB 80—15
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    JOSEPH MADDOX,
    ATTORNEY AT LAW,
    APPEARED
    ON BEHALF OF THE
    PETITIONER.
    WILLIAM
    SELTZER
    AND
    JOHN
    WILLIAMS,
    ATTORNEYS
    AT
    LAW,
    APPEARED
    ON
    BEHALF
    OF
    THE
    RESPONDENT.
    OPINION AND
    ORDER OF THE BOARD
    (by D.
    Satchell):
    This matter comes before the Board upon a petition appealing
    the denial of a solid waste disposal site development permit,
    filed January 18, 1980 by Environmental Site Developers,
    Inc.
    (ESD).
    The letter of denial cited violations of Rules
    313 and 315
    of Chapter
    7:
    Solid Waste Rules and Regulations which concern
    water pollution by landfills.
    The Board has received several
    written comments from the public.
    Hearings were held in Spring-
    field on April 24,
    30 and May 6,
    1980.
    Members of the public
    attended and commented.
    Since the hearings some members of the
    public have withdrawn their objections.
    The site in question is situated near Lake Springfield at the
    southeast corner of Springfield,
    Sangamon County.
    East Lake Drive
    runs generally east-west across Spaulding Dam at the northeast end
    of the
    lake.
    The City of Springfield
    (City)
    operates the V.
    Y.
    Dailman III coal-fired electric power unit
    south of East Lake
    Drive on the east side of the lake.
    There is
    a waterworks located
    adjacent to the power plant.
    Slurried fly ash and water treatment
    sludge are pumped under East Lake Drive,
    across to the east of the
    spiliway and Sugar Creek.
    ESD has
    an option to purchase a thirty-
    two acre tract to the north of the ash ponds and states the site
    will be about thirty—nine
    acres.
    It proposes to construct a series
    of berms
    to accept
    a calcium sulfate/sulfite sludge
    from
    the
    scrubber unit being installed in the power plant.
    An
    alternative site for the disposal of the sludge
    is Burk—
    ett’s landfill which is somewhat farther away
    (R.
    482;
    Resp.
    Ex.
    2).
    The Agency has issued
    a supplemental permit for the landfill
    to accept this sludge.
    Over its expected twenty year life
    a large
    amount of fuel will be saved by utilization of the ESD site which
    is very close to the power plant.
    The alternative
    site would

    —2—
    involve more movement of heavy trucks on city streets.
    In
    addition there
    is
    a possibility of selling the gypsum sludge for
    manufacture of wallboard or plaster of oaris.
    If it is mixed
    with other refuse it will lose its potential value
    (R.
    186)
    Section 39(a)
    of the Environmental Protection Act
    (Act) re-
    quires that
    in denying a permit the Agency transmit to the appli-
    cant a detailed statement of the reasons the permit was denied.
    The letter must identify regulations which may be violated if the
    permit were granted, the specific type of information,
    if any,
    which the Agency deems the applicant did not provide
    it and
    a
    statement of specific reasons why the Act and regulations might
    not be met if the permit were granted.
    On December 12,
    1979
    the Agency issued a letter of denial
    which stated as follows:
    The pollution potential to waters of the State of Illinois,
    from your proposed disposal of flue gas desulfurization
    sludges within the Based Flood* plain of Sugar Creek,
    is
    unacceptable.
    Rules
    313,
    315, Part
    III, Chapter
    7,
    Solid
    Waste,
    Illinois Pollution Control Board Rules and Regu-
    lations, adopted July
    27,
    1973.
    Based upon the above,
    Litis
    Aqency
    must
    deny
    tile i~erniitrequest.
    *“j3ased Flood” means
    a flood that has a one percent or
    greater c~ianceof recurring
    in any year or a flood of
    a magnitude equalled or exceeded once
    in 100 years,
    on
    the average, over a significantly long period.
    Considerable evidence was received concerning noise, dust
    and the possibility of mine subsidence under the proposed site.
    These problems are beyond the scope
    of the denial letter and will
    not be further considered by the Board.
    There is
    also testimony
    concerning fencing, cover and the intended practice of dumping
    from the berms rather than filling from the toe.
    These are not
    cited in the denial letter and also relate to the operating
    as
    opposed to the development permit.
    The Agency indicated that the basis of its concern was that
    the facility was to be located in a flood plain
    (R.
    88).
    At the
    hearing the Agency admitted that its objections were limited to
    its concern that flood waters would scour or damage the berms
    so
    as
    to allow leachate to migrate from the site and to the charact-
    erization of the sludge
    as inert
    (R.
    91,
    96).
    Petitioner seems
    to agree that it was adequately informed that this was the basis
    of the denial
    (R.
    144).
    The Agency was satisfied that the pro-

    —4—
    not
    have
    the
    odor
    problems
    and
    oxygen
    demand
    of the sulfide/sul-
    fite sludge and has a crystalline structurn which is mom
    favor-
    able to dewatering
    (R.
    177). Whereas the older sludges were 30
    water and had
    a consistency like toothpaste,
    the proposed unit
    will produce
    a moist powder with 10-20
    water
    (R.
    177;
    Pet.
    Ex.
    2).
    IL will contain about 0.08
    fly ash which could contain up
    to 150 ppm lead and other
    trace elements
    (R.
    206). The saturated
    leachate would contain about
    2500 ppm of soluble calcium salts.
    The only problems would be those associated with hardness or total
    dissolved solids
    (R.
    182).
    ESD proposes to install in each bermed
    area drains which will route any leachate to a pond for treatment
    if necessary. The Agency has issued to another operation a supple-
    mental permit for this same sludge
    (Pet.
    Ex.
    7).
    The Board has long held that the issue on appeal of a permit
    denial
    is whether the Agency erred and not whether new material
    which was not before the Agency persuades the Board that a permit
    should be granted.
    (Soil Enrichment Materials v. EPA, P03 72-264,
    5 PCB
    715
    (1972)1
    “The Agency errs
    in denying a permit only when
    the material,
    as submitted to the Agency by the applicant, proves
    to the Board that no violation of the Act or regulations will
    occur if the permit is granted,”
    Oscar
    Mayer and Company v. EPA,
    PCB 78—14,
    30 P03 397,
    399
    (1978)
    In its application ESD stated that the material was “inert.”
    “In a hearing on a Section 40 petition, the applicant must verify
    the facts of his application
    as submitted to the Agency,
    and,
    having done
    so, must persuade the Board that the activity will
    comply with the Act and regulations.”
    (Oscar Mayer and Company
    v.
    EPA, op. cit.,
    398)
    The evidence presented at the hearing has
    persuaded the Board that the material is indeed inert in the sense
    that its disposal as ESD proposes should pose little environmental
    hazard. The decision of the Agency is reversed.
    This case could have been handled more easily had the Agency
    fully complied with the requirements of Section 39(a)
    of the Act
    in issuing a denial letter and had ESD responded with a supple-
    mental application.
    This Opinion constitutes the Board’s findings of fact and
    conclusions
    of law in this matter.
    Mr. Werner concurred.

    —3—
    posed berms were high enough that they would not be overtopped
    by expected flooding
    CR.
    93).
    The Agency was satisfied that the
    soil at the site was suitable
    (R.
    92,
    470).
    Sugar Creek usually floods at least once a year between
    spaulding Dam and the Sanqamon River east of Springfield
    (R.
    17,
    535).
    The source of this flooding is water which backs up from
    the Sangamon and water from the lake
    wht~.’n the spillway gates are
    opened
    (B.
    480,
    535).
    The City operates ash ponds adjacent to
    tile spillway
    (R.
    532;
    Resp.
    Ex.
    1).
    At one time the City had
    difficulty witn berm erosion, but this was resolved by placing
    riprap alongside the channel from the spillway.
    There has been
    no difficulty resulting from erosion on the side away from the
    spillway
    (R.
    534,
    536,
    539).
    ESD’s berms will be beyond the
    existing ash ponds, away from the spillway and will be protected
    with riprap
    (R.
    107,
    149).
    Some of the citizen witnesses contended that construction
    of
    a berm around thirty—nine acres in a flood plain would tend to
    raise the flood level
    (R.
    21,
    330,
    364).
    Although this could have
    water pollution potential,
    it was not specified in the denial
    letter.
    The permit application described the sludge as
    “inert”
    (B.
    96,
    AcJeLlCy
    Record).
    Mr~Cavanauqh,
    Lhe Agency’s land permit: section
    lualiager,
    testified
    LiiaL
    flue
    gas
    desulfurization
    sludges
    (FGD)
    in
    his
    experience
    were
    not
    inert
    CR.
    90,
    96,
    440).
    lIe
    testified
    that
    ae
    consulted
    the
    “Flue
    Gas Desulphurization Sludge Disposal Manual”
    (R.
    442;
    Resp.
    Ex.
    11).
    The
    Petitioner
    seems
    to
    agree
    that
    this
    is a reliable source on this topic
    (R.
    183).
    The manual indicated
    that FGD sludges produce leachates far in excess of drinking water
    standards so that under proposed federal regulations it would be
    classified as a hazardous waste
    (B.
    442).
    The sludge involved in
    the permit application appeared to be similar to that in the
    manual
    (R.
    453,
    472,
    515).
    However,
    the FGD sludge most closely
    identified with the sludge involved here was blended with fly ash
    (R.
    435).
    Apparently results from comparable sludge were not
    available.
    The new scrubber represents a technological advance over the
    scrubbers described in the manual.
    The Dallman plant will have
    an electrostatic precipitator to remove around 99.5
    of the fly
    ash ahead of the two loop scrubbing operation
    (B.
    204).
    The
    scrubber employs limestone rather than lime and operates at a
    low pH in the first loop
    (B.
    175).
    Under these conditions calcium
    sulfide and sulfite are oxidized to the sulfate.
    The resulting
    product is
    in excess of 90
    calcium sulfate
    as gypsum.
    This does

    —s--
    ORDER
    The case is remanded to the Agency for issuance of a
    development permit.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that the above Opinion and Order
    were~adopted on the
    j~M
    day of~
    ,
    1980 by a vote
    (~4~
    ~
    ~hristan
    L. Mof
    t
    Clerk
    Illinois Pollution Control Board

    Back to top