ILLINOIS POLLUTION CONTROL BOARD
July
10,
1980
ANTHONY 3. CANFARELLI
V.
VILLAGE
OF ROMEOVILLE
Complainant,
Respondent,
)
)
)
)
)
)
)
PCB 79—75
ORDER OF THE BOARD
(by 3D.
Dumelle):
An Opinion and Order of the Board was issued in this
case on October
4,
1979,
ordering that the Respondent submit
to the Board and the Agency within 60 days a plan to minimize
overflows
in its sanitary sewer system.
Such a plan was
received by the Board on April
25,
1980, and by the Agency
on April
15,
1980.
Agency approval was received by the
Board on May 12, 1980,
and was conveyed to the Respondent
in a letter dated April 23,
1980.
The Board hereby accepts Respondent’s plan as submitted
and orders that implementation of the plan proceed and that
construction be completed before October 31,
1980.
IT
IS SO ORDERED.
I, Christan L. Moffett,
Clerk of the Illinois Pollution
Control Bo~rd,hereby ce tify that the above Order was adopted
on the
______
day of
_________,
1980 by a vote of
_________
Christan L. Moffe~’(~lerk
Illinois Pollution
~ntrol
Board