APPENDIX A
RO1-10 ABBREVIATION LIST
ACT
ENVIRONMENTAL PROTECTION
ACT
BACT
BEST AVAILABLE CONTROL
TECHNOLOGY
CO
CARBON MONOXIDE
ICC
ILLINOIS COMMERCE COMMISSION
IEPA
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY
LAER
LOWEST ACHIEVABLE EMISSION
RATE
MW
MEGAWATT
NAA
NONATTAINMENT AREA
NAAQS
NATIONAL AMBIENT AIR QUALITY
STANDARDS
NO
2
NITROGEN DIOXIDES
NO
x
NITROGEN OXIDES
NSPS
NEW SOURCE PERFORMANCE
STANDARDS
NSR
NEW SOURCE REVIEW
PM
PARTICULATE MATTER
PPM
PART PER MILLION
PSD
PREVENTION OF SIGNIFICANT
DETERIORATION
SO
2
SULFUR DIOXIDE
TPY
TONS PER YEAR
USEPA
UNITED STATES ENVIRONMENTAL
PROTECTION AGENCY
VOM
VOLATILE ORGANIC MATERIAL
WRAC
WATER RESOURCES ADVISORY
COMMITTEE
APPENDIX B
PERSONS TESTIFYING IN R01-10
Chicago Hearings
August 23, 2000
1.
Charles Fisher, Executive Director, Illinois Commerce Commission
2.
Thomas Skinner, Director, IEPA
3.
Christopher Romaine, Manager, Utility Unit, Permit Section, Division of Air
Pollution Control, Bureau of Air, IEPA
4.
Robert Kaleel, Manager of Air Quality Modeling Unit, Division of Air
Pollution Control, Bureau of Air, IEPA
5.
Greg Zak, Noise Advisor, IEPA
6.
Steve Nightingale, Manager, Industrial Unit, Bureau of Water Permits Section,
IEPA
7.
Rick Cobb, Manager, Groundwater Section, Bureau of Water, IEPA
8.
Todd Marvel, Assistant Manager of Field Operations Section and RCRA
Coordinator/USEPA Liaison/IEPA
9.
Dr. Brian Anderson, Director, Office of Scientific Research and Analysis,
IDNR
10.
Dr. Derek Winstanley, Chief, Illinois State Water Survey, IDNR
August 24, 2000
1.
Gerald Erjavec, Business Development, Indeck Energy Services, Inc.
2.
Greg Wassilkowsky, Manager, Business Development, Indeck Energy Services,
Inc.
3.
Arlene Juracek, Vice President, Regulatory and Legislative Services, ComEd
4.
Steve Nauman, Vice President, Transmission Services, ComEd
5.
Deirdre Hirner, Executive Director, IERG
6.
Richard Bulley, Executive Director of Mid-America Interconnected Network
7.
Freddi Greenberg, Executive Director and General Counsel, Midwest
Independent Power Suppliers
8.
Michael Kearney, Manager, Economic Development, Ameren Corp.
9.
Richard Trzupek, Manager, Air Quality, Huff & Huff
Suburban Hearings
Naperville
September 7, 2000
1.
Mayor George Pradel, Naperville
2.
State Senator Chris Lauzen
3.
State Representative Mary Lou Cowlishaw
4.
Mayor Vivian Lund, Warrenville
5.
Paul Hass, Zoning Manager, DuPage County Department of Development
Environmental Concerns
6.
Richard Ryan, President and Chairman, Standard Power and Light, Oak Brook
7.
Diana Turnball, Consultant to variety of citzen groups, private foundations and
businesses who have been in opposition to some of the peaker plants
8.
Carol Dorge, Attorney representing Lake County Conservation Alliance
9.
Connie Schmidt, Representative of River Prairie Group
10.
Mark Goff, Resident, Warrenville
11.
Cathy Capezio, Resident, Aurora
12.
Terry Voitik, Resident, DuPage County, and Founder of Citizens Against
Power Plants in Residential Areas (CAPPRA)
13.
Maurice Gravenhorst, Member, CAPPRA
14.
Lucy Debarbaro, Member, CAPPRA
15.
Terry Voitik on behalf of Steve Arrigo, CAPPRA
16.
Susan Zingle, Executive Director, Lake County Conservation Alliance
17.
Beverly Dejovine, Representative, Citizens Advocating Responsible
Environments (CARE), Bartlett
18.
Cathy Johnson, Vice Chair, Rural and City Preservation Association (R&CPA)
19.
Chris Gobel, Member, CAPPRA
20.
Elliot “Bud” Nesvig
21.
Sandy Cole, Commissioner, Lake County Board
22.
Chris Gobel, Member, CAPPRA
Joliet
September 14, 2000
1.
Dr. Thomas Overbye, Associate Professor, Department of Electrical and
Computer Engineering, University of Illinois, Champaign-Urbana
2.
Alan Jirik, Director, Environmental Affairs, Corn Products International, Inc.
3.
Carol Stark, Director, Citizens Against Ruining the Environment, Lockport
4.
Susan Zingle, Executive Director, Lake County Conservation Alliance
5.
Keith Harley, Chicago Legal Clinic
6.
Elliot “Bud” Nesvig
7.
Michael Shay, Senior Planner Responsible for Long-Range Planning, Will
County
Grayslake
September 21, 2000
1.
State Senator Terry Link
2.
State Representative Susan Garrett
3.
Tom Lynch, Trustee, Libertyville Township
4.
Betty Rae Kaiser, Trustee, Village of Wadsworth
5.
Daniel J. Kucera, Chapman & Cutler, appearing on behalf of the Lake County
Public Water District
6.
Jim LaBelle, Chairman, Lake County Board
7.
Sandy Cole, Commissioner, Lake County Board
8.
Bonnie Carter, Commissioner, Lake County Board
9.
Greg Elam, CEO, American Energy
10.
Larry Eaton, Attorney, on behalf of the Liberty Prairie Conservancy, Prairie
Holdings Corporation, and Prairie Crossing Homeowners Association
11.
Toni Larsen, Resident, Zion
12.
Chris Geiselhart, Chairperson, Concerned Citizens of Lake County
13.
Diane Turnball, Representing Liberty Prairie Conservancy, Concerned Citizens
of Lake County, CARE from McHenry County, Bartlett CARE, and Southwest
Michigan Perservation Association
14.
Lisa Snider, Resident, Wadsworth
15.
Verena Owen, Co-Chair, Zion Against Peaker Plants
16.
Elliot “Bud” Nesvig
17.
Carolyn Muse, Resident, Zion
18.
John Matijevich
19.
Dennis Wilson, Resident, Island Lake
20.
Terry Jacobs, Resident, Libertyville
21.
Jim Booth, Resident, Newport Township in Lake County
22.
William McCarthy, Resident, Libertyville
23.
Susan Zingle, Executive Director, Lake County Conservation Alliance
24.
Barbara Amendola, Resident, Zion
25.
Mark Sargis, Attorney, working with citizens who have been concerned about
peaker issues
26.
Cindy Skrukrud, Resident, Olin Mills, McHenry County
27.
Paul Geiselhart, Resident, Libertyville
28.
Dr. William Holaman, President, Illinois Citizen Action
29.
Evan Craig, Volunteer Chair, Woods and Wet Lands Group of the Sierra Club
30.
Phillip Lane Tanton
Springfield Hearings
October 5, 2000
1.
Roger Finnell, Engineer, Division of Aeronautics, Bureau of Airport
Engineering, IDOT
2.
John Smith, Representative of Illinois Section of American Waterworks
Association
3.
Brent Gregory, Representative of National Association of Water Companies,
Illinois Chapter
4.
James R. Monk, President, Illinois Energy Association
5.
Patricio Silva, Midwest Activities Coordinator, Natural Resources Defense
Council
6.
Brian Urbaszewski, Director, Environmental Health Programs, American Lung
Association
7.
Elliot “Bud” Nesvig
8.
Carol Dorge, Attorney representing Lake County Conservation Alliance
October 6, 2000
1.
Susan Zingle, Executive Director, Lake County Conservation Alliance
2.
Scott Phillips, Attorney, IEPA
3.
Kathleen Bassi, Attorney, IEPA
4.
Chris Romaine, Manager, Utility Unit, Permit Section, Division of Air
Pollution Control, Bureau of Air, IEPA
5.
Greg Zak, Noise Advisor, IEPA
6.
Todd Marvel, Assistant Manager of Field Operations Section and RCRA
Coordinator/USEPA Liaison/IEPA
7.
Steve Nightingale, Manager, Industrial Unit, Bureau of Water Permits Section,
IEPA
APPENDIX C
R01-10 EXHIBIT LIST
Exhibit Number
Description of Document
Illinois Commerce Commission
Prefiled testimony of Charles
Fisher
Exhibit 1 (8/23/00)
Illinois Environmental Protection Agency
Prefiled testimony of Agency
(Agency) Group Exhibit 1 (8/23/00)
witnesses (Thomas Skinner,
Christopher Romaine,
Robert
Kaleel, Greg Zak, Stephen
Nightingale, Richard Cobb,
and
Todd Marvel)
Agency Group Exhibit 2 (8/23/00)
Set of 20 documents,
beginning with
“Simple Cycle Gas Turbine
Application Diagram,” and
including two oversized
maps
Illinois Department of Natural Resources
Prefiled testimony of Brian
(DNR) Exhibit 1 (8/23/00)
Anderson
DNR Exhibit 2 (8/23/00)
Prefiled testimony of Dr.
Derek
Winstanley
Indeck Energy Services, Inc.
Prefiled testimony of Gerald
Erjavec
(Indeck) Exhibit 1 (8/24/00)
Indeck Exhibit 2 (8/24/00)
Copy of PowerPoint
presentation
and Supporting
Documentation
Commonwealth Edison Exhibit 1
Prefiled testimony of Arlene
Juracek
(8/24/00)
and Steven Naumann
Illinois Environmental Regulatory Group
Prefiled testimony of Dierdre
Hirner
(IERG) Exhibit 1 (8/24/00)
Mid-America Interconnected Network, Inc.
Prefiled testimony of
Richard Bulley
(MAIN) Exhibit 1 (8/24/00)
Midwest Independent Power Suppliers
Prefiled testimony of Freddi
Coordination Group Exhibit 1 (8/24/00)
Greenberg
Ameren Corporation Exhibit 1 (8/24/00)
Prefiled testimony of
Michael
Kearney
Huff & Huff Environmental Consultants
Prefiled testimony of
Richard
Exhibit 1 (8/24/00)
Trzupek, with attachments
Citizens Against Power Plants in Residential
CAPPRA Mission Statement
Areas (CAPPRA) Exhibit 1 (9/7/00)
and photographs
CAPPRA Exhibit 2 (9/7/00)
Steven Berning, et al. v. The
City
of Aurora, et al., 00-CH-
0361,
Second Amended Complaint
for
Declaratory Judgment
pending in
DuPage County Circuit
Court
CAPPRA Exhibit 3 (9/7/00)
Testimony of Michael
Warfel
CAPPRA Exhibit 4 (9/7/00)
Testimony of Steve Arrigo
DuPage County Board Exhibit 1 (9/7/00)
Versar Report
DuPage County Board Exhibit 2 (9/7/00)
Map - DuPage County
Municipalities and
Unincorporated
Areas
DuPage County Board Exhibit 3 (9/7/00)
Testimony of Paul J. Hoss,
Zoning
Manager for DuPage County
Department of Development
and
Environmental Concerns
Standard Light and Power Exhibit 1 (9/7/00)
Addendum No. 2 to
Application for
Prevention of Significant
Deterioration Construction
Permit
for Standard Energy
Ventures, LLC
Electrical Generation
Facility
BartlettCARE (Citizens Advocating
Testimony of Beverly
DeJovine
Responsible Environments) Exhibit 1 (9/7/00)
Susan Zingle (Zingle) Exhibit 1 (9/7/00)
“Peaker” Electrical
Generating
Plants Press Coverage –
2000
Zingle Exhibit 2 (9/7/00)
Testimony of Lake County
Conservation Alliance
Zingle Exhibit 3 (9/14/00)
Testimony of Lake County
Conservation Alliance with
attachments
Zingle Exhibit 4 (9/21/00)
Video Tape
Zingle Exhibit 5 (10/6/00)
“Typical Daily Load Curve”
of
Reliant Energy
Zingle Exhibit 6 (10/6/00)
“The Status of U.S.
Electricity
Deregulation”
Zingle Exhibit 7 (10/6/00)
Arthur Andersen’s “Impact
Analysis
Mallory Parcel –
Libertyville,
Illinois”
Zingle Exhibit 8 (10/6/00)
“Effects of the Proposed
Indeck
Facility on Property Values,
Land
Use and Tax Revenue”
Zingle Exhibit 9 (10/6/00)
August 15, 2000 letter from
Lake
County State’s Attorney,
Michael J.
Waller, to Kenneth L.
Larson
Zingle Exhibit 10 (10/6/00)
News Articles, beginning
with
“Ordinance Would Place
Provisos
on Peaker Plants”
Zingle Exhibit 11 (10/6/00)
“Business Overview –
Electrical
Generating Companies”
Sierra Club Exhibit 1 (9/7/00)
Testimony of Connie Sue
Schmidt
Dr. Thomas Overbye Exhibit 1 (9/14/00)
“Need for New Peaker
Generation
in Illinois” power point
presentation
Corn Products Exhibit 1 (9/14/00)
Testimony of Alan L. Jirik
Carol Stark (Stark) Exhibit 1 (9/14/00)
Testimony of Carol Stark
Stark Exhibit 2 (9/14/00)
Newspaper Article
Chicago Legal Clinic Exhibit 1 (9/14/00)
Petition to USEPA
requesting
revocation of the Nitrogen
Oxides
(NO
x
) waiver
Chicago Legal Clinic Exhibit 2 (9/14/00)
Testimony of Keith Harley
Link Exhibit 1 (9/21/00)
Statement of State Senator
Terry
Link
Lynch Exhibit 1 (9/21/00)
Comments of Tom Lynch,
Libertyville Township
Trustee
Kaiser Exhibit 1 (9/21/00)
Village of Wadsworth
Resolution
R130 and letter of December
21,
1999
Kucera Exhibit 1 (9/21/00)
Comments on behalf of the
Lake
County Public Water District
Lake County Exhibit 1 (9/21/00)
Testimony of Jim LaBelle,
Chairman Lake County
Board
Lake County Exhibit 2 (9/21/00)
Testimony of Sandy Cole,
Lake
County Board Member
Lake County Exhibit 3 (9/21/00)
Testimony of Bonnie
Thomson
Carter, Lake County Board
Member
Lake County Exhibit 4 (9/21/00)
Testimony of Gregory E.
Elam,
CEO of American Energy
Solutions, including power
point
presentation and Federal
Energy
Regulatory Commission
article
Lake County Exhibit 5 (9/21/00)
Lake County 2000 –
Legislative
Program
Eaton Exhibit 1 (9/21/00)
Testimony of Larry Eaton on
behalf
of Liberty Prairie
Conservancy,
Prairie Holdings
Corporation, and
Prairie Crossing
Homeowners
Association
Concerned Citizens of Lake County (CCLC)
Testimony of Chris
Geiselhart,
Exhibit 1 (9/21/00)
Chairperson
CCLC Exhibit 2 (9/21/00)
Comments of Richard
Domanik
during an April 25, 2000
hearing in
Libertyville, with attached
articles
Nesvig Exhibit 1 (9/21/00)
Testimony of E.M. Nesvig
Nesvig Exhibit 2 (9/21/00)
“Electric Power Monthly”
(July 2000 edition)
Nesvig Exhibit 3 (10/5/00)
Written testimony of E.M.
Nesvig
Nesvig Exhibit 4 (10/5/00)
Hard copy of Air Permit
Public
Hearing Presentation
(September 28, 2000) by
Elwood Energy II and
Elwood Energy III
Nesvig Exhibit 5 (10/5/00)
“U.S. Electricity Imports
and
Exports 1995–1999”
McCarthy Exhibit 1 (9/21/00)
Correspondence of William
McCarthy, PhD, regarding
proposed Libertyville plant
McCarthy Exhibit 2 (9/21/00)
Guidance for Power Plant
Siting and
Best Available Control
Technology
McCarthy Exhibit 3 (9/21/00)
“Catalytica” publication
regarding
“Xonon Technology”
Sargis Exhibit 1 (9/21/00)
Written comments of Mark
R.
Sargis (dated September 7,
2000)
Illinois Department of Transportation
October 5, 2000 letter from
James
Exhibit 1 (10/5/00)
V. Bildilli to Chairman
Claire A.
Manning
Gregory Exhibit 1 (10/5/00)
Written testimony of Brent
Gregory
Monk Exhibit 1 (10/5/00)
Written testimony of James
Monk
Monk Exhibit 2 (10/5/00)
“System Peak Load and
Capacity –
Historical 1990-2000 &
Projected
2001-2003
American Lung Association Exhibit 1 (10/5/00)
Joint Comments of the
American
Lung Association of
Metropolitan
Chicago and the Illinois
Environmental Council
Dorge Exhibit 1 (10/5/00)
Written comments of Lake
County
Conservation Alliance, with
attachments
Dorge Exhibit 2 (10/5/00)
“Peaker” Natural Gas Fired
Turbines – Permits Issued
Dorge Exhibit 3 (10/5/00)
“Peaker” Natural Gas Fired
Turbines Permits Issued –
PSD
Dorge Exhibit 4 (10/5/00)
Group of four exhibits,
beginning
with “Lake County
Conservation
Alliance written comments in
Carlton air permitting
proceeding"
APPENDIX D
R01-10 PUBLIC COMMENTS
1
Reliant Energy Power Generation, Inc. submitted by Cindy
Conte, Manager, State Affairs
2
Debbie Halvorson, Sentator, 40th District
3
Ron Molinaro
4
m Peter J. Cioni, Director of Community Development
5
Lake County Zoning Board of Appeals submitted by Bob
Mosteller, Deputy Director
6
Larry R. Eaton
7
Susan Zingle
8
Response to Questions of Charles E. Fisher
9
Agency Response to Questions
10
John A. Smith, Illinois State Water Survey
11
“The Status of U.S. Electricity Deregulation” submitted by Susan
Zingle, LCCA Executive Director
12
Gary Hougen
13
Robert Brooks
14
Amy Snyder
15
Gary A. Bellak
16
Sally J. Carr
17
Rollin and Sara Shaw
18
Paul and Cyndy Niles
19
Mike Miller
20
Bill O’Donnell
21
Wesley Landmeier
22
Lucille Landmeier
23
Julie and Curt Moon
24
Lester Landmeier
25
Joyce Landmeier
26
Jim Schindel
27
Diane Schindel
28
Joyce Sanders
29
Lawrence H. Robertson
30
Harold and Barbara Snyder
31
Curt W. Peters
32
Walter Quanstrom
33
Byron and Kristin Henn
34
Kris O’Donnell
35
John Geltz,
36
Brian J. Gelf
37
Veda E. Miller
38
Sheri and Keith Fitzgerald
39
Tim Geltz
40
Gail Geltz
41
Sue Andersen
42
Kenneth Andersen
43
Mrs. Arnold Nier
44
Gary Brigel
45
Jeanette Bower
46
James and Kelly Reuland
47
Linda J. Ott
48
Darrin J. Ott
49
Duane Rhoades
50
Steven R. Weissinger
51
William A. Thompson and Karen R. Thompson
52
Mary Backes
53
Ruth A. Brigel
54
Lisa Weissinger
55
Richard Pave
56
Marcia Lee
57
Leon Backes
58
Scott Ritter
59
Mr. and Mrs. Robert J. Krajecki
60
Dorothy Gum
61
Norman L. Curry, Fox
62
Mr. and Mrs. Jeffrey Berg
63
Doug Tuell
64
Jon and Lori Simon
65
David Young
66
Lynne B. Pave
67
Elaine Tuell,
68
Phyllis Pierson, Sugar
69
Margaret Kathleen McCrimmon
70
A. Gum, Big Rock, Illinois
71
Robert E. Pierson
72
Nancy Fayfar
73
Ronnie Simpkins
74
Kelly Salazar
75
“Sheila M. Simpkins
76
Patricia L. McKenzie
77
Wray V. McKenzie, Jr.
78
Marilyn Lasecki and Edmund Lasecki, Jr.
79
Patricia McBroom and Roger McBroom
80
Cheryl Romano and Thomas Romano
81
Dorothy Holland
82
Annie Buckmiller
83
Alice Hulka
84
Mary Copp
85
Patrick and Linda Barnes
86
Carla S. Miller
87
John and Carrie Loehmann
88
Helen LeBeau
89
James E. McCrimmon
90
Lynette and Dave Weidin
91
Jane Erdman
92
Frederick C. Runge
93
Julie A. Anderson, Elburn Illinois
94
(unable to read name) Elburn, Illinois
95
Ben Halls
96
Kathryn M. Hellwig,
97
Anita Sennett,
98
Gregory G. Goss and Jo A. Goss
99
William and Cheryl Oeser
100
Debra E. Raymond, Big Rock
101
Lawrence Von Ohlen
102
Ricky Gum
103
John Hellwig,
104
Diane M. Howard
105
Orville Howard
106
Rose Marie Diedesch and Bill C. Diedesch
107
Udo A. Heinze on Behalf of Ameren Corporation
108
Jeannine Kannegiesser, Center for Neighborhood Technology
109
Patricia Silva, Midwest Activities Coordinator, Natural Resources
Defense Council, Washington, D.C.
110
Illinois Municipal Electric Agency submitted by Ronald D. Earl,
General Manager & CEO
111
Association of Illinois Electric Cooperatives submitted by Earl W.
Struck, President/CEO
112
Verena Owen
113
Simon Klambauer
114
Peter and Dawn Roberts
115
Cathy Jo Magee
116
C. Beau and Sue Carlson
117
Richard A. and Mary C. LaFleur
118
Jennifer E. Johnson
119
William P. Fischer
120
Karen Yoeler
121
Bill Yoeler
122
Judy M. Hoffman
123
David R. Mag
124
Daniel Salazar
125
JoAnn I. Kline
126
Laurie Kazmiercek
127
Pam S. Wedeen
128
Ramona A. Kline
129
William F. Fline, Sr.
130
Jeff Hoffman
131
Ronald L. Burgess
132
Ed Whatley
133
Elaine and Harold Morris
134
James Scott
135
Lois Long
136
Dale N. Johnson
137
Elaine Fischer
138
Larry Hawhes
139
Cynthia S. Polfer
140
Mr. and Mrs. Mau
141
Ruth Pessina
142
Fritz Landmeier
143
Patricia and Joseph Heimonen
144
Elizabeth Simmons
145
Tom Pattermann
146
Sheela A. Faulkner
147
A. Denise Farrugia
148
Barry and Leah A. Morsch
149
Mary1 Hankes
150
Andy and Barb Kearns
151
Jackie Beane
152
Michelle Drauz
153
Marilyn Hannemann
154
Sandy Madden
155
James R. Kidd
156
W.R. Harmemamr, III
157
Mark and Lisa Spangler
158
Allen and Jeanette Krodel
159
Robert and Sharon Phillips
160
James Gasdiel
161
Mary Thurow
162
Margaret Bock
163
Midwest Generatin of EME, LLC submitted by Cynthia A. Faur
164
Commonwealth Edison company submitted by Christopher W.
Zibart
165
Joint Testimony of the American Lung Association of
Metropolitan Chicago (ALAMC) and the Illinois
Environmental Council (IEC) submitted by Brian
Urbaszewaki, Director of Environmental Health Programs,
American Lung Association of Metropolitan Chicago
166
Final Comments of Carol L. Dorge, Attorney on Behalf of the Lake
County Conservation Alliance (LCCA)
167
Illinois Energy Association submitted by James R. Monk, President
168
Illinois EPA Additional Comments submitted by Scott 0. Phillips,
Deputy Counsel
169
Sierra Club Woods & Wetlands Group submitted by Evan L. Craig
170
PG & E National Energy Group submitted by
Stephen Brick, Director, External Relations and
Evnironmental Affairs
171
Midwest Independent Power
Suppliers Coordination Group submitted by Freddi L.
Greenberg, Executive Director and General Counsel
172
Sierra Club, Illinois Chapter
173
Indeck Energy Services, Inc. submitted by
Gerald M. Erjavec, Manager, Business Development
174
Marvin and Eunice Gapinske
175
Ronald and Mary Jane Davis
176
Clifford and Gloria Sisko
177
Donald and Linda Czachor
178
Clara Arm Babel
179
Julie and Karl Kettelkamp
180
Audrey and David Boston
181
Suzanne Pyle
182
Terry and Sherilyn Sorensen
183
Donna Morris
184
Debra K. Galvan
185
Mr. and Mrs. Bradley Scott
186
Ersel C. Schuster, McHenry County Board, District 6
187
Illinois Environmental Regulatory Group submitted by Katherine
D. Hodge
188
Dr. Donna M. Lawlor and Lynn Hoeth
189
Concerned Citizens of Lake County & Liberty Prairie Conservancy
submitted by Dianne Turnball
190
Jim LaBelle, Chairman, Sandy Cole and Bonnie Thomson Carter,
Members of the County Board, Lake County, Illinois submitted by
Jim LaBelle
191
Marsha B. Winter
192
Ken Bentsen
193
Lois Scott and Burton Scott
194
Ralph N. Schleifer
195
Marci Rose
Appendix E
Thomas V. Skinner, Director
Illinois Environmental Protection Agency
1021 North Grand Avenue East
P.O. Box 19276
Springfield, Illinois 62794-9276
Brent Manning, Director
Illinois Department of Natural Resources
524
S. Second Street
Springfield, Illinois 62701-1787
Dear Director Skinner and Director Manning:
ILLINOIS POLLUTION CONTROL BOARD
6))))
Suuth
S cund St •
Swie
41)2 •
Sprm~)i ki. IL 6271)4
•
217 524
~5OU
•
x
2 7 ~24—S5US
October
25,
2000
On behalf of the Pollution Control Board, I am happy to present the
following information for the review of the Water Resources Advisory
Committee. While the Vonnahme-Park letter of October
5,
2000 to the
Committee seeks commentary in three assignment areas, these remarks focus on
“Assignment Number One”: the need for substantive changes in law or
regulation governing the usage of water in the State of Illinois.
In the June 6, 2000 press release announcing the establishment of this
committee, Governor Ryan explained: “I want this new committee to take a close
look at our water resources and specifically examine the impact of industry,
agriculture and population on Illinois’ groundwater and surface water supplies.
It’s important for us to look into the effects of our usage of our limited natural
resources.” More specifically, the Governor set forth the committee’s task as
follows: to focus on our water resources and its usage, including the effects of
peaker plants on groundwater and surface water supplies.
As all of you know, at the same time Governor Ryan created this
committee, he asked the Pollution Control Board to hold a series of Inquiry
Hearings concerning the potential environmental impact of proposed new natural
gas-fired peaker plants. Given the proliferation of these new facilities and the
expressed public concerns, he asked the Board to specifically address the issue of
whether further regulations or legislation is necessary to adequately protect the
environment. Pursuant to that request, the Board held seven days of public hearing (August
23-24, Chicago; September 7, Naperville; September 14, Joliet; September 21, Grayslake; and
October
5-6,
Springfield.) During those hearings, the Board heard testimony from over 80
individuals
--
representing a broad variety of interests: state and local government officials;
legislators; industry representatives, and concerned citizens. I have enclosed a list of those
persons who testified. The complete transcript of testimony for each hearing is available on
the Board’s Web site at www.ipcb.state.il.us.
While water usage was NOT the focus of these Board hearings, the issue of water usage
was nonetheless an expressed concern of many who testified. Since it is the function of this
committee to address those concerns, the Board has prepared a summary of all testimony
relevant to the issue of water usage. For review by this committee, I have attached that
summary. Especially important, I believe, is the testimony of local government officials who
seek greater regional or state regulation of the State’s precious supply of water.
For review of this committee, I have also asked Board staff to research the regulatory
framework of several other Midwestern states (Iowa, Indiana, Missouri, Minnesota, Ohio,
Wisconsin) as it concerns the use of water in each state. Interestingly, Illinois is alone in the
virtual absence of state controls or plans regarding the use of water.
Based upon the enclosed information, I believe it is time to focus the committee’s
attention on the development of a workable regulatory framework for the conservation and fair
allocation of water resources in this great State: one that meets the needs of all concerned
entities and citizens. I hope the enclosed information aids us in that important task. I look
forward to seeing you both at the next meeting of the Governor’s Water Resources Advisory
Committee.
incerely,
Claire A. Manning
Chairman
cc:
Renee Cipriano
Members of the Water Resources Advisory Committee
PERSONS TESTIFYING AT BOARD PEAKER HEARINGS
Chicago Hearings
August 23, 2000
1.
Charles Fisher, Executive Director, Illinois Commerce Commission
2.
Thomas Skinner, Director, JEPA
3.
Christopher Romaine, Manager, Utility Unit, Permit Section, Division of Air Pollution
Control, Bureau of Air, JEPA
4.
Robert Kaleel, Manager of Air Quality Modeling Unit, Division of Air Pollution
Control, Bureau of Air, TEPA
5.
Greg Zak, Noise Advisor, IEPA
6.
Steve Nightingale, Manager, Industrial Unit, Bureau of Water Permits Section, IEPA
7.
Rick Cobb, Manager, Groundwater Section, Bureau of Water, IEPA
8.
Todd Marvel, Assistant Manager of Field Operations Section and RCRA
Coordinator! USEPA Lialson/IEPA
9.
Brian Anderson, Director, Office of Scientific Research and Analysis, IDNR
10.
Derek Winstanley. Chief, Illinois State Water Survey, IDNR
August 24, 2000
1.
Gerald Erjavec, Business Development, Indeck Energy Services, Inc.
2.
Greg Wassilkowsky, Mauager, Business Developnient, Indeck Energy Services, Inc.
3.
Arlene Juracek, Vice President, Regulatory and Legislative Services, CornEd
4.
Steve Nauman, Vice President, Transmission Services, CornEd
5.
Deirdre Hirner, Executive Director, IERG
6.
Richard Bulley, Executive Director of Mid-America Interconnected Network
7.
Freddi Greenberg, Executive Director and General Counsel, Midwest Independent
Power Suppliers
8.
Michael Kearney, Manager, Economic Development, Ameren Corp.
9.
Richard Trzupek, Manager, Air Quality, Huff & Huff
Suburban Hearings
Naperville
September 7. 2000
I
Mayor George Pradel, Naperville
2.
State Senator Chris Lauzen
3.
State Representative Mary Lou Cowlishaw
4.
Mayor Vivian Lund, Warrenville
5.
Paul Hass, Zoning Manager, DuPage County Department of Development
Environmental Concerns
6.
Richard Ryan, President and Chairman, Standard Power and Light, Oak Brook
7.
Diana Turnball, Consultant to variety of citzen groups, private foundations and
businesses who have been in opposition to some of the peaker plants
8.
Carol Dorge, Attorney representing Lake County Conservation Alliance
9.
Connie Schmidt, Representative of River Prairie Group
10.
Mark Golf, Resident, Warrenville
11.
Cathy Capezio, Resident, Aurora
12.
Terry Voitik, Resident, DuPage County, and Founder of Citizens Against Power Plants
in Residential Areas (CAPPRA)
13.
Maurice Gravenhorst, Member, CAPPRA
14.
Lucy Debarharo, Member, CAPPRA
2
15.
Terry Voitik on behalf of Steve Arrigo, CAPPRA
16.
Susan Zingle, Executive Director, Lake County Conservation Alliance
17.
Beverly Dejovine, Representative, Citizens Advocating Responsible Environments
(CARE), Bartlett
18.
Cathy Johnson, Vice Chair, Rural and City Preservation Association (R&CPA)
19.
Chris Gobel, Member, CAPPRA
20.
Elliot “Bud” Nesvig
21.
Sandy Cole, Commissioner, Lake County Board
22.
Chris Gobel, Member, CAPPRA
Joliet
September 14, 2000
1.
Dr. Thomas Overbye, Associate Professor, Department of Electrical and Computer
Engineering, University of Illinois, Champaign-Urbana
2.
Alan Jirik, Director, Environmental Affairs, Corn Products International, Inc.
3.
Carol Stark, Director, Citizens Against Ruining the Environment, Lockport
4.
Susan Zingle, Executive Director, Lake County Conservation Alliance
5.
Keith Harley, Chicago Legal Clinic
6.
Elliot “Bud”
Nesvig
7.
Michael Shay, Senior Plamier Responsible for Long-Range Planning, Will Counly
Gravslake
SeDtember 21, 2000
1.
State Senator Terry Link
2.
State Representative Susan Garrett
3.
Tom Lynch, Trustee, Libertyville Township
3
4.
Betty Rae Kaiser, Trustee, Village of Wadsworth
5.
Daniel J. Kucera, Chapman & Cutler, appearing on behalf of the Lake County Public
Water District
6.
Jim LaBelle, Chairman, Lake County Board
7.
Sandy Cole, Commissioner, Lake County Board
8.
Bonnie Carter, Commissioner, Lake County Board
9.
Greg Elarn, CEO, American Energy
10.
i.arry Eaton, Attorney, on behalf of the I .iherty Prairie Conservancy, Prairie Holdings
Corporation, and Prairie Crossing Homeowners Association
11.
Toni Larsen, Resident, Zion
12.
Chris Geiselhart, Chairperson, Concerned Citizens of Lake County
13.
Diane Turnball, Representing Liberty Prairie Conservancy, Concerned Citizens of Lake
County, CARE from McHenry County, Bartlett CARE, and Southwest Michigan
Perservation Association
14.
Lisa Snider, Resident, Wadsworth
15.
Verena Owen, Co-Chair, Zion Against Peaker Plants
16.
Elliot “Bud” Nesvig
17.
Carolyn Muse, Resident, Zion
18.
John Matijevich
19.
Dennis Wilson, Resident, Island Lake
20.
Terry Jacobs, Resident, Libertyville
21.
Jim Booth, Resident, Newport Township in Lake County
22.
William McCarthy, Resident, Libertyville
23.
Susan Zingle, Executive Director, Lake County Conservation Alliance
24.
Barbara Amendola, Resident, Zion
4
25.
Mark Sargis, Attorney, working with citizens who have been concerned about peaker
issues
26.
Cindy Skrukrud, Resident, Olin Mills, McHenry County
27.
Paul Geiselhart, Resident, Libertyville
28.
Dr. William Holaman, President, Illinois Citizen Action
29.
Evan Craig, Volunteer Chair, Woods and Wet Lands Group of the Sierra Club
30.
Phillip Lane Tanton
Springfield Hearings
October
5.
2000
1.
Roger Finnell, Engineer. Division of Aeronautics, Bureau of Airport Engineering,
IDOT
2.
John Smith, Representative of Illinois Section of American Waterworks Association
3.
Brent Gregory, Representative of National Association of Water Companies, illinois
Chapter
4~
James R~Monk, President, Illinois Energy Association
5.
Patricio Silva, Midwest Activities Coordinator, Natural Resources Defense Council
6.
Brian Urbaszewski, Director, Environmental Health Programs, American Lung
Association
7.
Elliot “Bud” Nesvig
8.
Carol Dorge, Attorney representing Lake County Conservation Alliance
October 6. 2000
I.
Susan Zingle, Executive Director, Lake County Conservation Alliance
2.
Scott Phillips, Attorney, IEPA
5
3.
Kathleen Bassi, Attorney, IEPA
4.
Chris Romaine, Manager, Utility Unit, Permit Section, Division of Air Pollution
Control, Bureau of Air, IEPA
5.
Greg Zak, Noise Advisor, IEPA
6.
Todd Marvel, Assistant Manager of Field Operations Section and RCRA
Coordinator/USEPA Liaison/IEPA
7.
Steve Nightingale, Manager, Industrial Unit, Bureau of Water Permits Section, IEPA
6
Testimony and Comments Regarding
Use of Water by Peaker Plants
—
given to IPCB in
context of Peaker Plant Hearings
CHICAGO HEARINGS
Commonwealth Edison
—
Prefiled Testimony of Arlene A. Juracek and Steven T.
Naumann
Water
impacts, including with regard to any potential contamination and water
supply, are also carefully assessed during the planning and development of any
peaker plant. Stringent state requirements regulate the discharge of
contaminants while local authorities often directly oversee issues of water
supply. In addition, the impact of peaker plants and other facilities on water
resources and usage will be closely examined by Governor Ryan’s newly
appointed Water Resources Advisory Committee, which will present its
recommendations to the Governor by December 2000.
Midwest
Indenendent Power Sunuliers Coordination Groun
--
Prefiled Testimony of
Freddi Greenberg
While water usage will vary depending upon the specifics of the plant involved,
the simple cycle technology currently used for peaker facilities typically places a
small demand on water resources. For example, the owner of onepea.ker plant
located in Kane County advises that the plant consumes no more than
2.5
million gallons of water in a year. In comparison, the average golf course in
the Great Lakes region consume~sj almost 31,000,000 gallons of water in a
year. (Weathermetrics, Inc. 1999 website) MWIPS recommends that the
Pollution Control Board defer its consideration of the impact of peaker plants on
water resources so as to consider the report the impact of peaker plants on water
supply which will be issued by Governor Ryan’s Water Resources Advisory
Committee.
Indeck Ener~vServices. Inc.
--
Gerald M. Eriavec
Prefiled Testimony
To counter this effect, various methods are
employed to cool the inlet air and
increase its density. One such method is the use
of chillers; however, these
require power to operate and are sometimes counter productive. Another
method is called evaporative cooling, in which the air stream is passed over
water and the air is cooled through evaporation, much like perspiration cools the
skin, This cooling effect can be limited on humid days. While water
consumption varies based on temperature and humidity, an evaporative cooleron
a 300 MW plant will average about 40 gallons per minute (gpm) of water
consumption.
Even though these hearings are directed at peaking plants, the subject of
combined cycle plants is sure to come up, so a brief discussion of them is in
order. Simply put, a combined cycle plant adds a steam cycle to the process but
directing the hot exhaust gas from the combustion turbine through a boiler,
which generates steam to turn a steam turbine. Because more energy from the
fuel is recovered and used to produce electricity, combined cycle plants can be
as much as
50
more energy efficient tha~n “simple cycle” peakers; however,
they are not suited to peaking use because they cannot be brought on line
quickly enough to function as peakers. Combined cycle plants also have
increased water needs compared to peakers. The first use of water, in the steam
system, is minimal, about 25 gallons per minute in a system that has been
coupled to 300 MW of combustion turbines to create a 200 MW steam cycle.
Water can also be used to cool the steam after it passes through the steam
turbine. If water is the sole medium, up to 2,500 gpm can be consumed, which
may be significant in some areas. Fortunately, advances have been made in
cooling technologies so that this use can be greatly reduced or eliminated if the
situation calls for it.
Water consumption impacts were also compared against other enterprises and
found, in most cases, to be at the low end of the impacts.
Testimony at Hearing
Water consumption can vary by humidity and temperature. For example, on a
very humid day, you’ll evaporate very little water. So very little water will be
used. On a hot, dry day would probably be your maximum consumption.
Typical for, say, a 300 megawatt unit would be about an average of 40 gallons
per minute. It can range from about zero to 80, depending upon the
temperature and the humidity.
One of the things that’s a concern about this type of plant here is the water use,
and I would like to bring that up. The water use, there’s two places. Number
one, there’s water in the steam system going around this way. You have to
—
you get some trace contamination going in there. So you have to occasionally
blow it down. The steam cycle on this plant, this is based on putting a heat
recovery unit on the back of a 300 megawatt plant, would probably be about 25
gallons per minute, which is not a lot.
You can use about 2500 GPM, which can trend toward, depending upon where
you are, significant numbers.
Now, the good news is that there are other ways to attack this problem.
They’ve made significant advances in dry-cooling systems, which would not
require this water at all. There are some hybrid systems that cut down on the
amount of water use.
Water use, as ~Inoted before, when operating a typical 300 megawattpeaker
plant with an evaporative cooler uses a maximum of 80 gallons per minute, an
average of about
50.
Technology, the evaporative cooler generally is only used
above 60 degrees.
** *
What is
80
gallons per minute? Well, basically it’s the
equivalent
of 11 homes
watering their lawns at the same time. If you walk down the street and you saw
11 homes watering their lawns, you probably wouldn’t think anything of it. On
an annual basis, approximately the consumption of about 30 homes, 30 average
homes. Other water impacts that need to be considered are wastewater and
starmwater. Stormwater is captured on site.
Water consumption, a million gallons per year. Compare your 300 megawatt
peaking plant to a 50-home subdivision, a typical high school, or a retirement
home, a 200-bed medical center, or a 400-room hotel, way down at the low
end, I think my laser pointer is dying here, of water consumption.
IDNR
--
Testimony of Brian
Anderson. Director. Office of Scientific Research and
Analysis
In Illinois, except for withdrawals of water from Lake Michigan, thereis
extremely limited regulatory authorities associated with water withdrawals from
our other surface waters and from groundwater. It’s, therefore, more
appropriate to deal with water quantity issues in front of
—
in the context of
Water Resources Advisory Committee, however, we do acknowledge the
relationship between these issues and I have asked Dr. Derek Winstanley, Chief
of the Illinois Water Survey, to provide a concise summary of some of the water
quantity issues relating to peaker power plants.
Illinois State Water Survey,
IDNR
—
Testimony of
Dr. Derek
Winstanley, Chief of the
illinois State Water
Survey
One focal point that I do wish to make is that the discussion of peaker power
plants and the impacts on groundwater resources should be placed within the
context of all other water demands including those
for
combined cycle plants as
well as Illinois’ growing water needs for domestic, municipal, agricultural and
other industrial uses. We do need to look at total demands from groundwater
resources as a basis for sound water resource management. The water demands
from the peaker power plants vary widely depending upon plant design, their
intended use and the number of days of operation.
I would like to give you some examples of the quantities of water that may be
associated with operations of peaker power plants by putting that in context of
some other water uses. First of all, peaker power plants, and I am going to
focus on just a simple cycle power plant when I refer to the peaker power
plants, these are typically small producing a few tenths to a few hundred,
perhaps a thousand megawatts of electricity. They do not operate everyday of
the year. The typical period of operation is from perhaps 20 to 90 days per
year. The range of water use there is from less than 100,000 gallons per day to
about 2 million gallons per day. Translating that into an annual use that gives
us a range of from about 1.4 to 180 million gallons of water per year.
Turning to baseload power plants, which is combined cycle, these are obviously
much larger, typically generate maybe 500 to several thousand megawatts of
electricity and are intended to operate more or less continuously throughout the
year. They consume water within the range of about
5
to 20 million gallons per
day. Translating that to an annual water use, that gives us a range from about
1,500 million gallons per year to 6,000 million gallons per year.
So in context, the peaker power plants consume about a fraction of 1 percent to
about 3 percent of the water used by typical baseload combined cycle plants.
Another example of water use, municipal water use, and I give you data from
Champaign, Urbana, for context. Champaign, Urbana, has a population of
about 120,000 people, and they need that water supply regularly 365 days per
year. Champaign, Urbana, currently consumes about 20 million gallons per day
of groundwater, which translates into an annual use of about 7,300 million
gallons per year.
So to put the water use by peaker plant in context of a municipal use, a typical
peaker plant would use the same amount of water as between about 25 and
3,000 people, depending upon the nature of the peaker.
One concept that is important in examining not only peaker power plants but all
groundwater use is the concept of sustainable yields. And in my written
testimony, I refer to that as potential yield. Sustainable yield is a fairly diffuse
concept but generally, it tends to mean the yield of water that can be sustained
over the long term so that it can be used not only by the current population but
also by future
generations
and a yield that will have no significant impacts.
The determining sustainable yield is a complex scientific exercise that involves
consideration of variables such as rainfall, recharge rates, geology and impacts.
Impacts not only on existing wells, but on peaker systems and on stream flows.
4
The point here is that for most aquifers in Illinois, we do not have a very highly
accurate estimate of sustainable yield. We need much better scientific data and
modeling capabilities to be able to estimate sustainable yields.
Another important point is that aquifers themselves are not very sensitive to the
end uses of water. That is an aquifer doesn’t really differentiate whether a
million gallons of water is going to be used for drinking water or for peaking
power plants or for golf courses but the public often does differentiate among
those end uses and, I think, trying to incorporate the public values and
preferences into the equation on water resource management is an important
consideration as well as the actual amount of water used.
Water quality has been mentioned by people from Environmental Protection
Agency giving previous testimony. There are natural occurrences of various
chemicals in the groundwaters throughout Illinois. These lead to mineral
concentrations that can effect not only the operation of the peaker plants, but
also the discharges from the peaker plants. So the water quality also needs to be
considered.
In conclusion, I would like to make two points, one focusing exclusively on
groundwater, the other combining groundwater with surface water.
Focusing on groundwater, it’s important to recognize that in the use of
groundwater resources, all uses of groundwater, not just peakers, that we need
to consider the scale of the natural resource, that is the aquifer.
Groundwater typically is found in discrete squifers that transcends political
jurisdictions. They cut across municipalities, counties and even states.
Plumbing management by individual communities will not solve problems in the
long term, we need to take an aquifer-wide perspective. Beyond just
groundwater, I think that we need much more consideration of the conjunctive
use of surface and groundwater. There can be many efficiencies gained in water
supplying usage~by considering conjunctive uses of surface and groundwater.
So my bottom line is that I think Illinois would benefit from moving towards
ziiuch more comprehensive regional water resource planning and management.
This will bring together communities and cut across jurisdictions and we’d
—
much more appropriate to the scale of the natural resources, that is the aquifers
in the case of the groundwater supplies and river basins and water sheds for
surface waters.
Let me give you one example I think is an excellent model of what is going on
in one part of Illinois and that is in central Illinois. We have a major aquifer,
the Mahomet aquifer, that extends from the Illinois River across to Indiana,
5
which embraces 15 counties. Now, in the past couple of years, the local
communities in that 15 county area have bonded together to form what is called
the Mahomet aquifer consortium and they’re collectively concerned about the
future of their own water resources, want to better characterize those resources
and opportunities as a basis for self-management to the water resources. So, I
think, on the one hand we may need new laws, regulations, but I think we also
need to encourage local communities to attempt to solve their own problems.
IEPA
—
Prefiled Testimony of Richard
P. Cobb. Mana2er of
the
Groundwater Section of
Bureau of Water
However, the few Illinois court decisions since the enactment ofthe Water Use
Act have interpreted that “reasonable use” for groundwater does not restrict the
use of groundwater except from malicious or wasteful purposes of the user.
Concurrent with the requirement for these hearings, Governor Ryan, by
Executive Order, established a WaterResources Advisory Committee. The
committee’s task will be to focus on our water resources and its usage,
including the effects of peaker plants on groundwater and surface water
supplies. The committee will also examine the various economic and social
issues related to energy producing facilities and water use in Illinois and present
recommendations for action to the Governor by December 2000. I plan on
attending this committee’s first meeting on August 31, 2000.
IEPA
—
Prefiled Testimony of Christonher Romaine. Manager of the Utility Unit in the
Permit Section of Division of Air
A key factor in the design of a peaker plant is the capability to maximize the
power output of the plant to be able to meet peak electric power demand. This
leads to a number of variations on the basic simple cycle turbine, all due to the
scientific fact that the power output of a gas turbine varies based on the density
of the air being used in the turbine. The denser the air, the more air that can be
pushed through the turbine and the higher the power output. This means that in
the absence of any adjustments, the output of a given gas turbine will be
significantly less on a 90°Fday in July, when peak power is most likely to be
needed, than on a 20°Fday in January. To correct for this phenomenon, the
modem simple cycle turbines used in peaking plants are routinely equipped with
devices to cool the air going into the turbine. While it may appear
counterproductive to cool the air in a turbine before heating it, cooling the air
allows more air to be handled by the air compressor, thereby allowing more fuel
to be burned and increasing the power output of the turbine.
Gas turbines can be equipped with several different types of air cooling systems
that vary in the effectiveness with which they can cool the inlet air to boost a
gas turbine’s power output. In the simplest system, water is injected directly
6
into the incoming air to cool the air by evaporative cooling. Clean
demineralized water must be used to prevent excess build up of scale or erosion
of the blades in the air compressor of power turbine. In more advanced
systems, water may also be injected at a point in the air compressor itself. The
inlet air may also be cooled by indirect systems in which the air passes through
cooling coils. In this case, water may still be used in an open cooling tower
where evaporation of water is used to dissipate the heat generated by a
mechanical refrigeration unit. Alternatively, a dry cooling system may be used
in which the heat generated by a refrigeration unit is dissipated to the
atmosphere by dry cooling towers or radiators. The more complex the cooling
system, the greater the amount of energy that is consumed in its pumps and
compressors, which accounts for some of the increase in power output.
Another approach to boost power output of a gas turbine is to inject clean water
of steam into the burners or to inject steam after the burners. All these
measures increase the gas flow through the power turbine and thus increase its
power output. Because fuel must be burned to evaporate the water (either in the
turbine itself or in a separate boiler to make steam), these measures to increase
power output are accompanied by a loss of fuel efficiency by a gas turbine.
NAPERVILLE HEARING
Connie Schmidt, Representative of River Prairie Group
DuPage County is so close to Chicago, one would think it is very urban. I
myselfhave a well and septic on my property and I am incorporated. I live
within the city limits of Warrenville. So it is not totally unusual
—
and all my
neighbors do because we don’t have city water in our neighborhood. So the
groundwater use as well as what happens to it after it’s been used, I think, is a
realistic concern in our area.
Mark
Goff.
Resident, Warrenville
So obviously well water is a concern.
Lake
Coun~Conservation Alliance
—
Testimony of Susan Zin2le. Executive Director
A lot of people have talked about water supply. Some of the peakers do use
vast amounts of water. Some of them as much as a combined cycle plant
We’re looking at Zion is going to use over 200 gallons (sic) a day. That’s as
much as the entire city of Zion in itself. McHenry and parts of Wisconsin draw
on that same aquifer. How can Woodstock and Zion even be aware of each
other’s plants let alone determine which of the two plants is built if either.
Water supply is not a local issue
7
Rural and City Preservation Association (.R&CPA~.Cathy Johnson, Vice Chair
The water issue, which is a major one in Mdllenry County, is barely even
considered in the new standards. A new peaker plant has to only respond to
how the water it uses affects the area one-quarter of a mile around the plant.
This is ridiculous. This standard isn’t there to protect us.
JOLIET HEARING
Corn Products Internal. Inc., Alan Jirik. Director. Environmental Affairs
With regards to cooling water consumption, our plant currently takes water
from the Sanitary and Ship Canal. The water is used for non-contact cooling
purposed for the corn wet milling operating and then returned to the canal
-
In a
clever and environmentally friendly approach, we plan to use the existing
cooling water flow to supply cooling water io the new cogeneration operation.
We
accomplish this by routing an additional loop from our existing cooling
water line to serve the cooling needs of the cogen. After servicing the cogen,
the water will return to our existing line and be discharged the same as it is
today. Thus, the project will not increase our current water withdrawal and will
not result in any new water discharges, any new intake or outfall structures, or
cause any other disruptions to water bodies, water tables, groundwater, aquifers
or burden the community drinking water supply.
Citizens A2ainst Ruining the Environment. Lockport.
Carol Stark, Director
and
Exchan2e
with
Board Member Kezelis
We. also have information that states the aquifers located on this
site
are joined
together. This is the first of our concerns. The fact that the aquifers, our water
supply, could be affected by this peaker using thousands of gallons a day is not
a comforting
thought.
Board Member Kezelis: Ms. Stark, do you know what the source of your
public water supply is in Lockport?
Ms. Stark: We do
-
Board Member Kezelis: Is it the aquifer?
Ms. Stark: Yeah. We do have
--
and then there are some people that are on
wells, but yes, it’s the aquifer. We have never tied into Lake Michigan water.
8
Will
County,
Michael Shay. Senior Planner Responsible for Lon2-Ran2e Plannin2 and
Exchange with Chairman Manning. Board Members Flemal. Girard. Kezelis and
McFawri
The largest thing that we found that concerned us was that Will County’s
aquifer reserve water is about 66 million gallons a day. That’s how much we
have
—
it’s currently recharging
--
that we could use for water supply. We
contacted several facilities and went on several industry websites and they said
five
to 12 million gallons a day per facility for a combined cycle facility and
roughly a million gallons a day for a simple cycle facility.
So we contacted some of them that actually started operation in Will County,
including the one that you visited today. We arrange tours. On our
tour, we
found out they’re actually planning
—
or they were planning for an expansion
and this comes to a key point that I’d like to discuss today. There was
discussion earlier about separating simple and combined cycle plants. We do
not think you can separate those two facilities.
Simple cycle facilities are designed and physically organized to be converted to
combined cycle facilities down the road and that plans that we received as we
reviewed these petitions explicitly and clearly state that; that they are designed
to be converted or added Onto at a later date. So we do not want to see those
two issues separated at all.
So they
--
we get into more discussions with them and they say 16 million
gallons a day for one of the facilities which we visited, which means that four
such facilities of which there are already that many could eat up the entire
reserve water capacity for Will County. We are not likely to get more lake
water. River water is another issue altogether regarding quality of our water.
So when you add that to the fact that we are the fastest growing
—
numerically
growing county in Illinois and also the fastest in the sunbelt, we see a problem
for a collision between growth and these facilities for that resource.
We are also concerned
--
when we continue to do our research, we said, that’s a
lot of water to draw from one facility. How do you get that? Well, they drop
wells in the aquifer obviously and they pull it up at such a rate that it creates a
drawdown. It creates a reverse cone or a cone of water supply and
the radius
on that for a facility of the magnitude that we were discussing is six miles
drawdown, 300 feel drawdown at the point of the well and still 35 to 50 feet of
the six-mile radius.
..
. .
Will County has thousands and thousands of wells; residential, industrial or
group wells. We’re concerned about well failure because we continue to place
9
these facilities over time and if they’re to be converted to combined use
facilities.
Board Member Kezelis: I have a question. I, too, hope to be brief, Mr. Shay.
That status of the suggestions that you and the planners for Will County propose
to your board, what is the current status?
-Mr. Shay: Well, we have a first set of regulations in place. We re currently
discussing the second set of-- we’re researching and discussing the second set.
If I had to provide a guess, which bureaucrats despise doing, but I will do
nonetheless, I would suspect that they will prohibit the use of aquifer water for
electric generation.
Board Member McFawn: Is the only industry that you’re concerned about the
drawdown well or is that general a concern?
Mr. Shay: It’s the only industry we know of that draws that amount that
quickly. We can’t find another that draws from the aquifer at that rate, but
we’re unaware of one that draws at that rate.
Let me illustrate this real quickly. When you’re talking about 16 million gallons
a day, that means that three of those facilities could put a pipe on the end of the
Fox River in St. Charles and the river would end while it was in operation.
Chairman Maiming: Where did you get those figures in terms of the drawdown
effect and how much water is actually being used by these facilities?
Mr. Shay: We got from the-- well, we got the information on flow and amount
of the aquifers and reserve capacity from the Illinois Water Survey. They
regularly publish those statistics and we acquired them from them and then we
acquired numbers on the use actually directly from the industry itself.
The engineers who built the Elwood plant, we
--
our land use and zoning
committee and planning and zoning committee visited those facilities. In those
discussions, we asked them about water use and they gave us very frank
answers on that. The number that they gave us came out to 16 million gallons a
day and we confirmed with them that that was
an
accurate assessment. So we’re
fairly confident of those numbers.
Board Member Kezeiis: Mr. Shay, what’s your
understanding
about the
Elwood facility; single or combined?
Mr. Shay: My understanding is that it is currently a single cycle plant that the
two additional
--
the Elwood two and Elwood three will also be simple cycle.
to
All three of those phases, though, are designed to be converted to combined
cycle should they wish to do so.
Board Member Kezelis: So the 16 million gallons per day
--
Mr. Shay: Would be if they became a combined cycle. They are not currently.
They do have a well, but it’s comparably small.
***
Board Member Girard: Mr. Shay, if Will County passes an ordinance that
prohibits the use of aquifer water or electrical generating facilities, would that
also apply to a facility that tried to site itself inside a municipality in Will
County?
Mr. Shay: No. That’s why we’re concerned about jurisdiction hopping, but it
would also cover a number of the intersections of pipelines and transmission
facilities.
Board Member Flemal: One of the things that this board may see it necessary
to do ultimately in our decision here is to address the issue of how much local
and how much regional or state level oversight there ought to be in the siting of
these facilities.
We’ve heard quite a range of perspectives from it should be entirely in the
hands of the locals with the facility to what I think I heard you say that there
should be a strong top-down oversight on the plants.
First off, have I characterized where you’re coming from correctly?
Mr. Shay: Okay. I would like a strong state or national presence on the issue
of drawing from wells.
Board Member Flemal: Soley on that issue?
Mr. Shay: And issues that affect cross-jurisdictional
--
an aquifer doesn’t make
a jurisdictional boundary. It could go across several counties and several
municipalities, et cetera. Well, local authorities, because we are competing for
economical development efforts and because of the nature
of
the politics
between them, are often played against each other by the private industry
Board Member Kezelis: Mr. Shay, the water use, as you know, is not
something
that we
are
to address. The Governor has
appointed the water
commission to address water use for the state. Nonetheless, your reference to
the water use a few moments ago, I needed clarification of.
It
You indicated that approximately 16 million gallons per day would be used by a
combined peaker facility and that the drawdown for such a facility would impact
roughly a six-mile radius, is that correct?
Mr. Shay: That’s correct, according to the information we have from the
Illinois Water Survey
Board Member Kezelis: So you received that information from the Water
Survey itself?
Mr. Shay: Yes. We got it off their website. They have a very graphical
explanation.
GRAYSLAKE REARING
Testimony of State Senator Terry Link
Since the effect of peaker power plants, air quality, water supply, natural gas
supply, noise, taxes, are felt regionally, not just locally, I believe we must take
a regional approach in regulating the pearkers.
Testimony of State Representative Susan Garrett
Our aquifer is on the verge of being mined. We are concerned for our long-
term water supply. We need to resolve this.
Testimony of Sally Ball on behalf of State Representative Lauren Beth Gash
Our friends and neighbors are understandably worried about the impact of so-
called peaker plants on air quality and water supplies.
Appearin2 on behalf of the
Lake
County Public Water District, Daniel J. Kucera.
Chapman & Cutler and Exchange with Board Member Kezelis
Now, the term peaker plants is a misnomer because it implies an
oversimplification. The types of electric generating facilities being proposed
throughout the state, and which are raising environmental concerns for many
people, are both base-load plants and peak-demand plants. The environmental
impact issues raised by such plants, including water use, differ only in
magnitude.
In addition, these plants can be both simple cycle and combined cycle.
Accordingly, demand for water and resulting environmental impact of that
demand can vary according to the type of plant. Clearly, a combined cycle
plant, which uses steam to generate a portion of its electricity, can be expected
12
to use more water than a small simple-cycle plant, which uses water only for
cooling.
A witness for the Illinois State Water Survey in these proceedings, Mr.
Winstanley, has testified that simple-cycle peaker plants can use up to 2 million
gallons of water per day. And combined-cycle plants can use
5
million to 20
million gallons per day.
Presently with very limited exception, there is no permitting process or
regulatory oversight over the uses of water by peaker plants. Witnesses for
IEPA in these proceedings have acknowledged that IEPA currently has no
jurisdictional responsibility over peaker plant water use.
A public water supply providing Lake Michigan water to a peaker plant would
have to have a sufficient allocation from the Department of Natural Resources to
enable it to supply peaker plant demand.
-
The Illinois Water Use Act of 1983,
525
ILCS
45/
et seq.,
was cited by one of
the IEPA witnesses in this proceeding. Section 5 of the Act does provide that a
land owner who proposes a new well expected to withdraw over 100,000
gallons per day must notify the local soil and water conservation district. The
district is then to notify other units of local government whose water systems
may be impacted. And the district is to review the impact and make findings.
However, the statute provides no enforcement mechanism.
Moreover, this provision does not even apply to the region governed by
diversion and allocation of Lake Michigan water under 615 ILCS 50/1
et seq.
The Water Use Act states that the rule of reasonable use does apply to ground
water withdrawals, but it does not provide supporting, permitting
or regulation.
As to the need for permitting and regulator oversight, I would first address
Lake Michigan water. Lake Michigan is a valuable and limited domestic water
supply resource. It is valuable because in northern Illinois lake water is
perceived to be superior to ground water.
Aquifers in the region commonly contain high levels of iron, manganese and
other constituents which raise esthetic issues and which can require costly
treatment facilities Deep wells often contain high radium or alpha-particle
contents.
Further, in portions of northern Illinois, water levels in the aquifers have
diminished and some deep wells have been mined into salt water.
Obviously, there is a great demand for lake water to provide the domestic
water supply for as many communities as possible. However, Lake Michigan
13
water is a limited resource because of legal limits on how much water Illinois
may withdraw.
Accordingly, the use of Lake Michigan water by peaker plants
for cooling, steam production or even as backup to ground water for these uses
should be limited or even prohibited.
As to ground water, because peaker plants can be heavy users of ground water,
upwards of several million gallons per day, there should be regulatory
oversight over such uses. In particular, the potential effects upon aquifers and
ground water domestic water supplies should be evaluated as part of the
permitting and regulatory process. Mr. Winstanely has well stated the issues
in his testimony in this proceeding.
It is also important to point out that the ground water is a limited resource in
certain portions of the state. For example, in parts of central Illinois ground
water is extremely limited, even for domestic water supplies and, of course,
aquifers in northern Illinois have been subject to diminishment.
Finally, other surface water, needless to say where a peaker plan may withdraw
water from a stream or inland lake, the impact of such withdrawal also could
be evaluated. For example, it could reduce the resource value of the water
body for domestic water supply, aquatic life or recreation.
There are now some additional water issues that I would like to bring to your
attention, one of them is decommissioning.
For example, if a plant is terminated, who will be responsible for resulting
excess capacity in the local public water supply? Who will be responsible for
capping the plant s wells? Who will be responsible if leakage from the plant
has contaminated the source of supply for the local water utility or for
individual residential wells? Where is the accountability when these plants are
closed down?
It would seem appropriate to enact a decommissioning procedure to protect
water sources and the public when these plants are removed from service. At
the very least, there should be a procedure for a state administered trust
account, which peaker plants would be required to fund, to assure remediation
and restoration funds will be available if plant owners abandon plants without
protecting water resources.
Another possibility is a requirement that a surety bond or letter of credit be
posted to
secure the obligation to
protect
water
sources.
-
Another issue is competition. Public water supplies can be expected to remain
a highly regulated industry so as to continue to assure safe drinking water for
the public. Unlike other utility functions, public water supply is not likely to
14
be deregulated or to be subject to the competitive marketplace. The investment
in water infrastructure per customer far exceeds the comparable investment for
other utilities. This investment in water infrastructure will only continue to
increase under the Sale Drinking Water Act amendments as new requirements
are proposed. Redundant water systems do not make sense.
It is important, therefore, that electric generating plants not be permitted to
engage in helping to finance new public water supplies which may compete
with existing public water supplies. Such predatory competition could deny
customer the benefits of economies of scale.
Another issue we believe is siting. Presently siting of electric generating plants
is considered to be a local issue. However, there may be siting concerns of a
broader interest, as related to water use. Recent proposals indicate multiple
peaker plants in close proximity to each other. What is the impact of multiple
draw-downs on an aquifer at a particular location?
Another concern relates to soil conditions at a proposed site. How vulnerable
are site conditions to a contamination spill? Could a shallow aquifer be
adversely impacted? Presently, there is no regulatory oversight of these siting
issues.
Finally, cross-connection. When an electric generation facility is partially
served by a public water supply and partially served by the facility’s own
wells, there must be assurance that no cross-connections will exist. For
example, the public water supply may provide water for domestic use and fire
protection, while the facility uses its own wells for process water. However,
the public water supply might also provide backup in the event the wells are out
of service.
Local governments may not necessarily have the staff with skills to constantly
monitor for cross-connections in generating plants. Indeed, it is not clear that
they ever would have access to the plants. Who then will be responsible for
policing for cross-connections and protecting the public water supply?
The District understands that the Governor’s water advisory committee may be
considering waLer issues related to peaker plants. We are not aware whcther
that committee is soliciting public comment. Therefore, we believe it is
important that the Pollution Control Board in its report to the Governor include
water issues related to peaker plants discussed in the testimony and comments
submitted in
this proceeding.
In conclusion, we suggest that the Illinois legislature should adopt a permitting
of regulatory oversight requirement for process water used by all electric
generating facilities, including both base-load and peaker plants
15
***
Board Member Kezelis:
I
just have a question. Can you
for
the record tell
us
what your rate of capacity is and roughly how many gallons per day your
customers do take?
Mr. Kucera: Our peak day capacity is 6 million gallons per day. I think iii
actuality the customers average between 3 and 4 million gallons a day.
Lake
County Board. Jim LaBelle, Chairman
The process should not only consider air quality but also other environmental
factors such as water consumption impacts on aquifers or Lake Michigan water
allocations.
In addition to the JEPA considering the polluting impact of multiple plants, the
Department of Natural Resources and the ICC need to consider the impact on
ground water resources, natural gas availability and pricing impact if numerous
peakers operate at the same time.
The high volume of ground water usage can lessen the supply for any other
entity tapping the same aquifer.
Lake
County Board. Sandy Cole, Commissioner
Tn addition to air quality, peaker power plants may affect the region’s water
supply as they need to draw significant amounts of water from Lake Michigan
or local aquifers.
Lake County Board. Bonnie Carter, Commissioner
The village of Island Lake was being
asked to
annex the land. The plant
proposed for the small community on the far western edge of Lake County was
not a peaker plant. The plant was proposed to provide base-load power year
round with ground water usage of 4 to 8 million gallons daily.
Local officials, myself included, and concerned citizens began investigating the
issues surrounding the type of power plant involved. Many issues such as air
quality, noise and lighting were raised. Water usage was by far the most
overwhelming environmental concern. While gathering information, I became
well acquainted with the work of the Illinois State Water Survey, a division of
the Department of Natural Resources and an affiliate of the University of Illinois
at Urbana-Champaign. According to data assembled by the ISWS, the volume
of water required to supply the proposed plant for a year would have been far
greater than what was required for the village’s entire population.
16
I further learned that neither the Illinois Environmental Protection Agency, nor
the ISWS or any other state agency had any authority limiting ground water
withdrawal. The proposal for the Island Lake plant was eventually withdrawn
and most of the subsequent plant proposals in Lake County are forpeakers, not
base-load. This, I feel, is a direct result of the hightened awareness of the water
withdrawal issue and how precious a resource water is. Though the issue of
water usage is not as critical with peakers, it is still significant enough to
warrant scrutiny.
In February 1999 I drove to Springfield with my two constituents who had
originally brought this issue to my attention. We met with IEPA Director Tom
Skinner, officials from Storm Water Management, Illinois Department of
Natural Resources, Fish and Wildlife, the IEPA Bureau of Water, the IEPA
Bureau of Air and two state legislators. We expressed our deep concerns with
the permitting process of a 90-day review on construction applications, the lack
of regulatory authority over ground water withdrawal and the lack of public
hearings. We also discussed air quality impacts along with the noise and
-
lighting.
We all felt that the JEPA directors and supervisors that sat among us were
frustrated with having to review permit applications without being able to take
the regional impacts of these plants into consideration. They agreed that a
regional element should be included in the review. We were surprised and
shocked to learn that each division did not review the applications together.
One division follows the application approval process after the other division has
completed its work. They may never have been aware of the combined impact
on adjoining property owners or cumulative environmental impacts. In other
words, they didn’t talk to each other.
After we left Springfield that day, some minor changes did take place. The 90-
day review process was reversed back to 180 days. Public hearings started to
take place on applications and the IEPA Director Skinner never forgot us in
Lake County.
As you may see, we are still dealing with this issue today and we are still very
frustrated. I hope and pray we will all be heard today and that, as a result, you
recommend improvements, not only to the process, but to help reduce the
negative impact power plants could have depending on where they are sited.
As with many of the issues surrounding peaker plants, it is important to
recognize that ground water is a regional issue. It is also important to recognize
while one peaker plant may not threaten a region’s water supply, multiple
peakers may. Aquifers do not end at municipal or political boundaries. The
water consumed in one village not only limits the supply of its immediate
17
neighbors, but impacts the supply of further villages, commercial wells and deep
community wells which draw from the same aquifer.
In the case of the Island Lake proposal, adjacent villages would have realized
significant financial impacts. Nowhere in the permit application process
submitted by the applicant were those impacts acknowledged or addressed. One
neighboring village, the village of Wauconda, would have incurred expenses
close to $1 million to reset the pumping well head in two municipal wells. The
taxpayers of this neighboring village, not the power company, would have borne
this expense, $1 million. This village had no opportunity to voice its concern
during the application review. Surely, this demonstrates why a regional
application approach must be in place, must be put into practice.
Determining the amount of water available for peaker use as well as all other
users is a significant undertaking for any local community. Dr. Derek
Winstanley of the ISWS in his written testimony to this Board wrote of the
expense of collecting ground water data. Conducting a study to determine the
sustainable level of water usage for Lake County is estimated to be a multi-
million dollar project. To expect local communities to shoulder this burden is
unreasonable. Yet without regional data, a single community cannot make an
informed decision on water supply.
-
At the August 18th, 1999 meeting of the Lake County Public Works and
Transportation Committee, Illinois State Water survey Director Dr. Derek
Winstanley reported that around the year 2030, Lake County will maximize its
water use. Today, we are at the maximum sustainable level of the northeastern
Illinois deep bedrock. We cannot continue to increase withdrawals from the
deep aquifer. Water demand is up 20 percent, and we are at the point where
supply and demand are beginning to conflict.
Another large source of water for the Lake County area is Lake Michigan.
Here again, the County’s usage impacts the supply of other counties and states.
The supreme court fixes allocations. Local governments do not have an
endless supply.
Peaker plants will either draw ground water, which will have an impact on
neighboring wells, or draw on Lake Michigan water that has already been fully
allocated. Clearly this issue needs to be understood and addressed.
The quality of water will also be impacted by extensive withdrawal. Research
has shown that when too much water
is pumped, surface
waters can be
impacted. Water availability to stream beds, wetlands and lakes can decrease,
and the quality of the existing water may be threatened. Eventually, animal and
plant life will be threatened. Since the technology exists to convert peaker
plants to combines plants at any time, peakers should not be considered as a
18
minor use, but rather as a major use with regional impact. I would suggest that
all applications should be specific as to whether they are peaker or base-load.
Applications for peakers should question the intention toward possible future
conversion to a base-load.
Allowing one industry that provides a very few number ofjobs to have
unlimited use of our water supply impacts the economic growth in communities
where other industries also require water.
Officials in Lake realize that it is not only peaker plants that threaten our water
supply. Development of any kind, whether residential, commercial or industrial
will place an additional burden on limited resources. County officials further
realize that electricity may be one of the resources in short supply. However,
our analysis of the realities of peaker power plants and the marketing of power
do not convince us that peaker plants located in Lake County will alleviate a
power shortage in Lake county. We feel we are being asked to give up one
precious natural resource with no guarantee that the sacrifice will realize a
benefit for the county’s citizens.
The Water Use Act of 1983 and the Water Authorities Act do not give counties
the authority to regulate ground water withdrawal. A plan that regulates major
aquifer draw-downs is needed. The Lake County Board recommended
legislation to do just that. It is believed that there is support from state agencies
to clarify regulatory authority for ground water withdrawal. These initiatives
are included for your review.
-
The state needs to determine what the reasonable use is. I finally realize that the
IPCB does not have the authority to regulate ground water withdrawal. I have
the pleasure of being a member of the Water Resources Advisory committee that
was recently initiated by Governor Ryan. This issue will be covered in this
committee and our recommendations will be made to the Governor in
December. I feel it is imperative to point out that we need to share our
expertise with all governing state agencies in order to be better equipped to
make decisions involving, the power industry. It is too complex an issue for one
agency to comprehensively see all facets. I believe that the Pollution Control
Board, the ICC, the IEPA, the ISWS also all need to support each other and
work together. We need a regional cooperative group with regulatory authority
when reviewing applications.
The Lake County Board has made a decision last year to be proactive and not
reactive. Our actions support that position. I ask you to support this board and
the people of Lake County by doing the same. Place a moratorium on all
-
pending and new applications for power or peaker plants until such time as all
agencies have collaboratively worked together reducing and/or eliminating- the
19
negative impact to our quality of life. Thank you, Chairman Manning and the
IPC
Board.
Toni Larsen. Resident, Zion
In the Zion area, there are at least five pending permits which will be licensed
separately for future plants. I believe all facilities within Lake County need to
be evaluated regionally to assess the cumulative effect. One of the sites is in
Zion and it is zoned industrial, although most of the neighboring properties are
not in Zion.
These neighboring communities have no say what goes in their backyard.
These communities get their water from wells. One of the proposed peaker
plants plans on drilling an industrial well. This plant can use up to 2 million
gallons of water a day. I believe that needs to be more study on ground water
supply issues.
-
Concerned Citizens of Lake County. Chris Geiselhart, Chairperson
There is a potential drawdown of hundreds of thousands of gallons of water
from Lake Michigan, which already exceeded water usage for the mining of
deep well aquifers as sources of water for these facilities.
Zion A2ainst Peaker Plants, Verena Owen. Co-Chair
Environmental impact studies for peaker plants are required by other states, for
instance, Wisconsin, Indiana and Ohio. The environmental impact studies
should contain at a minimum hydrology and water quality, water usage, waste
water, water run-off and potentially polluted run-off containment, air quality,
biology, loss of habitat, loss of agricultural land, land use and community
character, archaeology, socioeconomic impact, visual
impact, impact on
local
services, traffic, noise and public health and safety.
Jim Booth. Resident.
Newport Township in Lake County
Upon investigation, I learned that the city of Zion, who purchases their water
from the Lake County Public Water District had exceeded its 822.345 million
gallons of Lake Michigan water by 22 million gallons. They purchased 844
million gallons from the Lake County Water District in the period May 1999
through April of 2000.
Zion, of course, is consideringi the peaker power plant, which would use a
maximum peak of 2.124 million gallons of water per day when they are
operating their five turbines. And they divide this by
365
days a year, of
course. And that would run 230,000 gallons per day. Unless Zion files and is
20
awarded an increased allocation of Lake Michigan water, they cannot serve my
business nor can they serve the proposed peaker plant.
The state of Illinois is in debt to Canada for exceeding their Lake Michigan
water allocation. This debt is to be repaid by 2019. I assume you are familiar
with that. For 20 years, Illinois took more than their allotted amount of water
out of Lake Michigan, and now they have to pay it back. The bottom line is
that there is less water to be divided among the municipalities, 177 or so, that
use Lake Michigan water.
But the peaker power plant has an alternative which I do not have. They can
drill wells and tap into the Ironton Galesville Sandstone Aquifer.
Circular 182 from the Illinois Department of Natural Resources Water Survey
by Adrian A. Zuchowski addressed the water level trends and pumpings into
the deep bedrock aquifers in the Chicago region in the period 1991 through
195.
On page 15 he wrote that Schiect in 1976 estimated that the practical sustained
yield of the deep bedrock aquifers regardless of the scheme of well development
cannot exceed
65
million gallons a day.
-
The practical sustained yield of the deep aquifers is defmed as the maximum
amount of water that can be withdrawn without eventually dewatering the most
productive water yielding formation, that is the Ironton Galesville Sandstone
Aquifer.
In a fax dated August 15th of this year, Mr. Scott Meyer of the Illinois State
Water Survey faxed me and said I recently estimated deep bedrock withdrawals
in that area, referring to Zion, at about 71 million gallons a day That is 6
million gallons above the practical sustained yield.
The point is this. One peaker power plant drawing 230,000 gallons per day
from the Ironton Galesville Sandstone may not seem overly significant. But it is
reported that there is some
55
peaker power plants proposed in the state of
Illinois. How many will be drawing water from the Ironton Galesville
Sandstone aquifer in the eight-county area?
Now, the survey that I referred to, the circular 182 involved water being taken
from the following eight counties: Cook, DuPage, Grundy, Kane, Kendall,
Lake. McHenry and Will. Now, five plants the size of the proposed Zion plant
would draw 1,150,000 gallons of water per day from that aquifer. For 20
months plants would draw 4,600,000 gallons per day average, but at peak
would draw 42 million gallons in one day. Now, this is out of an aquifer that
can only sustain 65 million gallons and is currently being drawn at 71 million
gallons.
-
21
The former state senator and minority leader Everitt McKinley Dickson once
said after attending his first budget meeting, a billion dollars here and a
billion
dollars there, and pretty soon it added up to some real money. The same thing
is true of the peaker power plants and their great appetite for water.
I ask you to consider the following questions. Should quality Lake Michigan
water by used for peaker power plants or should that be reserved for human
consumption? Should there be a limit on the quantity of water mined from the
Ironton Galesville Sandstone Aquifer considering eight counties depend upon
this water source, Cook, DuPage, Grundy, Kane, Kendall, Lake, mclienry and
Will Counties? This is not a local issue. This is a regional issue.
And remember, this Ironton Galesville Sandstone Aquifer begins in Minnesota,
runs through Wisconsin, northern Illinois, central Illinois, into Missouri and
finally into the state of Iowa. It can be mined dry.
William McCarthy, Resident. Libertyville
-
As far as water use is concerned, these plants do use a lot of water.
** *
Peaker Plants are inefficient. They only covert 28 percent of the power that
they burn into electrical energy. Combined-cycle plants convert 56 percent.
Obviously, you are going to get a lot more bang for your buck with a combined-
cycle plant.
The problem is combined-cycle plants use more than 2 million gallons of water
a day. Peaker plants use maybe 120,000 gallons a day. That is a big
difference.
And as has been mentioned before, Illinois is under water use restrictions
because they don’t want Lake Michigan being drained for all different
kinds
of
uses. And probably some of you read National Geographic and you are aware
of the Arrow Sea disaster in the Soviet Union. The Arrow Sea was completely
drained within a period of 20 years by overirrigation. And it is a water body
one fourth the size of Lake Michigan. So they drained
--
I think it was 100
billion trilliongallons of water. It is practically gone. If you could just look it
up on the Internet, you will see.
Cindy Skrukrud. Resident,
Olin Mills. Mcllenrv County
First, relating to the State’s commitment to water conservation, ground water
withdrawals, McHenry County is one of the many counties in Illinois totally
dependent on ground water for our drinking water. Combined-cycle plants with
their massive need for water pose a real competitive threat to these water
supplies. This is an issue we need to address.
SPRINGFIELD HEARINGS
Illinois Section of American Water-works Association
—
Testimony of John Smith
and
Exchange with Chairman Mannin2 and Board Members Girard and McFawm
Number three: Should new or expanding peaker plants be subject to siting
requirements beyond applicable local zoning requirements? ISAWWA believes
that peaker plant siting requirements should encourage the siting of these plants
near a sanitary water treatment plant, if practical, so as to utilize the discharge
from the sanitary water treatment plant known as gray water or cooling water.”
We only wish to comment on the use of water resources by these facilities.
Number one, the State of Illinois must manage, protect and enhance the
development of the water resources of the state as a natural and public resource.
Number two, water resources have an essential and pervasive role in the social
and economic well-being of the people of Illinois and is of vital importance to
the general health, safety and economic welfare. Number three, water
resources of the state must be used for beneficial and legitimate purposes. And
number four, waste and degradation of water resources must be prevented.
ISAWWA is not opposed to the use of water resources by peaker plants. We
are only asking for the responsible use of water resources by these facilities and
all major new water consumers. We believe the regulation or permitting of
large water resource withdrawals should be the responsibility of regional
agencies, such as municipalities, counties or water boards, and that a state
agency should have oversight of these regional agencies.
We believe that the basis for the decision on how much water can be safely used
from a designated water resource be based on the existing knowledge and
scientific studies of that resource, and, if knowledge of that resource is lacking,
then additional research into the adequacy of this source should be done before
allowing major withdrawals. The decision to allow the development of existing
or new water resources must be based on sound science, not politics. We
believe that funding must be adequate for the state agency to perform these
studies.
In conclusion, Illinois Section AWWA is not opposed to peaker facilities. We
are calling for the rules and regulations of water resources be based on
scientific studies of our valuable water resources and that an unbiased state
agency be charged with oversight of regional water use. Adequate funding for
the state agency must allow for the scientific study of our state water resources,,.
and the State must have a plan for the efficient management of water resources.
Chairman Manning: Thank you for being here today. I do have just one
question. Are you aware of any projects right now that are ongoing between a
23
peaker plant developer and a sanitary treatment facility in the state we could
speak to?
Mr. Smith: I’m not aware of any
Board Member Girard: So what you’re advocating is that we have a state water
resources board that allocates these large withdrawals? Is that what you’re
saying:
Mr. Smith: What we are saying is that we believe a state agency such as the
Illinois State Water Survey should have some oversight over the regional
agencies that normally would have some control over water. We believe that in
most cases, the regional agency has at least some knowledge of the water
resource and how much of that resource can be used safely without impacting
other consumers or their industries. However, if the local agency has
—
unreasonably tries to restrict the use of these water resources, then a state
agency could have oversight of the local agency.
Board Member McFawn: Is your association involved at all with any studies of
water resources, be they groundwater or surface water, and their adequacy or
even just their quantity?
Mr. Smith: Yes, we are. illinois Section of AWWA is involved with the
Mahomet Aquifer Consortium, which has
—
is trying to secure federal funding
to do further studies of the Mahomet aquifer located in the central part of
Illinois. This consortium and the action that we are doing to try to study this
reservoir has already generated interest from other states in that they have
inquired how we have put together the consortium and how we are going about
to try and initiate these studies.
Our friends and neighbors are understandably worried about the impact of so-
called peaker plants on air quality and water supplies.
National Association of Water Companies. Testimony of Brent Gre2ory,
Representative of Illinois Chauter and Exchan2e with Board Members
Melas
and
McFawn
The ability to provide water of sufficient quality and quantity to sustain
commercial, industrial and residential growth goes hand-in-hand with the
availability of electrical power. Water suppliers rely on adequate available
electricity, and generating plants rely on an adequate supply
of
water.
NAWC
supports the development of new electrical generating capacity as needed for the
economic advancement of Illinois.
24
We do not believe that peaker plants pose a unique threat to the environment
compared to other types of state-regulated facilities. We believe that existing
environmental regulations are adequate to address air and water quality concerns
from peaker plants.
We emphasize the need for water use decisions to be based on sound scientific
assessment of local and regional water resources. Where existing knowledge is
insufficient, the state technical agencies should provide the scientific studies
needed to permit or deny water withdrawals. State funding must be adequate to
support these efforts. The right of existing public water supplies to condition
withdrawing at theircurrent installed capacities should be grandfathered into any
program that is developed. The state should consider competent third-party
assessments presented by those seeking to utilize the water resource.
We believe that permitting of new peaker plants and siting requirements should
encourage conservation measures such as recycling of cooling water and use of
other discharges for cooling when possible, such as those from sanitary
treatment plants.
In summary, NAWC believes that the ability to expand power and water
resources is important to the economic growth of Illinois.
Board Member Melas: Do you have any comments about the quantity of the
—
or the adequacy of particularly groundwater supplies?
Mr. Gregory: Well, we recognize that in certain areas of the state in particular,
there may be some quantity concerns. We’re traditionally known as a water-
rich state, and yet due to concentrations of industry and populations and other
circumstances, there are areas where, particularly in long-term outlook, water
quantity is a concern. That’s why we concur that there is a need for sound
comprehensive management of the state’s water resources with regard to
quantity.
Board Member McFawn: You mentioned you thought that the quantity
--
I
believe it was the assessment of it should be done by an independent third party?
Could you explain that a little bit more?
Mr. Gregory: Yes, I can. If there is some legislative or regulatory control set
up over the use of Illinois water resources, it needs to be based on sound
scientific assessment of the resource, which we believe that the state has
—
is
the appropriate
—
has the appropriate technical resources to conduct those.
However,
if there would arise a dispute
over the use or the application for the
use of water or withdrawal of water and there is better science to be presented
by a petitioner for the use of that water, that should be allowed.
25
Board Member McFawn: We are talking about just quantification, not quality?
Mr. Gregory: That is really in the context of quantity.
Mr. Gregory: If somebody wants to withdraw water from an aquifer or from a
watershed and is able to hire a qualified consultant to demonstrate the
reasonableness of that petition, then that should be considered.
Natural Resources Defense Council
—
Testimony of Patricio Silva and Exchange with
Board Member McFawn
Mr. Silva: The water withdrawals were in part because there was some
concern about adverse impact from the water withdrawals on the Hudson River
for several fish species in that section of the Hudson River. I cannot remember
offthe top of my head if there was any impacts for nesting birds, but I don’t
believe so.
Board Member McFawn: You said that NRDC was concerned about water
used in single-cycle units. I’ve always thought that the single-cycles didn’t
cause that concern and it was the combined-cycles.
Mr. Silva: A great many single-cycle combustion turbine projects that we’ve
seen
--
not just the few that we’ve looked at in Illinois, but
--
in elsewhere
across the country
--
rely on once-through cooling. Water is used once for
evaporative cooling at the inlet duct and then essentially discarded. That,
depending on the size of the unit
--
and remember, the single-cycle turbines,
we’ve seen anywhere from 80, some projects have 1,000 megawatts, so the
water demand is going to be quite dramatic. Some of the combined-cycle units
we’ve seen actually rely on dry cooling where there is essentially a process that
involves a closed loop and onetime withdrawal of water.
So the demands
—
even though the unit
—
the technology’s more efficient, in
some applications the combined-cycle units can be hogs as well. They can be
quite water intensive. So
—
But there is
—
there are technology options.
Exhibit from Reliant Energy
How much water will the plant use?
The plant does not require a large amount of water. Unlike many older plants,
Reliant Energy Aurora does not use steam to generate electricity and its demand
-
for water is similar to other light industrial uses. The primary use of water will
be to cool the air flowing into the units and to control emissions.
26
The only other uses of water will be for the purposes of employee sanitation and
for fire
The plant will use an average of only 300 gallons per minute (gpm) during the
summer months and that the peak water usage rate will be gpm. The water will
be provided from a deep aquifer well (Cambrian Ordovician650) which is at
least one mile away from any known deep aquifer wells in the area. Compared
with the water used in the City of Aurora on an annual basis, the maximum
consumption from this well is less than 1 of’ the city’s water use.
Public Comment #3
--
Ron Molinaro
Thirdly, there is the amount of water used. These plants can consume up tol 2
million gallons of water a day. At a recent Zion City Council meeting a
gentleman who owns a local confectionery company spoke of the possibility of
the expansion of his business. When checking into the accessibility of
additional water he discovered that the city of Zion exceeded its allocated
amount for 1999 by 22 million gallons. If we were to allow these plants to be
constructed in Zion, will there be enough water allocated for the expansion of
existing business or the construction of new homes? This is a question that
needs to be answered before we allow any power plants to be constructed in this
region.
Public
Comment #7
—
Susan
Zingle
Attachments to Public Comment #7 submitted by Susan Zingle
—
three letters
from the Illinois State Water Survey.
27
Attachments to Public Comment #7 Submitted by Susan Zingle
~LL~NOIS
illinois State Water Survey
Main Oflice
•
2204 GrUlith
Drive
.
Chompcig”r. LàI820-7495•
Tel f217,)333-2210~
Far (217,) 333o540
Peoria Office. P.O. Oox 697’ Peo;ic, 61652-0697-
Tel
(309)671-3196. Fox
(309,)
611-3106
D~p~TUL.~4D0’
~SrouncI.Wwer Section
•
Tel ~2J?~333-4300
•
fox(217):
December 4,
1998
Mr. Robert Wargaski
Lake-Mel-lenry Environmental Cooperative
P.O. Box 134
Wauconda, IL 60084
Dear
Mr.
Wargaski:
This letter is in response to your request of December?, 1998, concerning the development of two
5-
million gallons per day (rngd) ground-water supplies from the Cambrian-Ordovician-Age aquifer system
for the purpose of steam generation in electrical
power
generating facilities. One site (designated herein
as the Island Lake Project) will be located in the SWV4 of Section 9, T.44N., R.9E, Lake County. The
other site (designated herein as the Libertyville Project) will be located in the NE¼
of Section 12,
T44N., R.1OE., Lake County. The distance between these sites is approximately 9 miles. You have
asked the Water Survey to comment on the potential impacts these ground-water withdrawals may have
on surrounding water wells finished within the same aquifer system. You also inquired about ground-
water
law
and regulation. The following are responses to the specific questions you posed to~LheWater
Survey concerning this matter:
“The
proposed
Island Lake and Libertyr.’ille sites are wIthin JO miles of each other. Each would draw up
to
$
,7LiLl
LolL
gaUonx
of water per clay. ?lea~ccomment on the impact they would hcu~’èoperating together
and simultaneously on the aqu(fer and the surrounding community wells. Which com?nw-iity wells would
be affected by the interface drawdown.”
Withdrawal of ground water from a well may cause water levels in nearby wells-tapping-the-source
aquifer to decline. This water-level decline is referred
to
as interference drawdown or, more simply, as
interference. Interference drawdowrt decreases with increasing distance in all directions from a pumping
well, defining an inverted conical water-level surface around the well. This is known as the cone of
depression. The size and shape of the cone of depression created by a pumping well will depend on the
areal extent and hydraulic properties of the aquifer, the pumping rate, and the duration of pumping at the
well. When interference drawdown causes the water level in a well to decline-belowthe-pump-intake-(-ki
which case the pump breaks suction)or below a level at which the pump can lift the desired volume of
water to the surface, remedial measures such as lowering the pump setting or sizing a higher capacity
pump may be necessary to restore a normal supply.’ The risk posed by a pumping ~vellon the ability of a
nearby well to deliver its normal supply is, therefore, a function both of the amount of interference and of
various construction features of the affected well chiefly. the pump setting. dynamic head rating of the
pump, and well efficiency.
For the Island Lake and LibertyviUe Projects, nearby existing wells finished
within the Cambrian-
Ordovician-Age aquifersystem, pre-dating the Lake
Michigan water
allocations to the area of question,
may not be severely impacted by the proposed well field because those wells were engineered and
I”
‘.~,d
‘j,,
r.~)-c1~~,l
J,’,p~’i
Mr. Robert E. WargaskilPage 2/December 4, 998
constructed when regional water levels were considerably lower
than at present. Prior to Lake Michigan
water allocations, pump intakes in water wells were set at lower depths and had greater water lifting
capacities because of lower ground-water
levels
caused by regional pumpage. However, wells fi~ishcd
in
the deep sandstones within the last few years could see more severe impacts because they were
consiructed after the regional “recovery” of water levels within the Cambrian-Ordovician-Age aquifer
system.
The impact of the withdrawal of
5
mgd from two sites on ground-water levels with
the
Cambrian-
Ordovician-Age aquifer system was determined through the use of ananalyticaLmathematicat model
using regional values for the hydraulic properties of this aquifer system. The use of this model required
that significant assumptions
be made to simplify the natural variability often encountered-in-aquifer
systems. Assumptions include homogeneous and isotropic aquifer hydraulic
prep-erties~(asopposed to
properties that may vary vertically and horizontally in three dimensions), no ground-water recharge,
infinite aquifer extent (as opposed to geologic and hydraulic features which may limit the size of the
aquifer), and a continuous pumping schedule (as opposed to a time-variantpumping rate).
The hydraulic properties and pumping scenarios were assumed to be identical at the Island Lake
and
Libertyville Projects sites. As you requested,
each
proposed well field pumped simultaneously in
our
model simulation. For purposes of
construction of
the
model, we
assumed
each
well field would consist
of eight wells (finished in the St. Peter and Ironton-Galcsville Sandstone
aquifers) supplying 5
rngd
(about 434 gallons per minute each) on a continuous
basis for 20 years. Given these parameters, the
model provided the graphic output shown in accompanying Pignre 1.
Under the pumping and hydraulic conditions described in
the above scenario, mutual interference effects
between the well
fields
may cause water level declines of as much as 280 feet. Interference effects
decline to approximately 150 feet at 12 miles.
This analytical model also suggests that as much as 520 feet of drawdown would be observed in the
centers of each well field. This would lower the potentiometric head of the Cambrian-Ordovician-Age
aquifer in the study area into the St. Peter sandstone. Dewatering of any artesian aquifer can lead to the
-
reduction in pumping capacity.
For a properly designed well field, the Cambrian-Ordovician-Age aquifer
should be nble
Co
yield the desired quantity of water on a suscairtablebasts.
Given the possibility that the aquifer properties, number of pumping wells, well spacing, pumping
rates,
pumping
periods, and total pumpage ofthe proposed wells may be different then
whet
was
assumed for
this report, we recommend a more detailed analysis be made of th-enumber of existing wells and their
distance from the proposed high-capacity well fields. In addition, static water levels, pumping water
levels, and pump intake settings of
nearby water wells
could be analyzed to determine if, and which.
domestic, industrial, or municipal water wells would be potentially impacted.
Pumping water from this aquifer in the Island Lake and Libertyville areas has wider ranging effects than
simply being a local phenomenon. Consideration should be given to the effects on the practical sustained
yield of the
entire aquifer system including
the effects of pumping on ground water within the State of
Wisconsin. The aquifer system is currently being pumped at. or slightly above, its estimated practical
-
sustainable yield of
65
mgd per day. Further development is likely to contribute to the mining of ground-
water in northeastern Illinois. A more sophisticated ground-water model of northeastern Illinois, one that
Mr. Robert E. WargaskilPage 3/December 4,
1998
can incorporate regional variations
in aquifer properties (unlike
the simplistic analytie~-model we
used
to calculate drawdowns for this letter), would be a very important planning tool for state
and local
governmental leaders
to have available to
theta
in their efforts tomange-thisnattwaLresource
We
recommend that a three-dimensional numerical ground-water model be used to better predict what
long-term impacts the proposed ground-water development
would have on the Cambrian-Ordovician-Age
aquifer
in northeastern Illinois. The Illinois State WaterSurvey has previously modeled this aquifer
system (Prickett 1971, Visocky 1982, Burch
1991); however, the WaterSurvey’s most recent model
(Burch 1991)
will need extensive updating. A three-dimensional numerical ground-water model could
incorporate natural variations
in aquifer
properties, thickness, and withdrawals from existing high-
-
capacity wells. Such a model would also allow studying the aquifer in a more regional context.
To reiterate, estimates of water-level decline contained in this letter were determined from a-strictly
theoretical consideration of aquifer hydraulics, making use of regional aquifer property data. More
accurate estimates would be possible given better aquifer property data and recharge rate.s collected
through properly conducted “on-site” aquifer tests. It is possible that the predictions in this letter will
not
prove to be accurate. We, therefore, recommend that further study be made of this particular issue. The
Illinois State Water Survey has the expertise to provide these services to the resid-ents-of-Lake and
McHenry Counties; however, such involved research would require a contractual agreement
(administered through
the University of illinois) between interested parties and the Water Survey.
-
As to your question relating to whichmunicipal water wells would be affected by the theoretical well
lields. the total number at wells tmpacted anti corresportdtng economic repercussions are impossible to
quantify at this time without further in-depth study.
‘Does Illinois have any regulations on the limit: of water that ca,~-bc-drawn-from-thc-aq~frr? Do other
States have limits and
which ones,”
The State of Illinois does not have
any
specific laws that limit growid-water-withdrawals. The Rule of
Reasonable Use allows “property owners to unlimited and non-permitted use of the water beneath their
land
as long as the
use is ‘reasonable’ and injury to a neighboring well does not arise but of malice” as
stated by Bowman (1991).
We suggest
that you contact Mr.
Gary Clark of the Office of Water
Resources, Illinois Department of Natural Resources, at (217) 785-3334 for further information on this
matter. Mr. Clark is one of the State’s leading experts on ground-water law, and we are confident he will
be able to address
any ground-water law
related questions that you pose to
him. For your information,
we have enclosed a copy of an Illinois Department
of Transportation 1985 report to the Illinois
Groundwater Association
Illinois Groundwater Law: The Rule of Reasonable Use.
Mr. Clark is the
author of this document. We are also enclosing a copy of Illinois State Water Survey Report of
Investigation 114
Ground-Water Quantity L.aws and Management,
for additional discussions of Illinois
ground-water laws and the law practiced in several other midwestern states.
“What i.c the cha.~zgcin the level of the deep sandstone aquifer since conm,,ZL,niiies swirch~dfrom aqu~/’er
wells
to
Lstke Michigan
water.”
For your information
on this particular subject, we have enclosed Illinois State \Vnter Survey Circular
182
Water-Level and Pumpage in the Deep Bedrock Aquifers in the C’hicago Region, 1991-1995.
This
Mr. Robert E. Wargaski/Page 4/December4, 1998
publication is an excellent resource for the analysis of water level trends in the Cambrian-Ordoviciari-
Age aquifer system.
Figure 9
on page 30
of this document shows changes in the potentiometric surface
of
the deep bedrock aquifers
between 1991 and
1995.
In Lake County, therewere areas
that observed
aim
increase in water levels (potentiometric head) of over 250 feet. Wauconda Municipal Well 4, located
in
Section 24, T.44N., R.9E., Lake County, experienced a rise in ground-water levels of 45 feet between
1991 and
1995.
With the growing population trend in Lake and McHeniy County, what (ilnitations
would
you suggest
be incorporated to protect the aquifer and keep it healthyforfuture gezrerations.”
The Illinois State Water Survey is a strictly an objective scientific organization. We do not make, nor do
we enforce,
rules and regulations. However,
our research and guidance is often utilized in the
development of water-related laws and statutes. In the case of the issues addressed in this letter, we have
the knowledge and expertise to offer the citizens and their governmental
representatives
to make
informed decisions about how to develop their natural resources. However, additional research will be
needed before we can more accurately address yotir many concerns.
For your
information, I have enclosed all prior letter correspondence that deal with power generation in
Lake and
McHcnry County
arca~.-
If
we
can be of
~imy
further assistance, p1ea~efeel free
to call or write.
Sincerely,
Andrew
Cr.
Buck, P.O.
/4\
ANDREW G. BUCK
(217) 333-6800
\~9O0O65~,,,,J
iLLIN0~S
--
Enclosures as
stated
cc~
Winstanley, ISWS
l3howmik, ISWS
Roadcap, ISWS
Clark, IDNR-OWR
2:
(0
I-
Lt)
-‘5
I-
z
Drawdown
created by
two
welifields
each pumping 5 MGD
from
8 Wells.
(1 15,000 gpd/ft, S 0.0004)
160
L
~QO~
1;.
240 -~
RQE
R1OE
RilE
LL N
0
iS
Illinois State Water Survey
Main Ottice 2204 G4fi~hDrive ‘Cbompcigri. 0.6 820-7495’
Tel (217,) 333-2210- tOx (217) 333.o5~C
Peoria
OlOce. P.O. Box 697’ Peoric.
I~,
61652-0697’ Tel ~3O9~67i-319ô‘Fax
f309,)
67I-3I0~
W.~TU~AL
-
P,E5OU R (ES
Ground-Wotar Section
Tel
(217,) 333.43w
•
Fax(217) 2~!4-0777
Decembcr 2, 1998
Mr. Kenneth C. Hopps
Natural Gas Pipeline Company of America
747
East
22’~’Street
Lombard. Illinois 60 148-5072
Dear Mr. Hopps:
-
This lerter is in response to your request concsrning the development of a 2.5- million gallon per day
(mgd) ground-water supply from the Carnbrian-Ordovician-Age aquifer system for the purpose of
steam generation in an electrical power generating facility, We understand that the proposed power
plant wilt be located in the SW’/s of Section 9,T.44N,, R.9E., Lake County. You have asked the
Illinois State Water Survey to comment on the potential impact this ground-water withdrawal may
‘nave on surrounding water wells finished within the overlying unconsoiidatedraad~andgravel
deposits and Silurian-Age dolomite bedrock aquifer. It should be noted that the Water Survey has
previously provided estimates of theoretical water level drawdowns in the Cambrian-Ordovician-
Age aquifer system given several different water withdrawal scenarios. These previous letter reports
to your company were dated September 3 and October 13, l99S, and addressed the interference
effects caused by a theoretical well field on wells finished within the Cambrian-Ordovician-Age
aquifer.
-
Withdrawal of ground water from a well will cause water levels in nearby ~ve11stapping the source
aquifer to decline. This water-level decline is referred to as interference drawdown or, more simply,
as interference. Interference drawdown decreases with increasing distance in all directions from a
pumping well, defining an inverted conical water-level surface around the well known as the cone
of
depression. The size and shape of the cone of depression created by a pumping well will depend on
the areal extent and hydraulic properties of the aquifer, the pumping rate, and the duration of
pumping at the ~vcli. When interference drawdown causes the water level in a ~vellto decline below
the pump intake (in which c~sethe pump breaks Suction) or below a level at which the pomp can lift
-
the desired volume of water to the surface, remedial measures such as lowering of the pump setting
or sizing a higher capacity pump may be necessary to restore a
normal supply. The risk posed by
a
pumping well on the abilIty of a nearby well
to deliver its normal supply is, therefore,
a function both
of the amount of interference and of various construction features of the affected well
--
chiefly the
pump
SCItiUC,
dynamir head rating of the pump, and well efficiency.
With respect to your question, the key variable when determining whether a well(s) withdrawing
ground water will adversely impact a nearby well(s) is dependent on the hydraulic connection
Pr,,::ed,n~r,’,~Cicd
on’s-i’
Mr. Kenneth C. HoppsfPagc 2lDecember 2, 1998
bc~weenthe source aquifers. In
this case, you have asked us to address the potential impacts on
wells finished itt the unconsolidated sand and gravel deposits above bedrock and
wefls
completed in
the Silurian-Age dolomite when the deeper lying Cambrian-Ordovician-Age sandstone aquifers arc
pumped. For your reference, we have enclosed an excerpt from Illinois State Water Survey Circular
182, titled
Water-Level Trends and Pwnpagc in (he Deep Bedrock ~4quifcrs in the chicago
Region, 1991-1995
(Visocky et al.,
1985,
page 6 and 7, figure
2), which shows the
stracigraphy,
water-yielding properties of the rocks, and the character of the ground water in northeastern Illinoi.c.
In this part of Illinois, the Ordovician-Age Maquoketa shale separates the unconsolidated materials
and Silurian-Age dolomite from the deeper lying Cambrian-Ordovician-Age (St. Peter and Ironcon-
Gatesvi I Ic sandstones) aquifers.
The Maquokeca shale is approximately 105 feet thick in the area of interest. Under natural
conditions, the Maquokeca acts as an effective hydraulic barrier between the upper (sand and gravel
and dolomite) andlower (Cambrian-Ordovician-Age sandstones) aquifer systems. Consequently,
changes in ground-water levels in the Cambrian-Ordovician-Age are relatively independent of those
in the shallower aquifer systems. Given this, pumping the Cambrian-Ordovician-Age aquifer system
should not affect water levels in the shallower sand and gravel and-dolomite aquifers. It should be
noted that this assumes that a well finished in the Cambrian-Ordoviciart-A.ge sandstones must be
constructed such that the geologic materials from the Ordovician-Age St Peter sandstone and above
are “cased off”. An “open” bore hole hydraulically connecting the Silurian-Age dolomite and
dcepcr-lyir.g sandstone formations would render the above coaclusions false. Water levels itt the
shallower aquifers probably wilt be impacted by water withdrawals from the Cambrian-Ordovician-
Age sandstone aquifers if the geologic materials above the St. Peter sandstone were not sealed off by
well casing
If we can be of any further assistance, please feel free to call or write.
Sincerely.
Andrew 0. Buck, P.O.
Assistant Hydrogeologist
Ground-Water Section
Phone: (217) 333-6800
agb/psl
Enclosure as stated
2
I ~.
r~:
0 I S
Illinois State Water Survey
Mom Oltice ‘2204 Gti(fiIh
Dike ‘Cho~pcQn.
II 6l~2C~’.95
-
Tat (217)333.2210
-
Fox ~2!7~
33J.o5~0
PeorioOl’Oce -P.O. Cox ô~7
- ?eoriO. II.
olo52.o~c7
-
Tel (309) 67l’39o ‘Fax
(30c)
671.3106
olrAIT~l~H~a,
N.ATUR.
Ground-Wale; SecTion.
TCI
(2l7)333-~3C0
October I, l99S
Mr. Stan A. Smogorzewski
LS Power, LLC
13522 Calais Drive
Del Mar, California 92014
Dear
Mr.
Smogorze~vski:
This letter is in response to your request concerning the development of a 10.8 million gallon per day
(mgd) ground-water supply from
the
Cambrian-Ordovician-Age aquifer system for the purpose of
steam generation in an electrical power generating facility. We understand
that you are considering
two sites
for this facility. One site (designated herein as McHcrtry Project) will be partially Located
in the E½of the NE¼,of SectionS, T.44N., R.9E., McHcnry County and partially
in
the
NWV4
of
Section 9, T.44N,, R,9E., Lake County. Thc other site (designated herein as Lee Project) will be
located
in the NY2 of the SEY3 of Section 32, T.21N., R.8E., Lee
County. You have asked
the Water
Survey to comment on the potential impacts these ground-water withdrawals may have on
surrounding
water wells finished
within the same aquifer system given this
pumping rate over a I-
year period. In this letter report, we will address the theoretical impact that a 7,500 gallon per
minute (gprn) ~velLmay have
on ground-water leveLs within the Cambrian-Ordovician-Age. aquifer
system.
Withdrawal of ground water from a well will cause water levels in nearby wells tapping the source
aquifer to decline. Th~~water-level decline is referred to as interference drawdown or, more simp!y.
as interference. Interference drawdown decreases with increasing distance in all
directions from a
pumping well, defining an inverted conical water-level surface around the well known as the cone of
depression.
The size arid shape
of the cone of depression created by a pumping
well will-depend on
the areal extent and hydraulic properties of the aquifer, the pumping rate, and the duration of
pumping
at
he well. When interference drawdown causes the water level in a well to decline below
the pump intake (in which case the pump breaks suction) or below a level at which the pump cam’. lift
the desired volume of water to the surface, remedial measures such as lowering of the pump setting
am, sizing a higher capacity pump may be necessary to restore a normal supply. The risk posed by a
pumping well on the ability of a nearby well to deliver its normal supply is, therefore, a function both
of the amount of interference and of various construction features of the affected well
--
chiefly the
oump setting, dynamic head radng of the pump, and well efficiency.
For the Mci-Ienry Project, nearby existing wells finished within
the Cambrian-Ordoviciarm-Agc
aqui1c~system. pre-dating the Lake Michigan water allocations to the area of question. may not be
severely impacted by the proposed well field because those wells were engineered and constructed
when regional water
levels
were considerably lower than at present. Prior to Lake Michigan water
,.,,,
tm
Mr. Stan Smogorze’.vskifPage 2/October 1, 1998
allocations, pump intakes in water welts were set at lower depths and had greater water lifting
capacities because of lower ground-water levels caused by regional pumpage. Ho~v~ver,wells
finished in the deep sandstones within the last few years could see more severe impacts because they
were constructed after the regional “recovery” of water levels within the Cambrian-Ordovician-Age
aquifer system. This
situation
does not apply to the Lee Project because water levels in that area
have not been regionally lowered.
The impact of the withdrawal of 7,500 gpm on ground-water Levels with the Cambrian-Ordovician-
Age aquifer system were determined through the use of an analytical mathematical model using
regional valucs fo~the hydraulic properties of this aquifer system. The usc of this model required
significant assumptions be made to simplify the natural variability often encountered in aquifer
systems. Assumptions include homogeneous and isotropic aquifer hydraulic properties (as opposed
to properties that may very vertically, horizontally,
and with direction), infinite
aquifer extent
(as
opposed to geologic and hydraulic
features which may limit the size of the aquifer), and a continuous
pumping schedule (as opposed to a time-variant pumping rate).
Because the hydraulic properties and pumping scenarios were assumed to be identical at the
McHenry and Lee Projects, the distance-drawdown estimates shown below apply to both sites. As
you requested, the proposed well field was assumed to consist of only one well (finished in the St.
Peter and J.rotmton-Galesville Sandstone aquifers) supplying 10.8
mgd (7,500 gpm) on a continuous
basis for one year. Given these parameters, the model provided the following distance-drawdown
relationships (also see the enclosed distance-drawdown plot and map):
flic’a,’ee frpni nnrnned well
Drawdown after mm-tome -veer
Vs
mile
350 feet or less
½
miLe
285 feet or less
I mile
225
feet or less
2 miles
170 feet or less
3 miles
135 feet or less
4 miles
110 feet or less
5 miles
90 feet or less
Although these impacts are considerable. the available drawdown in
deep sandstone wells is
probably adequate for the desired
amount of ground-water yield, assuming a properly designed well
field. The number of wells
impacted and corresponding economic repercussions are
impossible to
quantify at this time without further in-depth study.
Given
the possibility that the
aquifer properties, number of pumping
wejls. well spacing,
pumping
rates, pumping periods, and total pumpage of the proposâd wells may be different than what was
assumed for this report. we recommend a more detailed analysis be made of the number of weLls and
their distance from the proposed high-capacity wefl field. In addition, static water levels, l)U~P~
water levels, and pump intake settings of nearby water wells could be analyzed to determine if, and
Mr. Stan Srnogorzewski!Page 3/October 1, 1992
which, domestic, industrial, or municipal water ~vclIswould be potentially impacted. Also, i would
be prudent to ruti a sophisticated numerical ground-water model to better predicc
~hatlong-term
impacts the proposed ground-water development would have on the Cambrian-Ordovicittn-Age
aquifer in northeastern Illinois. Such a model could incorporate natural variations in aquifer
properties, thickness, and withdrawals from existing high-capacity wells. This would be a very
important planning
tool for local
governmental leaders to have available to them in their efforts to
manage this natural resource.
-
Another issue in any use of water from
the
Cambrian-Ordovician-Age aquifer system- is water
quality. There are reports of radioactive isotopes associated with these waters which can be a faccor
in its use.
To reiterate, estimates of water-level decline contained in
this letter were determined from a strictly
theoretical consideration of aquifer hydraulics, making use of regional aquifer property data. More
accurate estimates would be possible given better aquifer property data collected through properly
conducted “On-site” well tests. It is possible that the predictions in this letter will not prove to be
accurate. We, therefore, recommend that further study be made of this particular issue. The Illinois
State Water Survey has the expertise to provide these services to LS Power and the citizens of Lake,
McHenry and Lee Counties:
however, such involved research would require a contractual agreement
(administered through the University of Illinois) between your firm
and
the Water Survey.
To further your knowledge
of the water resources of the deep sandstones aquifers of Illinois, we have
enclosed Cooperative Report 10, titled
Geology. Hydrology, and Water Quality of 1/ze cambrian
and Ordovician Syste,ns in Non/tern Illinois
and Illinois State Water Survey Circular 182, titled
Warer-Ler’el Trends and Pw-npage in I/ac Deep Bedrock.Aquifers in the Clrica~jRegion, 1991-
.1995.
If we
can
be ofanyfurthcr assistance, please feel free to call or write.
Sincerely.
~
~
Andrew G. Buck
Assistant Hydrogeologist
Ground-Water Section
Phone: (217) 333-6800
ngb/psl
Enclosures as stated
0
200
400
0
0
600
800
1000
1200
Regional drawdown in the Cambrian-Ordovician aquifer
produced by
I
well pumping 7500 GPM.
(1= 20,000 gpd/ft2,
S
=
00004, time
=
I year)
7
I~i~rJi
I 1TT11
Tm~TT
li I m
-1
0
1
2
3
4
5
6
Dist:
~
(mies)
5)
E
0
V
C
a
0
Regional drawdown in the Cambrian-Ordovician aquifer
produced by
1
well pumping 7500 GPM.
(T= 20,000 gpd/ft2, S
=
0.0004, time
=
1 year)
Distance (miles)
SUMMARY OF WATER QUANTITY LAWS FROM
MIDWESTERN STATES
IOWA
Statute: Code of Iowa, 455B (1999)
Regulatory Entity: Department of Natural Resources; Environmental Protection
Division
Summary: Permit is required for any person who diverts, stores or withdraws more
than 25,000 gallons of water per day (surface or groundwater); Permits are generally
issued for 10 years but, depending on geological conditions, can be for lesser period of
time; Permit program insures consistency in decisions on allocations; Allocations
based upon concept of “beneficial use” the key points of which are (1) water resources
are to be put to beneficial use to the fullest extent; (2) waste and unreasonable uses are
prevented: (3) water conservation is expected; (4) established average minimum
instream flows are protected: Administrative process resolves water use conflicts;
Provisions in place for public involvement in issuing water allocation permits and in
generally establishing water use policies.
MINNESOTA
Statute: Minnestota Siatute 103G.265
Regulatory Entity: Department of Natural Resources; Waters Office
Summary: Permit is required for all users withdrawing (surface and groundwater)
more than 10,000 gallons per day or I million gallons per year (Exceptions include:
domestic uses serving less than 25 persons, certain agricultural drainage systems, test
pumping of a groundwater source, and reuse of water already authorized by permit,
e.g., water purchased from a municipal water system); Permits granted for no longer
than
5
years; Policy: to manage water resources to ensure an adequate supply to meet
long-range seasonal requirements for domestic, agricultural, fish and wildlife,
recreational, power navigation, and quality control purposes; Water Appropriation
Permit Program exists to balance competing management objectives that include both
development and protection of Minnesota’s water resources; Permitted users required
to submit annual reports of water use; Reported information used to evaluate impacts
and to aid in resolving conflicts.
OHIO
Statute: Ohio Revised Code Sections 1521.16; 1521.17; Sections 1501.30 and
1501.33
Regulatory Entity: Department of Natural Resources; Division of Water
Summary: Permits are required for those making a new or increased consumptive use
of water greater than an average of 2 million gallons per day over a 30-day period;
Registration is required for
any facility
or combination of facilities with the capacity to
withdraw more than 100,000 gallons of water (surface or ground) daily; Chief of DNR
Division of Water has authority to designate “ground water stress areas” and to require
water withdrawal registration in these areas for users of water less than the normal
100,000 gallon threshold; Annual reporting is required of those who must register;
Purpose of registration and reporting requirements: to gather data to assist in resolving
future water use conflicts; Chief also has responsibility to maintain Water Resources
Inventory which must include information to assist in determining the reasonableness of
water use; While “reasonable use” is used by courts to determine water conflicts,
legislature has set forth nine specific factors (applicable to both surface and
groundwater) which define reasonableness; Consumptive use is defined as a use of
water resources, other than a diversion, that results iii a loss of that water to the basin
from which it is withdrawn and includes, but is not limited to, evaporation,
evapotranspiration, and incorporation of water into a product or agricultural crop.
INDIANA
Statute: Indiana Code, 14-25
Regulatory Entity: Department of Natural Resources (DNR); Natural Resources
Commission (NRC)
Summary: Registration and annual reporting requirement for owners of significant
water withdraw facilities (withdrawal of 1,000,000 gallons per day of surface water,
groundwater, or euiiibiuatioai); NRC has statutory authority to require, by rule, a
permit for most water withdrawals from navigable waters, but authority has not yet
been exercised; NRC is required to develop and maintain inventories, gather and
assess all information needed to properly define water resource availability; NRC can
establish, by rule, minimum stream flows; Where groundwater threat, DNR may
designate a “restricted use area.” Permit then required for withdrawal of more than
100,000 gallons per day beyond use at time of restricted use designation; In granting or
refusing a permit, the DNR considers the concept of beneficial use.
MISSOURI
Statute: Missouri Revised Statutes, Chapter
256
Regulatory Entity: Department of Natural Resources (DNR)
Summary: Major water users must register with DNR; A major water user is defined
as an entity that is capable of withdrawing or diverting 100.000 gallons or more per day
from any water source; Failure to register may result in DNR request that Attorney
General file action to stop all withdrawal or diversion; Purpose of registration program
is to insure the development of information required for the analysis of certain future
water resource management needs.
WISCONSIN
Statute: Wisconsin Statutes, Chapter 281; DNR Rules, Chapter
NR 142
Regulatory Entity: Department of Natural Resources (DNR)
Summary: Wisconsin law provides for (1) development of statewide water quantity
resources plan; (2) registration and annual reporting (with fees) of major withdrawals
(over 100,000 gallons per day in 30-day period); (3) permit approval process (with
administrative hearing process) for construction, development and operation of wells
where capacity and rate of withdrawal of groundwater from
all wells on one property
is
in excess of 100,000 gallons a day;
Specifics ofPermit Approval Process:
90-day
approval process. Approval withheld or restricted if withdrawal will adversely effect
or reduce availability of public utility water supply or doesn’t meet grounds for
approval which are: (a) No adverse effect on public water rights in navigable waters;
(b~No conflict with any applicable plan for future uses of waters of state or water
quantity resources plan; (c) Reasonable conservation practices have been incorporated;
(d) No significant adverse impact on environment and ecosystem of the Great Lakes
basin or the upper Mississippi River basin; (e) Plan for withdrawal consistent with the
protection of public health, safety and welfare and not detrimental to public interest; (f)
No significant detrimental effect on the quantity and quality of the waters of the state;
(Even more factors apply if the proposed withdrawal will result in an “interbasin
diversion). Regulations define water loss and consumptive use; Also, permit is
required for any diversion of water from any lake or stream for diversions of 2,000,000
gallons per day in any 30-day period; If DNR receives application for a withdrawal
from
the Great Lakes
basin
that will
result
in a new water loss averaging 5,000,000,
gallons per day in any 30-day period, DNR notifies governor of other Great Lakes
States, requesting their input. The rules incorporate methods for citizens to initiate
DNR investigations of alleged violations.
APPENDIX F
NEW YORK SITING PROCESS
In the State of New York, applications to construct and operate an electric generating
facility with a capacity of 80 MW or more are ruled upon by the New York State Board on
Electric Generation Siting and the Environment (NYS Siting Board) after various filings and
hearings. The NYS Siting Board is comprised of chairmen and commissioners of various state
agencies. The NYS Siting Board also includes two members of the public, appointed by the
Governor of New York for each project, who reside near the proposed site.
The New York siting process requires the applicant to file a preliminary scoping
statement for the proposed project, describing the following: the proposed facility and its
environmental setting; potential environmental impacts from construction and operation;
proposed mitigation of potential environmental impacts; and reasonable alternatives to the
proposed facility. During this pre-application phase, a hearing examiner may mediate
disagreements on the scope and method of any environmental impact studies needed in the
application.
The application itself must contain the following: a description of the facility and the
site including all applicable environmental characteristics; studies of impacts on air, water,
visual resources, land use, noise levels, health, and other matters; proof that the proposed
facility will meet state and federal health, safety, and environmental regulations; applications
for air and water permits; and a complete report of the applicant’s public involvement program
activities and how it encouraged citizens to participate.
The applicant must publish notice that it filed the preliminary scoping statement and the
application, and serve copies of those documents on interested state agencies, members of the
legislature, municipalities, local libraries, and other interested persons and organizations.
During the siting process, the applicant must carry out a meaningful public involvement
program. The applicant is expected to hold public meetings, offer presentations to individual
groups and organizations, and establish a presence in the community (
e.g.
, establishing a local
office, toll-free telephone number, Internet Web site, or a community advisory group).
To facilitate the ability of local government and the public to evaluate the proposed
project, New York requires that the applicant provide funds for intervenors to use in the siting
process. When the applicant submits the application, it must include a fee of $1,000 per MW
of capacity, not to exceed $300,000, to be used as an intervenor fund. The funds are awarded
to municipal and other local parties to help pay for the expenses of expert witnesses and
consultants. At least 50% of the fund is designated for the use of municipalities. The
applicant receives any intervenor funds remaining at the end of the case.
The New York State Department of Environmental Conservation (DEC) reviews
applications for air and water permits submitted as part of the siting process application. The
DEC must provide the permits to the NYS Siting Board before that board decides whether to
approve siting by granting the applicant a Certificate of Environmental Compatability and
Public Need. To grant a Certificate, the NYS Siting Board must determine:
•
Either:
Construction of the facility is reasonably consistent with the most recent state energy
plan (the final 1994 plan assesses the state’s current energy supplies, infrastructure, and
policies, and forecasts energy needs and supplies through 2012), or
The electricity generated by the facility will be sold into the competitive market;
•
The nature of the probable environmental impacts, including an evaluation of
cumulative air quality impacts;
•
The facility minimizes adverse environmental impacts, given environmental and other
pertinent considerations;
•
The facility is compatible with public health and safety;
•
The facility will not discharge or emit any pollutants in violation of existing
requirements and standards;
•
The facility will control the disposal of solid and hazardous wastes;
•
The facility is designed to operate in compliance with state and local legal provisions,
other than those local legal provisions that the NYS Siting Board finds unreasonably
restrictive; and
•
The construction and operation of the facility is in the public interest.
Various state agencies involved in the environment, public health, or energy are
normally active parties in the New York siting process. Any municipality or resident within a
five-mile radius of a proposed facility can become a party to the proceeding. Any organization
or resident outside of the five-mile radius may request party status. Party status enables the
person or entity to submit testimony, cross-examine witnesses, and file legal briefs. The NYS
Siting Board’s goal is to decide whether to grant siting within 14 months after it receives the
application.
APPENDIX G
CALIFORNIA SITING PROCESS
California has empowered the California Energy Commission (CEC) to conduct a
consolidated approval process for siting all power plants that will have electric generating
capacities of 50 MW or larger. The CEC’s siting responsibilities include statewide planning
analysis. The siting process allows the project applicant to submit a single application for all
necessary state and local approvals and provides analysis of all aspects of a proposed project,
including need, environmental impact, safety, efficiency, and reliability.
The CEC has exclusive authority to approve the construction and operation of these
plants. While the CEC’s authority supercedes the authority of other state and local agencies,
the CEC solicits their participation in the siting process to ensure compliance with all
applicable requirements, including local requirements. Under this approach, the applicant
seeks a single regulatory permit from the CEC.
The California siting process, which has public hearings and allows the public to
participate, has two main phases. The first phase is expected to take nine months to one year
to complete. It typically involves a conceptual review of the project, determining the need for
a proposed plant, site suitability and acceptability, and alternatives to the proposed project.
The second phase is expected to take 12 to 18 months to complete. It involves consideration of
the specific site, technology, and equipment. In the second phase, the design, construction,
operation, and closure of the power plant is reviewed against applicable laws, rules, and
ordinances. The second phase is used to identify negative environmental effects and ways to
mitigate them. The CEC also determines, or reconfirms, the need for the facility.
The California siting process includes a public adviser, nominated by the CEC and
appointed by the Governor of California to a three-year term. The public adviser is
responsible for ensuring that the public and other interested parties have full opportunities to
participate in the siting process. The public adviser does not act as the public’s legal counsel
before the CEC but instead advises the public on how to effectively participate in the
proceedings.
California has experienced delays with its siting process, resulting in changes to the
program. The CEC amended its procedures to allow any proponent of a natural-gas fired
merchant power plant to proceed to the second phase without applying for an exemption from
the first phase. Apparently the California legislature created a “fast track” siting process of six
months for new electric generating facilities presenting no significant adverse environmental
impacts. It also appears that, under that legislation, a simple cycle peaker plant can receive a
three-year operating permit in less than four months if it presents no significant adverse
environmental impacts and is equipped with certain stringent emission control technology. A
permit condition, however, requires the facility, within three years, to either convert to a
combined cycle operation or cease operating.
APPENDIX H
ILLINOIS SB 172 SITING CRITERIA
The Environmental Protection Act’s pollution control facility siting criteria are as
follows:
i.
the facility is necessary to accommodate the waste needs of the area it is
intended to serve;
ii.
the facility is so designed, located and proposed to be operated that the
public health, safety and welfare will be protected;
iii.
the facility is located so as to minimize incompatibility with the character
of the surrounding area and to minimize the effect on the value of the
surrounding property;
iv.
(A) for a facility other than a sanitary landfill or waste disposal site, the
facility is located outside the boundary of the 100 year floodplain or the
site is flood-proofed; (B) for a facility that is a sanitary landfill or waste
disposal site, the facility is located outside the 100-year floodplain, or if
the facility is a facility described in subsection (b)(3) of Section 22.19a,
the site is flood-proofed;
v.
the plan of operations for the facility is designed to minimize the danger
to the surrounding area from fire, spills, or other operational accidents;
vi.
the traffic patterns to or from the facility are so designed as to minimize
the impact on existing traffic flows;
vii.
if the facility will be treating, storing or disposing of hazardous waste,
an emergency response plan exists for the facility which includes
notification, containment and evacuation procedures to be used in case of
an accidental release;
viii. if the facility is to be located in a county where the county board has
adopted a solid waste management plan consistent with the planning
requirements of the Local Solid Waste Disposal Act or the Solid Waste
Planning and Recycling Act, the facility is consistent with that plan; and
ix.
if the facility will be located within a regulated recharge area, any
applicable requirements specified by the Board for such areas have been
met. 415 ILCS 5/39.2(a) (1998).
APPENDIX I
Area
LAWS and
REGULATIONS
DESCRIPTION
ARIZONA
Energy
Portfolio
Electric Utility Restructuring
Efforts
(5/00)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
The ACC issued an order that requires electricity providers to derive 1.1
% of their total product from renewable energy sources by 2007.
Implementation will begin with 0.4 % from renewables by January 1,
2001. 50 % of their renewable power must be derived from solar-
generating facilities.
CALIFORNIA
Siting
“
Guidance for Power Plant
Siting and Best Available
Control Technology
,”
July 22, 1999
http://www.arb.ca.gov/powerpl/p
owerpl.htm
In July 1999, the CA Air Resources Board approved guidelines for
major power plant permits. The guidelines are intended to ensure that
air districts require power plants to use the cleanest emissions control
technology currently available. Districts will also be expected to require
newer, cleaner control technology as it becomes available. This
document doesn’t establish any new laws or rules but provides
guidance on applying existing state & federal rules and authority to
peaker/merchant power plants.
•
SITING:
California Energy Commission (CEC) and local Air
Districts have control over siting power plants >50 MW. Electric
generating facilities >50 MW are required to receive certification
from the Energy Facilities Siting and Environmental Protection
Division. Certifications are open to the public.
In the siting phase, the design, construction, operation, and closure
of the power plant is closely examined in relation to applicable laws,
ordinances, rules, and standards. Adverse environmental effects
are identified and mitigation measures established. The need for
the facility is determined, or reconfirmed, if preceded by a Notice of
Intent. The siting process ensures that the proposed power plants
are safe, reliable, environmentally sound, and comply with all
applicable requirements. The Siting Division also oversees
construction and operation.
Air
•
AIR DISTRICTS:
Local Air Districts provide analysis and
recommendations to the CEC on proposed projects to determine
compliance with air pollution control regulations. The Local Air
Districts utilize a permitting process to control emissions from non-
vehicular sources (stationary sources) that is incorporated into the
CEC’s power plant siting process. The CEC’s power plant siting
regulations specifically provide for the district’s participation in the
process. Each district’s regulations may vary depending on the air
quality conditions in the district and the district’s policies and
strategies for attaining or maintaining compliance with the federal
and State ambient air quality standards. The district’s analysis and
recommendations are provided to the CEC in a document known
as a Determination of Compliance (DOC).
State Laws & Regulations
Peaker Plants
Air
•
BEST AVAILABLE CONTROL TECHNOLOGIES:
Major sources
are required by permit to use “California BACT”, which is equivalent
to the more stringent federal lowest achievable emission rate
(LAER) in most California air districts.
•
EMISSIONS OFFSETS:
Air pollution control and air quality
management district (district) new source review (NSR) rules and
regulations employ both best available control technology (BACT)
and emission offset requirements to reduce the impact on air
quality from new or modified stationary sources. If emission
increases are above certain specified levels, district NSR rules
require the application of BACT. If the emission increases after the
installation of BACT are still above specified levels, then emission
offsets may be required.
•
AIR IMPACT ANALYSIS:
California Health & Safety Code requires
Air Districts to evaluate air quality impacts in addition to the Federal
CAA requirements on Prevention of Significant Deterioration. This
ensures new permits will not be issued for emission units (sources)
that will prevent or interfere with the attainment or maintenance of
any applicable air quality standard.
•
HEALTH RISK ASSESSMENT:
Power plant applicants are asked
to submit a Health Risk Assessment under the California
Environmental Quality Act and the Health & Safety Code. A health
risk assessment addresses three categories of health impacts from
all pathways of exposure, if appropriate: acute health effects from
inhalation only, chronic non-cancer health effects, and cancer risks
from multiple exposure paths.
•
ADDITIONAL PERMITTING CONSIDERATIONS:
Permits
address startup/shutdown emissions, continuous air monitoring,
sulfur content of fuel, and ammonia slip from air pollution controls.
Water
Water Recycling Act of 1991
http://leginfo.ca.gov
•
Established grants and loans for water reclamation projects and
encouraged water reuse among suppliers.
•
Applies only to public entities that produce or supply water and to
entities responsible for groundwater replenishment.
CONNECTICUT
Energy
Portfolio
An Act Concerning Electric
Restructuring
(RB 5005)
(4/98)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/tab5rev.html#CT
•
The bill requires renewable energy funding, a 5.5 % renewable
portfolio standard, and environmental protections.
Noise
State Policy Regarding
Noise
(CT General Statutes Ch. 442,
Sec. 22a-67 to 22a-76)
http://www.cslib.org////statutes/tit
le22a/t22a-p5.htm
•
Noise regulations address impulse noises and a model ordinance.
FLORIDA
Siting
Electrical Power Plant Siting
Act, 1973
(Florida Statute Section
403.501-.518)
http://www.dep.state.fl.us/siting/P
rograms/progER-pps.htm
•
FL has an
Siting Coordination Office
that is responsible for siting
of:
¾
Electrical Power Plants
¾
Electrical Transmission Lines
¾
Natural Gas Transmission Pipelines
¾
High Speed Rails
¾
Hazardous Waste Facilities
•
Electrical Power Plant Siting Act applies only to steam or solar
electric generation > 75MW. This would include combined-cycle
plants but not simple-cycle combustion turbines.
•
Final approval body for the permits is not the Siting Board, but the
Department of Environmental Protection.
•
Fees are charged to the applicant.
•
BACT for NOx is 9 ppm based on dry low NOx combustion
technology.
Ten Year Site Plan
Requirements (TYSP)
(Part of the electrical power
plant siting process)
•
The Public Service Commission (PSC) oversees the submission of
plans by the utilities that describe current generation capacity and
anticipated need for more capacity. The TYSPs also provide
generic information on future sites for power plants to
accommodate the anticipated need. This information includes land
use data, environmental factors, and similar topics which allows
other state and local agencies to comment on the Plans to the
PSC. Based on this information and its own conclusions, the PSC
will determine the suitability of the plan.
Need Determination
(Part of the electrical power
plant siting process, s.
403.519, F.S.)
•
Need Determination is a formal process and is conducted by the
Public Service Commission (PSC). The PSC reviews the need for
the generation capacity that would be produced by the proposed
facility in relation to the needs of the region, and to the state as a
whole. The PSC also looks at whether the facility would be the
most cost-effective means of obtaining the capacity.
Environmental Impact
Statement
(Statute section 62-1.211(1),
F.A.C.)
http://www.dep.state.fl.us/siting/L
aw_Rule/apform-pps-a.htm
•
Site certification application forms for power plants resemble an
Environmental Impact Statement. Site Certifications are issued by
the Governor and Cabinet. Prior to issuance of a Site Certification,
the Department of Environmental Regulation (DER), Department of
Community Affairs (DCA), Public Service Commission (PSC),
Water Management Districts (WMD), and other affected agencies
are required to assess the potential effects upon the environment,
ecology and society by the proposed plant in order to insure that
the construction and operation of the plant will be consistent with
applicable environmental standards.
GEORGIA
Water
Water Withdrawal Permits
http://www.ganet.org/dnr/environ/abo
utepd_files/branches_files/wrb.htm
•
GA has a Water Withdrawal Permit Program.
•
Develops short-term and long-term water management policies and
strategies to address environmental problems induced by
unsustainable use of Georgia's water resources.
Air
Air Permit Modeling
http://167.193.59.200/metdata/
•
GA maintains a Web site with geographical meteorological data for
air permit modeling based on 5 years of data.
HAWAII
Noise
Noise Pollution
(Hawaii
Revised Statutes Chapter
342F)
http://www.capitol.hawaii.gov/hrs
current/Vol06/hrs342f/HRS_342F
.htm
•
Hawaii’s noise regulations incorporate both a permit program and
enforcement provisions.
ILLINOIS
Air
Air Pollution
(35 IL Admin Code, Subtitle B)
http://www.ipcb.state.il.us/title35/
35conten.htm
•
State rules follow federal requirements.
Energy Portfolio
Renewable Energy
Initiatives
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
09/00 - Chicago Mayor Richard M. Daley announced that the City
of Chicago and 47 other local government bodies plan to buy
electric power as a group, requiring that 20% of the purchase (80
MW) come from renewable energy. The City has issued a request
for proposals to the 13 licensed power providers in Illinois. This is
the first opportunity that government agencies have had to
purchase power competitively since Illinois passed its restructuring
law.
•
10/99: Commonwealth Edison plans to allocate $250 million to a
special fund to support environmental initiatives and energy-
efficiency programs throughout the State.
Noise
Noise
(35 Illinois Admin.
Code 900 – 952)
http://www.ipcb.state.il.us/title35/
35conten.htm
•
According to Greg Zak of the IEPA, Illinois is more active than any
other state in regulating noise. However, some states may have
cities that regulate noise through local ordinances.
INDIANA
Air
•
Requires BACT for all new projects emitting >25 tons per year
VOM.
Siting
•
Requires public utilities to obtain a
certificate of necessity
prior to
constructing electric generating facilities. (The Indiana Utility
Regulatory Commission considers Independent Power Producers
to be public utilities.)
Water
Water Rights & Resources
(Indiana Code, 14-25)
http://www.ai.org/dnr/index.html
http://www.ai.org/legislative/ic/co
de/title14/ar25/ch4.html
•
Registration and annual reporting requirement for owners of
significant water withdrawal facilities (> 1,000,000 gallons/day of
surface water, groundwater, or combination).
•
Natural Resources Commission (NRC) has statutory authority to
require, by rule, a permit for most water withdrawals from navigable
waters, but authority has not yet been exercised.
•
NRC is required to develop and maintain inventories, gather and
assess all information needed to properly define water resource
availability.
•
NRC can establish, by rule, minimum stream flows.
•
Where groundwater is threatened, Department of Natural
Resources (DNR) may designate a “restricted use area.” Permit is
then required for withdrawal of >100,000 gal/day beyond use at
time of restricted use designation. In granting or refusing a permit,
the DNR considers the concept of beneficial use.
IOWA
Energy
Portfolio
Electric Utility Restructuring
Legislation
(3/00)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/tab5rev.html#CT
•
The DNR has proposed including a Renewable Portfolio Standard
in restructuring legislation. The proposal would require renewable
energy sources, such as wind, to be 4% in 2005 and increase to
10% by 2015.
•
Each peaker application is reviewed for acid rain potential and, in
some cases, new sources must purchase credits from USEPA.
Water
Water Allocation and Use;
Flood Plain Control
(Code of Iowa, 455B.261-290)
(1999)
http://www.state.ia.us/dnr/organiz
a/epd/wtrsuply/alloca.htm
http://www.legis.state.ia.us/cgi-
bin/IACODE/Code1999SUPPLE
MENT.pl
•
Permit is required for any person who diverts, stores or withdraws
>25,000 gal of water/day (surface or groundwater). Permits are
generally issued for 10 years but, depending on geological
conditions, can be for lesser period of time.
•
Permit program insures consistency in decisions on allocations.
Allocations are based upon concept of “beneficial use,” the key
points of which are:
1. water resources are to be put to beneficial use to the fullest
extent;
2. water and unreasonable uses are prevented;
3. water conservation is expected;
4. established average minimum instream flows are protected.
•
Administrative process resolves water use conflicts.
•
Provisions are in place for public involvement in issuing water
allocation permits and in generally establishing water use policies.
KENTUCKY
Air
•
State rules follow federal air requirements.
Noise
Kentucky State Noise
Control Act
(Kentucky Revised Statutes:
KRS 220.30-100 to 220.30-
190)
http://162.114.4.13/KRS/224-
30/CHAPTER.HTM
•
Regulations address a model ordinance.
MAINE
Energy
Portfolio
Electric Utility Restructuring
Legislation
(5/97)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
Maine's restructuring legislation contains the nation's most
aggressive renewables portfolio, requiring 30% of generation to be
from renewable energy sources (including hydroelectric).
MASSACHUSETTS
•
Energy
Portfolio
Electric Utility Restructuring
Legislation
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
Massachusetts restructuring legislation includes a renewable
portfolio requirement and established a renewable energy fund,
funded via a system benefits charge. Funds will also be used to
create initiatives to increase the supply of and demand for
renewable energy.
MICHIGAN
Air
Emissions Limitations and
Prohibitions – New Sources
of VOC Emissions
(R336.1702)
http://www.deq.state.mi.us/pub/a
qd/rules/part7.pdf
•
Requires BACT for all new sources of VOCs.
MINNESOTA
Siting
Power Plant Siting Act
(MN Admin Code 116C.51-
69.)
http://www.revisor.leg.state.mn.u
s/stats/116C/
•
Power Plant Siting Act applies to facilities greater than 50 MW.
•
The siting authority is the State Environmental Quality Board whose
purpose is to locate facilities compatible with environmental
preservation and efficient use of resources. The Board is to choose
locations that minimize adverse human and environmental impact
while insuring continuing electric power system reliability and that
electric energy needs are met.
•
The Board develops an inventory of study areas to guide the site
selection process. The inventory is developed in a public planning
process where all interested persons can participate in developing
the criteria and standards to be used by the Board.
•
A utility (public or private) must apply to the Board for designation
of a specific site for a specific size and type of facility. The
application shall contain at least two proposed sites. The Board
has 12-18 months to issue a decision. When the board designates
a site, it issues a
certificate of site compatibility
to the utility with any
appropriate conditions. No large electric power generating plant
can be constructed except on a site designated by the Board.
•
In designating a site, the Board considers:
¾
effects on land, water and air resources;
¾
effects of water and air discharges and electric fields resulting
from such facilities on public health and welfare, vegetation,
animals, materials and aesthetic values, including base line
studies, predictive modeling, and monitoring of the water and air
mass at proposed and operating sites and routes;
¾
new or improved methods for minimizing adverse impacts of
water and air discharges and other matters pertaining to the
effects of power plants on the water and air environment;
¾
sites proposed for future development and expansion and their
relationship to the land, water, air and human resources of the
state;
¾
effects of new electric power generation and transmission
technologies and systems related to power plants designed to
minimize adverse environmental effects;
¾
potential for beneficial uses of waste energy from proposed
large electric power generating plants;
¾
direct and indirect economic impact of proposed sites and
routes including, but not limited to, productive agricultural land
lost or impaired;
¾
adverse direct and indirect environmental effects which cannot
be avoided;
¾
alternatives to the applicant's proposed site
¾
irreversible and irretrievable commitments of resources should
the proposed site or route be approved; and
¾
where appropriate, consideration of problems raised by other
state and federal agencies and local entities.
•
The Board must hold a public hearing in the county where the
proposed facility is to be located.
Water
Water Supply Management
(MN Statutes: Ch. 103G)
http://www.revisor.leg.state.mn.u
s/stats/103G
http://www.dnr.state.mn.us/water
s/programs/water_mgt_section/ap
propriations/permits.html
http://www.dnr.state.mn.us/water
s/programs/water_mgt_section/ap
propriations/progdesc.html
•
Permit is required for all users withdrawing (surface and
groundwater) more than 10,000 gallons per day or 1 million gallons
per year. (Exceptions include: domestic uses serving less than 25
person, certain agricultural drainage systems, test pumping of a
groundwater source, and reuse of water already authorized by
permit, e.g., water purchased from a municipal water system.)
•
Permits are granted for no longer than 5 years.
•
Policy is to manage water resources to ensure an adequate supply
to meet long-range seasonal requirements for domestic,
agricultural, fish and wildlife, recreational, power navigation, and
quality control purposes.
•
Water Appropriation Permit Program exists to balance competing
management objectives that include both development and
protection of MN’s water resources.
•
Permitted users are required to submit annual reports of water use.
Reported information is used to evaluate impacts and to aid in
resolving conflicts.
Noise
Noise Pollution Control
(MN Rules Chapter 7030)
http://www.revisor.leg.state.mn.u
s/arule/7030/
http://www.pca.state.mn.us/progr
ams/pubs/noise.pdf
•
The Minnesota Pollution Control Agency (MPCA) is empowered to
enforce the state of Minnesota noise rules.
MISSOURI
Air
•
State air rules follow federal requirements.
•
Major source threshold is 100 tons per year.
Water
Geology, Water Resources
and Geodetic Survey
(
Missouri Revised Statutes,
Chapter 256)
http://www.dnr.state.mo.us/dgls/
wrp/waterusestatutes.htm
http://www.moga.state.mo.us/stat
utes/c200-299/2560400.htm
•
Major water users must register with Department of Natural
Resources (DNR). A major water user is defined as an entity that
is capable of withdrawing or diverting 100,000 gal or more per day
from any water source.
•
Failure to register may result in DNR request that Attorney General
file action to stop all withdrawal or diversion. Purpose of
registration program is to insure the development of information
required for the analysis of certain future water resource
management needs.
NEVADA
Energy
Portfolio
Electric Utility
Restructuring, AB 366
(6/99)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/tab5rev.html#CT
•
AB 366 provides that the PUC establish portfolio standards for
renewable energy. The standard will phase-in a requirement
(beginning with 0.2 % by January 2001 and adding 0.2 % of a
percent biannually) that 1% of energy consumed be from
renewable energy resources.
NEW JERSEY
Water
Water Supply Management
Act
(NJAC 7:19-1)
•
Water resources management is required for >100,000 gallons per
day.
Noise
Noise Control Rules
(NJAC 7:29)
http://www.state.nj.us/dep/enforc
ement/pcp/olem-noise.htm
•
The NJ Department of Environmental Protection (NJDEP) has
developed a Model Noise Ordinance that can be adopted by local
municipalities.
•
NJDEP does not have a noise control program and does not
investigate noise complaints. Noise control is handled locally.
Energy
Portfolio
Electric Utility Restructuring
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
The restructuring legislation in NJ requires spending $230 million
for home weatherization, renewable energy and other programs,
and increases spending on new energy conservation programs.
Also, electric generation companies must disclose a set of
environmental characteristics, including power plant fuels and
emissions.
NEW YORK
Siting
Siting and Approval
(Article X of Public Service
Law)
http://www.dps.state.ny.us/articl
ex.htm
•
The NY Public Service Commission (NY State Board on Electric
Generation Siting and the Environment ) is in charge of siting and
approval of all new power plants.
•
Article X of the Public Service Law sets forth a unified and
expedited review process for applications for power plants > 80
MW.
•
Proceedings are open to the public
•
Siting Board may preempt local zoning.
•
Siting may take up to 18 months.
•
Siting Board must determine:
1.
either:
(a) construction of the facility is reasonably consistent with the
most recent
State Energy Plan
, or
(b) the electricity generated by the facility will be sold into the
competitive market;
2.
the nature of the probable environmental impacts (including an
evaluation of cumulative air quality impacts);
3.
the facility minimizes adverse environmental impacts, given
environmental and other pertinent considerations;
4.
the facility is compatible with public health and safety;
5.
the facility will not discharge or emit any pollutants in violation of
existing requirements and standards;
6.
the facility will control the disposal of solid and hazardous
wastes;
7.
the facility is designed to operate in compliance with state and
local legal provisions, other than those local legal provisions that
the Siting Board finds unreasonably restrictive; and
8.
the construction and operation of the facility is in the public
interest.
Intervenor Fund for Siting
Review
(Article X, Section 164)
Power plant applicants are required to pay $1,000 per MW of
capacity up to $300,000 to establish an Intervenor Fund.
Funds are used to defray expenses associated with the siting
review.
Proposed Amendment to
Article X
(New York State Bill A09039)
The bill would authorize the Commissioner of Environmental
Conservation to issue environmental permits necessary to the siting
of an electric generation facility if the Siting Board is unable to do so
and would make some technical changes to the siting law.
The bill would also require the Energy Planning Board to do a
reliability study of the state’s transmission and distribution systems.
New York State Energy Plan
1994
(New York State Energy
Office)
•
The Final 1994 State Energy Plan calls for significant reductions in
State energy taxes and endorses greater competition in utility
purchases of electricity in order to lower electric rates in the state.
The plan reaffirms the state's long-term energy, economic and
environmental goals and its commitment to energy efficiency, but
places increased emphasis on the use of energy policy as a means
to promote sustained economic development. The plan assesses
New York's current energy supplies, infrastructure and policies, and
forecasts energy needs and supplies through the year 2012. Based
on those findings, the plan sets policy goals and objectives and
recommends 180 specific actions. The plan was prepared by the
staffs of the State Energy Office and the State Departments of
Environmental Conservation and Public Service in response to
1992 legislation that formalized Governor Mario Cuomo's model for
integrated energy planning. The State Energy Planning Board,
which approved the plan on October 31,1994 is made up of the
commissioners of those three agencies. State energy law requires
that any state action related to energy be reasonably consistent
with the plan's findings and recommendations.
Water
Water Supply Permits
(Chapter 6, New York Codes,
Rules and Regulations. Part
601: 6 NYCRR 601)
•
Required for suppliers of potable water with 5 or more service
connections.
•
Applicants must demonstrate:
1. Plans are justified by public necessity.
2. Plans take proper consideration of other sources of supply
which are or may become available.
3. Plans provide for proper and safe construction of all work
connected therewith.
4. Plans provide for proper sanitary control of the watershed and
proper protection of the supply.
5. Plans provide for an adequate water supply.
6. Plans are just and equitable to the other municipal corporations
and civil divisions of the state affected thereby and to the
inhabitants thereof, particular consideration being given to the
present and future necessities for sources of water supply.
7. Plans make fair and equitable provisions for the determination
and payment of any and all damages to persons and property,
both direct and indirect, which result from the acquisition of said
lands or the execution of said plans.
8. Plans, in accordance with local water resources needs and
conditions, include a description of an adequate near term and
long range water conservation program.
•
Entities holding Water Supply Permits must report average and
peak usage to the NY Department of Environmental Conservation
annually. If customer demand grows (i.e., new peaker plant begins
withdrawing from the water supply), supplier must re-demonstrate
the above to the state if the demand exceeds amount authorized in
the Water Supply Permit.
Water Well Program
(Environmental Conservation
Law 15-1525)
•
Pre-notification must be filled with the state prior to drilling
specifying desired yield.
•
No restrictions are specified on the amount of water withdrawal.
However, under NY Civil Law, property owners have water rights.
If a well causes drawdowns that impact an off-site property owner’s
water use, then they can sue.
Water Withdrawal
Registration
(6 NYCRR, Chapter X,
Subchapter A, Article 1)
•
Applies to withdrawals from Great Lakes:
•
Great Lakes (6 NYCRR 675):
withdrawals >100,000 gpd averaged over 30-day period
-
OR -
lake water loss > 2,000,000 gpd averaged over 30-day
period
•
No restrictions are specified on the amount of water withdrawal, just
that withdrawals must be registered. Registration fee is $100 /
year.
Long Island Water
Withdrawal Restrictions
•
Water withdrawals from wells are restricted by quantity on Long
Island since over pumpage of groundwater on Long Island can
cause infiltration of saltwater into the aquifer.
Electric Utility Restructuring
•
Funds to support energy conservation and renewable energy are
made available to energy suppliers from the New York State
Energy Research and Development Authority. Funds were created
through the New York Public Service Commission order
establishing a system benefits charge on electricity sales.
OHIO
Siting
OH Admin. Code 4906:
Ohio
Power Siting Board
http://onlinedocs.andersonpublish
ing.com/oac/
•
The Ohio Power Siting Board within the Public Utilities Commission
is the approval authority for all major utilities > 50 MWe.
•
Meetings of the Board where action is taken or deliberations
conducted are open to the public.
•
Applicants for new facilities must consider at least 1 alternate site.
•
Applications are required to address:
¾
Justification of Need:
Description of generation and associated facility
alternatives
Type, number of units, and estimated net demonstrated
capability, heat rate, annual capacity factor, and hours of
annual generation
Land area requirement
Fuel quantity and quality
Types of pollutant emissions
Water requirement, source of water, treatment, quantity of
any discharge and names of receiving streams
¾
Siting issues:
Location
major features
the topographic, geologic, and hydrologic suitability for
each alternate site
¾
Water:
natural and man-affected water budgets
existing maps of aquifers which may be directly affected
¾
Emissions control & safety equipment
¾
Local ambient air quality of proposed sites
¾
Locations of major and anticipated sources of air pollution
¾
Plans for future additions and the maximum generating capacity
anticipated for the site.
¾
Financial data
¾
Environmental data
¾
Social and ecological data:
Noise
Health & Safety
Impact of water use
Economics, land use, and community development
Cultural impact
Agricultural district impact
•
After the Board certifies applications for new facilities, public
hearings are held in the local vicinity of the proposed facility.
•
The Board collects application fees.
Air
NOx – Reasonably Available
Control Technology
(OAC 3745-14)
http://onlinedocs.andersonpublish
ing.com/oac/
•
According to IEPA, certain minor sources must use BAT (Best
Available Technology), OAC 3745-14-3.
•
Major sources are required to use BACT per federal regulations:
15 ppm NOx for natural gas turbines, 42 ppm NOx for oil burning.
•
For NOx sources >100 tpy, Reasonably Available Control
Technology (RACT) is required in certain counties. RACT for
combustion turbines is 75 PPMVD for those firing gaseous fuels
and 110 PPMVD for those firing distillate oil or diesel fuel.
Water
Application for Permit for
major increase in withdrawal
of waters of the State
(Ohio Revised Code 1501.30
& 33)
Registration of facilities
capable of withdrawing
>100,00 gal/day;
Groundwater Stress Areas
(Ohio Revised Code 1521.16)
Determination of reasonable
use of water
(Ohio Revised Code 1521.17)
http://onlinedocs.andersonpublish
ing.com/revisedcode/
http://www.dnr.state.oh.us/odnr/w
ater/waterinv/waterinv.html
•
Permits are required for those making a new or increased
consumptive use of water than an average of 2 millions gallons per
day over a 30-day period.
•
Registration is required for any facility or combination of facilities
with the capacity to withdraw more than 100,000 gallons of water
(surface or ground) daily. Annual reporting is required of those who
must register. The purpose of registration and reporting is to gather
data to assist in resolving future water use conflicts.
•
Chief of DNR Division of water has authority to designate “ground
water stress areas” and to require water withdrawal registration in
these areas for users of water less than the normal 100,000 gallon
threshold.
•
Chief also has responsibility to maintain water Resources Inventory
that must include information to assist in determining the
reasonableness of water use.
•
While “reasonable use” is used by courts to determine water
conflicts, legislature has set forth nine specific factors (applicable to
both surface and groundwater) which define reasonableness.
•
“Consumptive use” is defined as a use of water resources other
than a diversion that results in a loss of that water to the basin from
which it is withdrawn and includes, but is not limited to, evaporation,
evapotranspiration, and incorporation of water into a product or
agricultural crop.
Energy
Portfoli
Electric Utility Restructuring
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
Restructuring legislation includes a provision for a $110 million
revolving load fund for residential and small commercial energy
efficiency and renewable energy projects. Also, electricity
marketers must disclose environmental information to consumers.
OREGON
Noise
Noise Control Classification
of Violations
(Oregon Admin. Rules 340-
012-0052)
http://arcweb.sos.state.or.us/rules/
OARS_300/OAR_340/340_012.h
tml
•
Regulations address a model ordinance.
PENNSYLVANIA
Air
Stationary Sources of NOx &
VOCs
(Pennsylvania Code Ch.
129.91)
http://pacode.com/secure/data/025
/chapter129/chap129toc.html
•
PA charges emissions fees: $42/ton (1999).
•
PA requires RACT (Reasonably Available Control Technology) for
all major sources of VOC, NOx.
Energy Portfolio
Electric Utility Restructuring
(9/00)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
A $21 million Green Energy Fund was created by the Public Utilities
Commission (PUC) to be used for investment in green energy
projects such as wind, solar, and biomass. The fund, which
currently has $5 million, is expected to grow to more than $20
million over the next six years. The fund was created as part of a
negotiated settlement between the PUC and PPL in the utility's
restructuring case two years ago. Businesses and nonprofit
organizations that wish to invest in green energy within PPL's
territory may apply for the funds.
TEXAS
Water
Use of Reclaimed Water
,
(Texas Admin Code Title 30
Part 1 Chapter 210)
(1997)
http://www.tnrcc.state.tx.us/oprd/
rules/index.html
•
Establishes general requirements, quality criteria, design, and
operational requirements for the beneficial use of reclaimed water
that may be substituted for potable water and/or raw water.
•
Due to limited supply and high demand, reclaimed water can be
much less expensive than using municipal drinking water or treating
groundwater. The rule is intended to conserve surface and ground
water and to help ensure an adequate supply of water resources for
present and future needs.
•
Use of reclaimed water is voluntary.
•
Locating reuse facilities near the municipal wastewater treatment
plant helps to minimize infrastructure costs in constructing a
distribution line.
•
Reclaimed water is provided to the user on a demand-only basis.
•
Approved uses include cooling tower make up water under §210.32
(2)(F).
Water Use Permits
(Texas Water Code, §11.121)
http://www.capitol.state.tx.us/stat
utes/wa/wa001100toc.html
•
Texas industries must obtain water rights to use surface water or
protected groundwater. Such authorization may be with or without a
term, on an annual or seasonal basis, or on a temporary or
emergency basis.
Siting
Siting
•
Does not have a siting commission for power plant projects.
•
Texas requires
certificates of convenience and necessity
for power
plant projects initiated by utilities, but not for projects initiated by
independent power producers.
Energy
Portfolio
Electric Utility Restructuring
(9/00)
http://www.eia.doe.gov/cneaf/elec
tricity/chg_str/pbp.html
•
Texas' renewables portfolio standard requires that the State's
utilities install or contract to buy power from 2,000 MW of
renewable generating capacity by January 1, 2009.
WISCONSIN
Siting
State Energy Policy
(Wisconsin Statute: 1.12)
http://folio.legis.state.wi.us/cgi-
bin/om_isapi.dll?clientID=11157
1&infobase=stats.nfo&jump=ch.
%20196
Power Plant Siting
(WI Admin Code Ch. PSC 111,
112)
Environmental Analysis
(WI Admin Code Ch. PSC 4)
http://folio.legis.state.wi.us/cgi-
bin/om_isapi.dll?clientID=95483
&infobase=codex.nfo&jump=top
•
Wisconsin’s State Energy Policy includes policy on:
¾
considering the maximum conservation of energy resources as
an important factor when making any major decision that would
significantly affect energy usage
¾
reducing the ratio of energy consumption to economic activity in
the state
¾
renewable energy resources
¾
protection of natural areas, including wetlands, wildlife habitats,
lakes, woodlands, open spaces and groundwater resources.
•
Ch. PSC 111, 112 require the Public Service Commission (PSC) to
develop a Strategic Energy Assessment (SEA) for power plants.
The SEA involves an assessment of electric demand and supply,
and information from electricity suppliers on economic, pollutant,
and energy conservation data.
•
Ch. PSC 111,112 require
Certificates of Public Convenience and
Necessity
for electric generating facilities. According to the Illinois
Commerce Commission, this requirement applies to facilities > 100
MW. Applications for certificates include:
¾
at least 2 sites: preferred & alternate
¾
number of units, type, size, fuel
¾
hours of operation
¾
generating capacity
¾
pollutant emissions
¾
need for facility in terms of demand
¾
alternative sources of electric supply including energy
conservation & efficiency
¾
Natural resources affected
¾
Ecological resources affected
¾
Community information
•
According to IEPA, siting is required for facilities >12,000 kW.
•
Ch. PSC 4 establishes procedures to provide the PSC with
adequate information on the short- and long-term environmental
effects of its actions as required by the WI Environmental
Protection Act, ch. 274, section 1, laws of 1971 and s. 1.11 of the
Wisconsin Statutes. PSC 4 requires the PSC to prepare an
Environmental Assessment (EA) to assist the PSC in determining
environmental impact of proposed facilities. Combustion turbines
are included as types of projects requiring an EA. The PSC can
approve or deny siting based on the EA or Environmental Impact
Statement (EIS). The EA is made available to the public, and
hearings are held.
Water
Water Resources
(Wisconsin Statues, Chapter
28, Subchapter II)
Water Quality and Quantity;
General Regulations
(Wisconsin Statues, Chapter
28, Subchapter III)
http://www.legis.state.wi.us/rsb/S
tatutes.html
DNR Rules, Chapter NR 142
•
Wisconsin law provides for:
1. development of statewide water quantity resources plan
2. registration and annual reporting (with fees) of major
withdrawals (>100,000 gal/day in 30-day period)
3. permit approval process (with administrative hearing process)
for construction, development and operation of wells where
capacity and rate of withdrawal of groundwater from all wells on
one property is in excess of 100,000 gal/day. Approval is
withheld or restricted if withdrawal will adversely effect or
reduce availability of public water supply or doesn’t meet
grounds for approval which are:
¾
No adverse effect on public water rights in navigable waters
¾
no conflict with any applicable plan for future uses of waters
of state or water quantity resources plan
¾
Reasonable conservation practices have been incorporated
¾
no significant adverse impact on environment and
ecosystem of the Great Lakes basin or the upper
Mississippi River basin
¾
plan for withdrawal consistent with the protection of public
health, safety and welfare and not detrimental to public
interest
¾
no significant detrimental effect on the quantity and quality
of the waters of the state (even more factors apply if the
proposed withdrawal will result in an “interbasin diversion”)
4. permit approval process for diversion of water from any lake or
stream >2,000,000 gal/day in any 30-day period. If DNR
receives application for a withdrawal from the Great lakes basin
that will result in a new water loss averaging 5,000,000 gal/day
in any 30-day period, DNR notifies governors of other Great
Lakes States, requesting their input.
•
Regulations define “water loss” and “consumptive use.”
•
Rules incorporate methods for citizens to initiate DNR
investigations of alleged violations.
Note: