ILLINOIS POLLUTION CONTROL BOARD
    October 17,
    1980
    ILLINOIS POWER COMPANY,
    (Hennepin Power Plant),
    )
    Petitioner,
    v.
    )
    PCB 79—243
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD
    (by D.
    Satchell):
    On October 10, 1980 Illinois Power Company filed a motion to
    extend the stay of NPDES permit conditions granted by the Board
    in Orders entered March
    6 and July
    10, 1980
    (37 PCB 479 and
    PCB
    ).
    Under the July 10 Order the stay will expire thirty-
    five days after the board’s Opinion and Order of October 2,
    1980.
    Illinois Power states that it is considering filing a motion
    for
    reconsideration and that it wants the stay extended to beyond the
    Board’s decision on any such motion.
    The motion is granted.
    If
    a motion for reconsideration of the October
    2,
    1980 Order is filed
    by either party within the time provided by Procedural Rule 333,
    then the March
    6 stay will continue until thirty-five days after
    entry of an order deciding such motion; otherwise,
    the stay will
    expire
    as provided in the July 10,
    1980 Order.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Conti~l
    Board, her b
    certify that the above Order was adopted on the
    /7
    ~
    day of
    _______________,
    1980 by a vote of
    ~‘f—o
    Christan L. Mo
    Clerk
    Illinois Pollution Control Board