ILLINOIS POLLUTION CONTROL BOARD
August 23, 2001
CHEMREX, INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 02-19
(UST - Appeal)
ORDER OF THE BOARD (by C.A. Manning):
On August 14, 2001, ChemRex, Inc. (ChemRex) filed a petition for review of an Illinois
Environmental Protection Agency (Agency) determination disapproving ChemRex’s
groundwater and off-site soil investigation report and corrective action plan (characterized by the
Agency as a High Priority Corrective Action Plan and budget). ChemRex’s facility is located in
Chicago Heights, Cook County.
The Board accepts this matter for hearing. The Board's rules require that the Agency file
its entire record within 30 days of notice of the petition. See 35 Ill. Adm. Code 105.116.
Hearings must be scheduled and completed in a timely manner, pursuant to the applicable
statutory decision deadline, or the deadline as extended by waiver. See 35 Ill. Adm. Code.
101.308, 105.114.
On August 14, 2001, the petitioner also filed a waiver of the decision deadline for 60
days to February 11, 2002.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the
above order was adopted on the 23rd day of August 2001 by a vote of 7-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board