ILLINOIS POLLUTION CONTROL BOARD
    May 2, 1996
    HYDROSOL, INC.,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 96-221
    (Permit Appeal - Air)
    ORDER OF THE BOARD (by C.A. Manning):
    On April 25, 1996, Hydrosol, Inc. filed a petition for review of permit regarding its
    facility located at 8407 South 77th Avenue, Bridgeview, Cook County, Illinois. This matter is
    accepted for hearing.
    The hearing must be scheduled and completed in a timely manner. The Board will
    assign a hearing officer to conduct hearings consistent with this order, and the Clerk of the
    Board shall promptly issue appropriate directions to that assigned hearing officer.
    The assigned hearing officer shall inform the Clerk of the Board of the time and
    location of the hearing at least 40 days in advance of hearing so that public notice of hearing
    may be published. After hearing, the hearing officer shall submit an exhibit list, a statement
    regarding credibility of witnesses and all actual exhibits to the Board within five days of the
    hearing. Any briefing schedule shall provide for final filings as expeditiously as possible and,
    in time-limited cases, no later than 30 days prior to the decision due date, which is the final
    regularly scheduled Board meeting date on or before the statutory or deferred decision
    deadline. Absent any future waivers of the decision deadline, the statutory decision deadline is
    now August 23, 1996 (120 days from April 25, 1996); the Board meeting immediately
    preceding the due date is scheduled for August 15, 1996.
    If after appropriate consultation with the parties, the parties fail to provide an
    acceptable hearing date or if after an attempt the hearing officer is unable to consult with the
    parties, the hearing officer shall unilaterally set a hearing date in conformance with the
    schedule above. The hearing officer and the parties are encouraged to expedite this proceeding
    as much as possible. The Board notes that Board rules (35 Ill. Adm. Code 105.102) require
    the Agency to file the entire Agency record of the permit application within 14 days of notice
    of the petition.
    IT IS SO ORDERED.

    2
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the _____ day of ___________, 1996, by a vote of
    ______________.
    ___________________________________
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board