ILLINOIS POLLUTION CONTROL BOARD
October 3, 1996
NPK STORAGE, INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 97-22
(UST - Appeal)
ORDER OF THE BOARD (by C.A. Manning):
On July 25, 1996 the Illinois Environmental Protection Agency (Agency) and NPK
Storage, Inc. (NPK) filed a joint notice of extension of the 35-day appeal period pursuant to
Section 40 of the Environmental Protection Act, relating to the June 28, 1996 Agency
determination. The final determination concerns the NPK’s
site located at 1101 East
Sangamon Street, Decatur
,
Macon County, Illinois. On September 27, 1996 the Board
received the NPK’s petition for review accompanied by a waiver of the decision deadline until
May 1, 1997. This matter is accepted for hearing.
The hearing must be scheduled and completed in a timely manner, consistent with
Board practices and the applicable statutory decision deadline, or the decision deadline as
extended by a waiver. (Petitioner may file a waiver of the statutory decision deadline pursuant
to 35 Ill. Adm. Code 101.105.) The Board will assign a hearing officer to conduct hearings
consistent with this order, and the Clerk of the Board shall promptly issue appropriate
directions to that assigned hearing officer.
The assigned hearing officer shall inform the Clerk of the Board of the time and
location of the hearing at least 40 days in advance of hearing so that public notice of hearing
may be published. After hearing, the hearing officer shall submit an exhibit list, a statement
regarding credibility of witnesses, and all actual exhibits to the Board within five days of the
hearing.
Any briefing schedule shall provide for final filings as expeditiously as possible and, in
time-limited cases, no later than 30 days prior to the decision due date, which is the final
regularly scheduled Board meeting date on or before the statutory or deferred decision
deadline.
If after appropriate consultation with the parties, the parties fail to provide an
acceptable hearing date or if after an attempt the hearing officer is unable to consult with the
parties, the hearing officer shall unilaterally set a hearing date in conformance with the
schedule above. The hearing officer and the parties are encouraged to expedite this proceeding
2
as much as possible. The Board notes that Board rules (35 Ill. Adm. Code 105.102) require
the Agency to file the entire Agency record of the corrective action completion report within
14 days of notice of the petition.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
the above order was adopted on the _____ day of ___________, 1996, by a vote of
______________.
___________________________________
Dorothy M. Gunn, Clerk