ILLINOIS POLLUTION CONTROL BOARD
    December 19, 1996
    CITY OF MOLINE,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 97-39
    (Variance - Water)
    OPINION AND ORDER OF THE BOARD (by J. Yi):
    On August 23, 1996, the City of Moline (Moline) filed a request for variance from the
    Board's regulations 35 Ill. Adm. Code 306.303, 306.304, and 306.305 for a period of four
    years.
    1
    Moline makes this request to reinstate a former sanitary sewer overflow so that it can
    investigate and correct an infiltration and inflow problem that has led to sewer surcharging and
    basement back-ups during periods of extended wet weather and/or heavy rainfall events.
    On October 3, 1996, the Illinois Environmental Protection Agency (Agency) filed its
    recommendation recommending that the variance be granted with certain conditions.
    2
    Moline
    did not file a response to the Agency’s recommendation. Moline waived hearing and no
    hearing was held.
    The Board's responsibility in this matter arises from the Environmental Protection Act
    (Act) (415 ILCS 5/1 et seq. (1994).) The Board is charged in the Act with the responsibility of
    granting variance from Board regulations whenever it is found that compliance with the
    regulations would impose an arbitrary or unreasonable hardship upon the petitioner. (415
    ILCS 5/35(a).) The Agency is required to appear in hearings on variance petitions. (415
    ILCS 5/4(f).) The Agency is also charged, among other matters, with the responsibility of
    investigating each variance petition and making a recommendation to the Board as to the
    disposition of the petition. (415 ILCS 5/37(a).)
    BACKGROUND
    Moline states that homeowners in the City have recently experienced unprecedented
    basement flooding believed to be due to excessive inflow and infiltration from yet unknown
    sources, public or private, resulting in surcharging of the sanitary sewer system. (Pet. at 1.)
    Moline claims that in order to comply with 35 Ill. Adm. Code 306.305 an existing sanitary
    1
    The petition filed by Moline will be referenced to as “Pet. at ”and petitioners exhibits will be
    referenced to as “Exh. at ”.
    2
    The Agency’s recommendation will be referred to as “Rec. at ”.

    2
    sewer overflow (SSO) was removed in 1995 in conjunction with a street construction project at
    27
    th
    Street. (Pet. At 1.) Moline asserts that the former overflow pipe was approximately 12",
    was connected to an 18" storm sewer and discharged to a ravine. (Pet. at 1, Exh. D.)
    Moline states that it is requesting this variance in order “to reinstate the former sanitary
    sewer overflow at the existing sanitary manhole on the existing 10" sanitary sewer,
    approximately 150 feet north of the intersection of 27th Street and 24th Avenue”. (Pet. at 1.)
    Moline maintains that the reinstated SSO would be reinstated at its prior elevation since the
    former overflow pipe through the existing manhole wall still exists as a plugged pipe. (Pet. at
    1.) Additionally Moline states that “[t]he flow line of the existing plugged pipe is
    approximately 4 feet above the invert of the existing sanitary manhole” and would be
    “reconnected to the existing 18" storm sewer system at a newly constructed storm sewer inlet
    structure adjacent to the existing sanitary manhole”. (Pet. at 1.) Moline alleges that the
    volume of the proposed SSO will vary depending on the intensity and duration of a particular
    rainfall event if there is any volume at all. (Pet. at 1.) Moline states that “[t]he concentration
    of the sanitary sewage will likely be diluted by inflow and infiltration introduced to the
    sanitary sewer”. (Pet. at 1.)
    Moline states that the claimed basement flooding in May 1996 occurred during a period
    of sustained rainfall for most of the month and that the “records obtained from the National
    Climatic Data Center, the Moline weather station recorded 9.26 inches of precipitation in
    May”. (Pet. at 1-2.) Moline asserts that there were 19 days where at least 0.01 inches of rain
    was received, resulting in saturated ground conditions and that the total rainfall was 4.96
    inches above the May norm. (Pet. at 2.) Moline claims that that similar weather conditions
    are not expected to reoccur in the near future. (Pet. at 2, Exh. at G, H, and I.) Moline
    believes that the sewer back-ups are caused by a combination of the heavy rainfalls and
    possible illegal connections and dilapidated conditions of the sewer. (Pet. at 1-2.)
    The Agency states that it agrees with Moline’s statement of facts and that it is “not
    aware of any additional facts, besides those contained in the petition and this recommendation,
    that are relevant to the disposition of this matter”. (Rec. at 2.)
    REGULATORY FRAMEWORK
    Moline is requesting a variance from the Board's water regulations set forth at 35 Ill.
    Adm. Code 306 Performance Criteria. Specifically, Moline requests variance from 35 Ill.
    Adm. Code 306.303, 306.304, and 306.305. Section 306.303, Excess Infiltration states:
    Excess infiltration into sewers shall be eliminated, and the maximum practicable
    flow shall be conveyed to treatment facilities.
    Section 306.304 Overflows
    Overflows from sanitary sewers are expressly prohibited.

    3
    Section 306.305 Treatment of Overflows and Bypasses
    All combined sewer overflows and treatment plant bypasses shall be
    given sufficient treatment to prevent pollution, or the violation of
    applicable water standards unless an exception has been granted by the
    Board pursuant to Subpart D.
    Sufficient treatment shall consist of the following:
    a)
    All dry weather flows, and the first flush of storm flows
    as determined by the Agency, shall meet the applicable effluent
    standards; and
    b)
    Additional flows, as determined by the Agency but not
    less than ten time the average dry weather flow for the design
    year, shall receive a minimum of primary treatment and
    disinfection with adequate retention time; and
    c)
    Flows in excess of those described in subsection (b) shall
    be treated, in whole or in part, to the extent necessary to prevent
    accumulations of sludge deposits, floating debris and solids in
    accordance with 35 Ill. Adm. Code 302.203, and to prevent
    depression of oxygen levels; or
    d)
    Compliance with a treatment program authorized by the
    Board in an exception granted pursuant to Subpart D.
    In determining whether any variance is to be granted, the Act requires the Board to
    determine whether a petitioner has presented adequate proof that immediate compliance with
    the Board regulations at issue would impose an arbitrary or unreasonable hardship. (415 ILCS
    5/35(a)(1992)) Furthermore, the burden is upon the petitioner to show that its claimed
    hardship outweighs the public interest in attaining compliance with regulations designed to
    protect the public. (Willowbrook Motel v. Pollution Control Board, (1985), 135 Ill. App.3d
    343, 481 N.E.2d 1032.) Only with such a showing can the claimed hardship rise to the level
    of arbitrary or unreasonable hardship.
    A further feature of a variance is that it is, by its nature, a temporary reprieve from
    compliance with the Board's regulations, and compliance is to be sought regardless of the
    hardship which the task of eventual compliance presents an individual polluter. (Monsanto
    Co. v. IPCB, (1977), 67 Ill.2d 276, 367 N.E.2d 684.) Accordingly, except in certain special
    circumstances, a variance petitioner is required, as a condition to grant of variance, to commit
    to a plan which is reasonably calculated to achieve compliance within the term of the variance.
    COMPLIANCE PLAN

    4
    Moline states as part of its compliance plan that “[b]eginning in the Summer of 1996,
    the City will undertake a sewer system evaluation study to identify potential sources of inflow
    and infiltration”. (Pet. at 2.). Moline states further that the “study will include smoke and
    dye flow testing, sewer televising and household surveys” and is expected to proceed
    throughout this summer and fall. (pet. at 2.) Moline claims that “[i]f illegal connections to
    the sanitary sewer are found, they will be eliminated”. (Pet. at 2.) Moline provided the
    following compliance plan in its petition:
    27th Street Area Sanitary Sewer Compliance Time Schedule
    Start Finish
    Estimated Costs
    Phase
    Undertaking
    Date
    Date
    I.
    Conduct Sewer Study
    7/15/96 6/15/97
    By City Forces
    II.
    Eliminate Illegal Connections
    If Found
    1/1/97 9/19/97
    By City Forces
    III.
    Complete Point Repairs
    If Required
    10/1/97 10/1/97
    By City Forces
    or Contractor
    $100,000
    ±
    IV.
    Evaluate effectiveness of previous
    actions. Implement other actions as necessary.
    1/1/99 6/30/00
    By City
    $ - ?
    Moline state that it will achieve compliance by June 30, 2000 by eliminating the SSO
    connection to the storm sewer. (Pet. at 2.)
    ENVIRONMENTAL IMPACT
    Moline states that “[t]he environmental impact of the proposed variance is projected to
    be minimal on plant and animal life subject to the sanitary sewer discharge into the storm
    sewer and the storm sewer’s subsequent discharge”. (Pet. at 2.) Moline asserts that the
    impact on human health of the SSO should be viewed as an improvement when compared to
    the possibility of raw sewage backing up into household basements. (Pet. at 2.) Additionally,
    Moline claims that “[t]he sanitary sewer overflow will likely be diluted by the additional flow
    contributions from other area storm sewers, prior to discharge in a remote ravine location”.
    (Pet. at 2, Exh. D, E, and F.)
    The Agency asserts that the environmental impact during the variance period should be
    minimal. (Rec. at 2.) The Agency states, citing to page 2 of the petition, “[a]s described in

    5
    the petition, the SSO should be diluted by the additional flow contributions from tributary
    storm sewers prior to being discharged to the ravine, and should then be further diluted as
    more of the storm water ravine discharges join together prior to the final discharge point at the
    Rock River”. (Rec at 2-3.)
    HARDSHIP
    The claimed hardship stated by Moline is that during heavy rain events numerous
    homeowners have sewage backing up into their houses. (Pet. at 1.) Moline further asserts
    that to determine a plan to correct for the inflow and infiltration depends on the findings of the
    sanitary sewer plan discussed previously. (Pet. at 3.) Therefore without the variance Moline
    will not be able to provide immediate relief from inflow and infiltration, which results in the
    sewer back-ups into houses causing health problems and property damage. (Pet. at 3.)
    The Agency states that “Moline has demonstrated that compliance with the Illinois
    PCB’s regulations would impose an arbitrary or unreasonable hardship as required by Section
    35 of the Environmental Protection Act (‘Act’) 415 ILCS 5/35”. (Rec. at 3.)
    CONSISTENCY WITH FEDERAL LAW
    Moline makes no statement as to whether the grant of the requested variance would be
    consistent with federal law. The Agency states that there are no applicable federal laws or
    regulations which preclude the granting of this variance as long as Moline receives a National
    Pollutant Discharge Elimination System (“NPDES”) permit for the SSO. (Rec. at 3.) As part
    of the recommendation of grant, the Agency included certain conditions, one of which
    conditions was that Moline must obtain a NPDES permit for the SSO. (Rec. at 3.)
    We agree with the Agency that as long as Moline receives a NPDES permit for the
    SSO the grant of the variance would be consistent with federal law.
    CONCLUSION
    Based on the record the Board finds that Moline has established that immediate
    compliance with 35 Ill. Adm. Code 306.303, 306.304, and 306.305 constitutes an arbitrary or
    unreasonable hardship. Moline has demonstrated that there would be minimal environmental
    impact for the variance period.
    The Board finds that temporary relief which is granted by this variance does not pose a
    significant risk to environmental health. Moline has demonstrated that during the variance
    period there will be a limited number of times in which the SSO will be needed and as a
    condition to grant we will be requiring Moline to obtain an NPDES permit for those limited
    times there is a discharge from the SSO. The Board will grant the variance with the conditions
    recommended by the Agency. The Board notes that the four year variance period should be
    more than adequate for Moline to investigate and achieve compliance, and without an
    appropriate showing a request for a variance extension or another variance may not be
    appropriate.

    6
    This opinion constitutes the Board findings of fact and conclusions of law in this
    matter.
    ORDER
    The Board hereby grants the City of Moline a variance from 35 Ill. Adm. Code
    306.303, 306.304, and 306.305 so that it may investigate and correct the infiltration and
    inflow problem that has led to sewer surcharging and basement back-ups during periods of
    extended wet weather and/or heavy rainfall events. This variance becomes effective on the
    date of this final order and terminates on June 30, 2000. The variance is subject to the
    following conditions:
    1.
    During the variance period, Moline shall operate its sanitary sewer system to the
    best of its ability, providing the most efficient and effective transport as is
    practicable. Additionally, Moline shall perform the evaluation and take
    corrective action(s), such as disconnecting illegal connections and making
    repairs, as expeditiously as possible to minimize the period of time the SSO will
    need to be connected.
    2.
    Moline shall obtain an NPDES permit for the SSO prior to re-establishing the
    SSO.
    3.
    Moline shall obtain any other permits necessary to complete the project of
    rehabilitating the sanitary sewers described in its variance petition.
    4.
    This variance shall end when the overflow point is eliminated or on June 30,
    2000, whichever occurs first.
    5.
    Moline shall install an alarm system which will alert Moline that the SSO has
    been activated which will enable Moline, during the variance period, to monitor
    and sample the SSO as required by the applicable NPDES permit.
    IT IS SO ORDERED.
    Board member J. Theodore Meyer dissented.
    Board member Kathleen M. Hennessey abstained.
    If the petitioner chooses to accept this variance subject to the above order, within forty-
    five days of the grant of the variance, the petitioner must execute and forward the attached
    certificate of acceptance and agreement to:
    Margaret Howard

    7
    Division of Legal Counsel
    Illinois Environmental Protection Agency
    2200 Churchill Road
    Post Office Box 19276
    Springfield, Illinois 62794-9276
    Once executed and received, that certificate of acceptance and agreement shall bind the
    petitioner to all terms and conditions of the granted variance. The 45-day period shall be held
    in abeyance during any period that this matter is appealed. Failure to execute and forward the
    certificate within 45-days renders this variance void. The form of certificate is as follows:
    CERTIFICATION
    I (we), ____________________________________________, hereby accept and agree
    to be bound by all terms and conditions of the opinion and order of the Pollution Control
    Board in PCB 97-39, December 19, 1996.
    Petitioner
    __________________________________________
    Authorized Agent
    __________________________________________
    Title
    __________________________________________
    Date
    Section 41 of the Environmental Protection Act (415 ILCS 5/41) provides for the
    appeal of final Board orders within 35 days of the date of service of this order. (See also 35
    Ill. Adm. Code 101.246, Motion for Reconsideration.)
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above opinion and order was adopted on the ________ day of ___________________,
    1996 by a vote of _______.
    ___________________________________
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board

    Back to top