ILLINOIS POLLUTION CONTROL BOARD
November 16, 1995
COMMUNITY LANDFILL CORPORATION,
)
)
Petitioner,
)
)
v.
)
PCB 95-137
)
(Variance-Land)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
)
DISSENTING OPINION (by J. Theodore Meyer):
I respectfully dissent from the majority opinion. I believe
the Board, in today's order, misapplied relevant case law,
overlooked pertinent facts in this matter and ignored new facts
presented in CLC's Motion for Reconsideration, facts which bear a
connection to due diligence and good faith efforts at compliance,
a key argument upon which the majority relied in its denial of
CLC's request for variance. Therefore, CLC's Motion for
Reconsideration should have been granted. I also reiterate my
position that the September 18, 1995 Board order in this matter
failed to properly weigh the negligible enviromental harm against
the hardships suffered by Community Landfill Corporation (CLC),
the City of Morris and the citizens of Morris. Therefore, CLC
should be granted a prospective variance.
Factual Examination and Application to Relevant Law
In its September 18, 1995 order the Board denied CLC its
request for variance from the deadline for submission of its
significant modification application. The Board reasoned that
CLC failed to prove due diligence in requesting the variance
because it had a deadline for parcel B, missed the deadline,
never asked for an extension of the deadline and then submitted
its request for variance 22 months late. I believe the Board
overlooked similar scenarios present in prior Board cases and
ignored the relevant facts of those cases presented to the Board
in CLC's Motion for Reconsideration. Based upon this new
information, I believe CLC should have received a variance as the
petitioners in prior cases have.
In its Motion for Reconsideration, CLC stated that it
discovered new information regarding the series of events that
occurred in Atkinson Landfill Company, Inc. v. IEPA, PCB 94-259
(January 11, 1995). Specifically, Atkinson missed a September
15, 1993 deadline for submitting its significant modification
application, requested and received an extension until February
15, 1994, missed that deadline, and without any explanation,
submitted a request for variance from that deadline over seven
months late. (Mot. for Recon. at 34.) The Board, in its order
2
granting a retroactive variance, did not seem overly concerned
with the tardy submission of Atkinson's petition for variance.
(Atkinson, PCB 94-259 at 6.).
In the instant matter, the Board relied on information that
Atkinson was subject to the general significant modification
application deadline of September 18, 1994, and therefore was
only two days late in submitting its petition for variance. (PCB
95-137 at p.9.) The Board pointed to this information to support
its argument that Atkinson was diligent and made a good faith
effort in timely requesting a variance, whereas CLC was late in
its request. (Id.) However, the new information CLC set forth
in its Motion for Reconsideration clearly shows a different
timeline of events in Atkinson. Since this information is
directly relevant to the issues in this matter, I would have
granted the Motion for Reconsideration.
In addition to filing their petitions for variance well
after their respective deadlines, both Atkinson and CLC cited to
ongoing negotiations and the desire to avoid the cost of
submitting duplicative applications as the reason for the tardy
filings. (Atkinson, PCB 94-259 at 6, CLC Pet. at 11-12.) The
same rationale was used in another case where the petitioner
submitted its petition for variance three months late. (Envirite
Co. v. IEPA, PCB 94-259 (January 11, 1995.) Arguably, CLC was
almost two years late in submitting its petition for variance, a
substantially more tardy submission than in Atkinson or Envirite.
However, the lateness of CLC's filing is a mitigating factor
relevant to the question of granting a retroactive variance, not
to the question of whether or not a variance should be granted at
all. One could also argue that the Agency recommended a grant of
the variance in Atkinson and Envirite but requested a denial for
CLC. Yet, it was the Agency that recommended CLC seek a variance
in order to achieve compliance. (Tr. at 233-38.) The Agency
cannot now be heard to recommend a denial of the very relief it
encouraged CLC to seek. In sum, the similarities between these
cases outweigh their differences; therefore, for the sake of
consistency and fairness, CLC should have been granted a
variance.
Environmental Impact versus Hardship
The rule of law regarding the burden of proof in petitions
for variance is very clear. The petitioner must prove that
immediate compliance with the regulations at issue would impose
an arbitrary or unreasonable hardship. (415 ILCS 5/35(a).) A
hardship is arbitrary or unreasonable if the petitioner can prove
that it outweighs the public interest in attaining compliance
with regulations designed to protect the public. (We Shred It,
Inc. v. IEPA, PCB 92-180 at 3 (November 18, 1993).)
The question in this case is whether the hardships resulting
3
from a denial of variance outweigh the public interest in
protecting the environment and timely submissions of significant
modification applications. CLC outlined the ramifications if it
is denied a variance: CLC will likely close operations at Morris
Community Landfill; the City of Morris will lose substantial tax
and royalty revenues; and the citizens of Morris will lose the
benefit of free garbage pickup and road services. (Mot. for
Recon. at 12.) On the other hand, little environmental impact is
anticipated since parcel A, the part of Morris Community Landfill
at issue, has been inactive since 1980. (Id.) It is evident,
then, that the hardships in this case outweigh the negligible
environmental harm; therefore, CLC's petition for variance should
have been granted.
As I stated in my previous dissent, the variance granted in
this case should be prospective only. As operator of Parcel B,
CLC was well aware that it had to submit a significant
modification application by June 15, 1993. If lease negotiations
prevented it from submitting an application by that date, CLC
should have asked for an extension. This lack of diligence on
CLC's part precludes the Board from justifying a retroactive
variance. However, a prospective variance is an appropriate
remedy. After all, the ultimate goal for the petitioner is to
achieve compliance as soon as possible. CLC was ready to comply
within 45 days of the Board's September 18, 1995 order. Rather
than delay compliance further, I would grant a 45-day prospective
variance for CLC to submit its significant modification
application to the Agency.
For these reasons, I respectfully dissent
_________________________
J. Theodore Meyer
Board Member
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, do hereby certify that the above dissenting opinion was
filed on the ____________ day of ______________, 1995.
_________________________
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board