ILLINOIS POLLUTION CONTROL BOARD
November 22,
1974
STATE OF ILLINOIS
)
DEPARTMENT
OF
MENTAL
HEALTH
LINCOLN
STATE SCHOOL
)
PETITIONER
v.
)
PCB 74—348
ENVIRONMENTAL
PROTECTION
AGENCY
)
RESPONDENT
)
OPINION
AND
ORDER OF THE BOARD
(by Mr. Marder)
This action involves
a request for variance filed on September
24,
1974, by the Lincoln State School.
Relief is sought from Rule 203
(g) (1) (B)
of the Illinois Pollution Control Board’s Air Pollution
Regulations as it pertains to Petitioner’s two power plants.
The
Agency has interpreted this petition to include
a request for variance
from Rule 2-2.53 of the Rules and Regulations Governing the Control
of Air Pollution
as well
as
a 203
(g) (1) (B)
request.
Although a spec—
ific request for a Rule 2-2.53 variance was not requested,
the Board
will consider the 203
(g) (1) (B)
request to include both pleadings.
Petitioner owns and operates a State School
(residential facility)
for approximately 1900 mentally retarded and otherwise development-
ally disabled persons.
The major facilities
are divided into two
campuses known as main campus and annex campus.
The facilities are
located in proximity to the city of Lincoln, Illinois.
Separate power
plants are required in that these two campuses are approximately 2 1/2
miles apart from each other.
The main campus has as its power plant facility three
50 x 106 BTU/hr
boilers which utilize about 18,000 tons
of coal per year.
The plant
is
used for heating as well
as electric generation.
This facility services
1000 persons.
~‘heannex power plant
is comprised of two 38 x 106 BTU/hr
and one 28 x 10
BTU/hr boilers.
These boilers are used for heating
purposes; however,
no mention is made of electric generating capacity
in the Petition.
Petitioner contends that its discharges
of particulates are approx-
imately 0.82 pounds per million BTU.
Rule 2-2.53 has an allowable em-
ission rate of 0.80 pounds per million BTU.
Agency calculations
using
Compilation of Air Pollutant Emission Factors,
1½P-42, Table 1.1-1, re-
veal the following:
Main Campus Emissions
0.707#/1~6BTU
Annex Campus Emissions
1.41*/lU
BTU
Allowable 2—2.53
0.80*1106 BTU
Main Campus Allowable
203(g)
O.32#/l06 BTU
Annex Campus Allowable 203
(g)
0.38#/106 BTU
14
—
531
—2—
From the above,
it is
clear that only the annex power plant is in
need of a variance from Rule 2—2.53,
and both plants will require var-
iance from 203
(g).
Petitioner has undertaken
a compliance plan which will yield meeting
203
(g)
specifications by November 1,
1975.
Said compliance plan in-
cludes the installation of multi-clone devices at a cost of $260,000.
Petitioner offers the following compliance dates:
Project Approved by State
Sept.
11, 1974
Architectural Design
Oct.
1,
1974
Complete Design
Jan.
1,
1975
Start Construction
March 1,
1975
Compliance
Nov.
1,
1975
The Agency
(Reco Pg.
4)
states that the above compliance plan is
reasonable, and the Board concurs in this conclusion.
While on its face the compliance plan would indicate an undue lack
of initiative on Petitioner’s
part,
the past history of this facility
shows otherwise.
During 1972 plans were initiated to convert all boil-
ers to oil firing;
indeed,
funds were appropriated
($225,000)
in 1973
for such conversion.
However, due to the shortfall of
#2 oil,
this
compliance plan was abandoned.
The above compliance plan was then
drawn up to supplant that which was invalidated by factors beyond Pet-
itioner’s control.
Although information on the subject of environmental impact
is very
sparse, the Board takes note that the location of the subject facili-
ties are in an area which is not normally of high particulate readings.
The Agency also reports that
no
citizen
complaints
have
been
received
pertaining to nuisances
in the area.
Petitioner claims a hardship will occur should this variance be den-
ied.
It is alleged that services for the some
1900 persons
in their
care would be impossible without the heat and electricity generated by
these units.
The Board again states that failure to grant a variance
is
riot a shutdown order but merely subjects Petitioner to possible en-
forcement action.
However,
in this case the possible hardship generated
would
not
be
on
Petitioner
but
on.
those
not
able
to
care
for
themselves,
and
is
thus
more
severe.
In light of the reasonable attempt made at comoliance, the minimal
environmental impact, and the potential hardship, the Board will grant
the requested variance.
In closing,
the
Agency
noted
that
there
were soecific
operational
boiler
deficiencies
~hich
would
serve
to
reduce
the
already
low
part-
iculate
capture
efficiency.
The
Agency
has
pointed
out
that
weekly
settling
chamber
cleanouts
would
serve
to maintain
rated
efficiency.
This
cleanout
procedure
will
become
part
of our order.
14
532
—3—
This
Opinion
constitutes
the
findings
of
fact and conclusions
of
law
of
the
Board.
ORDER
IT
IS THE ORDER of the Pollution Control Board that:
Variance
is
granted
from
Rule
2-2.53
of
the
Rules
and
Regulations
Governing the Control of Air Pollution for the Annex Campus boilers
until May 30,
1975.
Variance is granted from Rule 203
(g) for the Annex Campus boilers
from
May
30,
1975,
to
November
1,
1975.
Variance
is granted from Rule 203
(g)
for the Main Campus boilers
from May 30,
1975,
to November 1,
1975.
Variance is dismissed
as moot from Rule 2—2.53 of the Rules and
Regulations Governing the Control of Air Pollution for the Main Campus
boiler.
The above variances are granted subject to the following conditiions:
A)
Petitioner
shall apply for all necessary construction
and
operating
permits
for
its
coal—fired
boilers.
B)
Petitioner
shall
submit
quarterly
operating
reports
to
the:
Illinois Environmental Protection Agency
Division of Air Pollution Control
Control
Program
Coordinator
2200 Churchill Road
Springfield,
Illinois
62706
Such
reports
shall
contain
at
a
minimum
a
detailed
time-
table
of
the
entire
control
program
and
progress
made
toward completing the installation
of
the
multi-clone
collection devices.
C)
Petitioner
shall
clean
fly ash from the existing chamber
on
the
Annex
Campus
boilers
at
least
once per week.
I,
Christan
L.
Moffett7
Clerk
of
th~ Illinois
Poilution
Control
Board,
certify
tha~ the
above
Opinion
and
Order
was
adotted
by
the
Board
on
the~~~
day
of
~
1974,
by
a
vote
of