ILLINOIS POLLUTION CONTROL BOARD
June 30,
1988
IN THE MATTER OF:
PETITION O~THE CITY OF
JOLIET FOR A SITE SPECIFIC
)
R84—20
RULE FOR THE EAST SIDE
JOLIET WASTEWATER TREATMENT
FACILITY
PROPOSED RULE.
FIRST NOTICE.
PROPOSED OPINION AND ORDER OF THE BOARD
(by 3.
Theodore Meyer):
This matter
is before the Board on
a May 29,
1984 petition
for site specific rulemaking
filed by the City of Joliet.
Joliet
asks that
its East Side Wastewater Treatment Plant
(EWTP)I which
discharges
into Hickory Creek,
be exempted
from the effluent
limitations
for biochemical oxygen demand
(BOD)
and suspended
solids
(SS)
applicable
to Hickory Creek.
Those limitations,
found
at 35
Iii.
Adm. Code 304.120(c),
are 10 milligrams per
liter
(mg/i)
and
12
rng/l, respectively.
Instead, Joliet requests
that the discharges from EWTP be subject
to the BOD and SS
limitations
applicable to the Des
Plaines
River.
Those
standards, set forth at 35
Ill.
Adrn.
Code 304.120(b),
are 20 mg/i
BOD and
25 mg/i
SS.
The merit hearing
in this matter was held on September
25,
1984 at Joliet City Hall.
The Illinois Environmental Protection
Agency
(Agency) submitted supplemental
information on November
5,
1986,
and Joliet provided additional information on November
10,
1986 and January 15,
1987.
On October
14,
1987 the Department
of
Energy and Natural Resources
(DENR) submitted
its economic impact
study
(EcIS),
entitled
“The Economic
Impact of Proposed Site
Specific Changes
to Water Pollution Regulations Affecting Joliet,
Illinois.”
(Ex.
D.)
An economic impact hearing was held
at
Joliet City Hall on March
29, 1988.
The comment period closed on
April
29,
1988.
Background
Joliet’s EWTP
is
an activated sludge plant with
a design
average flow of 22.5 MGD.
The plant has a primary treatment
capacity of
33 MGD,
a secondary treatment capacity of
up
to 45
MGD,
and provides disinfection only for flows
from 45
to
66
MGD.
The
treatment units
include mechanical trash screens and
comminutors,
velocity control
(non—aerated) grit chambers,
rectangular primary clarifiers,
aeration tanks with diffused
aeration equipment, peripheral
feed final clarifiers,
return
sludge pumping equipment,
and chlorination facilities.
Primary
90—617
—2—
sludge and waste activated
sludge are digested
in the primary
anaerobic digesters.
The digested sludge
is concentrated
in the
secondary digester and applied
to farmland.
The plant is located along Hickory Creek
near
its confluence
with the Des Plaines
River.
Hickory Creek flows
into the Des
Plaines jus~below Brandon Dam.
Plant effluent
is discharged
into Hickory Creek
through outfall
001,
which
is located 450 feet
upstream from the Des Plaines.
Outfall
002 operates
as an
emergency bypass,
with those
flows receiving only disinfection.
This second outfall,
located upstream from outfall
001,
was used
Only twice between 1981 and 1984.
(Transcript
of September
25,
1984
(Tr.
I)
at
37.)
Most of
the land along Hickory Creek below
the plant’s outfalls
is owned
by Joliet.
Access
to the creek
is
limited by the plant
to the north
and dense vegetation
to the
south.
There
is
a foot bridge over
the creek about
1500 feet
upstream
of the outfalls.
(Tr.
I at 15—16,
51.)
The lower
portion of Hickory Creek, where
the EWTP
is located, has been
channelized by the Illinois Department
of Transportation
for
flood control purposes.
(Transcript of March
29,
1988 hearing
(Tr.
II) at
53; Tr.
I
at
43.)
Between January 1984 and October
1985,
the average
BOD
in
the plant effluent was 16.5 mg/i,
and the average SS was 17.3
mg/l.
(Ex.
F
at 6.)
The concentration of BOO
in the creek
is
more
than twice as high downstream
from outfall
001
(83 mg/i)
than
it
is upstream from the outfall
(39 mg/i).
(Tr.
I
at 19—
20.)
The levels of SS
are roughly
the same.
Joliet states that
the increased BOD concentration
is due
to backmixing from the Des
Plaines
River.
Dennis Duffield,
Director
of Public Works and
Utilities for Joliet,
testified that the flow of
the creek
literally changes direction,
so that sometimes the river backs
up
into the creek.
(Tr.
I
at 17.)
The testimony
of Richard
Pershall,
the principal author
of
the EcIS,
supports Joliet’s
contention.
Mr. Pershall explained that the backmixing
is
a
hydrologic phenomenon.
Because
the Des Plaines
is at a higher
elevation than Hickory Creek, water from the river flows into the
creek
to a point
a few hundred
feet upstream of
the EWTP.
(Tr.
II
at 27—28.)
Joliet has been working with the Agency
to evaluate
alternatives
to upgrade
the existing wastewater collection and
treatment system since
the mid—l970s.
As
a condition of the
National Pollutant Discharge Elimination system (NPDES)
permit
for
the EWTP,
Joliet is required
to develop and submit for review
a municipal compliance plan
to upgrade
its wastewater facilities
to meet existing rules and regulations.
That plan,
prepared by
Clark Dietz,
Inc.
and revised
in July 1986,
has been admitted
into the record of this case as
Exhibit
F.
The recommended
additions and modifications
to the system are
to be completed
in
seven phases between
1984 and 2007.
The total project cost
in
90—618
—3—
May 1985 dollars
is estimated
at $55,688,000.
(Ex.
F.
at 1.)
The phases of the plan
are:
(1) construction
of separate storm
sewers throughout Joliet;
(2)
the elimination
of combined sewer
overflows
(CSO) where storm sewers have
been constructed,
and the
reduction
in frequency of CSOs at other
locations;
(3) upgrading
the EWTP,
including addition of
final clarifiers and an anaerobic
digester, modification
of the chlorination facilities,
and
construction
of
an interceptor at McDonough Street
to transfer
some flow from the EWTP
to the West Side Wastewater Treatment
Plant
(WWTP);
(3A)
approval
of this site specific rule change or
construction
of
a new effluent sewer
so that the EWTP may
discharge
at levels applicable
to the Des Plaines River;
(4)
the
monitoring and evaluation of the existing CSOs,
so as
to identify
priorities
for
the elimination of the CSO5;
(5) design and
construction
of
improvements at the EWTP to provide for
nitrification;
(6)
a final assessment of the improvements
in
water quality as
a result of
the construction
of storm sewers;
and
(7) any additional work
if required, based upon
the results
of the final assessment of phase
6.
(Ex.
F at 48—55.)
The
Agency approved this plan
in July
1986,
and Joliet has begun work
on many of the phases.
(See Tr.
II at 46—52.)
Compliance Alternatives
There
are five
identified alternatives available
to Joliet
for reducing BOO and SS discharges from the EWTP.
The first
three alternatives
involve additions
to the plant
in the form of
advanced
wastewater technologies,
and include multi—media
filtration, carbon absorption/multi—media
filtration and chemical
coagulation.
The fourth and fifth alternatives, although failing
to reduce effluent levels,
relieve Joliet from meeting water
quality standards
for Hickory Creek
by routing
the plant’s
outfall
to the Des Plaines River which has higher standards
of 20
and
25 mg/l for BOD and SS, respectively.
One alternative
for
rerouting the outfall
is for
it
to
run south under the creek,
then west
in order
that
it discharges downstream from Hickory
Creek.
The other
alternative would involve routing
it directly
west
so that
it discharges
in the Des Plaines, upstream from
Hickory Creek.
The EcIS examined these five alternatives, and
made the following estimates of costs
for each alternative:
Multi—Media Filtration
(Alt.
1)
$
9,258,719
Carbon Absorption
(Alt.
2)
$19,377,263
Chemical Coagulation
(Alt.
3)
$17,834,638
Relocate Outfall
(under Hickory Creek)
(Alt.
4)
$
855,890
Relocate Outfall
(directly west)
(Alt.
5)
$
491,958
90—619
—4—
(Ex.
D at 29—45;
Ec.
D, Table
4.)
Joliet has rejected the advanced treatment technologies
(Alt.
1—3)
as too expensive.
(Petition
at
10; Tr.
I
at
23.)
If
its petition for
a site specific rule
is not granted, Joliet will
construct Alternative
4 and thus extend
the outfall pipe under
Hickory Creek and then west
to
the river.
(Tr.
I at 21—23;
Ex.
F
at
53.
)
Joliet does not believe that Alternative
5, which calls
for routing
the outfall directly southwest
of
the EWTP to the Des
Plaines
just below
the dam,
can be constructed
as
estimated
in
the EcIS.
Mr. Duffield stated that the discharge
at that point
would
be immediately adjacent
to the storm sewer outfall which
is
located
in the toe of
the riverwall.
(Tr.
II
at
54.)
Another
disadvantage with Alternative
5
is that some
or all
of the
effluent would
end up
in Hickory Creek
as Des Plaines River
backwater,
since
the outfall would be upstream from the mouth
of
the creek.
(Ex. D
at.
44.)
A sixth alternative
is
to run
the
outfall directly west of the plant
to the Des Plaines,
above
Brandon Dam.
However,
both Joliet and the EcIS
rejected this
option.
Since
the existing river wall
is
20 feet higher than the
treatment plant property,
a pump would
be required,
adding
significantly
to the cost of the project.
(Tr.
I at 26—27;
Ex.
D
at 44.)
Economic Impact
Joliet does not contend
that compliance with the BOO and SS
limitations
is not technically feasible, but argues that the cost
of compliance
is economically unreasonable when compared
to the
small benefit
to the environment.
Joliet points out that it
is
undertaking
a significant effort
to upgrade its
treatment
facilities and that its municipal compliance plan will
result in
a better
class of
treatment than
is now provided.
The upgrading
of the EWTP will result
in a
longer detention and aeration time
so that ammonia nitrogen will be removed.
Mr. Duffield testified
that the proposal would
at least retain the same level
of BOD in
the effluent,
if not
reduce that
level.
(Tr.
II at 63—64.)
Therefore, Joliet asks that instead of directing funds
to the
construction of
a new outfall the City be allowed
to use those
funds towards the upgrading
of their wastewater system, with
a
greater positive
impact on the environment.
(Tr.
II
at
70.)
In addition
to evaluating compliance alternatives and
estimating their costs,
the EcIS calculated
the costs to Joliet’s
utility customers of implementing each alternative.
Assuming an
average monthly bill of
$10.10, utility bills
would increase as
follows:
.0—620
—5—
Monthly
Increase
Increase
Multi—Media Filtration
(Alt.
1)
$3.38
34
Carbon Absorption
(Alt.
2)
$5.93
59
Chemical Coagulation
(Alt.
3)
$5.20
52
Relocate Outfall
(under
Hickory Creek)
(Alt.
4)
$
.21
2
Relocate Outfall
(directly
west)
(Alt.
5)
$
.10
1
(Ex.
D at 4.)
The EcIS also assessed
the benefits
of reduced
levels
of BOD and SS
in regard to six direct benefit
categories:
(1) recreational opportunities;
(2) aquatic
life;
(3) stream maintenance;
(4)
flood control;
(5) agriculture;
and
(6) human health.
The EcIS concluded that only recreational
opportunities and stream maintenance could be quantified:
the
other
four categories
are significantly impacted by reduced
pollutant levels.
(Ex.
0.
58—66.)
The benefit to
recreational
opportunities was
calculated at $460
(Ex.
D at 59—60), and the
benefit
to stream maintenance was valued at $2332
(Ex.
D at 64—
66).
The EelS thus found a large disparity between the costs of
each alternative and the associated benefits.
Costs
Benefits
Alternative
1
$
9,258,719
$2792
Alternative
2
$19,377,263
$2792
Alternative
3
$17,834,638
$2792
Alternative
4
$
855,890
$2792
Alternative
5
$
491,958
$2792
(Ex. D
at
5;
73—78.)
The cost of Alternative
5,
the least costly
option,
is 176
times as great
as the value of direct benefits.
Joliet believes that the EelS supports
its contention
that
the EWTP outfall
should remain in its current location and that
the additional expense
to relocate the outfall does not provide
benefits even approaching
the cost.
(Tr.
II
at
55.
)
However,
Joliet disputes
the cost estimates made by the EcIS
for
Alternatives
4
and
5.
(Tr.
II at 52—53.)
The EelS estimated the
cost of Alternative
4 at $855,890, while Clark Dietz estimated
the cost
of relocating
the outfall under Hickory Creek
at
90—621
—6—
$3,425,000.
(Ex.
F
at
62.)
Mr. Duffield testified
that he feels
that Clark Dietz’s estimate
is very conservative,
but stated that
the actual cost would approach $2,000,000.
(Tr.
II at
53.)
The
difference
in estimates
is partly attributable
to the fact that
the Clark
Dietz estimate done
for Joliet provides for
a longer
run of pipe out into the rivet rather than ending the pipe at the
river bank as
the
EelS assumed.
(Tr.
II
at
53.)
Mr. Duffield
stated
that he thought that Clark
Dietz had proposed
to extend
the outfall
out into the river so as
to get good mixing of the
effluent with the flow of the Des Plaines.
(Tr.
II
at
62.)
The
difference
in estimates for Alternative
4
is also partly due
to
Joliet’s belief that construction
of the outfall will be very
difficult,
since the pipe will run under the channelized portion
of Hickory Creek and then out into the river.
This will involve
rock excavation
in the river, since
the pipe will be buried.
(Tr.
II
at 53,
60,
62.)
As previously noted, Joliet does not
believe that Alternative
5 can be constructed
as proposed.
(Tr.
Ii at
54,
60—61.)
At the economic impact hearing Mr. Pershall presented
some
cost estimates
to bring
the outfall
into the Des Plaines.
He
estimated that
to bring
the outfall
structure 300 feet into the
river
(1/3 its width)
would cost $1,030,000.
Bringing the
structure 450 feet into the river
(1/2
its width) would cost
$1,112,500.
(Tr.
II
at
19.)
Mr. Pershall testified that there
is
no federal or state requirement that the outfall
be actually
in the river,
and that most wastewater treatment plants only
bring the outfall
to the edge of the river.
(Tr.
II at
20.
Environmental Impact
The record
in this ease contains
no information on the water
quality in the stretch
of Hickory Creek downstream from the EWTP
outfall,
and very little information on the water quality
of the
Des Plaines near its confluence with Hickory Creek.
Joliet
states that due
to the substantial backmixing
of the Des Plaines
in the lower
stretch
of the creek,
the water quality
in the creek
at this point would be expected
to closely resemble that of the
Des Plaines.
Joliet has provided 1976 data from a monitoring
station
in the Des Flames downstream of Hickory Creek which
shows
a mean value
of 9.0 mg/i of dissolved oxygen
(DO)
and 3.03
mg/i
of
ammonia nitrogen.
(That monitoring station was closed by
the Agency
in
1976 due
to budgetary constraints.)
At the merit
hearing the Agency asked
if the effluent from the EWTP causes any
water
quality standard violations
of
DO or ammonia nitrogen in
Hickory Creek.
Joliet stated that
it had
no information on that,
and promised
to do sampling and investigate the issue further.
(Tr.
I at 46—47.)
However,
no such information has been
received.
In sum, Joliet’s position
is that since
the downstream
portion of Hickory Creek
is so closely integrated
with the Des
Plaines River,
little benefit can be achieved by extending
the
outfall from the plant into
the river.
(Petition at
9.)
90—622
—7—
The EelS used water pollution models
in an attempt
to
predict the impact of BOD and
SS on the water quality
in Hickory
Creek.
The
EelS concluded that the environmental degradation
associated with current levels
of effluent
is minimal.
The BOO
model,
using various concentrations
of
effluent BOD, showed that
in all average conditions the DO
in Hickory Creek remained above
S mg/i, which
is considered
sufficient
to support
a healthy
aquatic environment.
(Ex.
D at 49—53.
)
Suspended solids
discharged from the EWTP will not routinely settle
in the creek
because of their minute particle size.
Turbidity
is not expected
to cause problems because current concentrations are well below
harmful
levels.
(Ex.
D at 53—55.)
In its post—hearing comments,
the Agency again expressed its
concern that
the levels
of DO and ammonia nitrogen might be
adversely affected by Joliet’s proposal,
and pointed out that
Joliet had promised
to investigate
the matter.
The Agency stated
that
it continues
to support Joliet’s request for effluent
relief,
but intends
to require water quality monitoring as
a
specific NPDES permit condition.
(Public Comment
(P.C.)
#6
at
1—
2.)
The Agency points out that Hickory Creek is channelized for
flood control purposes and
is therefore unlikely to support
a
diverse aquatic community regardless of water quality.
The
Agency insists that this fact does not justify degradation of
water quality,
but states that
it does not anticipate that
Joliet’s investigation of water quality impacts will reveal any
water quality problems.
(P.C.
#6 at 3.)
The Agency does contend that the BOD model contained in the
EelS should be discounted by
the Board.
First,
the Agency states
that Mr.
Pershall indicated
that he did not really model BOD and
its effects on the creek’s DO,
but rather did
a simple mass
balance calculation of
the DO after
the effluent mixes with the
creek.
(Tr.
II at 34—35.)
Second,
the Agency maintains that the
EelS’s assumption that the DO in the effluent varies directly
with the BOD concentration is simplistic and typically
inaccurate.
Third,
the Agency notes
that the BOO model assumed
that there
is no entrapment of the creek flow at its mouth, while
Joliet has documented the likelihood
of such occurrences.
Finally,
the Agency submits that the model addressed only average
stream conditions,
giving
the model limited utility in
a low flow
situation where adverse impacts are more likely
to occur.
(P.C.
#6 at 3.)
The Board
notes
that the Des Plaines River
is part
of the
Illinois
& Michigan
(I&M)
National Heritage Corridor.
The
Hearing Officer specifically solicited comments on whether that
status
should have any bearing on the proposed regulation.
Responses
to this request were received from the Agency
(P.C.
#6),
the I&M National Heritage Corridor Commission
(P.C.
#2),
the
Illinois Department of Conservation
(P.C.
#3),
the United States
Environmental Protection Agency
(USEPA)
(P.C.
#4), and Joliet
90—623
—8—
(P.C.
#5).
These comments agree that the Des Plaines’ status
as
part of the Corridor should have
little
impact on the Board’s
consideration of Joliet’s proposal.
The Agency and Joliet state
that they believe approval
of the rule would
not adversely affect
the character of the river.
Additionally,
both the Corridor
Commission and the Department of Conservation point out that the
federal
legislation which created
the Corridor specifically
states
that such status
is not
to change existing environmental
standards.
(Public Law 98—398,
Sec.
115(a).)
The comments submitted by the Department
of Conservation and
USEPA also addressed the merits of
the proposal.
The Department
of Conservation opposes Joliet’s request,
based upon its concern
that
a greater BOD load
in the lower
stretches of Hickory Creek
would adversely impact
the area’s
fish.
The Department states
that
a 1983
fisheries sample below Brandon Dam included
12
species
of
fish,
a substantial
improvement over the
4
species
collected
in 1974.
The Department feels
that granting Joliet’s
petition would be
in direct opposition
to the Department’s
efforts
to improve the DO situation and
the fisheries.
(P.C.
#3.)
On the other hand,
by
a
letter from Valdas Adamkus, Regional
Administrator, USEPA states that overall, Joliet’s proposal
appears appropriate.
USEPA feels that the petition is not
contradictory
to federal or state antidegradation provisions,
and
appears consistent with federal antibacksliding provisions.
USEPA concurs with Joliet’s contention the expenditures
to
relocate the outfall
to the river do not appear
justified at this
time.
However,
(JSEPA does note the concerns with assuring
protection of water quality
in Hickory Creek
in the future.
USEPA believes that as
a condition
of approval, adequate
monitoring be
required downstream from the EWTP to characterize
both average and potential low flow conditions
in the creek.
USEPA concludes that granting temporary relief should recognize
the potential need for additional treatment in the future,
if
necessary to protect water quality or potential uses.
(P.C.
#4.)
Conclusions
After considering the record
in this case,
the Board
concludes that Joliet has demonstrated that relief is
warranted.
Therefore,
the Board will propose for First Notice
a
regulation exempting Joliet’s EWTP from the BOD and SS
limitations applicable
to Hickory Creek.
Instead,
the BOD and
SS
limitations applicable
to the Des Plaines
River will apply
to the
EWTP.
The Board believes that the cost
of
relocating
the outfall
to the Des Plaines
is not justified by any predicted
environmental benefits at this time.
The Board also notes that
Joliet
is spending significant sums
to upgrade
its wastewater
collection
and treatment system by carrying out the municipal
compliance plan,
with resulting environmental benefits.
Further,
90—624
—9—
the Board notes
that Joliet’s chosen compliance alternative
(relocating
the outfall) would not reduce
the levels
of BOO and
SS discharged from the EWTP, but simply discharge the effluent
directly
to the Des Plaines.
Thus,
the denial
of Joliet’s
petition would,
at best,
improve the water quality of only the
450
feet of Hickory Creek between
the present location
of the
outfall and the creek’s confluence with the Des Flames.
However,
the Board shares
the concerns voiced by the Agency,
the Department of Conservation,
and USEPA about the effect of the
proposal on water quality standards, especially levels
of DO and
ammonia nitrogen.
The little information
in the record on water
quality is either outdated or
speculative.
Therefore,
the
regulation proposed today will be temporary,
and will expire on
January
1,
1994.
This period will allow Joliet
to conduct water
quality monitoring
for approximately three years,
and still
have
time
to petition
the Board
for permanent relief
if the monitoring
results are positive.*
Joliet should work with the Agency
to
develop
a monitoring program.
That program shall include
information on,
among
other
things,
average and low flow
conditions
in Hickory Creek downstream from the EWTP,
especially
levels
of DO and ammonia nitrogen.
The program shall
also
address the effects of the EWTP discharge on the area fish and
their
ability to move between
the Des Plaines
and the upstream
portion
of Hickory Creek.
By promulgating
a temporary regulation
the Board
is able
to grant relief
to Joliet while addressing
the
water quality concerns raised
in this proceeding.
ORDER
The Board hereby directs the Clerk
of the Board
to cause
publication
in the Illinois Register
of the First Notice of the
following amendment.
TITLE
35:
ENVIRONMENTAL PROTECTION
SUBTITLE C:
WATER POLLUTION
CHAPTER
I:
POLLUTION CONTROL BOARD
PART 304
EFFLUENT STANDARDS
SUBPART C:
TEMPORARY EFFLUENT STANDARDS
Section 304.302
City of Joliet East Side
Wastewater Treatment Plant
*This schedule assumes that the proposed
regulation will be
finally adopted and effective before January
1,
1989.
Of course,
Joliet need
not wait until then
to begin
a monitoring program.
90—625
—10—
This Section applies
only to the City of Joliets
East Side
Wastewater Treatment Plant which discharges
into Hickory Creek
in
Will County,
Illinois.
The discharges
of
that plant shall not be
subject
to the standards
of Section 304.120(c), provided
that
those discharges meet
the five day biochemical oxygen demand
(BOO)
and suspended solids limitations of Section
304.120(b)..
This Section will expire on January 1, 1994.
(Source:
Added at 12
Ill. Reg.
_____,
effective
________________)
IT IS SO ORDERED.
I, Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
Board, hereby certify that the above ,P~roposedOpinion and Order
was adopted on the
JO~day
of
_________________,
1988, by a
vote of
7~
.
Illino
on Control Board
90—626