ILLINOIS
POLLUTION
CONTROL
BOARD
Ju:Ly
25,
1974
CHICKASAW
HILLS
UTILITY
COMPANY
INC
Petitioner,
PCB
74~59
ENVIRONMENTAL
PROThCT ION
AGENCY,
Respondent
OPINION
AND
ORDER
OF
THE
BOARD
(by
Nr~
Henss)
Chickasaw Hills Utility Company,
lnc. owns and operates a
sewage treatment plant at North Aurora, Il1inois~ The plant
has a design average flow of
0,1
mgd and at
this
time the flow
which is tributary to the plant is approximately 0~037mgth
Chlorinated plant effluent is discharged
to Long Run Creek~ Under
Rule 404(f)
of the
Water Pollution Regulations of Illinois the
effluent standards for this facility are 4
mg/i
BOD,
5 mg/i
suspended solids and 400 fecal coliforms per 100 ml,
Grab
sampling by the Agency indicates that the plant is operating in
violation of Rule
404(f) but EPA field personnel have not ob~
served any adverse environmental impact attributable to Petitioner~s
effiuent~ Plant expansion and upgrading
is currently underway to
achieve compliance with Rule 404(f)
by
September
1, i974~
Petitioner recuests variance from Rule 404(f)
so that sewer
lines may
be
installed to connect to
a proposed subdivision known
as Pebble Creek~
It
is stated that the entrepreneurs in Pebble
Creek have made
a considerable investment and that installation
of
the sanitary sewer is of paramount importance to them~ These
entrepreneurs are not parties
to
this
proceeding~
The Petitioner
utility
company alleges that a failure to install the sewer lines
will
result in a loss of potential customers in the subdivision,
and that such
loss constitutes an unreasonable hardship for the
utility company~
The EPA has informed Petitioner that “the combination
of
the
existing waste load and the anticipated future waste load on the
treatment facilities will place the existing treatment units at
approximately 70
of their design capacity of
1,000
P.:E.
In other
words the existing facilities have sufficient capacity to provide
treatment for approximately another
300 P~E~
We will issue permits
to construct and operate sanitary sewers
to serve only another
300
P E.”
—
2~
The record does not reveal how much additional load
Petitioner wishes to receive through the installation of the
new sewer lines.
As far as we know the permits to construct
and operate sanitary sewers to serve an additional
300
P.E.
could very well be adequate.
The Agency takes the position
that it will be proper to issue such a limited permit even
though Petitioner is not in compliance with Rule 404(f), since
Petitioner~sinability to currently meet the requirements of
Rule 404(f)
is not due to hydraulic or organic overload.
The
Agency states that
“
the connections of sewer extensions and
laterals to the system has no effect on the treatment plantts
ability to meet standards,
and the Agency thus believes it is
not precluded from issuing permits
for such facilities by
operation of Rule 921(a)
of Chapter
3”.
Therefore,
the Agency
has issued the necessary permit to install and operate trunk
sewers serving the subdivision and will issue a permit for the
lateral sewers in due course.
Under this set of circumstances we fail to see any arbitrary
or
unreasonable
hardship
to
the
Petitioner.
The
only
hint
of
hardship
has been Petitioner2s claim that it will be unable to
obtain additional customers if the Agency refuses to issue a
permit for the installation of the underground sewer lines.
The
record
indicates
that
this
alleged
hardship
has
not
materialized.
The
EPA
recommends
that
the
variance
be
denied
since
proof
that the
sewage
treatment
plant
is
currently
in
violation
of
Rule 404(f)
is
not
in
itself
sufficient
grounds
for
the
grant
of
a
variance.
We
agree
and
will
deny
the
variance
because
Petitioner
has
failed
to
show
that
it
will
suffer
an
arbitrary
or
unreasonable
hardship.
The record does not indicate that sewer connections to this
facility have been prohibited either by the Agency or by this Board.
The reasons for Petitioner~sinability to meet the standards of
Rule
404(f)
are unclear from the record but will apparently be
overcome through upgrading which is to be completed by September 1,
1974.
Under those circumstances it would be proper to proceed
with the installation of the sewers to the new subdivision.
Con~
struction at the subdivision should be authorized
to proceed
concurrently with the upgrading of the sewage treatment plant and
the installation of sewer mains and laterals.
It is our opinion that the utility company already has what
it requests and has failed to establish its legal right to a
variance.
Therefore,
the variance petition will be denied without
prejudice.
This Opinion constitutes the findings of fact and conclusions
of law of the Illinois Pollution Control Board.
13
—
188
—3—
ORDER
It is ordered that the variance petition filed herein by
Chickasaw Hills Utility Company,
Inc. be and it is hereby
denied without prejudice.
I, Christan L, Moffett, Clerk of the Illinois Pollution Control
Board,
e eby c
tify the above Opinion and Order was adopted
this
1974 by a vote of _______to~~,
13
—
189