ILLINOIS POLLUTION CONTROL BOARD
March 25,
1976
JACKSONVILLE MENTAL HEALTH
&
DEVELOPMENTAL CENTER,
)
Petitioner,
V.
)
PCB 75—451
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Zeitlin):
This matter is before the Board on an Amended Petition for
Variance filed January 21,
19.76, wherein Petitioner Jacksonville
Mental Health
& Developmental Center
(Jacksonville)
seeks relief
from the particulate emission limitations contained
in Rule 2—2.53
of the Rules and Regulations Governing the Control
of Air Pollution
(hereinafter
“old rules”)
and Rule 203(g)
of Ch.
2: Air Pollution,
of this Board’s Rules
and
Regulations.
The Amended Petition
supplements
an earlier Petition which the Board found inadequate
in
an Interim Order dated December
4,
1975.
A Recommendation was filed
by the Environmental Protection Agency
(Agency)
on February
20, 1976.
No hearing was held in
this
matter.
The Variance requested herein constitutes an extension of
a
Variance granted in
a previous case,
PCB 74-356
(December
19,
1974.
In that case,
the Board granted Jacksonville a Variance from Rule
2-2.53 of the “old rules” and from the compliance date of May 30,
1975
contained in Rule
203(g)
o~h.
2:
Air Pollution
(hereinafter “Regula-
tions”), until October
1,
1975.
The Board’s Opinion and Order there
approved Jacksonville’s compliance plan for control of particulate
emissions from four existing coal-fired,
steam boilers. That plan,
estimated to have a total cost of $180,000, called for the installation
of multi—clone collection devices on the existing boilers.
Boilers
No.
1 and No.
3 were to be retrofitted with the collection devices
by October
1,
1975, while boilers No.
2 and No.
4 were
in use.
(Only
two boilers are used at any one time at the Jacksonville facility.)
20—397
—2—
However, Jacksonville states that it cannot begin work on
No.
3
boiler until the work on No.
1 has been completed, and that it antici-
pates a “completion date of March
1,
1976.”
The Agency’s Recommendation
points out that the Amended Petition filed by Jacksonville
is not
entirely accurate; work on boiler No.
1 only will be completed by
approximately March
1,
1976.
It will require until April
1,
1976
to
complete work on boiler No.
3.
After that, boilers
No.
1 and 3 will
be in compliance with the applicable particulate standards, and boilers
No.
2 and
4 can be taken off line,
and will themselves be retrofitted
and
in compliance by January,
1977.
(It is not entirely clear whether
boiler No.
2 will
in fact be retrofitted for compliance,
or retired.)
The Agency Recommendation also points out that Jacksonville has
attempted in good faith to comply with the provisions of our Order
in
PCB 74-356, with the exception of obtaining the appropriate operating
permits from the Agency.
The required compliance plan information and
interim compliance reports have been properly submitted to the Agency.
Although the Amended Petition does not directly address the reason for
the delays
in bringing boilers No.
1 and
3 into compliance,
the Agency’s
Recommendation fills this gap by pointing out that the delays have been
caused by a 6-week work stoppage at the project, and by problems
in
obtaining necessary appropriations for completion of the project, both
being beyond Jacksonville’s control.
Based on these facts and on our earlier
Opinion
and Order
in
PCB 74-356, we are again disposed to grant a Variance.
With its Amended Petition,
Jacksonville submitted relevant data
from the Agency’s 1974 Annual Air Quality Report, citing specific
data concerning particulate readings at Petersburg,
Illinois
(30 miles
northeast of Petitioner’s
facility)
and Springfield,
Illinois
(35 miles
east of Petitioner’s facility).
Air quality monitors
in Petersburg
recorded an annual concentration
in
1974 of 59 ug/m3, and two sampling
stations in Springfield recorded 72 and 66 ug/m3, respectively.
While we agree with the Agency that data from sampling points so
far removed from Petitioner’s facility cannot fully indicate the effects
of that facility on ambient air quality, we nonetheless find that the
data is sufficient to allow a grant of a Variance here.
The sampling
sites cited are the closest ones to Jacksonville at which samples are
taken for particulate matter,
and would tend to indicate that the area
is generally in compliance with
the
appropriate standard.
In light
of
the relatively small amount of emissions
in question
(1.148 lbs.
particulate per million btu),
and the relatively short Variance period
(compliance by April
1,
1976)
,
we
do not feel that the alternative,
an
individualized program of modeling and/or monitoring for the site in
question,
will be necessary here.
20—398
—3—
Concerning the issue of which boilers
a Variance should apply
to, and for what period of time,
we find that only the operation of
boilers No.
2 and
4 need be covered by a Variance here, while boilers
No.
1 and
3 are being retrofitted with appropriate controls.
Once
boilers
No.
1 and
3 are operating properly,
and since two boilers are
normally in use at any one time,
no other Variance should be needed
for any other boiler.
The Supreme Court’s affirmation of the Appellate
Court’s reversal of Rule 203(g) (1) leaves
in effect the applicable
old rules,
as specifically provided for in Section 49 of the Environ-
mental Protection Act and Rule 114 of Chapter
2:
Air Pollution,
of the
Regulations.
Ill.
Rev.
Stat., Ch.
111—1/2,
§1049
(1975.)
Boilers No.
2 and
4 both constitute “existing sources,” as defined in the old rules,
and are thus covered under Rule 2-2.53.
Finally, the Agency’s Recommendation notes that although controls
on boilers No.
1 and No.
3 should be complete by April
1,
1976,
a
Variance will be necessary until April 15,
1976,
to allow sufficient
time for “debugging”
of the equipment.
We agree that this will
provide a reasonable time for the completion of controls on boilers
No.
1 and
3.
This Opinion constitutes the findings of fact and conclusions
of law of the Board in this matter.
ORDER
IT IS THE ORDER OF THE POLLUTION CONTROL BOARD that Petitioner
Jacksonville Mental Health
& Developmental Center be granted
a Variance
from Rules 2-2.53 of the Rules and Regulations Governing the Control
of Air Pollution for the period October
1,
1975 until April 15,
1976,
to allow the operation of its coal-fired boilers designated boilers
No.
2 and No.
4,
subject to the following conditions:
1.
Petitioner shall apply for and obtain all
appropriate operating permits for its coal-fired
boilers.
2.
Petitioner shall apply for and obtain
all
appropriate construction permits to cover the install-
ation of controls on its coal—fired boilers, as detailed
in the foregoing Opinion.
20
399
—4—
3.
Petitioner shall, during the month of March,
1976,
submit to the Illinois Environmental Protection
Agency a progress report on its compliance plan for
boilers No.
1 and No.
3.
Petitioner shall notify the
Agency in writing immediately upon completion of that
phase of the compliance plan.
4.
Petitioner shall subsequently submit quarterly
reports to the Environmental Protection Agency detailing
progress on its
compliance
plan for boilers No.
2 and
No.
4,
and a final report upon completion of the compliance
plan.
5.
That portion of the Petition for Variance
in this matter requesting Variance from Rule 203(g)
of Chapter
2: Air Pollution,
of the Pollution Control
Board Rules and Regulations,
is dismissed.
I, Christan L.
Moffett, Clerk of the Illinois Pollution
Control Board, her~bycertify the a ave Opinion and Order were
adopted on the
~‘
day of
_________,
1976,
by a vote of
~
Illinois Pollution
20—400