ILLINOIS POLLUTION CONTROL BOARD
    March 25,
    1976
    JACKSONVILLE MENTAL HEALTH
    &
    DEVELOPMENTAL CENTER,
    )
    Petitioner,
    V.
    )
    PCB 75—451
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr.
    Zeitlin):
    This matter is before the Board on an Amended Petition for
    Variance filed January 21,
    19.76, wherein Petitioner Jacksonville
    Mental Health
    & Developmental Center
    (Jacksonville)
    seeks relief
    from the particulate emission limitations contained
    in Rule 2—2.53
    of the Rules and Regulations Governing the Control
    of Air Pollution
    (hereinafter
    “old rules”)
    and Rule 203(g)
    of Ch.
    2: Air Pollution,
    of this Board’s Rules
    and
    Regulations.
    The Amended Petition
    supplements
    an earlier Petition which the Board found inadequate
    in
    an Interim Order dated December
    4,
    1975.
    A Recommendation was filed
    by the Environmental Protection Agency
    (Agency)
    on February
    20, 1976.
    No hearing was held in
    this
    matter.
    The Variance requested herein constitutes an extension of
    a
    Variance granted in
    a previous case,
    PCB 74-356
    (December
    19,
    1974.
    In that case,
    the Board granted Jacksonville a Variance from Rule
    2-2.53 of the “old rules” and from the compliance date of May 30,
    1975
    contained in Rule
    203(g)
    o~h.
    2:
    Air Pollution
    (hereinafter “Regula-
    tions”), until October
    1,
    1975.
    The Board’s Opinion and Order there
    approved Jacksonville’s compliance plan for control of particulate
    emissions from four existing coal-fired,
    steam boilers. That plan,
    estimated to have a total cost of $180,000, called for the installation
    of multi—clone collection devices on the existing boilers.
    Boilers
    No.
    1 and No.
    3 were to be retrofitted with the collection devices
    by October
    1,
    1975, while boilers No.
    2 and No.
    4 were
    in use.
    (Only
    two boilers are used at any one time at the Jacksonville facility.)
    20—397

    —2—
    However, Jacksonville states that it cannot begin work on
    No.
    3
    boiler until the work on No.
    1 has been completed, and that it antici-
    pates a “completion date of March
    1,
    1976.”
    The Agency’s Recommendation
    points out that the Amended Petition filed by Jacksonville
    is not
    entirely accurate; work on boiler No.
    1 only will be completed by
    approximately March
    1,
    1976.
    It will require until April
    1,
    1976
    to
    complete work on boiler No.
    3.
    After that, boilers
    No.
    1 and 3 will
    be in compliance with the applicable particulate standards, and boilers
    No.
    2 and
    4 can be taken off line,
    and will themselves be retrofitted
    and
    in compliance by January,
    1977.
    (It is not entirely clear whether
    boiler No.
    2 will
    in fact be retrofitted for compliance,
    or retired.)
    The Agency Recommendation also points out that Jacksonville has
    attempted in good faith to comply with the provisions of our Order
    in
    PCB 74-356, with the exception of obtaining the appropriate operating
    permits from the Agency.
    The required compliance plan information and
    interim compliance reports have been properly submitted to the Agency.
    Although the Amended Petition does not directly address the reason for
    the delays
    in bringing boilers No.
    1 and
    3 into compliance,
    the Agency’s
    Recommendation fills this gap by pointing out that the delays have been
    caused by a 6-week work stoppage at the project, and by problems
    in
    obtaining necessary appropriations for completion of the project, both
    being beyond Jacksonville’s control.
    Based on these facts and on our earlier
    Opinion
    and Order
    in
    PCB 74-356, we are again disposed to grant a Variance.
    With its Amended Petition,
    Jacksonville submitted relevant data
    from the Agency’s 1974 Annual Air Quality Report, citing specific
    data concerning particulate readings at Petersburg,
    Illinois
    (30 miles
    northeast of Petitioner’s
    facility)
    and Springfield,
    Illinois
    (35 miles
    east of Petitioner’s facility).
    Air quality monitors
    in Petersburg
    recorded an annual concentration
    in
    1974 of 59 ug/m3, and two sampling
    stations in Springfield recorded 72 and 66 ug/m3, respectively.
    While we agree with the Agency that data from sampling points so
    far removed from Petitioner’s facility cannot fully indicate the effects
    of that facility on ambient air quality, we nonetheless find that the
    data is sufficient to allow a grant of a Variance here.
    The sampling
    sites cited are the closest ones to Jacksonville at which samples are
    taken for particulate matter,
    and would tend to indicate that the area
    is generally in compliance with
    the
    appropriate standard.
    In light
    of
    the relatively small amount of emissions
    in question
    (1.148 lbs.
    particulate per million btu),
    and the relatively short Variance period
    (compliance by April
    1,
    1976)
    ,
    we
    do not feel that the alternative,
    an
    individualized program of modeling and/or monitoring for the site in
    question,
    will be necessary here.
    20—398

    —3—
    Concerning the issue of which boilers
    a Variance should apply
    to, and for what period of time,
    we find that only the operation of
    boilers No.
    2 and
    4 need be covered by a Variance here, while boilers
    No.
    1 and
    3 are being retrofitted with appropriate controls.
    Once
    boilers
    No.
    1 and
    3 are operating properly,
    and since two boilers are
    normally in use at any one time,
    no other Variance should be needed
    for any other boiler.
    The Supreme Court’s affirmation of the Appellate
    Court’s reversal of Rule 203(g) (1) leaves
    in effect the applicable
    old rules,
    as specifically provided for in Section 49 of the Environ-
    mental Protection Act and Rule 114 of Chapter
    2:
    Air Pollution,
    of the
    Regulations.
    Ill.
    Rev.
    Stat., Ch.
    111—1/2,
    §1049
    (1975.)
    Boilers No.
    2 and
    4 both constitute “existing sources,” as defined in the old rules,
    and are thus covered under Rule 2-2.53.
    Finally, the Agency’s Recommendation notes that although controls
    on boilers No.
    1 and No.
    3 should be complete by April
    1,
    1976,
    a
    Variance will be necessary until April 15,
    1976,
    to allow sufficient
    time for “debugging”
    of the equipment.
    We agree that this will
    provide a reasonable time for the completion of controls on boilers
    No.
    1 and
    3.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board in this matter.
    ORDER
    IT IS THE ORDER OF THE POLLUTION CONTROL BOARD that Petitioner
    Jacksonville Mental Health
    & Developmental Center be granted
    a Variance
    from Rules 2-2.53 of the Rules and Regulations Governing the Control
    of Air Pollution for the period October
    1,
    1975 until April 15,
    1976,
    to allow the operation of its coal-fired boilers designated boilers
    No.
    2 and No.
    4,
    subject to the following conditions:
    1.
    Petitioner shall apply for and obtain all
    appropriate operating permits for its coal-fired
    boilers.
    2.
    Petitioner shall apply for and obtain
    all
    appropriate construction permits to cover the install-
    ation of controls on its coal—fired boilers, as detailed
    in the foregoing Opinion.
    20
    399

    —4—
    3.
    Petitioner shall, during the month of March,
    1976,
    submit to the Illinois Environmental Protection
    Agency a progress report on its compliance plan for
    boilers No.
    1 and No.
    3.
    Petitioner shall notify the
    Agency in writing immediately upon completion of that
    phase of the compliance plan.
    4.
    Petitioner shall subsequently submit quarterly
    reports to the Environmental Protection Agency detailing
    progress on its
    compliance
    plan for boilers No.
    2 and
    No.
    4,
    and a final report upon completion of the compliance
    plan.
    5.
    That portion of the Petition for Variance
    in this matter requesting Variance from Rule 203(g)
    of Chapter
    2: Air Pollution,
    of the Pollution Control
    Board Rules and Regulations,
    is dismissed.
    I, Christan L.
    Moffett, Clerk of the Illinois Pollution
    Control Board, her~bycertify the a ave Opinion and Order were
    adopted on the
    ~‘
    day of
    _________,
    1976,
    by a vote of
    ~
    Illinois Pollution
    20—400

    Back to top