ILLINOIS POLLUTION CONTROL BOARD
December 20,
1984
ALL-STEEL,
INC.,
Petitioner,
PCB 83—239
ILLINOIS
ENVIRONMENTAL PROTECTION
/~GENCY,
Respondent.
MESSRS.
ED
SCHAEFER AND JEFF
MASI,
NON-ATTORNEYS, APPEARED
ON BEHALF
OF
PETITIONER; AND
PETER
H.
ORLINSKY,
ESQ0, APPEARED ON BEHALF OF RESPONDENT.
OPINION AND ORDER OF THE BOARD
(by J. Marlin):
This
matter
is before the Board upon the December 29,
1983
petition by All—Steel,
Inc.
(All—Steel) for a
six month variance
extension from 35
~.
~
çQd~E~
215.204(g)
(Old Rule 205(n)
(1)(G)
of Chapter
2)
for its facility located in
Montgomery,
Illinois.
In response to a Board Order dated January 12,
1984,
All—Steel fLied
an
amended petition on February 15,
1984.
The
Illinois Environmental
Protection Agency (Agency) filed its
recommendation on March
29, 1984.
Hearing was held in Aurora,
Illinois
on June
11,
1984.
There was
no citizen testimony at
the hearing and the Board has received
no public
comment
in this
matter.
All-Steel owns and
operates a metal office furniture manu-
facturing facility which
includes six paint spray booths and
three paint dip
tanks which apply surface coatings to its pro-
ducts0
All—Steel utilizes in
excess of 100 types and colors
of industrial finishes which are subject to the limitations of
Section 215.204(g), which requires
compliance by December 31,
1982.
A
previous one year variance
was granted by the Board
to All—Steel until December 31, 1983
(51 PCB 129, February 10,
1983; PCB 82-110).
it is the intention of All—Steel to achieve
compliance with the Regulations
with the use of high solids,
low VOC coatings by July 1,
1984.
This compliance plan is as-
sociated only with
the
spray booths since All—Steel’s dip tanks
were apparently in compliance by the December 31,
1982 deadline.
All-Steel’s original
compliance plan (instituted in January,
1980) contemplated total compliance by the
deadline, but unfore-
seen problems necessitated additional time
in which to achieve
compliance.
A1l~Stee1alleges that
by July 1,
1984 it will
r~1
-~
2
finish the equipment modification to allow for the application
of
remaining reformulated coatings.
Petitioner’s specific time
schedule for compliance is as follows:
January,
1984:
Begin final installation of heaters
February,
1984:
Begin final installation of pumps
March,
1984:
Begin high solids tinting system
April, 1984:
Complete installation of heaters
and pumps
May,
1984:
Complete tinting system
June,
1984:
Complete de-bugging
The Agency states that the additional six month time period
requested by All-Steel
to complete conversion of its system
ts
reasonable.
In addition,
the Agency mentions that All-
Steel has spent over $1 million complying
with the regulations
(Ag.
Rec.
at 2).
As of December 1983,
approximately 90
of
Petitioner’s coatings had been successfully reformulated.
~~1onthtyVOC emissions decreased from
83,760.3 pounds in
January,
1983
to 15,704 pounds in December,
1983.
The Board
notes the problem associated with reformulation of coatings
where customer approval tests and equipment modification
is
necessary.
All—Steel’s facility is located
in an industrial area
with the nearest residence approximately one mile distant.
The Agency has received no complaints concerning this petition.
The Agency believes that the extension requested
in
the
instant petition will not cause any increased health effects
and that compliance with its episode plan by All-Steel will
result in
a reduction of emissions during any period of high
ozone concentration.
All-Steel’s facility is located in an
area which
is
classified as nonattainment for ozone.
In 1982,
the 0.12 ppm federal ambient air quality standard was not
ex-
ceeded at the nearest monitor in Glen Ellyn.
In 1983
it was
exceeded twice
(Ag. Rec. at
4).
The Agency recommendz. grant of
the variance since All—Steel
has been diligently
seekinL; a
means to reduce its
VOC
emissions.
Additionally,
its episode action plan provides sufficient safe-
guards during periods of high ozone concentrations and the pro-
posed period
of non-compliance
is
only six months.
The alternative
to the variance
extension would be the costly installation of
thermal incineration controls which the Board finds would impose
an arbitrary or unreasonable hardship on All-Steel.
The Agency
believes that the variance,
if granted, must be submitted to
the U.S. Environmental Protection Agency as a revision to the
State Implementation Plan and states its intention to
so proceed.
The Agency therefore recommends a grant of variance subject to
certain conditions.
3
When the Board initially adopted the VOC emission
limitations
in 1979,
it recognized that the regulations would be technology
forcing and anticipated the use of the variance procedure for
re1ief~ if necessary.
By manifestations at hearing,
it appears
All-Steel
is now in compliance.
It intended to be in compliance
by July
1, l984~ The Board
notes that All-Steel should have
timely filed its petition ninety days before the expiration
of the last variance.
Although All-Steel has not timely filed
its petition, given its efforts at compliance
in conjunction
with the minimal adverse environmental impact, the Board will
grant a retroactive variance subject to certain conditions.
This Opinion constitutes the Board’s findings
of
fact and
conclusions of
law in this matter.
ORDER
1.
All—Steel,
Inc.
is hereby granted variance from
35
~l.
~
~
215.204(g)
subject to the conditions below.
2.
This variance covers the period from January
1, 1984
until July
1,
1984.
3.
Within forty-five days of the date of this Order,
All-Steel,
Inc.
shall execute and forward
to the Illinois
Environmental Protection Agency,
2200 Churchill Road, Spring-
field,
illinois
62706,
a Certificate of Acceptance and Agree-
ment to be bound to all terms and conditions of this Order.
This forty-five day period shall be
held
in abeyance for any
period this matter is being appealed.
The form of the certi-
fication shEll be as follows:
CERTIFICATE
I,
(We),
.
.
~,
having read the
Order of the Illinois Pollution Control Board in PCB 83-239,
dated
.
.
.,
1984 understand and accept the said
conditions thereto binding and enforceable.
Petitioner
By;
Authorized Agent
Title
Date
81-338
4
IT IS SO ORDERED~
I, Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
Board,
hereby certify that the above Opinion and Order was adopted
on the
~
day of LQL~r,~.I.z~A/
.,
1984 by a vote of
.
.
•~~L
.)L~-~
Dorothy
M. ~unn, Clerk
Illinois Pollution Control Board