ILLINOIS POLLUTION CONTROL BOARD
    December 20,
    1984
    ALL-STEEL,
    INC.,
    Petitioner,
    PCB 83—239
    ILLINOIS
    ENVIRONMENTAL PROTECTION
    /~GENCY,
    Respondent.
    MESSRS.
    ED
    SCHAEFER AND JEFF
    MASI,
    NON-ATTORNEYS, APPEARED
    ON BEHALF
    OF
    PETITIONER; AND
    PETER
    H.
    ORLINSKY,
    ESQ0, APPEARED ON BEHALF OF RESPONDENT.
    OPINION AND ORDER OF THE BOARD
    (by J. Marlin):
    This
    matter
    is before the Board upon the December 29,
    1983
    petition by All—Steel,
    Inc.
    (All—Steel) for a
    six month variance
    extension from 35
    ~.
    ~
    çQd~E~
    215.204(g)
    (Old Rule 205(n)
    (1)(G)
    of Chapter
    2)
    for its facility located in
    Montgomery,
    Illinois.
    In response to a Board Order dated January 12,
    1984,
    All—Steel fLied
    an
    amended petition on February 15,
    1984.
    The
    Illinois Environmental
    Protection Agency (Agency) filed its
    recommendation on March
    29, 1984.
    Hearing was held in Aurora,
    Illinois
    on June
    11,
    1984.
    There was
    no citizen testimony at
    the hearing and the Board has received
    no public
    comment
    in this
    matter.
    All-Steel owns and
    operates a metal office furniture manu-
    facturing facility which
    includes six paint spray booths and
    three paint dip
    tanks which apply surface coatings to its pro-
    ducts0
    All—Steel utilizes in
    excess of 100 types and colors
    of industrial finishes which are subject to the limitations of
    Section 215.204(g), which requires
    compliance by December 31,
    1982.
    A
    previous one year variance
    was granted by the Board
    to All—Steel until December 31, 1983
    (51 PCB 129, February 10,
    1983; PCB 82-110).
    it is the intention of All—Steel to achieve
    compliance with the Regulations
    with the use of high solids,
    low VOC coatings by July 1,
    1984.
    This compliance plan is as-
    sociated only with
    the
    spray booths since All—Steel’s dip tanks
    were apparently in compliance by the December 31,
    1982 deadline.
    All-Steel’s original
    compliance plan (instituted in January,
    1980) contemplated total compliance by the
    deadline, but unfore-
    seen problems necessitated additional time
    in which to achieve
    compliance.
    A1l~Stee1alleges that
    by July 1,
    1984 it will
    r~1
    -~

    2
    finish the equipment modification to allow for the application
    of
    remaining reformulated coatings.
    Petitioner’s specific time
    schedule for compliance is as follows:
    January,
    1984:
    Begin final installation of heaters
    February,
    1984:
    Begin final installation of pumps
    March,
    1984:
    Begin high solids tinting system
    April, 1984:
    Complete installation of heaters
    and pumps
    May,
    1984:
    Complete tinting system
    June,
    1984:
    Complete de-bugging
    The Agency states that the additional six month time period
    requested by All-Steel
    to complete conversion of its system
    ts
    reasonable.
    In addition,
    the Agency mentions that All-
    Steel has spent over $1 million complying
    with the regulations
    (Ag.
    Rec.
    at 2).
    As of December 1983,
    approximately 90
    of
    Petitioner’s coatings had been successfully reformulated.
    ~~1onthtyVOC emissions decreased from
    83,760.3 pounds in
    January,
    1983
    to 15,704 pounds in December,
    1983.
    The Board
    notes the problem associated with reformulation of coatings
    where customer approval tests and equipment modification
    is
    necessary.
    All—Steel’s facility is located
    in an industrial area
    with the nearest residence approximately one mile distant.
    The Agency has received no complaints concerning this petition.
    The Agency believes that the extension requested
    in
    the
    instant petition will not cause any increased health effects
    and that compliance with its episode plan by All-Steel will
    result in
    a reduction of emissions during any period of high
    ozone concentration.
    All-Steel’s facility is located in an
    area which
    is
    classified as nonattainment for ozone.
    In 1982,
    the 0.12 ppm federal ambient air quality standard was not
    ex-
    ceeded at the nearest monitor in Glen Ellyn.
    In 1983
    it was
    exceeded twice
    (Ag. Rec. at
    4).
    The Agency recommendz. grant of
    the variance since All—Steel
    has been diligently
    seekinL; a
    means to reduce its
    VOC
    emissions.
    Additionally,
    its episode action plan provides sufficient safe-
    guards during periods of high ozone concentrations and the pro-
    posed period
    of non-compliance
    is
    only six months.
    The alternative
    to the variance
    extension would be the costly installation of
    thermal incineration controls which the Board finds would impose
    an arbitrary or unreasonable hardship on All-Steel.
    The Agency
    believes that the variance,
    if granted, must be submitted to
    the U.S. Environmental Protection Agency as a revision to the
    State Implementation Plan and states its intention to
    so proceed.
    The Agency therefore recommends a grant of variance subject to
    certain conditions.

    3
    When the Board initially adopted the VOC emission
    limitations
    in 1979,
    it recognized that the regulations would be technology
    forcing and anticipated the use of the variance procedure for
    re1ief~ if necessary.
    By manifestations at hearing,
    it appears
    All-Steel
    is now in compliance.
    It intended to be in compliance
    by July
    1, l984~ The Board
    notes that All-Steel should have
    timely filed its petition ninety days before the expiration
    of the last variance.
    Although All-Steel has not timely filed
    its petition, given its efforts at compliance
    in conjunction
    with the minimal adverse environmental impact, the Board will
    grant a retroactive variance subject to certain conditions.
    This Opinion constitutes the Board’s findings
    of
    fact and
    conclusions of
    law in this matter.
    ORDER
    1.
    All—Steel,
    Inc.
    is hereby granted variance from
    35
    ~l.
    ~
    ~
    215.204(g)
    subject to the conditions below.
    2.
    This variance covers the period from January
    1, 1984
    until July
    1,
    1984.
    3.
    Within forty-five days of the date of this Order,
    All-Steel,
    Inc.
    shall execute and forward
    to the Illinois
    Environmental Protection Agency,
    2200 Churchill Road, Spring-
    field,
    illinois
    62706,
    a Certificate of Acceptance and Agree-
    ment to be bound to all terms and conditions of this Order.
    This forty-five day period shall be
    held
    in abeyance for any
    period this matter is being appealed.
    The form of the certi-
    fication shEll be as follows:
    CERTIFICATE
    I,
    (We),
    .
    .
    ~,
    having read the
    Order of the Illinois Pollution Control Board in PCB 83-239,
    dated
    .
    .
    .,
    1984 understand and accept the said
    conditions thereto binding and enforceable.
    Petitioner
    By;
    Authorized Agent
    Title
    Date
    81-338

    4
    IT IS SO ORDERED~
    I, Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board,
    hereby certify that the above Opinion and Order was adopted
    on the
    ~
    day of LQL~r,~.I.z~A/
    .,
    1984 by a vote of
    .
    .
    •~~L
    .)L~-~
    Dorothy
    M. ~unn, Clerk
    Illinois Pollution Control Board

    Back to top