ILLINC~ISPOLLUTION CONTROL BOARD
    September
    6, 1979
    ENVIRONMENTAL PROTECTION AGENCY,
    Complainant,
    v.
    )
    PCB 76-80
    ALLAERT RENDERING,
    INC.,
    Respondent.
    Mr. Dennis Fields,
    Special Assistant Attorney General, appeared
    for the Complainant;
    Mr. John Parker, John L. Parker and Associates,
    Ltd.,
    appeared
    for the Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr.
    Young):
    This matter comes before the Board on a six-count Complaint
    filed by the Environmental Protection Agency
    (Agency)
    on March 19,
    1976, against the Respondent, Allaert Rendering,
    Inc.
    (Allaert)
    alleging violations of
    the water pollution provisions of the
    Environmental Protection Act and the Chapter
    3 regulations.
    The
    Complaint charged Allaert with constructing and operating a waste
    treatment works without the necessary permits required by Board
    regulations, with depositing contaminants on land causing a water
    pollution hazard, with improperly constructing its treatment plant
    in violation of the spill and malfunction provisions of Rule 601
    and with operating the treatment works without a certified operator.
    In particular,
    the Complainant raised the following issues in the
    six counts of the Complaint as follows:
    1.
    Allaert caused or allowed the construction or modification
    of its treatment works without
    a construction permit from April
    16,
    1972, until March
    19, 1976,
    in violation of Rule 901(a), renumbered
    951(a)
    of Chapter
    3:
    Water Pollution Regulations
    (Chapter
    3)
    and
    Section 12 (a) and 12 (b)
    of the Environmental Protection Act
    (Act).
    2.
    Allaert operated its treatment works from April
    16,
    1972,
    until March 19,
    1976, without an operating permit in violation of
    Rule 902(a), renumbered 952(a) of Chapter
    3 and Sections 12(a)
    and
    12(b)
    of the Act.
    3.
    Allaert operated its treatment works f~omDecember
    31,
    1972, until March 19, 1976, without the necessary permits, in
    violation of Rule 903(a),
    renumbered
    953(a)
    of Chapter
    3 and
    Sections
    12(a)
    and 12(b)
    of the Act.
    35—28 1

    —2--
    4.
    Allaert operated its treatment works from July
    1,
    1970, until March
    19, 1976,
    by depositing contaminants on land
    in such
    a manner and in such
    a place to cause a water pollution
    hazard,
    in violation of Section 12(d)
    of the Act.
    5.
    Allaert operated its treatment works from April 16,
    1972, until March 19,
    1976,
    in violation of the malfunction
    and spill provisions of Rule 601 of Chapter
    3 and Section 12(a)
    of the Act.
    6.
    Allaert operated its treatment works without a certified
    operator from June 27,
    1973, until March 19,
    1976,
    in violation
    of Rule
    1201 of Chapter
    3 and Section
    12(a)
    of the Act.
    Hearings were held for this enforcement action on November
    8 and
    9,
    1978,
    in Rock Island,
    Illinois after which evidence
    was received in a variance proceeding, Allaert Rendering,
    Inc.
    v.
    EPA, PCB 77-334
    (September
    6,
    1979)
    concerning the same parties.
    In PCB 77-334, a petition for variance was filed December 14,
    1977,
    by Allaert for relief from those provisions
    of the Act and Board
    regulations which were the subject of this enforcement action.
    Specifically, Allaert sought a variance from Sections 12(a),
    12(b)
    and 12(d)
    of the Act and those Board rules which required a con-
    struction permit for a new or modified facility
    901(a),
    renumbered
    951(a),
    an operating permit for a new or modified facility
    902(a),
    renumbered 952(a),
    and an operating permit for an existing treat-
    ment works
    903(a),
    renumbered 953(a).
    Furthermore, Allaert
    sought a variance from the statutory prohibition against depositing
    contaminants on land,
    to operate
    its treatment facility without a
    certified operator as required by Rule 1201 and to relieve its
    facility of the Rule 601 requirements regarding maintenance and
    prevention of spills.
    On September
    6,
    1979,
    the Board rejected
    Allaert’s request from the aforementioned relief.
    The record in this matter includes
    a transcript of 496 pages
    and numerous exhibits submitted by the Agency and the Respondent.
    On January
    22,
    1979, the Complainant filed its Brief with the
    Board which was followed by Respondent’s Brief,
    dated March 30,
    1979.
    On April 19,
    1979,
    the Complainant filed a Reply Brief.
    During the hearing, the parties raised numerous objections, motions
    and requests for reconsideration which are considered
    in the
    following paragraphs.
    Pursuant to an interlocutory appeal order, dated September
    29,
    1977, the Board allowed the Agency and the Respondent
    to submit
    briefs regarding the scope of discovery in this enforcement pro-
    ceeding.
    The Complainant appealed an order of the Hearing Officer,
    dated June 16,
    1977, which required the Agency to produce a permit
    file pertaining to
    tI’e Fox Valley Grease Company,
    Inc.
    and ordered
    the deposition of ~i1liam
    H.
    Busch, then Manager of the Permit
    Section and Darryl
    P. Bauer,
    then an Agency permit engineer who
    had reviewed a permit application submitted by Fox Valley Grease
    Blending,
    Inc. who is not a party
    in this action.
    After due
    consideration,
    the Board reversed the Hearing Officer’s order on
    35—282

    —3—
    October 13,
    1977,
    on the basis that the inquiries were not
    material
    to the issues arising from the Complaint.
    It is Respondent’s contention that the denials of its
    permit applications submitted by Allaert on February
    10,
    1976,
    and on March 11,
    1977, were arbitrary and unreasonable.
    During
    the hearings and in Respondent’s Brief, Allaert has claimed that
    the permits were wrongfully denied because the Agency had
    established no criteria or guidelines
    to determine the parameters
    considered
    in design and evaluation of an infiltration—percolation
    system.
    According to the Respondent,
    the records and the
    deposition requested during discovery
    are necessary to review
    the propriety of the Agency’s standards and guidelines
    in the
    permit review and in the permit denial process.
    Since the October 13,
    1977, Order on this matter, the Board
    has considered at length the problems in structuring discovery
    for the review of permit denials pursuant to Section 40 of the
    Act.
    In Oscar Mayer
    & Co.
    v. EPA,
    PCB 78-14,
    30 PCB 397
    (June
    8,
    1978)
    ,
    the Board denied that applicant’s request for all
    material and depositions
    of all Agency personnel who participated
    in the determination which resulted in denial of applicant’s
    permit.
    In reviewincr the permit denial,
    the Board found that
    Agency procedures,
    criteria and activities pertaining
    to the
    permit decision—making process were not material
    to the
    Petitioner’s burden of proof in such a proceeding which is
    limited to a showing of compliance with the substantive require-
    ments of the Act based solely upon the permit application and
    supporting documentation as such may have been submitted
    by the
    applicant.
    A successful Petitioner in a Section 40 proceeding,
    after verifying the facts of
    its application, must persuade the
    Board that the activity in question will not cause a violation
    of the Act or Board regulations.
    In response, the Agency may
    contest
    the facts in the application or argue applicable law
    and regulations, or
    “it may choose to do either or it may choose
    to present nothing.”
    The action of the Agency in the denial of
    the permit is not the issue;
    the issue is simply whether or not
    in the sole judgment of the Board, the applicant has submitted
    proof that if the permit is issued, no violation of the Act or
    regulations will result.
    Propriety of this Board procedure
    was
    reviewed and upheld by the Appellate Court, Third District in
    SCA Services,
    Inc.
    v.
    PCB and EPA, ____Ill.App.3d
    ,
    389 N.E.
    2d
    953
    (May 16,
    1979).
    Although Allaert Rendering,
    Inc. did not formally petition
    for review of the Agency’s permit denials pursuant to Section 40
    of the Act, because of Allaert’s
    claim that Agency permit denial
    was arbitrary and unreasonable, the Board has reviewed the
    sufficiency of the permit applications and the Agency’s denials
    in this matter.
    35—283

    —4—
    Section
    39 of the Act provides that the Agency shall issue
    a permit on proof by the applicant that the permitted activity
    will not cause
    a violation
    of the Act or Board regulations.
    Applicant’s burden may he facilitated by showing
    that its
    system meets specific Agency guidelines;
    however, the ultimate
    decision to grant or deny the permit must turn on whether the
    information submitted by the applicant proves compliance with
    the Act and Board regulations.
    In this case, Allaert submitted its permit application on
    February
    10, 1976,
    which was denied by the Agency on March
    4,
    1976.
    The initial application failed to disclose the type and
    permeability of the rock under the infiltration-percolation
    system, the strength of the wastewater moving through the ground,
    the actual soil and bedrock conditions
    under the system and the
    direction of the groundwater flow.
    The application did contain
    general soil information from the U.S.
    Department of Agriculture
    which indicated that during the spring season, the groundwater
    in the vicinity of the infiltration-percolation system was
    present from zero
    to three feet below the surface.
    (R.
    234-51;
    C. Exh. Nos.
    1,
    2 and 4).
    Approximately one year later, on March 11,
    1977,
    Beling
    Engineering Consultants
    (Beling) submitted supplemental infor-
    mation on behalf of Allaert in response to the permit denial.
    In place of standards,
    Beling engineers claimed that Addendum
    No.
    2 of the Ten States Standards, essentially a ground disposal
    wastewater system, was used to develop criteria for the
    infiltration-percolation system.
    The supplemental information
    in Respondent’s second application included a letter from Mr.
    James Gibb, Associate Engineer,
    Illinois State Water Survey,
    dated October 27,
    1976; soil borings and map logs;
    a well
    location map; and lab analyses data on wells
    in the vicinity
    of Respondent’s treatment facility.
    (R.
    264—67;
    C. Exh.
    No.
    3).
    Addendum No.
    2 of the Ten States Standards has established
    certain other criteria for the design of ground disposal waste-
    water systems which
    is not included in the information provided
    by the Respondent.
    Allaert’s permit applications fail
    to
    include such necessary geological information as the bedrock
    structure of the receiving lagoon,
    the character and thickness
    of
    surficial soil and glacial deposits
    and, especially for lime-
    stone, information about the solution openings and the sinkholes
    as recommended by Addendum No.
    2.
    Hydrological data required
    by the Ten States Standards in addition to high water table data
    includes information on the direction of the groundwater movement,
    chemical analyses of the groundwater quality and at least one
    groundwater monitoring well must be located in the direction
    of the movement.
    The recommended standards also require soil
    maps and data on the soil thickness of the area to be subjected
    to treatment.
    Addendum No.
    2 also indicated that disinfection
    before discharge was necessary and design controls are appropriate
    to prevent runoff frcm entering or leaving the site.
    35—284

    —5—
    While the permit applications contained obvious deficiencies,
    their supplemental information does disclose a presence of
    dolomite bedrock under the glacial material in the vicinity of
    the receiving
    lagoon,
    a structure which
    is highly susceptible
    to fracture.
    Soil Boring Log Nos.
    1 through
    7 also disclosed
    that weathered and highly weathered limestone is evident at or
    near Respondent’s property under a 3.5 to 6.5 foot layer of
    predominantly silty clay.
    The ISWS letter suggested that,
    “Available data indicates a potential for polluting both the
    unconsolidated and bedrock units
    is high.”
    On June
    8,
    1977,
    the Agency denied the Respondent’s second permit application.
    (C. Exh. Nos.
    3 and 4).
    Having reviewed the permit applications and the Agency
    denials,
    the Board finds that the Agency clearly stated in its
    letters that the information not only failed to show that
    Respondent’s
    treatment system would not cause a violation of
    the Act, but also the material contained
    in the application
    indicated that the potential for water pollution is quite high.
    (C.
    Exh. Nos.
    1 and 3).
    The Board will affirm its October
    13, 1977 Order regarding
    the scope of discovery.
    Furthermore, the Board finds nothing
    to indicate that the Agency’s responses to the obvious
    deficiencies
    in the permit applications were arbitrary or
    unreasonable.
    Moreover, without reference to any consideration
    of the Agency’s action in denying the permit applications, the
    Board
    finds that Allaert did not provide sufficient proof in
    the application and supporting information that the Act and
    regulations would not be violated
    if a permit was issued.
    The
    remaining questions regarding permits, whether Allaert obtained
    the necessary permits before constructing and operating its
    treatment facility, will be considered later in this Opinion.
    On April
    7,
    1977, because of repeated failures of the
    Respondent to comply with discovery orders, the Hearing Officer
    imposed sanctions under the authority of the Board Procedural
    Rules,
    Part 7,
    and entered an order which prohibited the
    Respondent from introducing any evidence relating to the issue
    of economic reasonableness and any evidence relating to facts
    that would have been disclosed by Respondent’s compliance with
    the Hearing Officer’s order of February
    2,
    1977.
    At hearing,
    Respondent requested that the Hearing Officer reconsider the
    order
    of April
    7,
    1977;
    the request was denied.
    On April
    25, 1977,
    Allaert filed an Application of Non-
    disclosure with the Board pursuant to Section
    7 of the Act and
    Procedural Rule 107
    to limit disclosure of all financial records
    from 1970
    to 1976 to only Board members.
    On May 12,
    1977,
    the
    Board
    found Respondert’s application to exempt all financial
    35—285

    —6—
    records from public disclosure unjustified and denied the
    application without prejudice.
    At the conclusion of the
    November
    9,
    1979,
    enforcement hearing, Allaert submitted
    under an offer of proof, the “Application for Nondisclosure”
    for identification as Respondent’s Exhibit No.
    7 with the
    stated intention
    to “comply with Section
    7 of the Act.”
    Hearing Officer refused to admit this exhibit into evidence.
    The Respondent also submitted under an offer of proof,
    testimony
    by Paul Allaert concerning what he believed were reasonable
    alternative control technologies in light of the financial
    condition of Allaert Rendering,
    Inc.
    (R. 39—45,
    475,
    479-81).
    In reexamining Respondent’s Application for Nondisclosure,
    the Board will consider the procedures prescribed
    for evaluating
    nondisclosure applications in Procedural Rule 107 and the Opinion
    in Olin Corporation v. EPA, PCB 72-253,
    5 PCB 131,
    132
    (August
    10, 1972).
    In adopting Procedural Rule 107,
    the Board was mindful
    of the statutory mandate of Section
    7 of the Act requiring
    public hearings and providing that all documents
    (files,
    records and data)
    be open to the public.
    Since limiting the
    review of material “not subject
    to disclosure” seriously affects
    the public nature of any Board proceeding,
    the Board is obliged
    to limit and narrowly define the scope of exceptions of the
    public information rule and subject applications for nondisclosure
    to close scrutiny.
    To qualify any material for nondisclosure status,
    the
    material must not only meet specific criteria for an exception,
    but also the application for nondisclosure must contain the
    following:
    1.
    Identification
    of precise material,
    or parts of
    material for which nondisclosure is sought;
    2.
    Indication of the particular nondisclosure
    category into which the material falls;
    3.
    A concise, verified application stating the
    reasons for requesting nondisclosure.
    rn this respect, Allaert’s application has failed to satisfy
    the requirements of Procedural Rule 107 and thereby
    the mandate
    of Section
    7 of
    the Act in the following manner:
    First, Respondent has failed to identify the precise material
    or parts thereof
    to Le withheld from the public.
    The Board finds
    that Respondent’s blanket request for exemption for all financial
    records, including income tax returns, income statements and
    balance sheets for the years 1970 through 1976 is overly broad;
    such material cannot be withheld from public scrutiny on the
    bare contention that they are highly confidential.
    35—286

    —7—
    Second,
    the Respondent has denominated “all financial
    records”
    as falling within the “confidential data” and “trade
    secret” exception on the naked, generalized statement that the
    “information
    is considered highly confidential by Respondent.”
    Furthermore,
    the Respondent fails to distinguish what material
    the law would recognize as a “trade secret” and which material
    is believed to be “confidential data.”
    Third,
    the Agency advances compelling arguments that if
    the Board were to allow the nondisclosure of all Respondent’s
    financial records to any except the Board, the Complainant
    would be precluded from the effective cross-examination of
    the records and from assessment of Respondent’s financial status
    through the independent audit of an accountant.
    (R.
    133-34).
    After reviewing these findings,
    the Board will affirm its
    May 12, 1977, order denying nondisclosure.
    Furthermore,
    the
    Board will affirm the Hearing Officer’s April
    7,
    1977, order and
    uphold his decision
    to exclude the Application for Nondisclosure,
    Exhibit No.
    7
    from the record.
    Respondent’s persistent failure
    to comply with the Hearing Officer’s discovery orders and the
    Agency’s request for disclosure of financial records will,
    in
    accordance with Procedural Rule 701(c), disqualify all Respondent’s
    evidence
    in this record concerning economic reasonableness.
    In other preliminary motions, Respondent moved to vacate
    Complainant’s interrogatories filed with the Board on September
    22,
    1978, dealing with updating matters
    in the enforcement
    action,
    clarifying specific contentions
    in the variance case
    and serving as
    a final submission of Complainant’s request
    for Respondent’s financial records.
    An order from the Hearing
    Officer, dated September
    22, 1978,
    followed the interrogatories
    which required Respondent
    to answer the interrogatories and
    produce the documents on or before October
    9,
    1978.
    It is the
    Respondent’s contention that the issuance of the Hearing Officer’s
    order on the same day as the filing of the interrogatories
    violated the service requirements for interrogatories
    of
    Procedural Rules 305(c),
    308(c)
    and 313(c).
    In Respondent’s
    estimation, the Hearing Officer is precluded from submitting an
    order setting the response date until after the eleven days
    allowed under the Procedural Rules for service and response.
    Anything less,
    according
    to the Respondent, will effectively
    preempt Respondent’s right to oppose the interrogatories.
    After
    reviewing
    this matter at hearing,
    the Hearing Officer granted
    Respondent’s motion.
    While the Board need not consider further
    the consequences of Respondent’s failure to submit financial
    records during the discovery proceeding,
    the Board will not
    question Hearing Officer’s decision to vacate the order so
    long
    as the Complainant was not prejudiced by this decision.
    (R.
    45-
    56)
    35—287

    —8—
    Exhibits received into evidence for the Complainant and
    the Respondent included Complainant’s Exhibit Nos.
    1 through
    7,
    8A through 8H,
    9A through 9C, 10,
    11,
    13 and 14(1—13) and
    Respondent’s Exhibit Nos.
    4 and
    5.
    The offer of the Application
    for Nondisclosure, Respondent’s Exhibit No.
    7,was denied by the
    Hearing Officer.
    (R.
    475).
    During the hearings, Respondent objected to Complainant’s
    Exhibit Nos.
    2,
    4,
    6,
    7,
    BA through 8H,
    9A through
    9C, 11,
    13
    and 14(1-13).
    Complainant contested the admissibility of
    Respondent’s
    Exhibit
    Nos.
    4 and
    5.
    After reviewing the
    objections
    to the admission of the exhibits,
    the Board will
    sustain the decisions
    of the Hearing Officer regarding the
    exhibits of the Complainant and the Respondent, with the
    exception that the photographs identified and admitted as
    Exhibit Nos.
    8B and 8C will be excluded from evidence on the
    basis that the record fails to show whether the photographs
    were
    a true and accurate portrayal of the subject matter.
    (R.
    154—55)
    On Complainant’s motion to exclude witnesses,
    the Board
    finds
    that it is within the discretion of the Hearing Officer
    to determine whether or not to exclude the witnesses in the
    interest of fairness, provided that the ruling precedes any
    testimony of witnesses.
    (R.
    59).
    Respondent’s motion to
    quash subpoenas served upon Henry Mayer, William Karlovitz
    and Earl Beling
    (deceased)
    is moot since both Mr. Mayer and
    Mr. Karlovitz were present at the hearings.
    (R.
    31—37).
    Finally, the Board will deny Motion for Summary Judgment
    submitted by the Respondent because the Agency failed to produce
    a Mr. Gerald M. Kehoe for these hearings.
    Since the record
    discloses that Mr. Kehoe is no longer an employee of the Agency,
    the Agency was under no burden to produce the witness.
    Accord-
    ing to Procedural Rule 315 (a),
    the Respondent should have sub-
    mitted a motion to the Hearing Officer or to the Board to issue
    a subpoena for attendance of a particular witness at these
    hearings.
    (R.
    487—90).
    The subject of this enforcement action concerns Allaert
    Rendering,
    Inc.,
    an Iowa corporation incorporated in April,
    1974, which
    is the continuation of a sole proprietorship owned
    by Wilbur Allaert dating back to 1940.
    Since April,
    1974,
    Allaert Rendering,
    Inc.
    has operated the rendering plant on
    a portion of a one hundred acre parcel known as Allaert Acres
    and owned by Wilbur Allaert near the Village of Carbon Cliff,
    in Rock Island County, Illinois.
    Paul W. Allaert has been
    Vice President and General Manager since 1974 and has served
    in various capacities
    at the plant since
    1945.
    (R.
    62—64,
    456—
    60;
    C.
    Exh.
    No.
    1).
    35—288

    —9—
    In view of the evidence in the record disclosing that
    Allaert Rendering,
    Inc.
    “has been a corporation since April
    of
    1974,” the Board will interpret this testimony to mean that
    Allaert Rendering,
    Inc. did not exist as a corporate entity
    until April 30,
    1974.
    For purposes
    of this enforcement action,
    the Board will limit the scope of the complaint period from
    April
    30,
    1974, until March 19,
    1976, the date of the filing
    of the Complaint.
    Evidence occurring outside this time frame
    will
    be excluded unless
    it proves germane to matters of
    aggravation or mitic~ation, in considering Section 33(c)
    factors,
    or as evidence of the continuous nature of the violation.
    (R.
    62)
    The rendering plant in question processes approximately
    50,000
    60,000 pounds
    a day of
    fallen animals, restaurant
    grease,
    scraps and bones
    in cookers and presses designed to
    separate grease and oil from the animal solids.
    Well water
    used to trap oil and grease vapors from the cooking process
    is collected with the clean—up waters containing such residues
    as dead animal cuttings,
    hair and bone before the wastewater
    is discharged to Allaert’s treatment
    system.
    The rendering
    plant effluent averages
    29,750 gallons per day with concentrations
    of BOD5
    at 468 mg/l,
    suspended solids at 392 mg/l and oil and
    grease at 193 mg/l.
    The Allaert process wastewater and
    associated clean—up waters
    are discharged to three—l,000 gallon
    septic tanks arranged in parallel before emptying into one-l,500
    gallon septic tank.
    This primary treatment system,
    installed
    between
    1973 and 1975,
    is designed to separate and remove the
    grease and oil from the wastewaters and
    to reduce odors, suspended
    solids and BOD.
    Effluent from the 1,500 gallon septic tank is
    passed through
    a final grease trap before it
    is discharged
    to
    the receiving lagoon.
    Constructed in the
    fall of
    1973, the
    receiving lagoon is
    located within the flood plain of the Rock
    River.
    (R.
    68—72,
    82—83,
    99,
    184,
    326, 482;
    C. Exh. No.
    1).
    Allaert Rendering,
    Inc.
    installed the existing treatment
    system over a period beginning in the fall,
    1973 through 1975
    without construction permits and discharged to the system with-
    out
    an operating permit.
    In 1973—74, the three—l,000 gallon
    septic tanks were installed followed by the 1,500 gallon septic
    tank
    in 1974-75.
    The receiving lagoon,
    denominated an infiltration-
    percolation system, was also constructed in the fall,
    1973,
    without
    the benefit of percolation test or other studies to
    determine the effectiveness of Respondent’s infiltration—
    percolation system to filter and absorb contaminants before
    reaching and mixing with the groundwaters.
    According to the
    record,
    the Respondent,
    in excavating the receiving lagoon,
    removed six feet of top layer exposing the limestone bedrock.
    (R.
    75—76,
    83—84,
    88—89, 110—11,
    223,
    364,
    382;
    C.
    Exh. No.
    3).
    35— 289

    —10—
    The record also indicates that the Agency first became
    aware of the Allaert treatment system through an Agency sewage
    treatment survey conducted at Respondent’s rendering works on
    November 14, 1974.
    Subsequently, the Agency sent Allaert a
    letter,
    dated January
    20,
    1975, which provided the Respondent
    with a copy of the Water Pollution Regulations of Chapter
    3
    and informed the same of the need for a construction and
    operating permit.
    A follow-up investigation on May 14, 1975,
    disclosing
    no efforts toward compliance, prompted the Agency
    to write
    a letter,
    dated July
    18, 1975, warning the Respondent
    of the need for permits
    for a second time.
    (R.
    200—12,
    328-35,
    342;
    C.
    Exh. Nos.
    6 and 7).
    In response to the Agency inquiries, Allaert contacted
    Beling Engineering Consultants on or before July,
    1975,
    to
    conduct a study on Allaert’s existing facility and to prepare
    a report recommending necessary facility improvements.
    On
    February
    10, 1976,
    the Respondent submitted a permit application
    prepared by Beling requesting approval of Allaert’s infiltration--
    percolation system which claimed no discharge
    to surface waters.
    The application proposed to modify the existing facility by
    constructing berms
    to the 25-year flood elevation and fencing
    in the treatment system.
    As indicated above, the Agency denied the permit application
    on March
    4, 1976.
    Additional materials were submitted
    in
    Respondent’s second permit application, dated March
    11,
    1977.
    However,
    the Agency also rejected Respondent’s supplementary
    permit application on June
    8,
    1977, because of the inadequacy
    of the information and the potential
    for water pollution from
    Respondent’s treatment facility.
    (R.
    247,
    426—27;
    C.
    Exh. Nos.
    1,
    2,
    3 and 4).
    Based on this evidence and other testimony and exhibits
    pertinent to the alleged violations, the Board will review the
    charges alleged in the Complaint.
    WATER POLLUTION
    Counts
    I,
    II,
    III, V and VI allege that the Allaert treat-
    ment works are in violation of Section
    12(a)
    of the Act which
    reads:
    No person shall cause or threaten or allow the discharge
    of any contaminants into the environment in any State
    so as
    to cause or tend to cause water pollution in
    Illinois,
    either alone or in combination with matter
    from other sources, or so as
    to violate regulations
    or standards adopted by the Pollution Control Board
    under this Act.
    35—290

    —11—
    During the time frame pertinent to this Complaint period,
    the record shows that Larry Marques,
    a former Agency inspector
    currently with the Illinois Department of Public Health, visited
    Allaert Rendering,
    Inc.
    and inspected its treatment works on
    three different occasions, November 19,
    1974, May 15,
    1975,
    and November 19, 1975.
    On the last date, Mr. Marques took
    photographs depicting the conditions of the Allaert treatment
    works which, with a sketch of the surroundings, were admitted
    into evidence as Exhibit No.
    11, the sketch and Exhibits Nos.
    13 and 14, photograph location map and photographs 1-13,
    respectively.
    On Mr. Marques’
    first and second visits to the Allaert
    treatment works,
    in addition to inspecting the receiving lagoon,
    Mr. Marques discovered a trench originating at or near the lagoon
    which extended “as
    far as
    I could see”
    in the direction of the
    Rock River.
    Since the stated purpose of these visits was to
    inform Respondent of the need for a permit, the witness did not
    follow the trench to its termination point, nor did the witness
    observe an actual discharge to the Rock River on either occasion.
    (R.
    324,
    329,
    332,
    336).
    In other evidence derived from conversations with Mr. Paul
    Allaert on November
    19, 1975,
    Mr. Marques learned that the trench
    was originally excavated from the pond to the river to drain the
    area so that the pond could be enlarged.
    However,
    at the time
    that Mr. Marques observed the termination point of the trench
    on November 19,
    1975,
    400 to 600 feet
    (sic)
    of
    the lower portion
    near the river and the upper segment of the trench near the
    receiving lagoon had been filled in.
    According
    to conversations
    during the November, 1975,
    inspection, the ditch had been filled
    in approximately four months before the inspection or by July,
    1975.
    (R.
    315,
    324;
    C. Exh. No.
    13).
    Since
    this occurrence witness stated that he had no
    personal knowledge nor evidence of samples of any wastewater
    discharged from the Allaert treatment works
    to the Rock River,
    the Board finds the evidence patently insufficient to support
    a finding that Respondent caused or allowed a discharge to
    the surface waters of the Rock River in violation of Section
    12(a)
    of the Act.
    (R.
    325,
    326,
    329).
    Turning our attention to other evidence in Complainant’s
    case-in-chief,
    alleging water pollution violations
    to surface
    and groundwaters, the Board has discovered that the record,
    taken as
    a whole, will not support a finding of
    a causal
    connection between Allaert’s discharge and any actual environ-
    mental harm.
    The record supplies no information concerning
    the concentration of contaminants
    in the receiving lagoon,
    provides
    limited data on conditions under the lagoon in question
    and merely suggests the direction of the groundwater flow from
    the lagoon toward the Rock River.
    The Board finds no evidence
    in the record to support the allegations that the Respondent
    caused or allowed water pollution.
    35—29 1

    —12--
    Section 12(a)
    of the Act further authorizes the Board
    to protect the waters of Illinois from serious threats
    to
    the environment from water pollution.
    It is clear that in-
    clusion of the word “threaten”
    is intended to allow the Board
    to act before water pollution seriously affects the environ-
    ment.
    The Act permits the Board in considering “threaten”
    violations
    of Section
    12(a)
    to entertain evidence of actual
    violation, testimony pertaining to persistent
    or continuing
    violations and also evidence of potential violations with a
    reasonable likelihood of occurrence.
    Without this authority,
    “the Board could only lock the stable after the horses have
    been spirited away.”
    Springfield Sanitary District v.
    EPA,
    PCB 70-32,
    1 PCI3 181
    (January 27,
    1971); EPA v.
    Ayshire Coal
    Company, PCB 71—323,
    1 PCB 415
    (April 25, 1972); EPA v. James
    McHugh Construction et al., PCB 71—291,
    4 PCB 511
    (May 17,
    1972)
    In considering the threat to surface waters,
    the evidence
    indicates that the lagoon was constructed in 1973 without berms
    or other
    flood control measures on the flood plain within 1,000
    -
    2,000 yards of the Rock River.
    Since the record does disclose
    that the receiving lagoon is the repository of highly contaminated
    wastewater,
    this evidence alone supports a finding of a Section
    12(a)
    violation which threatens surface waters in the vicinity.
    (R.
    68,
    482;
    C.
    Exh. No. 1).
    The Allaert rendering facility discharged approximately
    30,000 gallons per day to the unprotected ground in the
    Rock
    River
    flood plain where the receiving lagoon is currently
    located.
    On cross—examination,
    Paul Allaert conceded that the
    entire processing facility had been flooded in 1973, before
    the construction of the receiving lagoon.
    The record also
    discloses that in May,
    1978,
    the receiving lagoon was inun-
    dated by Rock River flood waters.
    The May,
    1978 inspections
    also revealed evidence of discharge solids on the land between
    the receiving lagoon and the Rock River.
    Based upon this
    evidence
    in the record,
    the Board finds the operation of the
    Allaert treatment system has threatened and will continue to
    pose a serious threat
    to the surface waters within the vicinity
    of the Rock River.
    (R.
    99,
    151,
    165,
    187—88,
    482;
    C. Exh. Nos.
    8B,
    8D,
    BE and 9C).
    In considering evidence pertaining to the threat of ground-
    water contamination,
    the Board
    finds
    that the receiving lagoon,
    denominated an infiltration—percolation system, was constructed
    and operated without permits
    in the fall of 1973 and also with-
    out the benefit of percolation tests
    or other studies
    to determine
    the effectiveness of the system.
    While the Respondent claims
    that there is no known discharge from its treatment facility,
    Allaert ignored evidence,
    as disclosed by the record, which
    indicated the following:
    35—292

    —13—
    1.
    The excavation of the receiving lagoon caused the
    removal of six feet cf top layer of silty loam exposing the
    bedrock;
    2.
    Groundwaters in the vicinity of the receiving lagoon
    rise during the spring months of the year from zero to three
    feet below the ground;
    3.
    The bedrock in the vicinity of the receiving lagoon
    consists of weathered or highly weathered limestone from 3.5
    to 6.5 feet below the soil layer.
    (C. Exh. Nos.
    1 and 3).
    Accordingly,
    the Board
    finds that the highly contaminated
    wastewater collected in the Respondent’s receiving lagoon
    threatens the groundwater directly under the site and in the
    vicinity of the receiving lagoon with water pollution in
    violation of Section 12(a)
    of the Act.
    CONSTRUCTION AND OPERATING PERMITS
    Counts
    I,
    II and III allege that Allaert has caused or
    allowed the construction and operation of
    a new, modified or
    existing treatment works without the necessary permits in
    violation of Rules
    901(a),
    902(a)
    and 903(a),
    renumbered 951(a),
    952(a) and 953(a), respectively, of Chapter
    3 and in violation
    of Sections
    12(a)
    and 12(b)
    of the Act.
    Rule 104 of Chapter
    3 defines “treatment works”
    as
    “those
    constructions or devices
    .
    .
    .
    used for collecting, pumping,
    treating or disposing of wastewater
    .
    .
    .
    .“
    Since Respondent’s
    facility described
    as an infiltration-percolation system was
    intended
    to treat the wastewater discharged by the Allaert
    rendering facility,
    the system clearly
    falls within the scope
    of “treatment works,”
    and therefore,
    becomes subject to the
    aforementioned Part IX requirements regarding construction and
    operating permits.
    The Board regulations requiring permits for the construction
    and operation of wastewater treatment facilities were adopted on
    March
    7,
    1972, and became effective on April
    16,
    1972.
    Respondent
    was formally informed of the permit requirement on January
    20,
    1975,
    by an Agency letter which was accompanied by a copy of
    Chapter
    3:
    Water Pollution Regulations which includes
    the
    permit regulations.
    However, the Respondent did not submit its
    initial permit application until February 10,
    1976.
    In this case,
    the Agency has proved that permits were never
    applied for and never issued by the Agency prior to construction
    of the receiving lagoon in 1973, or before the installation of
    35—293

    —14—
    the three—l,000 gallon and the 1,500 gallon septic tanks or the
    grease trap over
    a period from 1973 through 1975.
    Nor were the
    necessary permits obtained before the operation of the system.
    Furthermore, Respondent’s submission of permit applications on
    February 10,
    1976, and also on March 11,
    1976, were properly
    denied by the Agency on the basis that the permits failed to
    show that the installations combined with the proposed improve-
    ments, a 25—year flood berm and fencing, would not cause
    violations of the Act or Board regulations.
    (R.
    75-76,
    84,
    222—23,
    364—65;
    C.
    Exh.
    Nos.
    3,
    4 and 6).
    The Board hereby finds that since the Respondent was never
    issued
    a construction or operating permit during the time frame
    of this Complaint, violations of the aforementioned Part IX
    Rules of Chapter
    3 and of Section 12(b)
    of the Act have been
    established.
    WkTER POLLUTION HAZARD
    Count IV alleged that the Respondent’s operation created
    a water pollution hazard
    in violation of Section 12(d)
    of the
    Act from July
    1,
    1970,
    until March 19,
    1976.
    In accordance with
    a finding of violation of Section 12(a)
    which “threatens” water pollution,
    proof of a Section
    12(d)
    violation need not include evidence of actual water pollution,
    since both provisions of the Act are intended to correct potential
    water pollution threats and hazards before actual harm has
    occurred.
    EPA v. Ayshire Coal Company,
    PCB 71-323,
    4 PCB 415
    (April 25, 1972); EPA v.
    James McHugh Construction Company,
    PCB 71-291,
    4 PCB 511
    (May 17, 1972).
    In each case,
    however,
    proof must be sufficient to show that the material in question
    either threatens water pollution or creates
    a water pollution
    hazard.
    In this matter,
    to the extent that the Respondent has
    deposited approximately 30,000 gallons per day of wastewater
    containing high concentratior~of contaminants during periods
    of this Complaint,
    and to the extent that the receiving lagoon
    was constructed
    in 1973 within the flood plain of the Rock River
    without effective
    flood control measures, the Board finds that
    this evidence,
    in and of itself,
    establishes that Respondent’s
    discharge to its receiving lagoon creates
    a water pollution
    hazard within the meaning of Section
    12(d)
    of the Act.
    (R.
    97—
    99, 165;
    C.
    Exh. No.
    1).
    Since the scope of this complaint period extends from April
    30,
    1974, until March 19, 1976,
    the evidence of flooding from
    the Paul Guse inspections on May
    9 and 15,
    1978,
    is limited
    to
    proof of the continuing nature of the violation.
    The record
    35—294

    —15—
    also indicates that Larry Marques took photographs and made
    visual observations of the conditions of the Allaert treatment
    works on November 19,
    1975.
    However, after reviewing this
    evidence, the Board finds that the Marques’ observations and
    photographs, absent samples and laboratory analyses of the
    suspected materials,
    falls
    far short of proving that a water
    pollution hazard existed on the day in question.
    (R.
    151,
    152,
    311-13;
    C.
    Exh. Nos.
    BA,
    8D and 8E, 9A,
    9B and 9C,
    14(1,
    2,
    3,
    5,
    6,
    7 and 8).
    MALFUNCTION AND SPILL REQUIREMENTS
    Count V charged Allaert with violations of the Rule 601
    malfunction and spill requirements which provide as follows:
    (a)
    Malfunctions.
    All treatment works and associated
    facilities
    shall be so constructed and operated
    as
    to minimize violations of applicable standards
    during such contingencies
    as flooding,
    adverse
    weather,
    power failure, equipment failure,
    or
    maintenance,
    through such measures
    as multiple
    units, holding tanks, duplicate power sources, or
    such other measures as may be appropriate.
    (b)
    Spills.
    All reasonable measures,
    including where
    appropriate the provision of catchment areas,
    relief vessels, or entrapment dikes,
    shall be
    taken to prevent spillage of contaminants from
    causing water pollution.
    Provisions
    in this part are intended to impose upon the
    operator of the treatment works
    a duty to reduce,
    if not eliminate,
    the threat of malfunctions or spills which cause or contribute
    to water pollution.
    In adopting Rule 601 in January
    6,
    1972,
    the Board stated that reasonable measures should be taken to
    ensure that systems do not unreasonably threaten water pollution.
    In the Matter of:
    Effluent Criteria,_et al., PCB P.70—4,3 PCB 401,
    420
    (January
    6,
    1972).
    Having reviewed the record, the Board finds that the con-
    struction and the operation of Respondent’s treatment works with-
    in the flood plain of the Rock River without protective
    berrns or
    other flood control r~easuresand the excavation of the receiving
    lagoon to bedrock,
    indicates a conscious disregard on the part of
    Allaert for reasonable control measures to prevent malfunctions
    and spills.
    (R.
    88—89,
    97—99,
    110,
    165)
    During the period of this Complaint, the record shows that
    Respondent completed construction of its treatment works without
    concern for the permit requirements.
    In its permit application,
    35—295

    —16—
    dated February 10,
    1976,
    its proposed improvements,
    a 25-year
    flood berm and fencing cannot be considered reasonable remedial
    measures for a receiving lagoon constructed in the fall of 1973.
    For purposes of this alleged violation,
    it also indicates that
    Respondent has failed to consider reasonable measures to prevent
    malfunctions due
    to flooding or adverse weather or to guard
    against spills.
    Since it
    is unnecessary to show proof of actual pollution
    within the complaint period for a Rule 601 violation,
    the Board
    finds sufficient evidence in the record to hold the Respondent
    in violation of Rule 601 of Chapter
    3 and in violation of the
    provisions of Section 12(a)
    of the Act which,
    “threaten
    .
    the discharge of any contaminants into the environment
    .
    .
    .
    so
    as to violate regu1~tionsor standards adopted by the Pollution
    Control Board under this Act.”
    CERTIFIED OPERATOR REQUIREMENTS
    Count VI alleged that Respondent operated its treatment
    works without
    a certified operator in violation of Rule 1201 of
    Chapter
    3 and Section 12(a)
    of the Act.
    Evidence advanced
    in support of this allegation is limited
    to the testimony of Mr. Charles Feliman, Manager of the Permit
    Section in the Agency.
    Mr. Feliman testified that at some time
    prior to the hearings he telephoned Mr. Bob Voss, Operator
    Certification Specialist
    in the Agency,
    to inquire whether the
    Respondent Allaert Rendering,
    Inc. had a certified operator
    running its treatment works.
    Mr. Fellman was told that Allaert
    had no certified operator under its employment.
    (R.
    378—82).
    While this evidence is admissible under Procedural Rule
    320(A), the Board will not afford such evidence the same
    weight as
    the testimony of an operator certification specialist
    during the hearing or his affidavit.
    The Board hereby finds
    that this singular statement challenged by the Respondent can-
    not support
    a finding of violation of Rule 1201 against the
    Allaert Rendering,
    Inc.
    ALLAERT’S EFFORTS TOWARD FACILITY IMPROVEMENTS
    The record indicates that,
    in response to Agency inquiries,
    Allaert contacted Beling in July,
    1975,
    to conduct a study on
    Allaert’s existing facility and to prepare a report recommending
    the necessary facility improvements.
    According to the limited
    evidence in the record,
    the Beling report recommended that:
    35—296

    —17—
    1.
    Allaert connect to a municipal sewer system and reclaim
    the land currently supporting the infiltration-percolation
    system; or
    2.
    Allaert should expand or complete its infiltration-
    percolation system.
    (R.
    426—27,
    432).
    Although the record is silent concerning the Respondent’s
    legitimate efforts
    to “expand or complete”
    its treatment system
    beyond the proposed installation
    of fencing and a 25-year flood
    berm of its permit applications, Paul Allaert conducted
    negotiations with the City of Silvis “some years back” concern-
    ing the availability of
    a sewer extension from Allaert to the
    City of Silvis.
    At the time negotiations were conducted, the
    City was
    in the process of purchasing
    land for a new sewage
    treatment plant.
    However,
    the Respondent claimed that the City
    of Silvis recommended that it would be better if Allaert
    connected with the City of East Moline.
    (R.
    127—28).
    It was not until October,
    1978,
    that Allaert could begin
    serious negotiations
    to direct its wastewater
    to the East Moline
    regional sewage treatment plant via
    a newly—completed
    sewer
    extension constructed by the Village of Carbon Cliff.
    By
    January,
    1979, Allaert had entered into an agreement with the
    Village of Carbon Cliff to annex
    the rendering works into the
    Village as
    a prerequisite for acceptance of the rendering plant
    wastewater.
    (R.
    127-28).
    Mr. Allaert also retained Beling to construct the sewer
    extension to the Carbon Cliff sewer system.
    According to current
    plans, Beling intends
    to install a sewer extension to the Carbon
    Cliff sewer system that will transport wastewater from the Allaert
    septic tank system to the Carbon Cliff sewer system after grease
    and solids have been removed from the wastewater.
    Once completed
    and operational,
    the Respondent has stated that receiving lagoon
    will be bulldozed over and the land will be used to plant crops.
    The cost of this sewer extension is estimated at $120,000 and
    the anticipated date of completion
    is December 15,
    1979.
    (R.
    128—
    30,
    276).
    After reviewing the evidence in this part with other evidence
    in the record,
    the Board finds that
    it cannot distinguish a sus-
    tained program for compliance with the Act and Board regulations
    until the recent flurry of activity after connection with the
    Carbon Cliff sewer system became available.
    Furthermore, the
    Board concludes that the Respondent’s tardy and incomplete permit
    applications and its belated proposal to install fences and a
    25-year flood berm do not qualify as serious
    efforts towards
    compliance.
    35—297

    -18--
    SECTION 33(c)
    FACTORS AND REMEDIES
    Section
    33(c)
    of the Act requires the Board to consider
    all
    facts and circumstances bearing upon the reasonableness of
    the discharges or the deposits before the Board may impose the
    remedial provisions of the Act for violations
    alleged and proven
    in the proceeding.
    In this case, alternative treatment systems
    are presumed to be economically reasonable since the Respondent
    has refused
    to submit financial records during discovery at the
    Agency’s request and pursuant to Hearing Officer order.
    How-
    ever, apart from the issue of economic reasonableness,
    the Board
    will review the four criteria of Section
    33(c)
    of the Act in
    determining the reasonableness of Respondent’s conduct.
    The character and degree of the violation in this matter
    must be considered in light of the findings in this Opinion.
    The Respondent has claimed that there have been no ill effects
    as a result of the discharge of its wastewater and to his
    knowledge
    its treatment system has caused no water pollution.
    Respondent’s consulting engineers claim no pollution to ground—
    water
    in the vicinity of the receiving lagoon solely on the basis
    that laboratory reports
    from nearby wells indicate no pollution.
    (R.
    120—21,
    247).
    In considering Respondent’s claims in light of the findings
    of a water pollution threat and a water pollution hazard and the
    violations of the permit, malfunction and spill requirements
    of
    Chapter
    3, the Board believes that the Allaert treatment works
    in its current condition poses a real threat to the surface and
    groundwaters in the vicinity of the rendering works.
    Of equal importance are the permit violations found in
    Counts
    I,
    II and III which seriously affect the efficient
    operations
    of the water pollution permit programs
    (NPDES permits
    and construction, modification and operation permits)
    that are
    designed to protect the public from injury or interference with
    health and property.
    It is well established that the permit
    systems adopted by the Board are essential
    to the proper manage-
    ment of the water as well
    as the air and the solid waste control
    programs of this State.
    Whenever necessary,
    the Board must use
    its penalty provisions and appropriate injunctive relief to
    ensure compliance.
    EPA v.
    Joliet, PCB 78-130,
    PCB
    (July 12,
    1979); EPA v. Time Chemical, Inc., PCB 75—291,
    19 PCB 386,
    387
    (December
    4,
    1975); EPA v.
    Chenoa Stone Co.,
    PCB 75-152,
    19 PCB
    659,
    660
    (January 14,
    1976).
    The Respondent has submitted
    evidence
    concerning the render—
    ing works
    and its social and economic value to the community;
    however,
    this will not excuse the Respondent’s rendering plant
    from the continuous and persistent violations
    of the State’s
    water pollution and permit regulations which are also designed
    to protect individuals
    in the vicinity of the rendering facility
    and water uses downstream from the site.
    35—298

    —19—
    The Board has reviewed the suitability of the Allaert treat-
    ment system to the area in which it is located in prior parts
    of this Opinion and also in the Opinion dealing with the variance
    proceeding, PCB 77-334, and agrees with the Agency that the
    construction of the treatment works
    to bedrock and its location
    within the flood plain poses
    a serious, continuing threat to
    the surface and groundwaters which diminishes
    the social and
    economic value of Allaert Rendering,
    Inc.
    Despite the refusal
    by Allaert to produce financial records
    pursuant to discovery orders, the Respondent made numerous offers
    of proof during the hearings in an attempt
    to induce the Board
    to consider testimony concerning the financial condition of
    Allaert Rendering,
    Inc.,
    the net income figures of Paul Allaert
    from 1970 until 1976 and testimony of Paul Allaert regarding
    economically reasonable treatment alternatives.
    The Board is,
    however, not persuaded by these offerings.
    The record clearly
    shows the Respondent had ample opportunity to comply with the
    Hearing Officer’s orders both before the Board Order denying
    Respondent’s Application for Nondisclosure and afterward.
    (R.
    131,
    133,
    136,
    141,
    469,
    477—79).
    The cost of alternative compliance measures as estimated
    by Beling engineers were accepted into evidence and tabulated
    in the PCB 77-334 Opinion on the basis of treating 30,000
    to
    40,000 gallons of wastewater per day.
    The figures are as
    follows:
    Cost Data
    Compliance Alternative
    Capital Costs
    0
    & M~
    1975
    Non-aerated Lagoon
    258,000
    35,000
    1975
    Aerated Lagoon
    92,000
    23,000
    1975
    Biodisc
    76,000
    22,000
    1975
    Activated Sludge System
    76,000+
    30,000+
    1975
    Trickling Filter System
    76,000+
    30,000+
    1975
    Physical Chemical Treatment
    System
    76,000+
    30,000+
    1975
    Infiltration—Percolation System
    65,000
    11,000
    1977
    Connection to Carbon Cliff
    120,000
    11,000
    *Annual operation and maintenance cost.
    (R.
    267—77)
    In assessing the estimates by the Respondent’s consulting
    engineers
    in comparison with the current costs of diverting
    Respondent’s wastewater to the Carbon Cliff sewer system, the
    Board concludes that certain technological alternatives available
    to Allaert in 1975 are substantially similar
    in construction,
    operation and maintenance costs
    as the current Allaert compliance
    program which contemplates completion by December 15,
    1979.
    Accordingly, the Board
    finds
    no evidence in the record
    to dispute
    the holding that compliance with the water pollution
    35—299

    —20—
    requirements of the Act and Board regulations was not technically
    practical and economically reasonable
    for the Respondent
    as
    early
    as the Beling report in 1975.
    Since
    the Respondent has taken nearly five years
    to devise
    and implement a competent compliance plan,
    the Board must assess
    a penalty of
    $3,000 as the minimum necessary to ensure future
    compliance with the Act and Board regulations;
    $750 for the
    violation of 12(a)
    of the Act,
    $750 for violation of Rule 601
    and $1500
    for violation of the construction and operation permit
    regulations.
    Furthermore, the Board will require that the
    Respondent post a bond of $127,000 pursuant to Section 33(b)
    of the Act as assurance that the Respondent shall do the follow-
    ing:
    1.
    Allaert shall complete the proposed plan to divert
    its wastewater
    from its existing treatment facility to the
    Carbon Cliff sewer system as contemplated in the plan on or
    before December
    15, 1979;
    and
    2.
    Allaert shall remove the standing water
    in its re-
    ceiving lagoon on or before December
    31, 1979.
    The Respondent, Allaert Rendering,
    Inc., shall cease and
    desist from further violations of the Act and Board regulations
    on or before December
    15, 1979.
    This Opinion constitutes
    the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    1.
    Respondent, Allaert Rendering,
    Inc.,
    is found
    to have
    violated Section 12(a)
    of the Environmental Protection Act
    by discharging wastewater into a receiving lagoon which threatens
    the surface and groundwaters
    of the State with water pollution.
    2.
    Respondent, Allaert Rendering,
    Inc.,
    is found to have
    caused or allowed the construction and operation of its treatment
    works without the necessary permits from April
    30, 1974, until
    March 19,
    1976,
    in violation of Rule 901(a), renumbered 951(a),
    902(a),
    renumbered 952(a),
    and 903(a), renumbered
    953(a) of
    Chapter
    3:
    Water Pollution Regulations and Section 12(b) of
    the Environmental Protection Act.
    3.
    Respondent, Allaert Rendering,
    Inc.,
    is found
    to have
    violated Section 12(d)
    of the Environmental Protection Act by
    discharging wastewater into a receiving lagoon creating
    a water
    pollution hazard to the surface and groundwaters of this State.
    35—300

    —21—
    4.
    Respondent, Allaert Rendering,
    Inc.,
    is found in
    violation
    of the malfunction and spill requirements of Rule
    601 of Chapter
    3:
    Water Pollution Regulations and Section
    12(a)
    of the Environmental Protection Act.
    5.
    Count VI alleging that the Respondent operated its
    treatment works without a certified operator in violation of
    Rule 1201
    of Chapter
    3:
    Water Pollution Regulations and
    Section 12(a)
    of
    the Environmental Protection Act is hereby
    dismissed.
    6.
    Respondent, Allaert Rendering,
    Inc., shall,
    by
    certified check or money order payable to the State of Illinois,
    pay a civil penalty of $3,000.00 within 35 days of the Order
    which shall be sent to:
    Illinois Environmental Protection Agency
    Fiscal Services Division
    2200 Churchill Road
    Springfield,
    Illinois
    62706
    7.
    Respondent, Allaert Rendering,
    Inc., shall cease and
    desist from violations of the Act and Board regulations herein
    found on or before December
    15,
    1979.
    8.
    Respondent, Allaert Rendering,
    Inc., shall, in accordance
    with Section 33(b)
    of the Environmental Protection Act, post a
    performance bond in a form satisfactory
    to
    the Agency in the
    amount of $127,000 as assurance that the Respondent shall complete
    the following:
    A.
    Allaert shall complete the proposed plan to
    divert its wastewater
    from its existing treat-
    ment facility to the Carbon Cliff sewer system
    on or before December 15,
    1979,
    the date con-
    templated
    in the plan;
    and
    B.
    Allaert shall remove the standing water
    in the
    existing receiving lagoon by pumping to the
    Carbon Cliff sewer system on or before December
    31,
    1979,
    or as soon as practicable thereafter
    in accordance with a schedule to receive the
    wastewater negotiated with the Village of
    Carbon Cliff and approved by the Illinois
    Environmental Protection Agency.
    IT IS SO ORDERED.
    Mr. Werner dissented.
    35—30 1

    —22—
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the above Opnion and Order were
    adopt~jon the
    ~f”4
    day of~
    1979,
    by a vote
    Christan L.
    Moffe
    erk
    Illinois Pollution
    rol Board
    35—302

    Back to top