ILLINOIS POLLUTION CONTROL BOARD
    November 12, 1982
    MOBIL CHEMICAL CO.,
    Petitioner,
    v.
    )
    PCB 82—18
    ILLINOIS ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    EUGENE W.
    BEELER, JR.
    (MANGUM, BEELER, SCHAD
    & DIAMOND) AND
    WINFRED
    T.
    COLBERT APPEARED ON BEHALF OF PETITIONER,
    E.
    WILLIAM HUTTON APPEARED ON BEHALF OF RESPONDENT, AND
    LOUIS
    J.
    PERONA, ASSISTANT STATE’S ATTORNEY,
    APPEARED ON BEHALF
    OF THE COUNTY OF BUREAU.
    OPINION AND ORDER OF THE BOARD
    (by J.
    Anderson):
    This matter comes before the Board on the petition for
    variance of Mobil Chemical
    Co.
    (Mobil), filed February
    23,
    1982
    as amended July
    14,
    1982.
    Mobil
    seeks variance for two ‘~fluent
    discharges from its De Pue, Bureau County,
    fertilizer manufacturiTig
    plant.
    As
    to its Outfall
    001, Mobil
    seeks
    a three—year variance
    from Section 12(a)
    of the Environmental Protection Act (Act) and
    from the 15.0 total
    suspended solids
    (TSS)
    effluent standard of
    35
    Ill.
    Adm. Code 3O4.124(a)
    formerly
    Rule 408(a)
    of Chapter 3~
    Water Pollution.
    As
    to Outfall
    002,
    a two year variance
    is
    sought from Section 12(a)
    of the Act from the water qualit~y
    standards
    for ammonia nitrogen
    (1.5 mg/I),
    fluoride
    (1.4 mg/i),
    and total dissolved solids
    (TDS)
    (1000.0 mg/i)
    contained
    in
    35 Iii.
    Adm. Code 302.208
    formerly
    Rule 203(f)
    of Chapter 3.
    On April
    15,
    1982 the Illinois F~nvironmentalProtection
    Agency
    (Agency) filed its initial Recommendation that variance
    be denied as to Outfall
    001,
    but granted in part, with conditions
    as to Outfall
    002.
    Based on information obtained as a result of
    May 26 and July 22,
    1982 meetings with Mobil,
    the Agency amended
    its Recommendation August 30, 1982 to suggest that variance with
    conditions be granted as to each outfall, hut that variance for
    Outfall
    002 be limited to one year.
    49-275

    2
    Pursuant to Bureau County’s March
    15,
    1982 objection to
    the petition, hearing was held on August
    31,
    1982 at which the
    parties, the County and members of
    the public were
    in attendance.
    On September 16,
    1982,
    the County petitioned the Board for leave
    to intervene
    in this matter.
    In the “Argument” attached thereto,
    the County states its support of grant of variance for the terms
    and with the conditions outlined
    in the Agency’s amended Recorn-
    rnendation.
    The petition for leave
    to intervene is granted.
    As
    the Hearing Officer allowed the County to present testimony of
    two witnesses at hearing, “de facto”
    leave had already been
    granted,
    in a situation where a formal
    leave to intervene would
    have been within the Hearing Officer’s power to grant.
    Finally, on September 30,
    1982 Mobil
    moved for leave to file
    instanter
    a “Response to Agency’s Recommendation”.
    The motion and
    Response recite that the Agency has no objection to this late
    filing, and the response outlines post—hearing discussions between
    Mobil and the Agency concerning both agreed
    to and still contested
    modifications
    to variance conditions suggested in the Agency’s
    amended Recommendation.
    The motion is granted.
    At hearing, technical testimony in Mobil’s behalf was
    presented by its employee Robert
    D.
    Stevens.
    The Agency
    presented
    no witnesses.
    Bureau County presented two witnesses
    whose testimony was primarily directed to the Outfall 002
    problem:
    Kenneth Abrahams whose mother-in—law was the former
    owner of the property on which that outfall
    is located, and
    Kathryn Zawacki whose home
    is located on the unnamed tributary
    of the Illinois River into which the outfall discharges, one
    mile downstream of that discharge.
    Mobil’s phosphate fertilizer manufacturing operation employs
    117 employees to produce 250,000 tons of fertilizer per year from
    the raw materials phosphate rock,
    sulfur,
    and ammonia.
    The
    facility consists of a sulfuric acid manufacturing plant,
    a
    phosphoric acid manufacturing plant,
    and a diammonium phosphate
    (DAP) plant.
    Outfall 001 discharges non-contact cooling water and boiler
    feedwater treatment effluent.
    Mobil currently draws
    15 million
    gallons per day
    (mgd)
    of water from the Illinois River
    for use
    in its operation,
    but has the capacity to draw 20.3 mgd.
    98
    of
    this water,
    14.6 mgd,
    is used “as
    is” for non-contact cooling of
    sufuric and phosphoric acids.
    An additional
    94,500 gallons are
    used “as is” for dilution water
    in the sulfuric acid plant.
    The remaining 290,000 gallons are used as boiler feed water,
    after the water is filtered and conditioned in a cold lime—zeolite
    softening system to remove background solids from the raw water.
    Several steps
    in the process between intake and use of the water
    produce effluent with high solids contents:
    49-276

    3
    1.
    The water enters a precipitator/clarifier where
    lime,
    soda ash and settling agents are added to clarify and precipitate
    calcium and magnesium.
    This process generates an average daily
    effluent of 1,000 gpd containing
    1,208 poun’~sof solids.
    2.
    Clarifier water from the precipitator is processed
    through
    2 large sand filters for further solids removal.
    Periodic
    backwashing of the filters, which frequency is dependent on
    solids content of the river water, generates a flow of 8,250 gpd
    containing 64 pounds of solids.
    3.
    The filtered water is then softened.
    Softener regeneration
    results in a discharge of 1,960 gpd containing
    0.5 pounds of
    solids.
    4.
    The finished water is then used for boiler feed water.
    Boiler blowdown results
    in a discharge of
    30,000 gpd containing
    0.5—0.6 pounds of solids.
    Precipitator underflow is reunited with the non-contact
    cooling water stream,
    which then flows to two 50’
    X 500’ settling
    lagoons.
    Filter backwash,
    softener regenerate,
    and boiler blow—
    down are also routed
    to the lagoons, prior to the lagoons’ dlscharge
    into De Pue Lake,
    a backwater lake of the Illinois River.
    Mobil asserts that the nature and extent of its failure to
    meet the 15 mg/i TSS limit of the Board’s rules and its NPDES
    permit
    (a condition appealed in still-pending PCB 79—209)
    “are a
    direct function of the TSS levels present in the influent
    (intake
    water)
    from the Illinois River,
    i.e.,
    the influent TSS levels are
    greater than 15 mg/i”.
    Mobil
    further notes that the TSS levels
    in its non—contact cooling water discharge have been 25
    -
    40
    lower than the TSS levels in the intake water
    (Ex.
    5).
    Mobil proposes to re—route the precipitator underfiow by
    pumping
    it to an existing gypsum pond water system
    (Outfall 002,
    which is discussed in more detail,
    infra), rather than reuniting
    it with the non—contact cooling water.
    This system would cost
    $35,000—$40,000 and could be complete and operational
    by December,
    1982.
    Mobil has also investigated the possibility of removing
    the
    remaining 5
    TSS loading added by the filter backwash, softener
    regenerate and boiler blowdown.
    Comparative
    costs of re—routing
    these streams are as follows:
    49-277

    4
    Estimated
    Estimated
    Waste
    Pounds/
    Percent
    Cost to
    Removal Cost
    Stream
    Day
    Total
    Remove
    Per_Pound~
    Precipjtator/
    1208
    95
    $
    40,000
    $
    33/lb.
    Clarifier
    Sandfiiter
    64
    5
    $200,000
    $
    3,125/lb.
    Backwash
    Combined Boiler
    1
    .0785
    $
    20,000
    $20,000/lb.
    Blowdown and
    Softener Regenerate
    Wastewater
    Mobil
    states that removal of the sandfilter backwash, boiler
    blowdown and softener regenerate wastewater would require the
    discharge
    of the backwash water into the existing closed—loop
    gypsum pond water system.
    At the current time,
    the water balance
    in this system is slightly negative
    (requiring small water
    additions).
    If the backwash water option was added to the gypsum
    pond system, the balance would become very positive,
    so that
    there
    would be water in excess of that required to run the plant.
    This
    would require additional capital expenditure
    riot identified in
    the mentioned construction cost to either increase the system’s
    water evaporation rate or treat contaminated pond water and
    discharge.
    As a result,
    Mobil considers this option infeasible.
    Mobil asserts that if variance is granted to allow for
    re-routing only of the precipitator underflow,
    that environmental
    harm would be minimal, as the TSS in its effluent would continue
    to be lower than that in the irifluent river water.
    In its amended Recommendation,
    the Agency recommends
    variance with conditions from 35 Iii.
    Adm. Code 304.124, hut not
    from
    the Act itself.
    The Agency does not dispute Mobil’s economic
    claims,
    and is particularly concerned about the water balance
    problems alleged concerning re—routing of the filter backwash,
    which could exacerbate the water quality problems downstream from
    Outfall
    002.
    It suggested grant of variance for a three—year
    period,
    subject to conditions requiring investigation and
    reporting of emerging technology to cost effectively remove TSS
    from the process streams still tributary to Outfall
    002,
    and to
    maintenance of an
    8 foot depth in all portions of its settling
    lagoons.
    However,
    as Mobil
    recites in its Response,
    the parties
    have agreed that the intent of the latter conditions would be
    satisfied and more appropriately implemented by annual
    lagoon
    dredging and use of normal good operating practices.
    The Board finds that denial of variance would impose an
    arbitrary or unreasonable hardship, balancing the minimal
    environmental impact of less—than—full compliance against the
    49-278

    5
    major costs
    to achieve full compliance.
    A three—year variance
    from 35 Ill. Mm.
    Code 304.124 is granted, subject to the recom-
    mended and agreed conditions.
    Variance from the Act is denied
    as unnecessary.
    What has been called Outfall 002 consists of groundwater
    seepage
    from a gypsum storage area and clearwater pond used in
    Mobil’s phosphoric acid manufacturing process.
    The gypsum/
    clearwater pond treatment system operates on a closed—loop basis.
    In this recycling system, water serves as the transport medium
    for gypsum produced during acid manufacture and filtered out of
    the acid.
    Gypsum is slurried with pond water and pumped to the
    gypsum disposal area.
    The gypsum is settled in the gypsum pond,
    and most of the clear water
    is recycled to the acid plant.
    However, seepage from the gypsum pond flows into an unnamed ditch
    running along the perimeter of the gypsum/clearwater pond system.
    This ditch
    is tributary to Negro Creek, which is tributary to
    the Illinois River.
    Seepage to the unnamed ditch ranges from
    10,000 to 28,000 gpd.
    The ditch
    fails to comply with the state’s
    water quality standards for fluoride, ammonia nitrogen, TDS and
    pH,
    and with the federal phosphorus standard.
    Stream samples
    taken 1,200 feet downstream of the process wastewater treatment
    system in the period November,
    1981 through January,
    L982 showed
    levels for these parameters
    in the following ranges:
    Fluoride
    5.64
    36.0 mg/l
    Phosphorus
    131.
    402.0 mg/i
    Ammonia
    63.4
    230.0 mg/i
    pH
    6.54
    7.27
    TDS
    1,224.0
    4,556.0 mg/i
    Mobil has had a long history of problems with the pond
    system,
    which received its first operating permit in 1972.
    Mobil
    states that when the ponds were first constructed, state—of—the-
    art industry design recommendations were for installation of
    separate leak and seepage containment systems along the ponds’
    base.
    Mobil
    felt that an improved design eliminated the need
    for such containment systems, particularly since a natural clay
    layer between
    5 and 25 feet thick underlays the ponds.
    The same
    design system was employed
    in a 1976 expansion of the gypsum pond,
    at which time a 12 inch clay liner was put inside the expanded
    earthen dam.
    Leaks formed in the pond walls.
    In 1977 the Agency issued
    supplemental permit allowing for construction of a collection pond
    (swale) to contain seepage from the gypsum pond prior to its being
    pumped hack into a clearwater pond.
    An experimental permit was
    also issued to allow construction and installation of two pilot
    test collection trenches, one
    45 and the other 125 feet along, and
    appurtenant pipes, pumps, and to allow re—routing of the unnamed
    ditch.
    The system was permitted to test the feasibility of
    intercepting seepage from the gypsum pond before its entry into
    the ditch.
    The Agency reports that only the 45 foot trench was
    built,
    and that its use was discontinued by Mobil
    in 1981 since
    49-279

    6
    the company felt it had no significant effect.
    Finally,
    in October 1981 the Agency issued Mobil
    a permit to operate a
    collection sump and pump back system.
    This involved the above
    described re—routing of a portion of the ditch and use of another
    portion to collect the seepage.
    The sump is used to dewater the
    general area upstream of the location where the existing ditch
    joins
    the by-pass.
    Water is pumped back to the swale.
    Mobil states that it expended $90,000 in 1978 to install
    the swale and pump system along the base of the affected pond.
    As this took care of only 90
    of the seepage,
    Mobil began further
    investigation as
    to the problem’s
    source.
    Some
    4 years and
    $95,000 later, Mobil states that it believes that an opening has
    developed along the base of the pond’s earthen dam allowing small
    quantities of water to seep out and flow below ground level along
    the top of the area’s underlying clay layer,
    to emerge
    in the
    unnamed ditch.
    Mobil seeks variance to allow it to further identify and
    define the area subject to seepage, and to contain and return
    seepage to the pond system while
    so doing.
    It proposes
    to deepen
    the existing collection trench by 4’
    -
    6’,
    and to excavate the
    collection sump to contain
    a surge volume of 85,000 gallons
    to
    intercept rainfall runoff.
    It also proposes to install a new
    pump to operate
    in parallel
    to the existing pump.
    Both pumps
    would be piped directly to the clearwater pond.
    Mobil believes that this project,
    as outlined, would increase
    pumpback system reliability to 90—95.
    Construction costs are
    estimated
    to be $90,000
    $110,000 and the increase
    in annual
    operation and maintenance costs to be
    $3
    $5 million.
    Project
    completion time
    is estimated to be
    10 months.
    Mobil considered
    and rejected two minimally quicker alternatives, each on the basis
    of lack of surge volume containment, higher costs, and greater
    operational difficulties.
    Mobil
    requests that variance be extended
    for 14 months after
    construction
    is completed,
    for
    a variance period totalling 24
    months.
    Two months of those months would provide
    a start—up
    cushion, while the other twelve are requested for collection of
    monitoring data and system evaluation.
    Mobil believes that
    this would allow it to define the limits of this latest system
    improvement and provide data necessary to plan any other necessary
    improvement.
    During the variance period,
    Mobil requests that the
    unnamed ditch be subject to interim water quality limits of 150
    mg/i
    for ammonia nitrogen,
    20 mg/i for fluoride, and 4,600 mg/i
    for TSS.
    Mobil states that denial of variance would impose an
    arbitrary or unreasonable hardship because
    1)
    it is unaware of any
    way to achieve immediate compliance with water quality standards,
    including plant shutdown,
    2)
    it is currently unaware of any way
    to
    eliminate
    the
    seepage
    source,
    and
    3)
    it believes that seepage
    would
    be unaffected by a production curtailment.
    49-280

    7
    Mobil states that this improvement was designed to produce
    100
    containment of its wastewater,
    and possibly contaminated
    runoff from rainwater,
    and that
    it hopes
    the system will enable
    it to achieve full compliance with water quality standards.
    In
    its amended petition,
    it states
    its belief that variance would
    result in
    “no significant detrimental impact to the nearby
    environment.
    The unnamed ditch flows
    1.2 miles from
    the treatment pond area southeasterly to Negro Creek
    which,
    in turn,
    flows
    1 mile south to the Illinois
    River.
    The ditch is thickly weeded and heavily wooded
    with scrub trees along most of its length,
    is not a
    source for public and food processing water supply, and
    we believe would have little,
    if any,
    use for swimming,
    fishing,
    or other recreational purposes.
    Slightly
    increased algae growth can be observed only
    in a few
    open areas approximately 1,000 feet downstream of the
    treatment pond area”
    (Am. Pet.
    at 13).
    In its Recommendations, the Agency strongly disagrees with
    this assessment, believing that Mobil’s discharge has had a sub-
    stantial adverse impact.
    Ammonia nitrogen levels are “excessive,
    being well above acute toxicity levels for many species of fish”
    and “would cause algae blooms
    in the stream”
    (Rec.
    p.
    15).
    Testimony given by Donald Bosnick and Kathleen Zawacki in
    PCB 79—209
    is cited to refute Mobil’s claims.
    These individuals
    testified to the degradation of the stream from a clear,
    recreationally usable waterway containing aquatic life to an ugly
    ditch devoid of life.
    Each had played by the stream as children;
    Mrs. Zawacki had recently observed children swimming
    in it, hut
    refuses to allow her own child to do so.
    She also testified to
    the strong odor occasionally given off by the stream, and to the
    occasional white and yellow colored bottom deposits.
    As Mobil
    has made no objection to the Board’s consideration of this
    testimony,
    and as Mrs. Zawacki herself again testified in this
    variance proceeding, the Board will consider this information.
    At hearing in this matter,
    Mrs.
    Zawacki testified to an
    occurrance in July,
    1982.
    As aforementioned, the Zawacki home
    is located about one mile downstream of the Mobil gypsum pond;
    the unnamed ditch runs behind the home and is approximately 120’—
    140’
    from the Zawacki’s well.
    Following a heavy rainfall, the
    ditch overflowed its banks.
    When the water receded, the ground
    had
    a “white—type, definite look”.
    The water had an “awful strong
    gagging smell”,
    which
    smell was said to be “also
    in our creek
    most of the time”
    (R.
    85—87).
    Due in part to the odor,
    Mrs. Zawacki has had the Agency
    sample the water
    in the creek on at least
    2 occasions (Bureau
    County,
    Ex.
    1,2), anaylsis of which samples show water quality
    violations.
    In September—October,
    1980 after her well water
    49-281

    8
    also begain to smell, the well water was sampled by some state
    agency, probably the Department of Public Health.
    Sample results
    were not entered into evidence
    (R.
    99).
    On cross—examination, Mr.
    Stevens, Mobil’s witness, testified
    that gypsum itself does not have an odor.
    He did however testify
    that he has smelled an odor near Mobil’s clearwater ponds.
    Mr. Stevens could not specify the odor’s source, but did not
    refute the Agency’s speculation that the source of the odor might
    be from sulfate concentrations, while agreeing that gypsum,
    a
    crystalline calcium sulfate,
    is considered an inert substance
    (P.
    109—110).
    Concerning Mobil’s hardship allegations,
    in its
    Recommendation, the Aency states
    its belief that “Mobil has made
    something
    less than an all-out effort to achieve compliance.
    Breakdowns and overflows of the bypass/sump/collection system
    began
    to occur
    in April
    1981,
    and the Agency notes that Mobil
    has given “no explanation for its continued failure to resolve
    them”.
    No explanation was given for the failure to dig the
    second pilot test trench
    for which an experimental permit was
    issued.
    Delay in follow—up on preliminary consultant’s reports
    was also noted
    (Rec.
    p.
    12).
    However, admitting the technical difficulty of obtaining
    immediate compliance,
    the Agency recommends grant of variance
    in the interests of ameliorating a severe environmental problem.
    In its Amended Recommendation,
    the Agency recommends grant of
    variance for one year, subject to imposition of Mobil’s suggested
    interim limits,
    a thrice weekly monitoring requirements and other
    conditions.
    In its Response, Mobil indicates that the Agency has agreed
    to the reasonableness of a modified monitoring plan calling for
    monitoring twice weekly, and also whenever there is a rainfall
    of greater than one
    inch.
    Disagreement continues to exist as to
    the duration of variance.
    It is the Agency’s position that variance should terminate
    upon the completion and start-up of Mobil’s contaminant mechanism
    in August,
    1984.
    The Agency feels that
    this short term is
    consistent with the objective of returning the unnamed ditch to
    its full use potential
    as quickly as possible, and would provide
    Mobil
    with an incentive to design, construct and operate its
    existing and planned facilities to as
    to provide complete
    containment of run—off.
    While noting that stricter limitations
    conceivably could he set during the second year of a two year
    variance,
    the Agency feels this to be infeasible.
    As no
    construction permit application had been filed,
    the Agency is
    unaware of the basis of design or specific manner
    in which the
    project would be carried out,
    so that there
    is insufficient
    information on which to propose water quality limits reasonably
    based upon expected performance levels.
    If additional variance
    relief proves necessary after equipment installation, the Agency
    49-282

    9
    says, Mobil can then petition for the Board for an additional
    variance “with appropriate interim water quality levels”.
    (As
    aforementioned, Bureau County has adopted the Agency’s position.)
    The Board finds that denial of variance would impose an
    arbitrary or unreasonable hardship.
    Mobil has, albeit with a
    certain measure of “footdragging”
    (which is not hereby excused),
    been engaged for some time in a costly attempt to develop tech-
    nology to cure what has become a serious environmental problem.
    The Agency’s objections
    to a two—year variance are well taken,
    although Mobil contended that time will he needed to assess the
    efficiency of the system.
    Should
    it be that, due to limitations
    in current technology and geologic conditions
    in the gypsum pond
    area,
    complete containment cannot be achieved
    (as the Agency ack-
    nowledges
    as possible), stricter interim water quality standards
    could not reasonably be fashioned in any subsequent variance
    proceeding
    in the absence of any performance data.
    The Board is
    therefore granting variance for an additional two months beyond
    the time recommended by the Agency.
    Variance from 35 Iii. Mm.
    Code 302.206 is therefore granted until November
    15,
    1983 subject
    to conditions as recommended.
    Variance from the Act is denied
    as unnecessary.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board in this matter.
    ORDER
    1.
    Petitioner, Mobil Chemical Co.,
    is granted variance for
    discharges from Outfall
    001 of its
    De Pue facility from the 15.0
    mg/l total suspended solids
    (TSS) effluent standard of 35
    Ill.
    Am.
    Code 304.124(a), subject to the following conditions:
    a)
    This variance shall
    terminate November 15,
    1985.
    b)
    Petitioner shall
    at all times maintain and
    operate both settling ponds
    in such a manner as to
    achieve optimal performance.
    c)
    Petitioner shall dredge its two settling
    ponds at least once annually.
    d)
    Petitioner shall monitor at Outfall 001 for
    TSS by means of
    a composite sample taken five times
    per week, and shall submit
    its results to the Agency
    with its monthly Discharge Monitoring Reports.
    e)
    Petitioner shall make a continuous and
    thorough effort to ascertain the existence
    of new
    cost—effective technology for treatment of TSS
    discharges from the sand filter backwash and boiler
    blowdown/softener regenerate wastewater.
    Petitioner
    shall report its findings to the Agency by July
    1 of
    1983,
    1984 and 1985.
    49-283

    10
    2.
    Petitioner is granted a variance for seepage from
    Outfall 002 of its De Pue facility from 35 Ill.
    Adm. Code 302.208
    as it pertains to total
    dissolved solids
    (TDS),
    ammonia nitrogen
    and fluoride subject to the following conditions:
    a)
    This variance shall terminate November
    15,
    1983.
    b)
    Petitioner shall
    at all times maintain and
    operate its existing bypass/sump/collection system in
    such
    a manner as
    to achieve optimal performance.
    c)
    Concentrations of the following contaminants
    in the unnamed ditch at Outfall 002 shall not exceed
    these levels:
    Ammonia Nitrogen
    —-
    150 mg/l
    Fluoride
    ——
    20 mg/i
    Total dissolved solids
    —-
    4,600 mg/i
    d)
    At its Sampling Station
    #4, Petitioner
    shall monitor flow,
    and levels of each of the above
    contaminants, by means of a composite sample taken
    two times per week and also whenever there
    is a
    rainfall greater than one inch
    (1”).
    These results
    shall
    be submitted to the Agency with Petitioner’s
    monthly Discharge Monitoring Reports.
    e)
    Petitioner shall design and construct the
    additional seepage control mechanisms specified in its
    Amended Petition
    in accordance with the following
    timetable:
    Installation of Containment
    April
    1,
    1983
    Complete Installation
    June
    1,
    1983
    Including Additional Excavation
    System Start—up and Evaluation
    June
    1,
    1983
    through August 1,
    1983
    A report of the progress made regarding this work shall
    be submitted to the Agency monthly.
    f)
    Petitioner shall submit a complete and
    detailed engineering plan regarding the above additional
    containment mechanisms to the Agency within 45 days of
    the date of this Order.
    3.
    Variance from Section
    12(a) of the Act is denied as
    unnecessary.
    49-2R4

    11
    4.
    Within forty—five days of the date of this Order,
    Petitioner shall execute and forward to the Illinois Environmental
    Protection Agency,
    2200 Churchill Road,
    Springfield,
    Illinois
    62706,
    a Certificate of Acceptance and Agreement to be bound to
    all terms and conditions of this variance.
    This forty—five day
    shall
    be held in abeyance for any period this matter
    is being
    appealed.
    The form of the certificate shall be as
    follows:
    CERFITICATE
    I,
    (We),
    ___________________________—,
    having
    read
    the Order of the Illinois Pollution Control Board
    in PCB 82—18,
    dated _______________________________,
    understand and
    accept
    the
    said Order realizing that such acceptance renders all terms and
    conditions thereto binding and enforceable.
    Petitioner
    By:
    Authorized Agent
    Title
    Date
    5.
    Bureau County’s September
    16,
    .1982 petition for leave
    to intervene is granted.
    IT IS SO ORDERED.
    I,
    Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that the above Opinion and Order
    was adopted on the j~.-~—
    day of
    ~
    ,~
    —,
    1982 by a
    vote
    of
    ~-C~
    ~
    Tt~/
    z~/i~
    Christan
    L.
    Mof
    ett,
    C1~k
    Illinois
    Pollution
    Control
    Board
    49-2R!S

    Back to top