ILLINOIS POLLUTION CONTROL BOARD
    May 26, 1977
    WILLIAM GILMAN,
    Petitioner,
    v.
    )
    PCB 77-35
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr.
    Zeitiin):
    The original Petition for Variance in this matter was filed on
    February
    1,
    1977,
    seeking relief
    from the requirements of Rule 962
    of Chapter
    3: Water Pollution, delineating the standards of issuance
    for non-NPDES Permits under sub-part B, Part
    9 of Chapter
    3,
    (Rule
    951 et seq.)
    Variance was sought to allow the construction of a
    sewer extension to serve a planned 10—lot subdivision
    (the “Gilman
    Addition to the City of Wenona”) which would be tributary
    to the
    City of Wenona sewage treatment plant.
    In an Interim Order entered February
    3,
    1977,
    the Board found
    Mr. Gilman’s Petition inadequate and ordered that additional infor-
    mation be filed.
    That information was filed
    in an Amended Petition
    received March 11,
    1977.
    The Recommendation of the Environmental
    Protection Agency
    (Agency) was received on April
    25,
    1977.
    No
    hearing was held
    in this matter.
    Petitioner wishes
    to construct a 5—acre subdivision of 10
    lots
    on land purchased for $25,000
    in September,
    1976.
    The subdivision
    would be served by a 576—foot sewer extension which,
    it is estimated,
    will carry 4800 gallons per day, including 8.2 pounds BOD and 9.6
    pounds Suspended Solids.
    The estimated population of the subdivision
    will be
    48 persons.
    The subdivision would be serviced by the City
    of Wenona, which currently has a combined storm and sanitary sewer
    system which outlets to
    a pumping station adjacent to Petitioner’s
    land.
    Petitioner alleges that the only alternative use for the land
    in question is farming, which because of the size of the parcel,
    could only realize a net income of approximately $500 per year.
    A Permit for the sewer extension was requested from the Agency
    on December
    1,
    1976.
    That Permit application was denied by the Agency
    because the City of Wenona’s sewage treatment plant cannot meet the
    applicable standards of
    4 mg/l BOD and
    5 mg/i SS for discharges
    to
    Sandy Creek, tributary to the Illinois River.
    Although the sewage
    treatment plant has
    a design population equivalent
    (PE) capacity of
    1,500 and has a current loading of only approximately 1000-1100 PE,
    the existing two-stage waste stabilization type treatment plant
    cannot meet applicable
    standards.
    25
    583

    The City has refused
    to accept Step
    II and Step III grants for
    improvement of the sewage treatment plant.
    Because the City refused
    the construction grants, and because it cannot meet its
    50 mg/i and
    100 mg/l NPDES permit limitations for BUD and
    SS,
    respectively, the
    Agency refused
    the Petitioner’s application to construct the sewer
    extension in issue.*
    The Petitioner alleges, and the Agency does not contest,
    that
    Wenona was not on Restricted Status prior to December
    1,
    1976.
    Nor
    does
    the Agency contest Petitionerrs allegations that an Agency
    representative informed Petitioner that a Permit could be obtained
    notwithstanding the City’s refusal to accept Step
    II and Step III
    funding.
    Petitioner alleges that his commitment to purchase and
    develop the land in question was made based on such assurance.
    The Agency’s Recommendation reiterates essentially the same
    facts
    as are alleged by the Petitioner and recommends
    that the Petition
    be granted.
    The Agency feels, apparently, that Petitioner should
    not be penalized under these circumstances for the City of Wenona’s
    failure
    to meet applicable standards.
    In addition,
    the Agency alleges
    that the addition of
    48 PE to the existing plant would not result
    in any additional degradation of the receiving waterway.
    The City
    has sufficient additional capacity to treat the additional
    load and
    still meet existing effluent levels.
    Although we feel that any additional
    load added
    to an already
    substandard sewage treatment p1an~
    must
    exacerbate an existing
    violation,
    we nonetheless agree with the Agency that the additional
    load
    to be generated by Petitioner’s subdivision will not generate
    such environmental damage as would outweigh the hardship to Peti-
    tioner
    if the Variance is not granted.
    Weighing these factors, we agree that the potential hardship
    to Petitioner outweighs the potential adverse impact on the environ-
    ment if the Variance were not granted.
    Likewise we agree with the
    Agency that the alternative
    -
    the installation of individual septic
    fields for each of the lots
    in question
    -
    would pose
    a potentially
    greater
    ~idverse
    impact
    upon
    the
    envjronment.
    We
    shall
    therefore
    grant
    the
    requested
    variance,
    but
    shall
    condition
    it
    upon
    a
    requirement
    that
    no
    more
    than
    the
    requested
    number
    of
    residences
    be
    connected
    to
    the
    proposed sewer extension.
    Under
    the
    circumstances,
    we
    do
    not
    feel
    that
    additional
    conditions
    are necessary.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board in this matter.
    *Although failure
    to meet NPDES standards
    is not pertinent to our
    decision here, Wenona’s refusal to accept grant funding is signifi-
    cant,
    inasmuch as that action deprives the City of any relief under
    Rule 409 of Chapter
    3,
    (‘‘delays in upgrading”).
    25
    584

    ORDER
    IT
    IS THE ORDER OF THE POLLUTION CONTROL BOARD that Petitioner
    William Gilman be granted a Variance from Rule 962 of Chapter
    3:
    Water Pollution,
    to allow the construction of
    a sewer extension
    tributary
    to the City of Wenona sewage treatment plant
    to serve a
    10-lot subdivision known as the “Gilman Addition to the City of
    Wenona.”
    Said Variance shall be conditioned upon the following:
    1.
    Petitioner shall connect no more than
    10
    individual residences
    to said sewer extension.
    2.
    Petitioner shall, within thirty
    (30)
    days of
    the date of this Order,
    execute and forward to the
    Environmen.tal Protection Agency, Control Program Coordi-
    nator,
    2200 Churchill Road, Springfield,
    Illinois 62706,
    a Certificate of Acceptance
    in the following form:
    I,
    (We), __________________________,
    having
    read the Order of the Illinois Pollution Control Board
    in case No. PCB 77—35, understand and accept said Order,
    realizing that such acceptance renders all terms and
    conditions thereto binding and enforceable.
    SIGNED
    TITLE
    DATE
    Mr. James Young dissented.
    I, Christan
    L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the above Opinion and Order were
    adopted on the
    ~
    day of
    _________,
    1977,
    by a vote of
    A.J1./
    Christan L. MoffettJ,A9’~erk
    Illinois Pollution ~4rol
    Board
    25
    585

    Back to top