ILLINOIS POLLUTION CONTROL BOARD
    April 14, 1977
    STEPAN CHEMICAL COMPANY,
    Petitioner,
    v.
    )
    PCB 76—161
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    )
    Respondent.
    Mr. Harley Hutchins, Attorney, appeared for the Petitioner;
    Ms.
    Kathryn Sheehan Nesburg, Attorney, appeared for the Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr.
    Zeitlin):
    This matter is before the Board on a Petition for Variance
    filed by the Stepan Chemical Company
    (Stepan) on May 21,
    1976.
    That Petition requested relief from the particulate standards
    in
    Rules 203(a)
    and 203(b), and the carbon monoxide limitations in
    Rule 206(c)
    of Chapter
    2: Air Pollution,
    of this Board’s Rules and
    Regulations.
    Stepan also sought relief from the organic emission
    limitations
    in Rule 205(f)
    and 205(g) (1) (c), also of Chapter
    2, or
    in the alternative
    a ruling that these limitations do not apply to
    the subject facility.
    Pursuant to an objection filed by the Envi-~
    roninental Protection Agency
    (Agency)
    on May 27,
    1976,
    the matter
    was set for hearing.
    An Amended Petition was filed by Stepan on September 28,
    1976,
    which extended certain dates contained in the original Petition’s
    compliance schedule by several months,
    as a result of delays caused
    by
    a strike.
    A further amendment to StepaxYs Petition was entered
    at hearing,
    (Cornpl.
    Ex.
    1,
    R.
    8),
    in which Stepan further extended
    the period for compliance.
    A final amendment was made orally at
    hearing,
    (R.
    5), by which Stepan admitted the applicability of
    Rule 205(f)
    to the organic emission from its facility, although it
    continued to contest the applicability of Rule 205(g) (1) (c),
    (id.).
    The Agency’s original Recommendation was filed on September
    3,
    1976.
    The Agency’s Recommendation was modified slightly at hearing,
    and a
    formal Amended Recommendation was filed on March
    3,
    1977.
    25
    281

    —2—
    A hearing was held in the matter on January 10,
    1977,
    at the
    Will County Courthouse,
    in Joliet.
    Witnesses were presented by both
    parties, although the Agency’s presentation was limited to expert
    testimony on the definition of “petrochemicals,” and the applica-
    bility of rules limiting emissions from “petrochemical processes”
    and “petrochemical manufacturing processes” to Stepan’s facility.
    Although special notice
    (in addition to the publication and notice
    normally required) was given to one citizens’
    group, no members of
    the public participated at the hearing.
    Stepan’s Petition concerns emissions
    from its phthalic anhydride
    manufacturing process at its Nilisdale Plant,
    located on the Des
    Plaines River
    in Will County.
    Stepan’s Milisdale facility is
    described in a prior Variance case, and that description need not
    be repeated here.
    Stepan Chemical Co.
    v. EPA, PCB 74-425,
    17 PCB
    105
    (May
    22,
    1975).
    In fact,
    a portion of the relief requested
    here is an extension of the Variance granted in PCB 74-425 with
    regard to the carbon monoxide limitations of Rule 206 (c).
    Phthalic anhydride is produced at the Milisdale Plant by the
    partial oxidation of O-Xylene in the presence of a catalyst.
    Stepar~
    produced 32,935,000 pounds of phthalic anhydride, utilizing
    34,456,000
    pounds of O-Xylene,
    in 1975.
    Waste gases from the process, exiting
    at approximately 140°F.,with little heat value, are vented to the
    atmosphere through a 75-foot stack.
    The composition of the waste
    gases, and the applicable emission limits, are as follows:
    WASTE
    GPS
    REtWT
    REWIRED
    OI4PCt~1ENT
    EMISSICNS
    LIMITATICES
    REGUlATION
    REDUCTION*
    CO
    5,000 PPM
    200
    PPM
    206(c)
    96
    (860 lb./hr.
    )
    *
    (arrected
    to
    50
    excess
    air)**
    hydrocarbons
    398 lb./hr.
    *
    8
    lb./hr.
    205 (f)
    85
    (per
    (including
    40 lb./hr.
    205(f) (1) (A)
    as particulate)
    hydrocarbons
    600
    PR4*
    100
    PPM
    205(g) (1) (C)
    78
    (equivalent
    nethane)
    particulate
    40 lb./hr.
    *
    29.5
    lb./hr.
    203 (a)
    40
    *
    Per
    EPA
    lecximendation,
    INI 7-10,
    apparently using 2\rrended
    Petition,
    ¶5.
    See,
    R.
    50.
    For 100
    operation ~nissions,see R.
    19-20.
    **
    The
    applicability
    of the “50
    Excess
    Air”
    correction
    to
    this
    type of facility
    is presently an issue in a
    pending
    Pegulatory
    proceeding, R75—9, R76—8,-12,-13.
    25
    282

    _3_.
    In PCB 74-425,
    the Board found that no technically feasible and
    economically reasonable method for compliance with the carbon monoxide
    limitation of Rule 206(c)
    then existed for Stepan’s phthalic anhydride
    plant.
    The Board granted a “research and development” Variance,
    permitting Stepan to continue its investigation and development of
    a ‘cold catalytic” compliance technology.
    Stepan was,
    at that time,
    funding a research program at Northwestern University,
    including
    bench and later pilot scale study of the new technology.
    A more
    complete description of that research program, and an analysis of
    the inapplicability of incineration as a control measure for Stepan’s
    plant, may be found in the Board’s previous Variance Opinion in
    PCB 74—425,
    supra,
    17 PCB at 106—108.
    Subsequent to the entry of our Order in PCB 74-425, while the
    cold catalytic oxidation study continued, Stepan was approached by
    the DuPont Company regarding a new control technology which DuPont
    felt would be applicable to the Millsdale Plant.
    The DuPont Torvex
    catalytic reactor utilizes precious metal
    (platinum) deposited on
    a ceramic honeycomb to remove both carbon monoxide and hydrocarbons
    from the exhaust stream,
    (R.
    70).
    This process is not a “cold”
    catalytic process;
    though it will require elevation of the exhaust
    gases above their 140°F.exit temperature,
    it will not require the
    excessive amounts of fuel for incineration,
    as discussed in PCB 74—425.
    Instead, the DuPont process
    (called a “combustor’~) utilizes waste
    heat and steam from the phthalic anhydride process itself, along
    with heat exchange,
    to achieve operating temperatures of approximately
    500°to 525°F., (e.g.,
    R.
    42).
    Except for startup, no additional
    fuel is required.
    An additional significant advantage of the combustor is that it
    will treat the entire emission problem at Stepan’s Milisdale Plant,
    rather than only the carbon monoxide emissions,
    or only the organic
    emissions,
    (R.
    41).
    The combustor will remove carbon monoxide with
    an efficiency of
    95 per cent or more,
    approaching 100 per cent,
    (R.
    72).
    The efficiency with regard to organics
    is stated to be “above 85 per
    cent,”
    (id.).
    Because of the operating temperatures involved, all
    organics are expected to be in the vapor phase, with the result that
    there will
    be no particulate emissions,
    (fl. 79).
    In
    fact,
    a principal
    use of the Torvex unit has been hydrocarbon emission control.
    A final advantage of the combustor
    is catalyst life.
    Unlike
    the cold catalytic system researched at Northwestern University,
    the catalyst is guaranteed by DuPont for a one-year period, yet the
    parties expect catalyst life of five years or better,
    (R. 81—83).
    25
    283

    —4—
    As amended,
    Stepan’s timetable for compliance called for a
    decision by February
    1,
    1977, as to whether the combustor or some
    other control technology will be used at the Milisdale Plant,
    (Pet.
    Ex.
    6).
    Petitioner’s post-hearing Brief indicates that the
    combust.or was chosen.
    Petitioner’s timetable then calls
    for the
    following:
    April
    1,
    1977
    Complete System Final Design
    and Approval Drawings.
    April
    1,
    1978
    Equipment Delivery.
    July 1,
    1978
    System Installation.
    August 15,
    1978
    System Start-Up and Debugging.
    The effect of Stepan’s present emissions of CO were detailed
    in the previous Variance Opinion,
    PCB 74—425, supra, and need not
    be repeated.
    The Agency’s Recommendation in this matter noted that
    the nearest monitors for particulates, more than five miles from the
    Millsdale Plant,
    (Rec.,
    ¶18), showed the following annual geometric
    mean concentrations for 1975:
    Rockdale,
    97; Wilmington,
    69.
    The
    only Will County monitor for ozone,
    located in Joliet, indicated
    77 violations of the 0.08 ppm maximum.
    As the Board found
    in the previous Variance case, supra,
    17
    PCB at 108:
    To deny the variance in the instant action
    would require utilization of existing control
    technology which not only would be expensive,
    but would have an adverse impact upon energy
    demand and the environment.
    Such a ruling
    would impose an arbitrary and unreasonable
    hardship upon Stepan while actually injuring
    the public and environment.
    Throughout
    this
    proceeding,
    as in the
    previous
    case,
    the Agency
    has
    recommended that the requested Variance be granted.
    We agree.
    Stepan has demonstrated a continuing effort to achieve compliance
    with the carbon monoxide Regulations, to the point of developing new
    technology.
    It has extended that effort to the other emissions in
    jssue here, despite the fact that the applicability of the relevant
    Regulations
    is honestly debatable.
    Stepan has now developed tech-
    nology which will allow compliance within a reasonable period of
    time,
    and is proceeding expeditiously to implement a suitable program.
    25
    284

    —5—
    With regard to the application of Rule 205(g) (1)
    (C)
    to Stepan’s
    facility, we note that Stepan is
    a party to a pending Regulatory
    proceeding which could resolve this issue.
    In R75-9,
    R76-8,--12,-13,
    Carbon Monoxide,
    the Board has been requested to separately define
    “organic chemical partial oxidation” processes.
    Since the existence
    of such a definition may resolve finally the application of Rule
    205(g) (1) (c) to Stepan’s facility, we decline to review our decision
    in Sherwin-Williams Co.
    v. EPA
    (Dec.
    18,
    1975).
    Under the circum-
    stances, we need not decide the narrow legal issue of the Rule’s
    applicability under the tests set out in Sherwin-Williams.
    Id.,
    Opinion at
    3.
    We shall grant the variance, pending decision in
    the Regulatory matter.
    Finally, we note that Stepan plans to expand phthalic anhydride
    production capacity at the Millsdale Plant,
    (R.
    26).
    Inasmuch as
    the parties agree that the control system to be constructed using
    the DuPont cornbustor technique will be adequate to control the
    emissions from such expanded operations,
    (R.
    51), we find that this
    planned expansion does not affect our judgement concerning this
    Variance.
    We shall grant the requested Variance, conditioned upon the
    compliance schedule indicated in Petitioner’s Exhibit
    6.
    We
    shall
    continue in effect the $25,000 performance bond required in the
    previous Variance,
    although it shall now cover construction under
    the new compliance plan.
    We shall also enter standard reporting
    and certification requirements.
    In addition, we shall release
    Stepan from the research requirements contained in the prior
    Variance.
    This Opinion constitutes the findings of fact and conclusions
    of law of the Board in this matter.
    ORDER
    IT IS THE ORDER OF THE POLLUTION CONTROL BOARD that:
    1.
    Petitioner Stepan Chemical Company be granted a Variance
    from Rules
    203(a),
    205(f),
    205(g) (1) (C),
    and 206(c)
    of Chapter
    2:
    Air Pollution,
    from May 22,
    1976 until August 15,
    1978,
    subject to
    the following conditions:
    a.
    Petitioner shall comply with the construction
    schedule for its catalytic reactor system as
    set forth in the accompanying Opinion and shall
    apply to the Environmental Protection Agency
    for all necessary construction and operating
    permits.
    25
    285

    —6—
    b.
    Petitioner shall, on or about the 15th day of each
    month subsequent
    to the entry of this Order, submit
    to the Environmental Protection Agency a written
    report detailing all progress towards compliance,
    such report to be submitted to:
    Environmental Protection Agency
    Control Program Coordinator
    2200 Churchill Road
    Springfield, Illinois
    62706
    c.
    Petitioner shall, within twenty-eight
    (28) days
    of the date of this Order,
    continue in effect
    its performance bond in the amount of Twenty—Five
    Thousand Dollars
    ($25,000.00),
    in a form satis-
    factory to the Environmental Protection Agency,
    to insure compliance with the control program
    detailed in the accompanying Opinion.
    Such bond
    shall be submitted to the Environmental Protection
    Agency at the address given in subparagraph
    (b)
    above.
    d.
    The Variance granted herein from Rule 205(g) (1) (c)
    shall terminate upon final Board action in the
    pending Regulatory proceeding R75-9,
    R76-8,-12,-l3,
    if a new or amended definition is adopted affecting
    Petitioner’s manufacturing process,
    in conformity
    with the Board’s Opinion in this matter, ~pra.
    e.
    Petitioner shall, within twenty-eight
    (28) days of
    the date of this Order,
    execute and forward to the
    Environmental Protection Agency,
    at the address shown
    in subparagraph
    (b)
    above,
    a Certificate of Acceptance
    in the following form:
    CERTIFICATE OF ACCEPTANCE
    I,
    (We),
    _______
    _______________—
    having read
    the Order of
    the
    Illinois PolluLion Control
    Bo~ircI
    in
    case No. PCB
    76-161, understand and accept said Order,
    realizing that such acceptance renders all terms and
    conditions thereto binding and enforceable.
    SIGNED
    TITLE
    DATE
    25
    286

    —7—
    2.
    Petitioner Stepan Chemical Company be released from the
    research and development program required by our Order in Stepan
    Chemical Company v. EPA, PCB 74-425, regarding cold catalytic
    oxidation.
    Mr. Jacob D.
    Duinelle dissents.
    Mr.
    Irvin G. Goodman concurs.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board,
    hereby certify the
    bove Opinion and Order were
    adopted on the
    /~t”
    day of
    _________,
    1977, by a vote of
    4/_/
    trol Board
    25
    287

    Back to top