1. CERTIFICATION
      2. VILLA GROVE FARMERS ELEVATOR CO.

ILLINOIS POLLUTION CONTROL BOARD
July
19,
1984
VILLA
GROVE
FARMERS
ELEVATOR CO.,
)
)
Petitioner;
)
)
)
PCB 84—53
)
ILLINOIS ENVIRONMENTAL PROTECTION
)
AGENCY,
Respondent.
MR.
DAVID
PRAHL,
OF VILLA GROVE FARMERS ELEVATOR, APPEARED FOR
THE PETITIONER;
MR. JOSEPH
R. PODLEWSKI, JR., ATTORNEYATLAW, APPEARED FOR THE
RESPONDENT.
OPINION AND ORDER OF THE BOARD
(by
B. Forcade):
This matter comes to the Board on a April 26,
1984, Petition
for Variance filed by Villa Grove Farmers Elevator Co.
(~Farmers”)
seeking a three—year variance from 35 Ill.
Adm, Code 212,462(d)
(old Rule 203(d)(8)(B)(ii) of Chapter 2:
Air Pollution),
That
regulation requires induced draft aspiration and a 90
by weight
particulate collection efficiency for dump pit areas.
On
May
31,
1984, the Illinois Environmental Protection Agency (“Agency~)
filed a recommendation that variance be granted with certain
conditions~
Hearing was held June
18, 1984 in Tuscola,
Illinois.
No public
comments
were
received,
Farmers
operates a country corn and soybean grain
elevator
in
Bongard, in Champaign County, about fifteen miles south
and
west
of Urbana,
The
elevator can store 350,000 bushels at
one
time
and handles about 904,000 bushels per year,
receiving
grain
from
the
farmers
for eventual shipment to market by truck
and
rail
(Pet,
pp.
1~2),
The
grain elevator presently consists
of
a
truck
dump
and boot
pit
grain receiving
area,
headhouse
rece:Lvir~g
legs,
a
dryer
leg,
a rack grain dryer,
nine
steel
storage
bins,
a
truck
and
rail
loadout
as well as the associated auxiliary
conveying
equipment
(Rec,
~2),
Farmers plans to tear
down
the
old
wooden
grain receiving and workhouse which had an open
dump
pit and
replace
it with new equipment.
The old structure is obsolete and
new equipment will increase their production rate and make Farmers
more competitive.
The
new equipment is totally enclosed and
will
reduce dumping time by two-thirds
(Pet,
p.
2),
Title
35,
Illinois
Administrative
Code,
Part
212,
Subpart
S
(Agriculture),
places restrictions on
the emissions from grain~
handling
and
drying
operations.
Section
212,462(b) requires
malor
dump
pit
areas to have an induced draft
air
stream,
and,
as
59-59

applicable
here~ pollut:Lon
control
equipment
with
a
particulate
collection
efficiency
of
not
less
than
90
by
weight,
Farmers
existing
operation
would
be
subject
to
this
limitation
except for
the
provisions
of
§212. 461 ic);
that
section
provides
an exemption
for
existing
grain
handling
operations
located
outside
of
a
major
population
area.
Since
~armers
presently
qualifies
for
the
exempt:~onr no
new
induced
draft/collection
system
is needed.
Farmers
need
only
comply
with
the
housekeeping
practices
of
§212.461(h).
However, Farmer~sreplacement of
the receiving and
workhouse constitutes modification of
the
facility, and
pursuant
to
§212.462(c)
Farmers modified faci:Lity will he subject to
the
induced draft!90
particulate
collection requirements.
The Agency has described Farmers as
an
insignificant
air
pollution source located in an isolated rural
county
that
is
in
attainment with total suspended particulate
(~TSP~)standards
(Rec. ¶~10,13).
Following an investigation, the Agency
calculated TSP
emissions
before
and
after
the
proposed
modi~
fication
as
follows
(Rec.~
9~
10—12)~
Emissions
Before
Modification
Dump
and
Boot
pit
7,56
tons
per
year
TSP
All other emissions
=
34.36 tons per
year
TSP
Total
Emissions
=
41. 92 tons per year TSP
Emiss:Lons
After
Modification
Dump
and
Boot
pit.
=
7.56
tons
per
year
TSP
All
other
emissions
5.88
tons per year
TSP
Total
Emissions
=
13.44
tons
per
year TSP
Thus,
while
total
TSP
emissions from Farmers will he reduced
by
approximately
68
as a result of
the
modifications,
the
emis-
sions
attributable
to
the
dump
and
boot
pit
will
remain
constant
at
7,56
tons per
year;
the allowable emissions for the dump pi6
would
be 0,76 tons per year
TSP.
The
cost
of
the
renovation
project for the facility is
$500,000~, about
one~~haifEarmer’s
total
net worth
(Pet.,
p~2).
Technology
for
the
dump
pit
controls
is
available
at
a
cost
or
approximately
$30, 000~ however
this added amount Farmers would
have
to
borrow
would
put
them over
the
limit
of 60
debt to
equity
~et
by
their
lender,
the
Saint
Louis
Bank
of
Cooperatives
(Pet.,
p.
2).
Thus,
Farmers
needs
more
time
to
reduce
the
debt
ratio
before
they
can
borrow
the
funds
necessary
to
finance
the
installation
of
dump
pit
controls,
Farmers
proposes
to
construct
aspiration
equipment
(cyclone),
pit
baffle,
arid
a
dust
bin,
which
the
Agency
believes
would
achieve
compliance
(Rec,,
¶16).
Farmers
proposes
completion
of
the
dunp
pit
pollution
control
equipment
by
September
1,
1987.
~
~

3
The Board will grant the requested variance,
The Board
finds that grant of variance will have minimal adverse environ-
mental impact,
since emissions during the variance period will
he
substantially below present emissions and the dump pit will only
be in operation during two harvest seasons
(a total
of 112.5
hours per year).
The Board finds that in view of the minimal
adverse environmental impact, immediate compliance would cause an
arbitrary or unreasonable hardship in that funding requirements
for pollution control equipment would exceed the debt/equity
ratio set by Farmer~slender,
The Board will condition this
variance on submission of a construction permit application and
program schedule for the dump pit
controls,
The Opinion constitutes the Board~sfindings of facts and
conclusions of law in this matter,
ORDER
Villa Grove Farmers Elevator is hereby granted a variance
from 35 Ill.
Adni, Code 212,462(b) subject to the following conditions:
1,
This variance shall expire September
1,
1987.
2,
No later than December 31,
1984, Farmers shall submit
to the Agency an application for a permit to construct
equipment on its new dump pit providing an induced
draft air stream confined and conveyed through air
pollution control equipment having an overall rated and
actual particulate collection efficiency of not less
than 90
by weight,
The equipment shall include,
at a
minimum, aspiration equipment
(H,E,
cyclone), pit
baffles, dust bin, and small dump pit enclosure,
3.
In
addition
to its application for a construction
permit, Farmers shall submit to the Agency no later
than December 31,
1984 a construction program schedule
which will provide a timetable for compliance with
Section 212,462(b)
not later than September 1,
1987.
4,
Within forty-five
(45) days of the adoption of the Board
Order in this proceeding, Farmers shall execute and
forward to:
Mr. Joseph R. Podlewski,
Jr.
Enforcement Attorney
Illinois Environmental Protection
Agency
2200 Churchill Road
Springfield, Illinois 62706
a Certificate of Acceptance and Agreement to be bound
by all terms
and.
conditions
of
this variance,
This
forty—five
(45) day period shall be held in abeyance
for any period during which this matter
is appealed.
The form of the certification shall
be as follows:
59-61

4
CERTIFICATION
Villa Grove Farmers Elevator Company hereby accepts and
agrees to be bound
by all
terms and conditions of the Order of
the Pollution Control Board in PCB NO. 84—53
dated
_________________
1984,
VILLA GROVE FARMERS ELEVATOR CO.
By: _________________________
As
Authorized
Agent
Title
Date
IT
IS
SO
ORDERED
Chairman
J.
D,
Dumelle
concurred.
I,
Dorothy M.
Gum,
Clerk of the Illinois Pollution Control
Board, hereby certify
the
above
Opinion
and
Order
were
adopted on
the
~
day
of
~
1984
by
a
vote of
~
~h~.~ii~n,Clerk
Illinois
Pollution
Control
Board