ILLINOIS POLLUTION CONTROL BOARD
    September 3,
    1981
    CITY OF QUINCY,
    )
    )
    Petitioner,
    v.
    )
    PCB 81—30
    ILLINOIS ENVIRONMENTAL PROTECTION
    )
    AGENCY,
    )
    Respondent.
    OPINION AND ORDER OF THE
    BOARD
    (by J
    .
    D. Dumel le):
    On February 26, 1981 the City of Quincy (Quincy)
    filed
    a petition for variance from Rules 403,
    404(a), and 408(a)
    of Chapter
    3:
    Water Pollution to allow the discharge of water
    treatment sludges from its Outlet 002 and to allow discharge
    to the Mississippi River of infiltrated sand present
    in
    the
    raw water suction well.
    Such relief
    is an extension of that
    granted by the Board on December 13,
    1979 in PCB 79—202
    (37
    PCB 25).
    That variance expired March 1,
    1981.
    The present
    variance request seeks to have the expiration date extended
    to March
    1, 1983.
    Hearing was properly waived and none was
    held.
    On May 28,
    1981 the Illinois Environmental Protection
    Agency
    (Agency)
    filed a recommendation that the variance be
    granted subject to certain conditions.
    Quincy has been operating a water treatment sludge
    disposal
    system pursuant to NPDES Permit No. IL0037591 and the Board
    variance
    (PCB 79-202).
    The variance allowed sludge waste
    consisting of sand, alum,
    lime,
    and silt to be discharged
    without
    treatment through Outlet 002 into the Mississippi River.
    The water treatment plant
    (WTP)
    serving Quincy is located
    on the east shore of the Mississippi at Front and Maine Streets.
    Mississippi
    River water is taken in through two 36—inch intake
    lines into
    a screened intake well.
    This water is then treated,
    resulting in an accumulation of sludge.
    Quincy has spent over
    $1.4 million to achieve compliance with NPDES standards for
    discharge, hut has experienced difficulty with sludge removal
    from the raw water settling basin.
    This is due to excessive
    amounts of sand
    (7 to
    9 feet deep),
    rocks, silt and floating
    debris which results in extreme difficulty in pumping through the
    sludge transfer pumps.
    Under the PCB 79—202 compliance schedule,
    these pumps were timely replaced by open impeller pumps.
    However, attempts to withdraw and pump large quantities of
    sand
    on a daily basis from the primary settling basin have

    —2—
    been perodically unsuccessful and have resulted in blockages
    and extreme abrasive wear on the impellers.
    This noticeably
    reduced the carrying capacity of the sludge transfer pipeline.
    In its petition Quincy has requested to be allowed to pump
    the sand from the raw water suction well back to the Mississippi
    via its outfall.
    However, on March 27,
    1981 Quincy applied for a
    construction permit for a submersible pump to remove that sand.
    On May 4,
    1981 the Agency issued the permit.
    As
    a result,
    that
    sand will be discharged back to the Mississippi directly
    and
    such
    variance relief for the outfall
    is no longer necessary.
    Instead,
    the solids will be gravity settled, the supernatant will be
    recycled to the intake, and the solids removed to the city
    landfill.
    As indicated in Ex.
    6 of the petition, six months will
    be needed to install this equipment
    (See Answer
    22).
    This,
    however, will not entirely solve Quincy’s difficulties.
    Since the sludge disposal system became operational
    in May
    of 1979, approximately 400,000 cubic yards of water treatment
    sludge have been stored.
    This
    has completely filled one of
    the
    two sludge holding beds which were to be used for this purpose.
    Quincy has requested grant funding for an estimated $800,000
    needed for purchase of dewatering and land application equipment
    that will be required to remove the water treatment and wastewater
    sludges from the holding basins to assure adequate future storage
    capacity.
    This grant application is currently under review.
    tinder present operations, both lime and alum sludges are
    generated.
    Apparently, there is no difficulty with transporting
    the lime sludge to the second water treatment basin,
    and this
    is currently being done.
    At present rates the second basin
    can accept the lime sludge for 1.9 years prior to its reaching
    capacity.
    The alum sludge cannot be handled in
    the
    same
    manner for two reasons:
    first,
    the sand problem prevents
    the transport of that sludge; and second,
    even
    if
    it could
    be transported, mixing of the alum and lime sludges would. make
    them unsuitable for land application.
    Thus,
    the hoped for
    ultimate disposal would be precluded.
    It therefore appears that variance is needed to allow
    the discharge of sand, alum, and silt for a six month period
    and that an eighteen month variance
    is needed for the discharge
    of alum and silt.
    By the end of this period, the lime sludge
    should be susceptible to land application and the alum sludge
    could be dewatered and landfilled.
    Since there is no apparent reason why these improvements
    cannot proceed simultaneously, the Board will grant variance
    for final compliance until March
    1,
    1983.
    The Board finds that the environmental impact should
    be
    small,
    given the large dilution provided by the Mississippi.
    However, as the Agency notes, spreading the discharges over
    43—288

    —3—
    a minimum of seven days in relatively equal proportions rather
    than on one or two days should minimize the impact on
    the
    River.
    considering the minimal
    impact on the environment,
    the
    absence of a feasible alternative solution,
    and the past
    good faith efforts at compliance, the Board finds that denial of
    variance would cause an arbitrary and unreasonable hardship.
    This Opinion constitutes the Board’s findings of fact
    and
    conclusions of law in this matter.
    ORDER
    1.
    It is hereby ordered that the City of Quincy be granted
    a variance from Rules 403,
    404(a),
    408(a) and Rule 914 of
    Chapter 3:
    Water
    Pollution Regulations until March
    1,
    1~)133,
    subject to the following conditions:
    a.
    Quincy shall provide a compliance schedule consistent
    with information already contained in its petition to
    the Agency within 60 days of the date of this Order;
    b.
    Quincy shall discharge the sludge from outfall 002
    over a minimum of seven days in equal proportions
    to
    reduce the impact of the load on the Mississippi River;
    c.
    Quincy shall submit all plans and specifications
    for the sludge dewatering and handling facilities and
    apply for all necessary permits from the Agency wit~in
    180 days of the date of this Order;
    d.
    Quincy shall re—apply for its NPDES Permit within
    60 days of the date of this Order; and
    e.
    Within 45 days of this Order, Quincy shall execute
    and forward
    to the Illinois Environmental Protection
    Agency,
    PWS Enforcement Programs and DWPC, Compliance
    Assurance Section, 2200 Churchill Road,
    Springfield,
    Illinois 62706,
    two copies of certificates of
    acceptance and agreement to he bound to all terms and
    conditions of this variance.
    This 45-day period shall
    he held in abeyance for any period this matter
    is
    beinj~
    appealed. The form of the certificate shall he as
    follows:
    43—289

    —4—
    CERTIFICATION
    I,
    (We) __________________________________
    ,
    having
    read the order of the Illinois Pollution Control Board in
    PC3
    81—30,
    dated
    ___________,
    understand and accept the said order,
    realizing that such acceptance renders all terms and conditions
    thereto binding and enforceable.
    Petftioner
    By:
    _____________________
    Title
    Date
    -.
    ____________
    ____
    2.
    The Agency is hereby granted authority to issue
    the
    NPDES
    Permit for discharge from Outfall 002 in a manner consistent
    with the terms of this Order.
    IT IS SO ORDERED.
    I, Christan
    L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that the above Opinion and Order
    was adopted on the ~
    day of
    ___________
    ~,
    1981 by
    avoteof
    ~•(
    .
    I
    Christan
    L. Moffett, clerk
    Illinois Pollution Control Road
    43—290

    Back to top