ILLINOIS POLLUTION CONTROL BOARD
january
22,
1976
VILLAGE OF
WINNETKA,
Petitioner,
v.
)
PCB 75—107
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION
AND
ORDER
(by Mr. Dumelle):
On March
4,
1975 the Village of Winnetka, Illinois
(Winnetka)
filed before the Illinois Pollution Control Board
(Board)
a
petition for
a variance from the particulate emissions standards
of the Illinois Air Pollution Control Regulations
(Air Rules)
for coal—fired boilers
4,
5,
6,
7, and
8 located at Winnetka’s
Tower Road electric generating plant
(Plant).
On April
6,
1975,
the Illinois Environmental Protection Agency
(Agency) filed
its Recommendation to deny the petition.
On June 25,
1975,
Winnetka filed an amended petition for variance seeking variance
from Air Rules 203 (g),
103 (b)
and 104 with respect to boilers
4,
5,
6, and
7 only.
Winnetka states that boiler
8 is
in
compliance with the Air Rules.
A timely objection to Winrietka’s
petition was filed by Respondent Agency.
A group known as
Wirinetkans Interested in Protecting Our Environment
(WIPE)
was granted leave to intervene
in the case.
A hearing was
held on June 30,
1975.
On July 17,
1975 Winnetka waived its
right to a decision within 90 days.
Winnetka seeks two separate variances,
“.
.
.an extension
of the existing variance until the interconnection is completed
and thereafter
in more limited circumstances
of emergency...”
(R.
17).
The Board will first address the variance requested
until such time as the interconnection with Commonwealth Edison
Company
(Edison)
is
in operation.
PRIOR TO COMPLETION OF INTERCONNECTION
The more recent of two previous variances granted
(PCB 74-180)
expired on May
20,
1975, which was the expected completion date
19
—
713
—2—
for the interconnection.
At the hearing, Mr.
Zimmerman,
Superintendent of Winnetka’s Water and Electric Department,
testified that completion was delayed due
to two specific
equipment manufacturing problems
(R.
71-72).
There is
every indication that these delays were completely beyond
Winnetka’s control.
Mr. Zimmerman also testified that the
project should be completed “no later than the end of
August”
(R.
72).
However, Petitioner has failed to show that
it needs such a variance.
In this case no hardship would
fall upon Winnetka by
a Board denial of the Amended Petition
for Variance.
Winnetka’s prior variance
(PCB 74-180)
expired
on May
20,
1975.
On Page
6 of its Amended Petition, Winnetka
states that,
“After May
20, 1975,
it has been the policy of
Petitioner to refrain from use of Boilers
5,
6, or
7,
and
from burning coal in No.
4,
except in certain emergency
conditions”.
The occurrence of “emergencies” is, indeed,
speculative.
The Board will not grant speculative emergency
variances
Galesburg State Research Hospital v.
EPA,
PCB 75—198
(July
31,
1975); City of Carlyle v.
EPA, PCB 75—165,
PCB 75—252
(July
17, 1975); City of Highland v.
EPA,
PCB 75—50
(December 18,
1975).
Subsequent to Completion of Interconnection
Assuming completion of the interconnection cable
Winnetka expects to rely upon purchased power for its base load.
If economically available,
natural gas would be burned
in boiler
8 and/or
4 for intermediate and peak load purposes.
If gas
is not available,
coal would be burned in boiler
8,
but only
for peak load purposes
(Amended Petition p.
3).
With its
electrical needs thus provided for, Winnetka seeks variance
to operate its coal-fired boilers
4,
5,
6, and
7
in case of
an
emergency.
In paragraph 10 of its amended petition, Winnetka states,
“It is Petitioner’s belief that the likelihood of either of
the above emergencies arising is very small,
these
are the
only “emergencies” which Winnetka seeks variance for
and
is
not quantifiable.
Such emergencies are expected to be of
very short duration, of no more than about four hours, except,
perhaps in the case of act of God...”
If such variance were granted, Winnetka would keep the
boilers in a maintained but cold condition
(R.
101).
However,
the start—up time for such
a boiler could very well exceed six
hours
(R. 99),
in which case a four hour emergency could
not be averted by use of these boilers.
Thus,
the effectiveness
19
—
714
—3—
of the boilers
in an emergency situation is just as speculative
as the potential for emergency situations to arise.
The existence of future “emergencies”
is,
indeed, speculative.
The Board has firmly stated that it will not grant speculative
variances
(See cases cited above).
The Board therefore denies Petitioner’s request for a variance
to operate boilers
4,
5,
6,
and
7 under speculative emergency
situations.
This Opinion constitutes the Board’s findings of fact and
conclusions
of law.
ORDER
The Village of Winnetka’s Amended Petition for Variance
is hereby denied and dismissed.
IT
IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution Contrr’4
Boar,~10 hereby certify the above Opinion and Order were adopted on the
______day of January,
1976 by a vote of __________________________
Illinois Pollution
trol Board
19
—
715