ILLINOIS POLLUTION CONTROL BOARD
May 25, 1978
COMMONWEALTH EDISON COMPANY,
)
Petitioner,
v.
)
PCB 78-79
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD
(By Mr. Dumelle):
Petitioner
(Edison) has requested a variance from the
Board’s thermal water quality standards
for
the lower
Des Plaines River
(the Five Mile Stretch).
The Agency
has recommended that Edison’s request be denied because
this
is not the proper proceeding to adjudicate
this matter.
No hearing was held.
The cooling water discharges from Edison’s steam—electric
generating facility outside Joliet
(Joliet Station)
have
been the subject of prior Board proceedings.
Rule 203(i) (4)
of Chapter
3: Water Pollution of the Board’s Rules and
Regulations was amended on June
28, 1973 to provide a
specific thermal standard for the Five—Mile Stretch.
The
amendments were adopted pursuant to a request by Edison.
They were based on the conclusion that
since
temperature
was not the limiting factor in the Five-Mile Stretch and
extensive improvement in water quality was expected by
mid-1977,
a temporary thermal standard would be adopted.
Based
on
the
data
available
in
1973,
the Board
concluded
that
by July,
1978 temperature would be the limiting factor
and that the general use “Other Waters” standard should
take effect at that time.
Edison’s concern in 1973 and
in this proceeding centers on the fact that the cooling
water discharges from its Joliet station have continued
to cause violations of the “Other Waters” temperature standard
in the Five Mile—Stretch.
The Joliet Station has thermal discharge points which
are located approximately seven miles upstream from the
beginning of the Five Mile Stretch.
Although these discharges
conform with the less stringent secondary contact standards
at the point of discharge,
they do not cool enough to
30
315
—2—
meet the “Other Waters” standard at the point those standards
take effect on July 1,
1978.
In Appendix
2 attached to its
Petition, Edison concludes that the “Other Waters” tempera-
ture standard would have been violated at the beginning of the
Five Mile Stretch on 2.6 percent of the days from 1973—
1977 and that the three degree excursion limit would have
been violated twice during March, 1977 and once during August,
1973.
Additionally, Edison points out that the more important
indicators of water pollution
(ammonia, dissolved oxygen,
130D and COD)
have not improved since 1973 as expected.
Edison’s conclusion is that since water quality has not
improved,
its thermal discharge
is not the limiting factor
it was expected to be.
Edison contends that the only technically feasible
ways to control its thermal discharge in a way that would
result in compliance with the “Other Waters”
standard would
be by the installation of natural or mechanical draft
towers or by derating the Joliet Station.
Draft Towers are
discounted because of their cost
(at least $21,750,000
in
1975 dollars), their effect on generating capability
(a
reduction of 2.5 to
3 percent), occasional local fogging,
and
a reduction in stream flow in the Des Plaines River.
Derating is discouraged because it would have to occur during
the summer months when maximum power is needed and would
result in additional generation costs of $3.6-7.6 million
per year depending on where the lost electricity would be
recovered.
Rather than incorporate either of these compliance
methods, Edison feels that a general revision of the water
quality standards for the Five Mile Stretch constitutes
a
more appropriate forum for this problem.
In the meantime,
Edison needs a variance so that its existing discharge can
remain lawful after July 1,
1978.
In its Recommendation the Agency does not challenge any
of Edison’s conclusions concernlnq the existinq water quality
of
the
Des Plaines River or Edison’s temperature daLa.
The Agency’s opposition is based on its feeling that
a
variance proceeding is simply not the proper forum for Edison
to obtain relief.
The Agency quotes from the Board’s Opinion which supported
the adoption of Rule 203(i) (4).
That Opinion states at
10 PCB 77 that the proper method for evaluation of the effect
of Edison’s thermal discharge should be by a hearing conducted
pursuant to Rule 203(i) (5)
and held between March,
1977 and
March,
1978.
The Agency contends that a 203(i) (5)
hearing
would have resulted in findings by the Board that either
corrective action was necessary,
in which case
a variance may
30— 316
may have been warranted,
or a regulatory amendment would have
been
in order.
No such hearing was requested by the Petitioner.
The Agency feels that a variance from present standards
would provide Edison with an unjustified “shield from
enforcement” which could place other dischargers
in jeopardy.
Additionally,
the
Agency rebuts Edison’s conclusion that
forthcoming
regulatory
proceedings could provide relief with
the statement that the Agency is not aware of any pending
proceeding concerning this discharge.
Edison’s contention that a henning conducted pursuant
to Rule
203(i) (5)
of Chapter
3 is not appropriate
in this
case is misplaced.
Even though the Joliet
tation discharges
into
waters
which
are covered by Rule 205,
She impact of
this
discharge
on
Rule 203 waters
is obvious.
The Board noted
this
impact
when
it stated:
Edison is required by Sec.
203(i) (5)
to conduct
a program
to monitor the effects
of their discharges
of heated water from the Joliet Plant and present
the results of that program to the Board at a hear-
ing to be held between March,
1977 and March,
1978,
If,
at that time, the Board is convinced that Edison’s
discharge has not caused,
or
is not reasonably ex-
pected to cause significant ecological damage to
the
Des
Plaines River,
the Board would not require
Edison to construct cooling facilities.
Edison
could then either ask the Board to amend its regu—
lation
to
extend
to the termination date to reflect
water quality as would then be present in the “Five—
Mile Stretch,” or seek a variance from the standard.
But if the Board is convinced that Ediec
has caused
or
is reasonably expected to cause siqc~icant ecolo-
gical damage in the future,
then the ~nd
is required
by Section 203(i) (5)
to order Edison to carry out
appropriate measures to correct ecological
damage.
Edison,
because it had relied upon existing Board
regulations,
would have the variance procedure avail-
able
to seek time to correct the problem.
(11 PCB
77,
78.)
The fact that Edison’s discharge points are located in
Rule 205 waters was known when the Board made the above
quoted statement.
There
is nothing in the record of this
case which would persuade the Board to deviate from its
prior position.
The Agency’s contention that a variance
in this case
would
provide
Edison with a “shield from enforcement”
is
well stated.
This
is precisely the purpose behind the
inclusion
of
Section
35 in the Act,
If this
“shield”
30
—
317
4-.
causes
undue
hardsnip
cr
~r
n~r5
that
problem
can
be
a1yidh~
A
regulatory
procec.c.
‘.‘
dischargers
into
the
Les
P
o..
-:
most appropriate way to
-e.~3
e
will make that decision &tcr
pursuant to Part VI of tis B
Edison
has
shown ta0~
.
t
hardship if it was forc:d
.
£
standard in Rule 203 a~(1
significant conszrcctaoL
.c’:~
in Edison’s delivery syatst w
hardship
becomes
unreasorab.,.e
the
marginal
improvement
-
.
-3.
result
from
compliance.
Five
years
ago (Jun
.
...
-
water quality
woald
ce
v4.’t.,.y
Sn3
Stretch.
The
Metropolitan
39
.~
Chicago
was
to
bring
into
beis.g
the
Tunnel
and
Reservoir
Syst
a
more
time
is
needed
for
titese
In
order
to
enable
tZ,
is
‘tr
for
a
203(i)
(5)
hearing
a~~’r
section,
Edison
stall
be
grot:
1981, to
submit
a
petitta.
s~i~:
I
of
Part
VI
of
the
Proceirr
-
Xi
This
Opinion
contt.
~
and
conclusions
of
la~
i
cL,~.:
re
-
I
It
is
the
Order
~r
-
—
Edison
be
grants!
a
•~
requirement
in
Rule
203
-
a
demonstration
of
she
en
discharge
from
the
J~.4..t
-
-.
from
the “Other Watets”
i’’
Chapter 3 subject
to ‘te
lot,.
~acharger,
-~-~‘
‘il.
scceeding.
-
thermal.
bethe
is.c Board
conducted
‘
95.
•
-
is.ant
.,ther Waters”
•
rnbodied in the
.~
location
triad.
The
..
A
against
-
-
would
nccted that
c Itre Mile
-
1
Greater
sn
and
complete
I ccn
done
and
npseted.
a request
by
that
‘t
~l April 2,
t
its
requirements
-
that
tram the
tandates
e
thermal
,198l
‘
~)(4)of
a
1
fact
•1
-S
—5~-
1.
During
the term
of this variance
Edison
shall
comply with
the thermal
standards
contained
in Rule
203(i)
(4)
pertaining
to the Five Mile
Stretch.
2.
Within 45 days of the
date of this Order,
Edison
shall
execute
and
forward
to the Illinois Environmental
Protection Agency,
2200 Churchill Road, Springfield,
Illinois
62706, a Certification of Acceptance and Agreement to be
bound
to all terms and conditions of this variance,
The
45-day period shall be held in abeyance during any period
this matter
is being appealed.
The
form of the Certification
shall
be as follows:
cERTIFICATION
I (We),
____________
_________________
having
read
and
fully understanding
Ehe Order
of the Illinois
Pollution
Control
Board
in PCB
78-79,
hereby accept
that Order
and
agree
to be bound
by all of
its terms and conditions.
Signed________
________________
Title
____________________________
Date__________
_____________________
I, Christan
L. Moffett, Clerk
of
the Illinois Pollution
Control Board, h~r~bycertify the above Opinion and Order were
adopted
e~~y
of
_______,
1978 by a
fy~
~
Christan L. Moffe
,
lerk
Illinois Pollution
trol Board
30
—
319