ILLINOIS POLLUTION CONTROL
BOARD
September 1, 1977
SNTRAL
ILLINOIS
PUBLIC SERVICE
)
COMPANY,
)
Petitioner,
cVrPOITMENTAL
PROTECTION
AGENCY,
)
Respondent.
MIt.
THOMAS
It
COCHRAN,
OF
SORLING,
NORTHRUP,
HANNA,
CULLEN
AND
COCHRAN,
REPRESENTED PETITIONER;
HONORABLE
WILLIAM
J.
SCOTT,
ATTORNEY
GENERAL,
BY
JOHN
VAN
VRANKEN~
REPRESENTED
RESPONDENT.
OPINION
AND
ORDER
OF
THE
BOARD
(by
Mr.
Goodman):
On
May
31,
1977,
Central
Illinois
Public
Service
Coepany
(CIPS)
filed
a
Petition
for
Variance
before
the
Board
seeking
temporary
relief from
the
sulfur
dioxide
removal
requirements ordered
by
the
Board
in a prior
case, PCB 75-~382.
CIPS filed
supplemental
in~for~
nation
on
June 6,
1977.
The Environmental
Protection
Agency
(Agency)
filed its
recommendation on
June
29,
1977,
A
hearing
was
held
on July
6,
1977,
in Newton,
Illinois.
No citizen
witnesses
testified.
cIps owns
and operates an electric
generating
facility
known
as
the Newton Power
Station in
Jasper County.
Newton
Unit
I
is
rated at 550 MW
and is scheduled for
commercial
operation
on
December 1,
1977.
Newton Unit
2 will also be
rated
at
550
MW
and
is
scheduled for
service
in 198L
On January
14, 1976, the Board
found
that
CIPS
had
violated
conditions of a
construction permit and
Section 9(b)
of
the
Act
by
allowing
construction
work
to
be done toward
erection
of
a
coal~
fired
boiler whose
emissions
would
violate
Rule 204(a) (1)
of
the
Air
~451-
~7-363
Pollution Regulations.
The
Board ordered
CIPS
to
comply
with
the
terms of the
Settlement Proposal submitted by the parties.
Item 17
through Item 21
of that Proposal
set
forth the conditions
from which
CIPS now seeks a
variance,
Generally,
the order
required
CIPS to
have a SO2
removal system instaJ
led and fully
operational
by the
time Unit
1 at Newton begins serv~ce.
It was the
intention of CIPS
at the time to install
either
a
lime scrubbing system
or
a double
alkali scrubbing
system.
CIPS
agreed that the
system
chosen would
treat the flue gas
to meet the 1,2
lbs./106 BTU
sulfur
dioxide
emission standard.
CIPS chose
and began construction
o:~ double
alkali flue gas
desulfurization system
on
Newton Unit
1,
:~PSstates
and the
Agency agrees
that the double alkali
system is
a “second generation”
type of SO~remdval
system and shows
marked
advances
in performance
and reliability over
~first generation”
lime/limestone
FGD systems.
The
FGD system to
be applied to Newton
Unit I
is the
first appli-
cation of the
double alkali system
on a ‘arge
utility
boiler.
CIPS
alleges and the Agency
agrees that,
because
this
application is the
first of its
kind on a large utility
boiler,
cost and
construction
schedules forecasted in
August,
1975 were not
accurate.
The original
cost projection was
$47 million, and
the
anticipated
completion date
was December
1,
1977.
CIPS now
contemplates
completion
of the FGD
system by November,
1979,
In its petition,
CIPS outlines the major design
changes and
significant increases
in
cost which preclude
it
from
adhering to
the original target
date,
The project
is
now
anticipated to cost
$108 million
more
than double the original cost
estimate.
Studies
undertaken at the beginning
of the project resulted
in a major
process change
in the regenerated liquor loop affecting
seven major
components and their
associated piping and instrumentation.
CIPS
indicates that, because
this system is
the
first
of
its
kind,
redundant and conservative
design
have been built
into the system.
CIPS also indicates that
this past severe winter
weather and man-
power shortages have
served to further delay
completion of the
project.
Load projections and
economics dictate
that the generating
unit
be commercially
available
on
the
December
1
schedule.
However,
CIPS alleges that early
completion of the FGD system
is
not a viable
option.
During the
period of the requested variance, CIPS
calculates
that its uncontrolled
SO2 emissions,
assuming Newton
Unit
1 will
burn 230 tons per
hour of
2.8
sulfur content coal,
will be 4.6 lb/
MM BTU.
Modeling and
monitoring studies conducted by
CIPS as well
as a dispersion
modeling study conducted by the Agency
conclude that
emissions from Newton
Unit
I
will not cause or contribute
to a
i3~
—3—
violation of the National Primary and Secondary Ambient Air
Quality Standards for SOD.
The Board notes, however, that the
information on these stuaies submitted by CIPS and by
the Agency
was rather incomplete.
Should the Board deny the requested variance, CIPS would be
forced to burn low sulfur coal
until
start-up of its FGD system.
CIPS indicates
in its petition that the total increased expense
to the Company for burning out—of-state low sulfur coal as opposed
to high sulfur Illinois coal until November, 1979, would be
$20,978,000.00.
An additional cost would likely be incurred in
order to restore the efficiency
of
the electrostatic precipitator,
which could be degraded because of the high ash resistivity normally
associated with low sulfur coal.
One possible solution to this
problem would be injection of sulfur trioxide into the gas stream of
the precipitator, which could cost from
$2
to $10 per kilowatt.
CIPS
indicates that in addition to degraded precipitator performance,
other technical difficulties could result from
the use
of low sulfur
coal
in
a
unit
designed to burn high sulfur coal.
The Company is
concerned about the pulverizer mill capacity affected by the coal’s
grindability and changes
in heat transfer affected by
ash slagging
characteristics.
CIPS furthermore alleges that completion and start-up of
the
FGD system earlier than November, 1979,
is not feasible because of
cash flow difficulties, difficulties in retaining sufficient con-
struction craft labor in the Newton area,
and the risk of problems
created by the accelerated completion of this first-of-its-kind
installation.
Because of
the
lack of experience in this type of
installation, CIPS has already encountered several unanticipated
problems resulting in delay.
CIPS indicates that completion of the
FGD system is scheduled for June
1,
1979,
but that during the period
from June to November,
1979,
the system will be operated
in a start-
up and shake-down mode.
Therefore, CIPS indicates,
the 1.2 lb/MM
BTU will be met during part of this
period,
and partial emission
reduction will occur during a siqnificant portion of this period.
The Board finds that
a denial of CTPS
wiriance request would
impose an arbitrary and unreasonable hardship upon
the company.
The Board agrees that CIPS has proceeded diligently
in its
construc-
tion program and that, considering that this
is the first
application
of this type of FGD system to a large utility boiler,
the delay has
been reasonable.
Because of the apparent lack of a threat to ambient
air quality and the costs and technical difficulties associated
with
burning
low sulfur
cc~a1, a
vari)a:I~s
~s
~
~t.u1
The
Board
also
finds
that,
due
to
the
manpow~r..shurtag~
in,
the
Newton
area
and
the
need
for
more
time
to
instal.~’
this first~’of~~its
k~1.n~system
than
would ordinarily be needed,, the
full~,variance
recuested is warranted.
In
addition,
we
find
that
the
two
yeaas~ experience
SIPS
will have
in operation of Unit
I
prior
t
start-up of
the
FOD
system
will
be
beneficial to the smooth
operatio~’i.of the system.
The Board, there-
fore, grants CIPS
a variance fromPCB 75—382
until November
3,
1979,
subject to the conditions belQw.
This Opinion consti~tutes~
~
Board~
findings
of
facts
and
conclusions of law in this matter.
ORDER
It is the Order of the Poliuti~nC~nti~ol
Board that SIPS
be
granted a variance from the Board
~G~der
~n
PCB
75-382
in order to
operate Newton Unit
1
in violation ci whe
.L2 lb/MM
BTU SO~emis-
sion standard until November
3,
1.9~9, subject to the following
conditLns:
1.
CIPS will
subi’nit
quarterly
repoits
until
June
1, 1979 describing the ~oqress
being made
toward the completion of the DAFGD: Systen..
2.
CIPS will submit monthly
~reports
from
June
1,
1979 until November
3,
1979, de’~cribingthe progress
being made in making the DAFG~System commercially
operational.
3.
CIPS
will
subrriit
‘to
th~ Agencv~ on
or
before
November
3,
1977,
,ar’opecat~ng
erm’~ttrapplicatcon for
Newton Unit 1, said application to. include the
re-
quisite stack testing data and infqr~nation.
Mr.
Dumelle
dissents,
I,
Christan
L.
Moffett,
,C1erk~of”th~
lllino3s
Pollution
Control
Board,
hereby
certify
t
e
ab~ove’
Opin±on’and
Order
were
~dopted
on
the
/~
day
of~
.
,
l977~y.
a
vote
of
‘j—/
Christan
It
Moffe&~t7J~1erk
Illinois
Poilutiotr-1~Sntrol
Board
~2/
:C~’