ILLINOIS POLLUTION CONTROL BOARD
    July 31,
    1975
    ILLINOIS POWER COMP1~NY,
    Petitioner,
    v.
    )
    PCB 75-31
    ENVIRONMENTAL PP.OTECTION AGENCY,
    Responc~nt.
    Mr. Sheldon A.
    ZabE~1,Attorney, appeared for the Petitioner;
    Mr. Henry
    J.
    Handzel, Jr., appeared for the Respondent.
    OPINION AND ORDER OF THE BOARD
    (by
    Mr.
    Zeitlin):
    On October 26,
    1970,
    Petitioner,
    Illinois Power Company
    (Illinois Power)
    dnnounced its intention to build a nuclear
    power station ne~ Clinton,
    Illinois
    (Clinton Station).
    The
    Clinton Station is
    to consist of two 991 megawatt units,
    both of which wi1~be nuclear
    fiiciad.
    To dispose of waste heat generated at the Clinton Station,
    Illinois Power proposes to construct an artificial cooling
    lake,
    to be created by damming Salt Creek approximately
    1,200 feet downstr?~amof its confluence with its North Fork.
    The resultant lake will be a U-shaped impoundment,
    extending
    approximately 14 miles upstream along Salt Creek, and
    8
    miles up its North Fork.
    The lake will have an average
    surface area of 4895 acres, and a mean depth of 15.6 feet.
    The lake’s capacity will be approximately
    24 million gallons.
    Operation of the Clinton Station will result in a
    discharge to the
    TLake
    (Clinton Lake)
    of approximately 1.7
    billion gallons per day
    (2534 cfs).
    That water, used for
    condenser cooling p~irposes,will be withdrawn from the North
    Fork arm of Clinton Lake,
    and thence discharged
    into the
    Salt Creek arm via ~ 3.1 mile discharge flume.
    After passing
    through spray modules
    in the discharge system,
    the effluent
    water temperature will nonetheless be in violation of present
    Board thermal standards.
    PCB Regs,
    Ch.3,
    Rules 203(i),
    402.
    18—
    241

    —2—
    PLEADINGS
    Illinois Power initially submitted the instant Variance
    Petition, with respect to its proposed Clinton Lake,
    on
    January
    23,
    1975.
    Illinois Power requested Variances from
    Rule
    203(1)
    (water quality temperature standards),
    Rule 402
    (effluent standard prohibiting discharges causing water
    quality standards violation), and Rule 970
    (barring Agency
    effluent discharge ~pproval
    for Federal permits in the
    presence of Illincis Statutory or Regulatory violations).
    Illinois Power,
    in its original
    Petition,
    claimed that
    the request for Varia.’ice
    is necessary for several reasons.
    First, Illinois Powe~’alleged that a Variance
    is necessary
    to allow progress
    or. its Clinton Station to continue while
    various legal uncertainties regarding the status of cooling
    lakes
    in general are resolved.
    Specifically, Illinois Power
    claimed that the requested Variances would:
    a.
    Permit the Illinois Environmental Protection
    Agency
    (IEPA)
    to issue
    “at least a partial certificationt’
    pursuant to Section 401 of the Federal Water
    Pollution Control Act Amendment of 1972
    (FWPCA)
    and U.
    S. ~nvironmenta1
    Protection Agency
    (USEPA)
    Regulations,
    40 CFR §122.8.
    Such a certification
    would elimi~-iatethe necessity of judicial determination
    of Rule 97U’s validity.
    b.
    IEPA could issue construction permits for Clinton
    Station, and Clinton Lake,
    and a full certification
    under Section
    401 of the FWPCA.
    c.
    Issuance of the requested Variance would eliminate
    the necessity of judicial determination of the
    question o1 Federal pre—emption of state thermal
    effluent and water quality standards
    by virtue of
    316(a)
    of
    tr.e FWPCA; and a number of other legal
    questions possibly related to the question of
    Federal prt~—emptionas a result of permit issuance
    by the Atomic Safety and Licensing Board.
    Illinois Powe:— also alleged that issuance of the requested
    Variance would eliminate unnecessary delay in the construction
    of Clinton Station, by perhaps as much
    as. one year, resulting
    in considerable financial savings for the company.
    Additional
    18—
    242

    —3—
    hardships alleged
    to
    be likely results of any further delay
    in the construction of Clinton Station
    were possible ‘blackouts’
    or “brownouts” with:~nthe Illinois Power service area.
    Public hardships
    we-re alleged insofar as delay
    in construction
    of the Clinton Station would result in considerable economic
    loss for the Clinton area;
    construction wages amounting to
    $250 million would be postponed or delayed.
    Petitioner also
    noted that unempQyment
    is presently high in the Clinton
    area.
    Thereafter,
    on. February 11,
    1975,
    IEPA submitted to the
    Board
    a Motion to T~ismissthis case, which Motion was subsequently
    withdrawn on February
    18,
    1975, after Illinois Power submitted
    an Amendment to its initial Variance Petition
    (Amended
    Petition).
    The Amended Petition, received by the Board on February
    18,
    1975,
    incorporates into the record several other reports and
    documents.
    These include Illinois Power’s Environmental
    Report to the Atomic Energy Commission
    (NRC),
    a final environmental
    statement prepared by the NRC, an NPDES permit application
    to the USEPA for Clinton Lake,
    Illinois Power’s application
    to USEPA for an alternate thermal standard under Section
    316(a)
    of the FWPCA,
    and Illinois Power’s construction
    permit application to
    IEPA, with an application for certification
    under the FWPCA under Section 401.
    The Amended Petition also included various statements
    alleged to const~bute compliance plans for Clinton Lake on
    the part of Illinois Power.
    Illinois Power proposed three
    methods of compliance:
    a.
    A pending rule change before the Board.
    (In the
    matter of:
    Cooling Lakes, R75-2.)
    b.
    A Section
    316(a) demonstration to the Pollution
    Control Board under the NPDES system,
    (Rule 410 (c)),
    once Iliin~is’administration of that program is
    approved by USEPA.
    c.
    A long term, permanent Variance,
    for which Illinois
    Power cites as authority the case of Commonwealth
    Edison,
    v.
    P.~C.B.,
    Ill.
    App.
    3d
    (1st
    fii~t.,
    974,
    No.
    57487).
    Illinois Power also mentioned as possible methods of
    compliance a judicial reversal of the Board’s prior Opinion
    lfl
    the
    “Lake Coffeen’
    case.
    Central Illinois Public Service
    Co._v.EPA,
    PCB 73—364,
    11 PCB 677
    (1974);
    see also,
    Citizens
    ForA
    Better
    Environr.ient v.
    Commonwealth Edison,
    PCB 73-248,
    18— 243

    —4--
    and Commonwealth Edison v.
    EPA, PCB 73-24 8
    (Consolidated),
    13 PCB 69
    (1974).
    (PCB 73—384 has been appealed to the
    Illinois Appellate Court,
    5th District, No.
    74—182).
    Petitioner
    also notes
    that it has a pending §316(a)
    Demonstration
    before the USEPA,
    pc’.rsuant
    to the FWPCA.
    Illinois Powe also introduced with its Amended Petition
    an affidavit purporting to show approximate costs associated
    with either altenate cooling systems for Clinton Lake or
    with a delay in construction of the Clinton Station pending
    approval of the current cooling system.
    Illinois Power
    claimed that approximately $50 million
    in costs have been
    added by a year’s delay already incurred due to administrative
    review of its proposed plant and lake, and that an additional
    year of delay would add another
    $50 million to the total
    cost of the plant.
    Insofar as cooling towers for the Clinton
    Station were estimated to cost between $50—and—$75 million,
    Illinois Power estimates that with the delay for construction
    of those towers,
    and pending determination that such towers
    would
    in fact be necessary,
    the total additional cost would
    be between $100 ~ii11ion and
    $125 million.
    Further, Illinois
    Power alleges thac the use of cooling towers at Clinton Lake
    would still require use of the proposed lake
    to provide
    makeup water used
    in conjunction with such towers.
    IEPA filed its Recommendation on March
    20,
    1975, which
    set out considerable factual data regarding the proposed
    Clinton
    Lake.
    The Fcecommendation compared predicted conditions
    for Clinton Lake with existing conditions at presently
    operating Illinois cooling reservoirs,
    of both the dammed
    and side channel
    (er “perched”) variety.
    The Agency recommended that the Variance be granted,
    for a period of from
    1 to
    5 years, subjeat
    ~o several conditions.
    With respect to the Variance request from Rule
    970,
    the
    Agency stated
    tha’:
    a Variance grant should be conditioned
    on:
    a.
    Adequate proof that it would not be technically
    feasible or economically reasonable
    to achieve
    cooling sufficient to meet present Board standards,
    or some other standard lower than the 96°F.
    requested by Illinois Power.
    18—
    244

    —5—
    b.
    Proof that upstream users of the water courses
    to
    be impounded have been informed and understand
    that construction of the impoundment would result
    in additional effluent requirements on them.
    c.
    Proof a~to the length of time for which a Variance
    is necessary.
    With respect to the Variances requested from Rules 203 and
    402,
    the Agency also recommended that the Variance be granted,
    but subject to the following conditions:
    a.
    Proofs as required with respect to the Variance
    from Rule
    970.
    b.
    Proof
    Lhat Variance would be necessary for Illinois
    Power to proceed with its Clinton project before
    “the NRC and USEPA while review processes are
    pursued~’.
    c.
    Proof that an Agency construction permit would be
    required during the next 1-year period.
    The Agency also reccmmended the following general conditions:
    a.
    A submission by Illinois Power of an acceptable
    lake management plan,
    preserving the lake’s recreational
    and fishery values.
    b.
    Submission by Illinois Power of
    a commitment to
    keep
    the
    lake readily available for public access
    throughout the life of the lake.
    c.
    Submission of an acceptable program for start up
    and shut down procedures
    to minimize adverse
    effects on aquatic life,
    d.
    That the Variance terminate on a denial of the
    Section 316(a) request pending before USEPA, or
    upon a decision in the pending cooling lake regulatory
    proceedings
    (R75-2) unfavorable to Illinois Power.
    IEPA then filed its Amended Recommendation before the
    Board on June 12,
    1375.
    Based on the fact that Illinois
    Power by that time had agreed to install a supplemental
    18
    245

    —6—
    cooling system,
    IEPA again recommended the Variance be
    granted.
    The Agency moved,
    in its Amended Recommendation,
    that the Variance requested with regard to Rule 203(i)
    and
    402 be granted without hearing, and further moved that the
    requested Variance from Rule 970 be dismissed as moot,
    Additional Motions to Decide Without Hearing were filed June
    20,
    1975
    (IEPA)
    and June 24, 1975
    (Illinois Power)
    The Agency also adopted further conditions relating to
    operation of the proposed supplemental cooling system to be
    constructed along
    ~ith Clinton Station and Lake.
    Certain of
    the initial conditions proposed by the IEPA were dropped or
    modified,
    and a further additional condition
    (that the
    Variance be conditioned on compliance with a final
    316(a)
    Determination) was added.
    Further, IEPA recommended that,
    should conditions in Clinton Lake,
    after it becomes operational,
    differ significantly from those predicted in the Section
    316(a) demonstration submitted by Illinois Power to USEPA,
    Illinois Power be required to take whatever corrective
    measures are necessary,
    to include the possible addition of
    further supplemental cooling facilities.
    The Board subsequently denied all Motions for Decision
    Without Hearing
    (Interim Order, June 26,
    1975),
    and a
    hearing was held in Clinton on July
    7,
    1975. The only relevant
    objections raised at that hearing related to the possible
    effects which an artificial impoundment,
    containing waters
    with increased temperatures, might have on surrounding
    agricultural
    conoerns.
    Two witnesses expressed fears that
    increased evapor~’tionresulting from the thermal component
    of Clinton Staticn’s effluent may have an adverse effect on
    crop growth,
    throigh a variety of mechanisms.
    It was feared
    that increased frost damage might result, and that additional
    local humidity would affect plant growth rate,
    and the
    manner in which fertilizers must be added to farm fields.
    Additional testimony was introduced with regard to the
    possibility that increased atmospheric moisture may have an
    adverse effect on grain drying and storage; one witness
    stated that the additional humidity would delay the drying
    of grain in the fields, and would cause mold growths
    on
    stored grain
    (R.
    26,27).
    (An additional objection, based on
    possible interference with drainage from surrounding farms
    is not relevant to our determination here,
    and may not lie
    within the Board’s jurisdiction.)
    1l1inois Power also
    agreed,
    in its closing statement,
    to abide by the conditions
    contained in the IE~A’sAmended Recommendation.
    At the conclusion of the pleadings, and the hearings,
    the Board was presented with
    a massive record on which to
    base its determination.
    18
    246

    .$UPPLEMENTAL COOLING SYSTEMS
    Steam electric generating plants utilize water for
    condenser cooling.
    The condenser
    is
    in effect a heat exchange
    mechanism;
    in it,
    3
    separate quantity of water, which
    is
    that actually heatad and used to drive steam turbines for
    electric generation
    is cooled for reuse.
    The water employed
    for condenser cool~ng is not itself used to drive the electrical
    generating mechanism.
    In the past,
    it has been commonplace for steam electric
    generating plants to utilize natural waters, withdrawn
    directly from
    a natural water body such as a river or lake
    for such cooling; that water
    is then directly discharged
    back into the body of water from which it is drawn.
    That
    process
    is known as
    “once through cooling”.
    Where once through cooling
    is not practical,
    either
    because no sufficiently large natural water body
    is available,
    or because such a method may result in violation of environmental
    or other standards
    other cooling systems must be employed.
    These have in the p~’stincluded the construction of artificial
    impoundments
    for cooling water,
    the use of cooling towers
    (of several vari~Lies), or the use of spray canals.
    In all
    of these methods,
    the basic mechanism for cooling involves
    both evaporation
    Etnd direct radiation of heat to the atmosphere.
    Depending on the supplemental cooling system to be used, and
    on myriad other factors,
    the cost and efficiency of condenser
    water cooling varies greatly.
    The Pollution Control Board
    (Board)
    has previously
    decided that where
    a.n artificial cooling impoundment is
    constructed by damr~:ingan existing protected water of the
    state,
    the resulting
    “artificial cooling lake” will be, and
    remains,
    a protected water of the state;
    it is thus subject
    to existing therr~’alstandards.
    Central Illinois Public Service
    Co.
    v.
    E.P.A., supra, and Citizens For A Better Environment
    v.
    Commonwealth Edison,
    supra.
    (This matter is actually more
    complex than can be discussed here,
    and
    is the subject of
    pending Board regulations.
    R75—2,
    supra.)
    For a more
    complete description of the problem,
    see the Board’s earlier
    case,
    and record
    in
    Lhe pending regulatory matter.
    Illinois
    Power has conceded that the proposed lake would fall within
    the protected waters classification.)
    Protected waters of the state are subject to the water
    quality temperature standards of Rule 203 Ci), which provides
    in relevant part:
    18— 247

    —8—
    203(i)
    Temperature
    (STORET numbers F°( 00011 and
    (C°) 00010)
    (1)
    There shall be no abnormal temperature changes
    that may adversely effect aquatic life unless
    caused by natural conditions.
    (2)
    Tn~ normal daily and seasonal temperature
    fluctuations that existed before the addition
    of heat due to other than natural causes
    shall be maintained.
    (3)
    The maximum temperature rise above natural
    temperatures
    shall not exceed 5°F.
    (4)
    In addition,
    the water temperature at representative
    locations
    in the main river
    shall not exceed
    the maximum limits in the following table
    dtring more than one percent of the hours in
    the 12-month period ending with any month.
    M3reover,
    at no time shall the water temperature
    at such locations exceed the maximum limits
    in the following table by more than 3°F.
    JAN
    FEB
    MAR
    APR
    MAY
    JUN
    JUL
    AUG
    SEP
    OCT
    NOV
    DEC
    60
    60
    60
    90
    90
    90
    90
    90
    90
    90
    90
    60
    Main river temperatures are temperatures of those portions
    of the river essentially similar to and following the
    same thermai regime as the temperatures of the main flow
    of the river.
    (5)
    The owner or operator of a source of heated
    effluent which discharges
    0.5 billion British
    therr~ia1units per hour or more shall demonstrate
    in a hearing before this Board not less than
    5
    nor more than
    6 years after the effective date
    of these regulations or, in the case of new
    sources, after the commencement of operation,
    that discharges from that source have not
    ca’i.~edand cannot be reasonably expected to
    cause significant ecological damage to the
    receiving waters.
    If such proof
    is not made
    to the satisfaction of the Board appropriate
    corrective measures shall be ordered
    to be
    taken within a reasonable time as determined
    by the Board.
    18
    248

    —9—
    (6)
    Permits for heated effluent discharges,
    whether issued by the Board or the Environ-
    mental Protection Agency,
    shall be subject
    to revision in the event that reasonable
    fiture development creates
    a need for
    reallocation of the assimilative capacity
    of ~riereceiving stream as defined in the
    regniation above.
    In addition,
    Rule 402 provides an effluent standard
    which prohibits any effluent from causing a violation of the
    applicable water quality standard.
    It should be noted that
    Rule
    201, Mixing .~ones, provides discharger with a mixing
    zone for its effluent.
    That Rule would provide, as a mixing
    zone, an area contained within
    a circle having a radius of
    600 feet;
    subject to certain other limitations,
    the applicable
    temperature standards need only be met at the edge of a
    mixing zone.
    See, Commonwealth Edison v.
    EPA, PCB 73-359,
    10 PCB 659,
    662
    (1974); Ohio Wabash Thermal Standards,
    71—12,
    2 PCB 563
    (19’l)
    As originally designed, Clinton Station would have
    utilized once through cooling;
    its proposed discharge under
    that system would have reached a maximum temperature of
    112°F.
    (Rec., P.6).
    In 1974,
    the Atomic Energy Commission
    (AEC)
    issued a final environmental statement for the proposed
    Clinton Station.
    Tnat statement imposed a maximum temperature
    discharge limitation of 96°F.,
    or such other temperature as
    may be appropriate ~nder
    the FWPCA.
    To achieve compliance
    with that limitation,
    Illinois Power proposed a supplemental
    cooling system to meet such a 96°F.
    limitation.
    That 96°
    limitation was the basis of a construction permit application
    and an NPDES permit application submitted by Illinois Power
    with respect to Clinton Lake.
    It was also the basis for an
    application to the USEPA for an alternative thermal
    limitation
    under Section
    3l6ta)
    of the FWPCA
    (as amended February
    24,
    1975)
    The supplemental cooling system chosen by Illinois
    Power for its Clintcn Station would involve the use of 232
    spray modules along the 3.1 mile discharge canal running
    from the Station to Clinton Lake.
    Illinois Power claims
    that, with the utilization of this system,
    current Board
    regulations will usually be met at Clinton Lake.
    By operating
    the spray modules from June
    1
    (or such earlier time as the
    condenser discharqe temperature reaches 92°F.) until around
    September 19 of each year, the discharge temperature will
    18—
    249

    —10—
    reach a maximum of 92°F.
    in normal years, and on one or two
    occasions in suen years.
    Only during extremely dry years
    should the discharge temperature approach the 96°limit
    proposed by Illinois Power in this procedure.
    (In the
    eventuality that conditions might indicate that 96°F. will
    be exceeded,
    plant operations are to be altered to meet that
    limit.)
    (Rec.
    Ex.
    ~‘.
    to Ex. B).
    FEDERAL CONSIDERATIONS
    Section 316(a)
    of the FWPCA grants the Administrator of
    the USEPA the power to determine an alternate thermal standard
    for an individual source,
    where it has been determined that
    existing standards are more stringent than necessary to
    protect an indigenous aquatic biota.
    (Again,
    this matter
    is
    somewhat complex,
    and the reader
    is referred to the appropriate
    federal statutory and regulatory provision describing the
    requirements of Section 316(a).)
    Illinois Power, as noted
    above, has applied to the USEPA for such an alternate thermal
    standard.
    In a letter
    ftorn Francis T. Mayo, Regional Administrator
    of the USEPA,
    dat:ed May
    9, 1975,
    that Agency tentatively
    approved such an alternate thermal standard for the proposed
    Clinton Lake.
    That tentative approval followed the submission,
    by Illinois Power,
    of voluminous
    data and predictions relevant
    to the proposed lake.
    The original submission to USEPA,
    October
    10,
    1974, was supplemented on February
    24,
    1975, and
    April
    14,
    1975.
    (Amended Rec.,
    Ex.
    C).
    The May
    9,
    1975,
    tentative approval by tJSEPA was subject to the following
    conditions:
    1.
    The proposed supplemental cooling system
    (spray
    canal)
    is
    to be operated during the summer under
    the method described above.
    2.
    The effluent to the lake will never exceed 96°F.
    3.
    Illinois Power is
    to conduct thermal research to
    determine the effects of thermal discharges on
    cooling
    lakes.
    That data,
    and data on the proposed
    Clinton Lake,
    are to be evaluated,
    and reports
    to
    be made to USEPA.
    4.
    If the research, data,
    etc.,
    indicate that Clinton
    Lake will be significantly different than the
    predictions in the 316(a) demonstration show,
    or
    if the cooling water use, recreational aspects, or
    protection and propagation of indigenous aquatic
    life cannot be assured, Illinois Power must agree
    to take whatever measures are necessary
    in correction,
    to include backfitting of additional
    cooling
    facilities.
    18—250

    —11—
    5.
    Illinois Power is
    to develop and maintain plans
    for n::isance algae and aquatic macrophyte control
    on Clinton Lake.
    6.
    Illinois Power is to develop a detailed fishery
    management plan for Clinton Lake.
    In
    a letter dated May 16,
    1975,
    (Rec.
    Ex.
    D), Illinois
    Power agreed to
    the
    above conditions.
    ISSUES
    In determining whether or not a Variance is warranted
    in this issue, the Board must examine the following issues:
    1.
    Is
    a Variance in fact needed by Illinois Power for
    its proposed Clinton Lake?
    2.
    Is such
    3
    Variance in fact needed at the present
    time,
    if at all?
    3.
    Have the elements normally necessary for the grant
    of the hardship been shown?
    A.
    F~asthe requisite hardship been demonstrated?
    B.
    Is the necessary compliance plan present?
    C.
    What will be tho resultant damage,
    if any,
    to
    the environment?
    4.
    How long
    a Variance is warranted on the present
    record?
    It would appear that there
    is some question as
    to
    whether this variance is
    in fact needed by Illinois Power.
    The Board notes that all of the engineering data leading to
    the estimate of a 96°F.discharge during unfavorable meterioloqical
    conditions are deiived from very conservative assumptions
    and calculations
    (eg. Amend.
    Rec.,
    Ex.
    B,
    pp.
    3,4;
    Ex.
    1 to Ex.
    B, pp.5,6)~ This, however,
    is as it should be.
    Illinois Power has c~esignedits facility to cool to 96°F.
    under worst—case conditions, and has committed itself
    to
    modification of plari~operations should the situation indicate
    that
    a 96° limit cannot be achieved.
    (Amend.
    Rec.
    Ex.
    D.
    responding
    to Rec.
    Ex.
    C,
    p.6 para 4).
    It is asking for a
    variance from the 90°F. limitation under the Board’s rules
    based on such a worst—case possibility.
    .
    .
    .
    a possibility
    which it seems is more likely than not during a drought year
    with high wet-bulb conditions during the summer.
    (Amend.
    Rec.
    Ex.
    1 to Ex.
    B, supra)
    There is no need to penalize
    18
    251

    —12—
    Illinois Power for its caution in both conservatively designing
    its cooling facilities and at the same time seeking a shield
    from prosecution under the grant of a variance, while constructing
    the facility.
    There would also appear to be some question as to
    whether the variance would be needed now,
    in light of the
    fact that Clinton Station will not be in operation until
    1981.
    In seeking ihe variance now,
    rather than at the time
    of operation,
    Illinois Power seeks a shield from enforcement
    which will,
    in effect, allow construction to commence.
    Such
    a request is not unreasonable,
    since a Variance is in fact
    needed,
    and in
    ligrrc of the hardships which delay might
    cause,
    a present grant is indicated.
    As regards hardship,
    the most obvious
    is the financial
    burden which a eenial of the variance would impose on
    Illinois
    Power.
    The original Agency Recommendation,
    (p.29),
    shows
    the costs for “alternate” cooling systems
    to be used in
    conjunction with Clinton Station.
    It was estimated that the
    following costs would be incurred:
    Alternate Cooling System
    Cost
    (1)
    wet mechanical draft tower
    $
    48,300,000
    (2)
    wet natural draft tower
    71,952,000
    (3)
    spray canal
    55,754,000
    (4)
    dry mechanical draft tower
    422,144,000
    It should be noted that the spray canal costs shown
    above would be those involved for an “alternate”
    cooling
    system,
    that
    is, one which would not be used for cooling
    in conjunction with the proposed artificial cooling lake
    (Lake Clinton).
    The supplemental cooling system which has
    been proposed by Illinois Power will,
    it is estimated, have
    a total cost of $34,524,800, covering all capital, operating
    and maintenance costs over a 30—year life.
    (Amended Rec.,
    Ex.
    1
    to Ex.
    B, p.2).
    In addition,
    the hardships described ~above, in the
    original Petition of Illinois Power, remain valid.
    Those
    are costs which would be incurred through delay in the
    commencement of construction at Clinton.
    Further,
    the
    Board may take notice of the fact that this country has
    experienced an enerçj crisis.
    For that reason,
    and because
    the Board may also take notice of current depressed economic
    conditions,
    the Board feels that sufficient hardship has
    been shown to,
    at least initially,
    justify the grant of
    a
    variance.
    18
    252

    —13—
    Such hardship. however, must also be balanced against
    the possibities of environmental harm resulting from the
    grant of the requested Variance.
    The bulk of the record
    in
    this matter, and in particular the 316(a) demonstration
    (with its supplements)
    submitted to USEPA,
    is largely concerned
    with predicting tne ecological effect that the thermal
    discharge from Clinton Station may engender.
    Based on the
    predictive data submitted for the proposed lake,
    and the
    data submitted for comparison indicating present conditions
    at other cooling water impoundments, the Board feels that
    the likelihood of environmental damage
    is minimal.
    The data and the pleadings
    indicated that possible
    problems may arise
    in Lake Clinton with respect to algal
    blooms
    (Amended Rec.,
    Ex.
    A, p.2).
    The 316(a) demonstration
    for Clinton Lake indicates that the lake will contain sufficient
    nutrients
    to suppoit rich planktonic flora.
    However,
    a
    large algal biom.iss on Lake Clinton will not necessarily be
    due to the thermal input;
    large blue-green algal growths
    occur naturally
    in nutrient-enriched waters,
    such as those
    predicted for Lake Clinton
    (316(a)
    demonstration, p.6-58).
    In addition,
    Illinois Power has adopted a willingness to
    employ necessary control measures should algal bloom become
    a nuisance
    (Amend.
    Rec.,
    Ex.
    6 to Ex. B).
    Additionally, Illinois Power has committed itself to
    control measures should aquatic macrophytes become a problem
    (Ex.
    4
    to Ex.
    B,
    Amend.
    Rec.).
    It is estimated that the
    growing season of the macrophytes may be extended as
    a
    result of the heated cffluent entering Lake Clinton, but it
    is also estimatei that the heated effluent will not increase
    macrophyte growth beyond those areas of the lake which would
    normally be inhabited
    (i.e., shallower areas)
    (316(a)demonstration,
    p.6-45,46). Nor
    is plant shut-down predicted to cause
    problems with macrophyte growth,
    as the largest temperature
    differentials
    (i.e.,
    thermal shock)
    are likely to occur in
    winter,
    when macrophyte growth and reproduction are minimal
    (id.)
    It is expected
    (Amend.
    Rec.
    Ex.
    7 to Ex.
    B), that
    passage through the condenser, and the subsequent passage
    through the spray cooling system, will prove fatal
    to all
    zooplankton entrained with the cooling water.
    It is also
    felt, however,
    that the proposed lake will provide sufficient
    cool habitats, and that rapid replacement of those individuals
    will take place,
    so that,
    over all,
    there will be little
    effect on the zooplankton population of Clinton
    Lake.
    In
    fact,
    due to the thermal effect,
    zooplankton community
    density will be higher during the cool months than would
    ordinarily be the case in central Illinois lakes
    (316(a)
    demonstration,
    Sec.
    6.3.5;
    Ex.
    7,
    to Ex.
    B, Amend.
    Rec).
    18—
    253

    —14—
    There has been some dispute as to the assumptions which
    can be made in predictions on the fishery to be maintained
    in Clinton Lake.
    ‘llinois Power Company,
    in an Amendment to
    its 316(a) proposal to USEPA
    (Ex.
    5 to Ex.
    B, Amend.
    Rec.),
    chose 92°F. as a hostile temperature for the eight important
    fish species prelicted for Clinton Lake.
    In the May
    9
    letter tentatively approving an alternate thermal standard
    for Clinton Lake,
    the USEPA disputed the use of 92°F. in
    that analysis
    (Amend.
    Rec.,
    Ex. C).
    USEPA felt that an 86°
    temperature would be more appropriate for analyzing thermal
    impact.
    The Boa-d.
    however,
    takes note that Illinois Power
    has committed itself to the maintenance of a viable fishery
    in the proposed lake,
    in conjunction with the Illinois
    Department of Conservation
    (See,
    Ex.
    3 to Ex.
    B, Amend.
    Rec.).
    Based on studies made at the Baldwin Reservoir,
    (a
    “perched” or “side channel” lake,
    also owned by Illinois
    Power),
    the Board feels that it will be quite possible for
    Illinois Power
    tu maintain an adequate recreational fishery
    in Clinton Lake
    (Ecological study
    of Baldwin Reservoir,
    Progress Reports,
    1 September,
    1970,
    to October,
    1974,
    submitted by Department of Zoology,
    Southern Illinois Tniversity;
    see also,
    Aquatic Vegetation Studies of Lake Baldwin,
    WAPORA,
    Inc., March
    25,
    1975).
    Further, Illinois Power has
    committed itself to the maintenance of this fishery as a
    public recreation facility.
    (This was one of the conditions
    which Illinois Power has assented to on the record in this
    matter.)
    While
    it appears from the record that some fish will be
    damaged in Lake Clinton under extreme conditions, we do not
    find this fact controlling.
    In balancing the economic and
    other hardships described above against the possibilities of
    environmental harm, we feel that a variance is warranted
    in
    this situation.
    Another issue remains, however.
    The Board has in the
    past required that a compliance plan exist, as a condition
    to any variance granc;
    Illinois Power has submitted such
    compliance plans, which are acceptable
    to the Board.
    First,
    Illinois Power shall, and has, participated
    in a pending
    regulatory proceeding before the Board which would,
    if
    successful, provide a means
    by which it could obtain the
    equivalent of
    a permanent variance, which is presently
    unobtainable.
    In the Matter of Cooling Lakes,
    R75-2.
    Should that Regulatory Proposal,
    or the alternatives suggested
    by
    IEPA,
    be adopted by the Board, Illinois Power could be
    granted a specific thermal effluent limitation;
    such a
    specific limitation would provide permanent relief
    (subject,
    of course,
    to future Board actions,
    such as those provided
    for under
    Ch.
    3,
    Rule 203(i) (5)), by granting a thermal
    standard exceeding
    ~he generally applicable one of Rule
    203 ~i)
    18—
    254

    —15—
    Second,
    the E~oardwould hope that federal approval of
    the Board’s NPDFS regulations is imminent.
    Such approval
    would cause Rule 410(c)
    of the Water Pollution Regulations
    to provide for just such specific,
    long—term relief as
    Illinois Power would require.
    Rule 410(c),
    by adopting the
    federal standard under Sec.
    316(a)
    of the FWPCA,
    provides
    for the adoption by the Board of an alternate thermal standard
    such as is requested by Illinois Power.
    Both of these alternatives,
    in light of the other
    evidence presented
    in this matter, present adequate compliance
    plans.
    In our opinion, these compliance plans justify
    a
    grant of the Variance for a two-year period.
    This will allow
    time for Illinois Power to pursue these compliance plans,
    and for the resciution of all r’emaining issues.
    THE VARIANCE
    Having determined
    that a Variance
    is in fact warranted
    in the present situation, the terms of that Variance shall
    be examined.
    It snould be noted first of all,
    however,
    that
    Illinois Power has,
    in the record
    in this matter, agreed to
    the conditions under which the Agency Recommendation of a
    Variance grant was made, and to the conditions under which a
    federal 316(a)
    tentative determination was made
    (R.40,4l;
    Amend. Rec.,
    Ex. D).
    As noted above,
    the Board will grant a Variance from
    Rules
    203(i)
    and 402,
    for a period of two years.
    The requested
    Variance from Rule
    970 will be dismissed,
    insofar as the
    Agency may issue the requested permit and certification based
    on the grant of Variances from Rules 203(i)
    and 402.
    The essential condition on which this Variance
    is
    granted is the operation of the supplemental cooling system
    described above.
    We shall, consistent with both the recommendation
    of the IEPA, and the tentative
    316(a)
    grant of USEPA, require
    that the spray canal cooling system,
    as described
    in Illinois
    Power’s letter o
    April
    14, 1975,
    to USEPA
    (Amend.
    Rec.,
    Ex.
    B), be operated
    luring summer months so as to prevent harm
    to the aquatic biota in the proposed lake.
    The system of
    operation as desclibed,
    which provides for a gradual start-
    up during warm weather months,
    should protect both the biota
    and allow for econoTnical operation by Illinois Power.
    18—
    255

    —16—
    As agreed
    to
    by the parties,
    and as we have also found
    to be effective
    to protect the hiota, we will also require
    that the effluent Lemperature to the lake not exceed 96°F.
    at any time.
    While it is expected that the 96°F. limitation
    will rarely,
    if ever,
    be reached,
    the Board nonetheless
    feels such an absolute limitation
    is required to protect the
    aquatic environment.
    Illinois Power has also agreed to submit an acceptable
    lake management ulan,
    to preserve the lake’s recreational
    and fisheries value.
    That agreement plays an important role
    in the Board’s approval of this Variance.
    That,
    and Illinois
    Power’s agreerneni
    to hold the lake open for public access,
    indicate a wise,
    m’..’ltiple use of scarce water resources.
    While the record indicates that start-up and shut-down
    procedures at the proposed Clinton Station will have little,
    if any, adverse effect on the aquatic biota, Illinois Power
    will also be required to develop and submit a program to
    minimize any adverse effects which may develop.
    The concept
    of thermal shOck remains
    a concern to the Board,
    such that
    we shall require assurance that no untoward effect will
    result.
    The Board has not conditioned this Variance on compliance
    with
    a
    final Section
    316(a) determination by the USEPA at
    Clinton Lake.
    First, no such determination now exists,
    so
    that the Board may not assume that such a final determination
    will be entirely consistent with this Opinion and Order.
    Secondly,
    it has not been demonstrated that a requirement of
    such compliance would not constitute
    “redelegation”
    of
    powers granted the Board under the Act.
    The fact that
    Illinois Power h~sagreed to such compliance,
    in the record
    in this matter,
    c~oesnot affect our decision on that point.
    The Board has also conditioned the grant of this Variance
    on a commitment
    by
    Illinois Power
    to take whatever corrective
    actions are necessary should environmental harm develop at
    the proposed cooling
    lake.
    This commitment,
    to which Illinois
    Power has also agreed,
    is a major factor in our grant of
    this Variance.
    This condition
    is consistent with the Board’s
    requirement under i~ule203(i) (5),
    set out fully above.
    We shall also require that Illinois Power submit quarterly
    progress reports on both the status of construction at the
    proposed Clinton Station and Lake,
    and on the status of its
    compliance with the other conditions
    of this Order.
    Certification
    of acceptance of this Variance, with all conditions,
    shall
    also be required.
    18
    256

    —17—
    This Opinion constitutes the findings of fact and
    conclusions of law of the Board in this matter.
    ORDER
    A)
    Petitioner Illinois Power Company is granted
    a
    Variance from the provisions of Rule 203(i)
    and
    Rule 402 for a period of two years from the date
    of this Order, subject
    to the following conditions:
    (i)
    ~rhat Illinois Power Company agrees to operate,
    as a minimum, a supplemental cooling system
    employing 232 spray modules, and otherwise
    consistent with that described in the accompanying
    Opinion in this matter,
    in the following
    r~ianner:
    (a)
    in the late spring when the condenser
    discharge temperature reaches 92°For on
    June
    1,
    whichever comes first,
    the
    supplemental cooling system will begin
    operation with approximately one-fifteenth
    (1/15)
    of the capacity being switched
    on;
    (h)
    each day thereafter another one-fifteenth
    (1/15)
    of the system will begin operation,
    until by June
    15, at the latest,
    all
    modules will be operating;
    (c)
    in the late summer, when the condenser
    discharge temperature reaches 92°Fon
    the declining side of the time/temperature
    curve, or on September
    19, whichever
    occurs last,
    the supplemental cooling
    system will begin to be sequenced off
    with approximately one—fifteenth
    (1/15)
    of the modules being shut down for the
    first six
    (6)
    days;
    (d)
    each day thereafter another two-fifteenths
    (2/15)
    or less of the modules will be
    shut off until
    by September 30, at the
    earliest,
    the complete system will be
    off.
    (ii)
    That the effluent temperature to the lake
    will not exceed 96°Fat any time;
    18—
    257

    —18—
    (iii)
    That Illinois Power Company prior to the
    filling of the impoundment submits an acceptable
    1a~,emanagement plan for approval by the
    Illinois Environmental Protection Agency and
    the Illinois Department of Conservation,
    which plan will preserve the lake’s recreational
    and fisheries value;
    (iv)
    That Illinois Power Company keeps
    the lake
    open to readily available public access
    throughout the life of the lake;
    (v)
    That Illinois Power Company develops and
    submits
    an acceptable program prior
    to operation
    showing startup and shutdown procedures which
    will minimize the adverse affect of such
    activities on aquatic
    life;
    (vi) That
    if
    it is determined after operation of
    the first unit or by ongoing research,
    that
    conditions
    in Clinton Lake will be significantly
    different than has been described
    in the
    316(a) demonstration,
    or
    if it is determined
    that the cooling water use, recreational
    aspects of the lake,
    or that protection and
    prcpagation of indigenous aquatic life cannot
    be assured, Illinois Power Company shall take
    whatever measures are needed to correct the
    problem, including backfitting of the proposed
    or ~xisting
    plant with additional cooling
    facilities.
    (vii) That Petitioner Illinois Power Company submit
    quarterly progress reports to:
    Illinois Environmental Protection Agency,
    Manager, Variance Section; Division of
    Water Pollution Control,
    2200 Churchill Road
    Springfield,
    Illinois
    62706
    (viii) Within 28 days after the dateof
    the Board
    Order herein the Petitioner shall execute and
    forward to the Illinois Environmental Protection
    Agency, Manager, Variance Section at the
    above address, and to the Pollution Control
    Board
    a Certification of Acceptance and
    agree~’nentto be bound to all terms and conditions
    of the variance.
    The form of said certification
    shall be as follows:
    18—
    258

    —19—
    CE RT IF
    I CATION
    I
    (We),
    ____________________________
    having read and
    fully understandin~ the Order of the Illinois Pollution
    Control Board
    in PCB 75-31 hereby accept said Order and
    agree to be boun.i by all of the terms and conditions thereof.
    Signed
    Title
    Date
    B)
    Petitioner Illinois Power Company’s request for
    a Variance from Rule 970 of Chapter
    3 is
    dismissed
    I, Chistan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby ce~tifythe above Opinion and Order
    w re adopted on tne,~j4
    day of~J
    ,
    1975, by a vote of
    trol Board
    Illinois Pol
    18—
    259

    Back to top