ILLINOIS POLLUTION CONTROL BOARD
    July
    8, 1976
    SALEM GRAVURE, DIVISION OF WORLD
    )
    COLOR PRESS,
    INC.,
    )
    )
    Petitioner,
    v.
    )
    PCB 76—51
    )
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    )
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Dr. Satchell):
    This matter comes before the Pollution Control Board
    (Board)
    as a petition for variance from Rule 205(f)
    of the
    Chapter
    2: Air Pollution Control Regulations.
    The original
    petition was filed February 26,
    1976.
    Additional information
    was filed by Salem Gravure
    (Salem)
    on March 26,
    1976.
    The
    Environmental Protection Agency
    (Agency)
    filed its Recommenda-
    tion on June 8,
    1976.
    No hearing was held in this matter.
    Salem is requesting a variance from Rule 205(f)
    of the Air
    Pollution Regulations
    to allow the running of three rotogravure
    printing presses until October
    1,
    1976.
    At this time, Petitioner
    will have installed and operating the solvent recovery systems
    necessary to be
    in compliance with all the Regulations.
    The
    controlling regulation is deemed to be Rule 205(f) (1) (B)
    and
    in the Agency’s opinion Petitioner should not encounter any
    problem in meeting the 85
    required control efficiency with the
    installation of the control system.
    Salem’s failure to complete the solvent recovery system
    with the rest of its new plant was caused by cancellation of
    its contract with the original supplier who because of poor
    financial condition might not have been able to complete the
    system.
    Failure to obtain this variance is alleged by Petitioner
    to impose an unreasonable hardship because of long term,
    multi-million dollar contracts to print weekly and monthly
    publications when missed deadlines could result in defaulted
    contracts and possible litigation.
    The economic impact of the placing of the new plant in
    Marion County is extremely favorable to the area.
    Petitioner
    states that the area had an unemployment figure of 16.6
    in
    February of 1976.
    Salem would employ about 2
    of the total

    —2—
    work force
    (about 425)
    in the county.
    By January
    1, 1982,
    Salem estimates
    it will be employing over 1,000 people with
    an average wage rate of $8.50 per hour.
    The Agency granted a construction permit
    (No.
    C 512020)
    on March
    4,
    1976 which included five printing presses,
    copper
    and chrome plating tanks, three boilers, four cyclones, five
    binders,
    and an activated carbon solvent recovery system which
    includes five carbon beds each containing 25,000 pounds of
    activated carbon.
    The Agency estimates the cost of the
    activated carbon units at about $1.3 million.
    The initial
    start-up of the solvent recovery system is scheduled for
    August 15, 1976.
    Petitioner states that the three presses being built
    at this time
    (No.
    301,
    a proof press, Nos. 302,
    303, produc-
    tion presses) will use about 1,216 pounds of solvents per hour:
    Roto Solvent (composition not given)
    961.44
    Naphtha
    (largely pentanesand hexanes)* 188.70
    Toluene
    (methyl benzene)*
    55.08
    Xylene
    (dimethyl benzene)*
    10.72
    Total
    1215.94
    *Merck Index 8th Ed. Naphtha listed as “petroleum benzin”.
    It is estimated five per cent of the solvent would be con-
    sumed.
    In conference with Agency personnel,
    Mr. Littlejohn, chief
    corporate engineer, World Color Press, stated #302 commenced
    operation in April,
    1976;
    #303 will be operative about July 1,
    1976 and #301 may be operative before October 1,
    1976.
    The
    solvent usage values supra are for full production rates.
    The Salem facility immediately borders the Salem Texaco
    Oil production area which the Agency would expect to be a
    major source of organic material emissions.
    Since Petitioner’s
    facility is new, the Agency cannot reliably estimate the degree
    of unreasonable interference this plant may cause to members
    of the public.
    The known chemical emissions
    (toluene, xylene
    and naphtha)
    all have a relatively low level of toxicity but
    are explosive in sufficient concentration.
    As with other
    organic chemical emissions,
    ~phb~ochemical smog and ozone
    production could be enhanced.
    The consideration of the effect of Petitioner’s emissions
    on ambient air quality with regard to applicable standards
    is not easily solved.
    The report submitted by P
    & W Engineers,
    Inc., titled “Addenda to the Variance Petition
    (PCB 76—51)
    for

    —3—
    World Color Press,
    Inc., Salem Gravure Division”
    (hereinafter
    Report)
    states that at the present time, 1,752 tons/year
    (hydrocarbons) are being emitted by various industrial pro-
    cesses in Marion County,
    of which 194.5 tons/year are emitted
    in the city of Salem.
    To determine the effects of Salem’s
    emissions, an atmospheric dispersion model was selected and
    the Pasquill equation used to calculate ground level concen-
    trations.
    The results are given in Table
    1 of the Report:
    Table
    1.
    Maximum Hydrocarbon Ground Level Concentrations
    Distance
    Hydrocarbons
    Hydrocarbons
    Hydrocarbons
    Total
    Downwind
    from 301
    from 302
    from 303
    Hydrocarbons
    0.1 KM
    0.00089
    mg/l
    0.0187
    mg/i
    0.0187
    mg/l
    0.0383
    mg/i
    0.5 KM
    0.000088 mg/l
    0.00184 mg/i
    0.00184 mg/l
    0.00377 mg/i
    1.0 KM
    0.000023 mg/i
    0.00048 mg/l
    0.00048 mg/l
    0.00098 mg/l
    Presumably based on this table, the Agency states the Report
    predicts a worst condition hydrocarbon concentration of about
    3,770 micrograms per cubic meter
    (~ug/m3)of air at a distance
    of one kilometer from the point of emission.
    This value would
    indicate the plant would “cause a serious air quality problem”
    (Agency Rec. at 6).
    Examination of the Table does not validate
    the quoted figure.
    The actual figure is believed to be
    0.00098 mg/l minus the contribution of #301
    (0.000023 mg/l)
    (since it would not be on stream)
    or 0.000957 mg/i which
    on conversion becomes 957 ~.iug/m3
    when presses Nos.
    302 and
    303 are operated 75
    of the time.
    In a document submitted
    July 2,
    1976 by P
    & W Engineers,
    Inc. entitled,
    “Supplementary
    Information for Variance Petition,” the actual operation of the
    one press at this time is given as 50
    of the time so that the
    emissions would be less than one-half of 957 ,ug/m3.
    An ambient air quality standard of 160 ~ug/m3maximum
    3-hour concentration has been established for non—methane
    hydrocarbons which is not to be exceeded more than once a
    year.
    (Chapter 2, Part III, Rule 309).
    The Agency states
    that the Report would indicate short term violations of
    ambient air quality for hydrocarbons, but that “the Agency
    believes that the report was too poorly constructed to give
    the projection any credence.
    Indeed, no reliable hydrocarbon
    dispersion model exists at this time.”

    —4—
    The Agency recommends that either the variance be denied
    or be granted subject to a number of conditions.
    The Board
    is disposed to grant the variance subject to the conditions
    stated in the Order for the following reasons:
    1.
    The environmental damages or hazards are believed
    to be insignificant if the ozone
    level is monitored
    and the plant shut down when levels of 0.17 ppm
    (1-
    hour averaging time)
    are reached for three consecutive
    days.
    2.
    The information gathered during the variance period
    would be very valuable in considering hydrocarbon
    dispersal in the future.
    This Opinion constitutes the Board’s findings of fact
    and conclusions of law in this matter.
    ORDER
    It is the Order of the Pollution Control Board that
    Salem Gravure, Division of World Color Press,
    Inc., be
    granted variance from Rule 205(f) (1) (B) of the Board’s
    Chapter 2: Air Pollution Control Regulations until October 1,
    1976 or until such time as the activated carbon recovery
    system is operational, whichever date comes first;
    and
    subject to the following conditions:
    1.
    Petitioner shall submit monthly progress reports
    to the Agency on the first business day of each
    month until the project is completed.
    Reports shall
    be sent to the following address:
    Program Control Coordinator
    Illinois Environmental Protection Agency
    Division of Air Pollution Control
    2200 Churchill Road
    Springfield, Illinois 62706
    2.
    No later than twenty-one
    (21)
    days after the date
    on which Petitioner completes construction and
    installation of its activated carbon recovery
    system, Petitioner shall submit to the Agency an
    application for an operating permit for said
    system and the printing presses which it controls;
    within ninety
    (90) days after the date said
    application for an operating permit is submitted
    to the Agency, Petitioner shall obtain an operating
    permit for both the presses and the activated carbon
    recovery system.

    —5—
    3.
    Proximate to its printing facility, Petitioner shall
    maintain, and operate for a period not less than one
    year from the date of this Order both in-stack and
    ambient air monitoring equipment to measure concen-
    trations of both ozone and hydrocarbons.
    Petitioner
    shall seek and obtain approval from the Agency re-
    garding the type and location of said equipment no
    later than twenty-eight
    (28)
    days from this Order.
    The Agency shall have the right to inspect Petitioner’s
    ambient air monitoring equipment and require operation
    of said equipment in accordance with methods approved
    by the Agency.
    During the variance period, Petitioner
    shall cease all operations which cause hydrocarbon
    emissions on the third consecutive day that ambient
    air monitors indicate an ozone level of 0.17 ppm or
    higher using a 1-hour averaging time and will not
    resume these operations until the day after the afore-
    mentioned monitors indicate an ozone level of 0.07 ppm
    or less using a 2-hour averaging time through one
    full day.
    4.
    Petitioner shall keep record charts to document
    emissions measurements from its stack monitoring
    equipment and ambient air monitoring equipment de-
    scribed in condition
    (3)
    above.
    Such records shall
    be kept on the premises of Petitioner’s facility
    available for Agency inspection for a period not
    less than one year from the date the record charts
    are made.
    Such records shall include emission
    measurements for each monitoring unit expressed in
    micrograms per cubic meter of air, time of measure-
    ment, and wind direction.
    5.
    To insure compliance pursuant to Section
    36 of the
    Illinois Environmental Protection Act, Petitioner
    shall file with the Agency’s Control Program Coordinator
    at the address above a performance bond in the amount
    of $50,000 and in a form acceptable to the Agency no
    later than twenty-eight
    (28) days from this Order.
    6.
    Within thirty-five
    (35)
    days of this Order herein,
    Petitioner shall execute and forward to the Control
    Program Coordinator, a Certification of Acceptance
    and Agreement to be bound to all terms and conditions
    of the Board Order.
    The form of said Certification
    shall be as
    follows,:

    —6—
    CERTIFICATION
    I
    (We),
    ,
    having
    read and fully understanding the Order of the Illinois
    Pollution Control Board in PCB 76-51 hereby accept said
    Order and agree to be bound by all the terms and conditions
    thereof.
    Signed by
    Title
    Date
    Mr. Jacob D. Dumelle dissents.
    I, Christan
    L. Moffett, Clerk of the Illinois Pollution
    Control Board here~y~ertifythe abov
    Opinion and Order were
    adopt~don the
    _________
    day of
    ______________,
    1976 by a vote
    of
    I4~
    llinois Pollution

    Back to top