ILLINOIS POLLUTION CONTROL
BOARD
June 18, 1976
LEHIGH PAVING COMPANY,
)
)
Petitioner,
V.
)
PCB 76—94
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION
AND
ORDER OF THE BOARD
(by Dr. Satchell):
This matter comes before the Board as
a Petition for
an Extension of a Variance from Rule 203(a)
of the Chapter
2:
Air Pollution Regulations.
The original variance, PCB 75-298,
was granted on October 16,
1975 and expires July 30, 1976.
The Petition for Extension now before the Board was filed
April
7,
1976.
The Agency Recommendation was filed June
1,
1976.
Petitioner’s response to the Agency Recommendation
was filed June 11,
1976.
No hearing was held in this matter.
The Board takes notice of the facts and opinion of
PCB 75—298.
Lehigh Paving Company
(Lehigh), owner and operator of
an asphalt paving plant, requests this extension on the
basis that there has been delay over which Petitioner has
had no control.
Koch Engineering Company
(Koch)
is the
manufacturer of the control equipment to be installed.
According to the original compliance plan Koch was to have
prepared drawings for approval
in two to three weeks and
shipment was to be within ten weeks after approval of the
drawing.
However it actually took Koch eleven weeks
to
prepare the drawings
for approval, and shipment
is not
scheduled until the first week in July,
1976.
By the time
the equipment arrives in mid-July there will have been a
five month delay from the February 15,
1976 date in the
original compliance plan.
On the basis of this delay Lehigh
is asking the Board to extend the variance from Rule 203(a)
until December 1,
1976
(the estimated end of the 1976
operating season)
in order to avoid arbitrary and unreason-
able hardship to Lehigh and its employees.
The Agency recommended that the variance be extended
only to August
15,
1976 and then it would be subject to
conditions.
The basis of this position
is that the Agency
states that the equipment should require no more than three
22— 173
—2—
weeks or 100 hours to install,
The Agency states,
“Lehigh
is expected to receive the equipment during the first week
of July,
1976”; the petition states shipment is scheduled
for the first week in July 1976.
This leaves the arrival
date indefinite.
Lehigh claims the installation will take
three months.
Petitioner’s normal asphalt production out-
put is during 100 to 120 days of operation per year from
May through November.
The production schedule
is limited due
to weather conditions
(Agency Recommendation at 2).
As
Lehigh cannot install the equipment and make asphalt paving
at the same time,
timing in July,
a good weather month,
would be critical to Petitioner’s business.
Considering
these timing factors and the time schedule of the original
variance the Board finds that Petitioner’s request for ex-
tension is reasonable.
However, the Board must also con—
sider whether Petitioner will contribute to a violation of
the ambient air quality standards.
The two monitoring
stations
in Petitioner’s region are Champaign and Bloomington.
In 1975 the Champaign station, located approximately 25 miles
SSW of Petitioner’s asphalt plant, registered an annual
geometric mean particulate level of
46 micrograms per cubic
meter of air.
The Bloomington Station, located approximately
straight west of Petitioner’s asphalt plant, registered an
annual geometric mean particulate level of 64 micrograms per
cubic
meter.
The State and Federal ambient particulate primary
standard allows an annual geometric mean concentration of
75
micrograms per cubic meter of air.
This information and the
information used
in the prior proceeding indicate that Peti-
tioner’s particulate emissions will not cause or contribute
to a violation of State or Federal ambient air quality stan-
dards.
Under these conditions the Board finds that extension
of the variance to November
1, 1976
is justified.
This allows
Petitioner time to install the equipment and guarantee its
operation for the 1977 season.
The Board does note that Lehigh has been dilatory
in
sending its monthly reports and posting the performance bond,
conditions of the first variance.
The Agency has received
only two monthly reports and the performance bond which was
to have been provided by November 15,
1975 was not provided
until May 10,
1976.
The monthly progress reports remain a
condition of any extended variance.
The Agency Recommendation urges the Board as
a condition
of the variance to limit Petitioner to emitting no more than
3 pounds per hour from the wet scrubber exhaust stack at a
process weight of 120 tons per hour.
This recommendation is
based on several factors.
First, the families of the two
22— 174
3—
residences proximate to the plant, being approximately one
fourth mile from the plant,
object to the extension of the
variance because of the emissions.
Second, Lehigh’s present
emission
is 36.3 pounds per hour.
The regulated limit is
32.7 pounds per hour.
The Agency does not feel that a
reduction of 3.6 pounds per hour will reduce the number of
complaints
it receives on the facility and that Lehigh will
still be causing air pollution in violation of Section 9(a)
of the Act.
The Board finds that such a limitation would be inappro-
priate at this time.
Petitioner’s equipment is yet to be
installed and
its
efficiency is theoretical.
If the Agency’s
calculations are correct, the equipment should he capable ot
99.9
efficiency which should reduce emissions to 2.6 pounds
per hour at a process weight rate of 120 tons per hour.
This
figure
is less than one tenth of the emission limitations
established by our regulations.
Even if Lehigh’s equipment
should not reach this efficiency rate or should do so only
part of the time,
it would appear that the emissions should
be reduced to well under the 32.7 pounds per hour standard.
Thus it is premature to determine at what point Lehigh would
still be causing a violation of Section 9(a)
of the Act.
This Opinion constitutes the Board’s findings of fact
and conclusions of law.
ORDER
It is the Order of the Pollution Control Board that
Petitioner, Lehigh Paving Company, be granted a Variance
from Rule 203(a) of Chapter
2: Air Pollution,
of the Illinois
Pollution Control Board Rules and Regulations, until Novem-
ber
1,
1976, subject to the following conditions:
1.
Petitioner shall apply for and obtain from the
Environmental Protection Agency all appropriate
construction and operation permits.
2.
Petitioner shall, on the first day of each month
after the date of this Order,
submit to the Agency
a report detailing progress toward completion of
the compliance program.
Those reports shall be
submitted to the following address:
Environmental Protection Agency
Control Program Coordinator
Division of Air Pollution Control
2200 Churchill Road
Springfield, Illinois 62706
22—175
—4—
3.
Within
30 days of this order Petitioner shall
execute and forward to the above address and
the Pollution Control Board, the following certi-
fication of acceptance:
CERTIFICATION
I
(We), ________________________________, having read the
Order of the Illinois Pollution Control Board in Case No.
PCB 76-94,
understand and accept said Order, realizing that
such acceptance renders all terms and conditions thereto
binding and enforceable.
SIGNED
TITLE
DATE
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify that the above Opinion and
Order were ado~t1edon the
j~~’’-
day of
~
,
1976
by a vote of
~
QJL.O~f~4~
Illinois Pollution
rol Board
22—176