ILLINOIS POLLUTION CONTROL
    BOARD
    June 18, 1976
    LEHIGH PAVING COMPANY,
    )
    )
    Petitioner,
    V.
    )
    PCB 76—94
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by Dr. Satchell):
    This matter comes before the Board as
    a Petition for
    an Extension of a Variance from Rule 203(a)
    of the Chapter
    2:
    Air Pollution Regulations.
    The original variance, PCB 75-298,
    was granted on October 16,
    1975 and expires July 30, 1976.
    The Petition for Extension now before the Board was filed
    April
    7,
    1976.
    The Agency Recommendation was filed June
    1,
    1976.
    Petitioner’s response to the Agency Recommendation
    was filed June 11,
    1976.
    No hearing was held in this matter.
    The Board takes notice of the facts and opinion of
    PCB 75—298.
    Lehigh Paving Company
    (Lehigh), owner and operator of
    an asphalt paving plant, requests this extension on the
    basis that there has been delay over which Petitioner has
    had no control.
    Koch Engineering Company
    (Koch)
    is the
    manufacturer of the control equipment to be installed.
    According to the original compliance plan Koch was to have
    prepared drawings for approval
    in two to three weeks and
    shipment was to be within ten weeks after approval of the
    drawing.
    However it actually took Koch eleven weeks
    to
    prepare the drawings
    for approval, and shipment
    is not
    scheduled until the first week in July,
    1976.
    By the time
    the equipment arrives in mid-July there will have been a
    five month delay from the February 15,
    1976 date in the
    original compliance plan.
    On the basis of this delay Lehigh
    is asking the Board to extend the variance from Rule 203(a)
    until December 1,
    1976
    (the estimated end of the 1976
    operating season)
    in order to avoid arbitrary and unreason-
    able hardship to Lehigh and its employees.
    The Agency recommended that the variance be extended
    only to August
    15,
    1976 and then it would be subject to
    conditions.
    The basis of this position
    is that the Agency
    states that the equipment should require no more than three
    22— 173

    —2—
    weeks or 100 hours to install,
    The Agency states,
    “Lehigh
    is expected to receive the equipment during the first week
    of July,
    1976”; the petition states shipment is scheduled
    for the first week in July 1976.
    This leaves the arrival
    date indefinite.
    Lehigh claims the installation will take
    three months.
    Petitioner’s normal asphalt production out-
    put is during 100 to 120 days of operation per year from
    May through November.
    The production schedule
    is limited due
    to weather conditions
    (Agency Recommendation at 2).
    As
    Lehigh cannot install the equipment and make asphalt paving
    at the same time,
    timing in July,
    a good weather month,
    would be critical to Petitioner’s business.
    Considering
    these timing factors and the time schedule of the original
    variance the Board finds that Petitioner’s request for ex-
    tension is reasonable.
    However, the Board must also con—
    sider whether Petitioner will contribute to a violation of
    the ambient air quality standards.
    The two monitoring
    stations
    in Petitioner’s region are Champaign and Bloomington.
    In 1975 the Champaign station, located approximately 25 miles
    SSW of Petitioner’s asphalt plant, registered an annual
    geometric mean particulate level of
    46 micrograms per cubic
    meter of air.
    The Bloomington Station, located approximately
    straight west of Petitioner’s asphalt plant, registered an
    annual geometric mean particulate level of 64 micrograms per
    cubic
    meter.
    The State and Federal ambient particulate primary
    standard allows an annual geometric mean concentration of
    75
    micrograms per cubic meter of air.
    This information and the
    information used
    in the prior proceeding indicate that Peti-
    tioner’s particulate emissions will not cause or contribute
    to a violation of State or Federal ambient air quality stan-
    dards.
    Under these conditions the Board finds that extension
    of the variance to November
    1, 1976
    is justified.
    This allows
    Petitioner time to install the equipment and guarantee its
    operation for the 1977 season.
    The Board does note that Lehigh has been dilatory
    in
    sending its monthly reports and posting the performance bond,
    conditions of the first variance.
    The Agency has received
    only two monthly reports and the performance bond which was
    to have been provided by November 15,
    1975 was not provided
    until May 10,
    1976.
    The monthly progress reports remain a
    condition of any extended variance.
    The Agency Recommendation urges the Board as
    a condition
    of the variance to limit Petitioner to emitting no more than
    3 pounds per hour from the wet scrubber exhaust stack at a
    process weight of 120 tons per hour.
    This recommendation is
    based on several factors.
    First, the families of the two
    22— 174

    3—
    residences proximate to the plant, being approximately one
    fourth mile from the plant,
    object to the extension of the
    variance because of the emissions.
    Second, Lehigh’s present
    emission
    is 36.3 pounds per hour.
    The regulated limit is
    32.7 pounds per hour.
    The Agency does not feel that a
    reduction of 3.6 pounds per hour will reduce the number of
    complaints
    it receives on the facility and that Lehigh will
    still be causing air pollution in violation of Section 9(a)
    of the Act.
    The Board finds that such a limitation would be inappro-
    priate at this time.
    Petitioner’s equipment is yet to be
    installed and
    its
    efficiency is theoretical.
    If the Agency’s
    calculations are correct, the equipment should he capable ot
    99.9
    efficiency which should reduce emissions to 2.6 pounds
    per hour at a process weight rate of 120 tons per hour.
    This
    figure
    is less than one tenth of the emission limitations
    established by our regulations.
    Even if Lehigh’s equipment
    should not reach this efficiency rate or should do so only
    part of the time,
    it would appear that the emissions should
    be reduced to well under the 32.7 pounds per hour standard.
    Thus it is premature to determine at what point Lehigh would
    still be causing a violation of Section 9(a)
    of the Act.
    This Opinion constitutes the Board’s findings of fact
    and conclusions of law.
    ORDER
    It is the Order of the Pollution Control Board that
    Petitioner, Lehigh Paving Company, be granted a Variance
    from Rule 203(a) of Chapter
    2: Air Pollution,
    of the Illinois
    Pollution Control Board Rules and Regulations, until Novem-
    ber
    1,
    1976, subject to the following conditions:
    1.
    Petitioner shall apply for and obtain from the
    Environmental Protection Agency all appropriate
    construction and operation permits.
    2.
    Petitioner shall, on the first day of each month
    after the date of this Order,
    submit to the Agency
    a report detailing progress toward completion of
    the compliance program.
    Those reports shall be
    submitted to the following address:
    Environmental Protection Agency
    Control Program Coordinator
    Division of Air Pollution Control
    2200 Churchill Road
    Springfield, Illinois 62706
    22—175

    —4—
    3.
    Within
    30 days of this order Petitioner shall
    execute and forward to the above address and
    the Pollution Control Board, the following certi-
    fication of acceptance:
    CERTIFICATION
    I
    (We), ________________________________, having read the
    Order of the Illinois Pollution Control Board in Case No.
    PCB 76-94,
    understand and accept said Order, realizing that
    such acceptance renders all terms and conditions thereto
    binding and enforceable.
    SIGNED
    TITLE
    DATE
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that the above Opinion and
    Order were ado~t1edon the
    j~~’’-
    day of
    ~
    ,
    1976
    by a vote of
    ~
    QJL.O~f~4~
    Illinois Pollution
    rol Board
    22—176

    Back to top