ILLINOIS POLLUTION CONTROL BOARD
January 22, 2004
TODD’S SERVICE STATION,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 03-2
(UST Fund)
ROBERT M. RIFFLE, OF ELIAS, MEGINNES, RIFFLE & SEGHETTI, P.C., APPEARED ON
BEHALF OF PETITIONER, and
JOHN J. KIM, OF THE ILLINOIS ENVIRONMENTAL PROTECTION AGENCY,
APPEARED ON BEHALF OF RESPONDENT.
OPINION AND ORDER OF THE BOARD (by N.J. Melas):
Todd’s Service Station (Todd’s) seeks review of a determination by the Environmental
Protection Agency (Agency) that modified Todd’s proposed budget amendment for the high
priority corrective action plan regarding a leaking underground storage tank (UST) site at 1303
Washington Road, Washington, Tazewell County. Todd’s challenges the Agency’s
determination that some of the hourly rates and number of hours for personnel charges for which
payment was requested were unreasonable. For the reasons below, the Board finds that the
record supports the Agency’s decision to modify Todd’s budget amendment.
PROCEDURAL BACKGROUND
On October 17, 2002, the Board accepted this matter for hearing. The Agency filed the
administrative record on November 19, 2002. Todd’s waived the statutory decision deadline.
Board Hearing Officer Carol Sudman held a hearing on July 15, 2003. Todd’s submitted a post-
hearing brief on August 22, 2003. The Agency submitted a post-hearing brief on
September 15, 2003, and Todd’s replied on September 26, 2003.
FACTS
Todd’s Service Station is located at 1303 Washington Road, Washington, Tazwell
County. Todd’s notified the Illinois Emergency Management Agency (IEMA) of a release at the
site on May 27, 1998. The site was classified as high priority due to contamination at the site
above the Agency generic cleanup standards (AR, at 13). IEMA assigned the site incident
number 981257. Pet. at Exh. A.
2
Todd’s retained Midwest Environmental Consulting & Remediation Services, Inc.
(Midwest) to remediate the site. Midwest began by preparing an initial High Priority Site
Investigation Corrective Action Plan (HPCAP) that proposed a phased remediation approach in
accordance with the Tiered Approach to Corrective Action Objectives (TACO). Pet. Br. at 1; Tr.
at 7; AR, at 2. The Agency received the HPCAP, accompanied by a proposed budget, on
September 20, 2000. AR, at 2. The HPCAP indicated that five USTs were removed from the
site on November 4, 1998. Two tanks contained gasoline (10,000 and 6,000 gallons), one tank
contained diesel fuel (6,000 gallons), one contained kerosene (1,000 gallons), and one was used
for waste oil (500 gallons). AR, at 13. The gasoline UST was leaking at the time of removal,
due to product line leaks, spills, and overfills.
Id
. The HPCAP also indicated that closure
strategy at the site would likely include a highway authority agreement (HAA) with the Illinois
Department of Transportation (IDOT), but that additional investigation would be necessary to
determine the extent of soil contamination. AR, at 17, 19.
The Agency approved the proposal in a letter dated November 1, 2000. Tr. at 7; AR, at
98. The Agency approved $21,028.75 of $21,640.75 of Todd’s proposed original corrective
action plan budget. Tr. Resp. Exh. 1. Specifically, the Agency approved $14,529 of $15,101
that Todd’s requested for personnel costs.
Id
.
After review of a High Priority Corrective Action Completion Report (CACR) that
Midwest prepared and submitted on behalf of Todd’s, the Agency issued Todd’s a No Further
Remediation (NFR) Letter on December 4, 2001. AR, at 102.
The final corrective action plan detailed TACO calculations and groundwater modeling
as well as HAAs and engineered barriers. The final plan required additional personnel time
beyond that which the Agency originally budgeted for costs associated with site closure. Pet. Br.
at 1. Todd’s contends the Agency orally authorized Midwest to perform the additional work.
Pet. Br. at 2.
Midwest submitted a budget amendment, dated April 18, 2002, to the Agency asking for
an additional $7,483.58 to cover additional personnel costs for site closure. Pet. Br. at 2; Pet. at
Exh. A. The budget amendment indicated the costs were associated with conducting a more
thorough TACO evaluation and acquiring the necessary HAAs. Pet. at Exh. A. The Agency
rejected Midwest’s budget amendment in a letter dated May 23, 2002 (AR, at 128), because it
was submitted after the Agency issued a No Further Remediation (NFR) letter for the site. Pet.
at Exh. B; AR, at 128. The budget rejection letter indicated that, pursuant to 35 Ill. Adm. Code
732.405(d), a budget must be submitted before issuance of an NFR letter.
Id
.
Midwest and the Agency discussed the Agency’s rejection and the Agency indicated in a
memo dated June 3, 2002, that it would reconsider the budget amendment denial if it received a
written request to do so. Pet. Br. at 2; AR, at 131. Midwest submitted a request for
reconsideration the next day, on June 4, 2002, and the Agency, on June 7, 2002, approved part of
the amendment and rejected the rest. Pet. Exh. D. Specifically, the Agency approved $2,806.08
of the $7,483.58 requested. Agency notes regarding the budget amendment reflect that the
original HPCAP budget approved on November 1, 2000 included hours for TACO calculation
and reimbursement; these are activities that Midwest accounted for again in the budget
3
amendment. The June 7, 2002 letter indicated it was a final and appealable Agency order.
Id
.
At hearing, counsel for the Agency, John Kim, testified the final total amount approved should
read $3,056.08 rather than $2,806.08 due to a mathematical error in calculating the number of
professional engineering hours approved. Tr. at 5-6.
Three witnesses testified, and each party filed one exhibit at hearing. Mr. Allen Green,
president of Midwest, testified on behalf of the petitioner. Mr. Green testified that Midwest’s
preliminary investigation of Todd’s site revealed contamination around the USTs located on the
site. Tr. at 14. Mr. Green stated that Midwest proposed a phased approach to assessing and
remediating Todd’s site that the Agency approved. Tr. at 15. Under this approach, stated Mr.
Green, Midwest would conduct a preliminary investigation of the site, determine the next course
of action, then submit a plan and budget for the subsequent course of action.
Id
. Mr. Green also
explained the time he and his staff spent obtaining the two HAAs. Tr. at 18. In formulating a
corrective action plan, Mr. Green stated that Midwest discovered the off-site contamination at
Todd’s extended underneath and on the other side of the highway, onto property owned jointly
by IDOT and the City of Washington. Tr. at 16; 37. Mr. Green explained Midwest had to obtain
HAAs from both IDOT and the City of Washington to perform corrective action on the property.
Tr. at 18. According to Mr. Green, the initial budget did not include the Highway Authority
Agreements, but the agreements were included in the amended budget. Tr. at 19. Mr. Green
stated that the corrective action plan budget amendment Midwest submitted accurately lists the
total number of hours Midwest spent for the TACO and tier two modeling and calculations,
obtaining the HAAs, the final closure documentation, the report to the Agency, and the final
reimbursement for that work. Tr. at 24-25.
Mr. Todd Birky also testified on behalf of the Todd’s. Mr. Birky is an environmental
geologist with Midwest. Tr. at 30. Mr. Birky testified that the Agency suggested doing off-site
sampling across a highway, which significantly increased the cost of the project. Pet. Br. at 3.
Mr. Harry Chappel, manager of a unit in the Leaking Underground Storage Tank Section,
Bureau of Land, testified on behalf of the Agency. Tr. at 47, 48. Mr. Chappel testified that he
signed the June 7, 2002 letter that modified the budget amendment. Tr. at 51.
APPLICABLE LAW
The Environmental Protection Act provides that in order to seek reimbursement from the
Fund, an owner or operator must submit an accounting of costs:
Any owner or operator intending to seek payment from the Fund shall submit to
the Agency for approval a corrective action budget that includes, but is not limited
to, an accounting of all costs associated with the implementation and completion
of the corrective action plan. 415 ILCS 5/57.7(b)(3) (2002).
The Act also requires the Agency to determine whether costs associated with a plan are
reasonable:
4
In approving any plan submitted pursuant to subsection (a) or (b) of this Section,
the Agency shall determine . . . that the costs associated with the plan are
reasonable, will be incurred in the performance of site investigation or corrective
action, and will not be used for site investigation or corrective action activities in
excess of those required to meet the minimum requirements of this Title. 415
ILCS 5/57.7(c)(3) (2002).
The Board’s procedural rules regarding costs reimbursable from the Fund provide:
Costs ineligible for payment from the Fund include but are not limited to: . . .
costs proposed as part of a budget plan that are unreasonable. 35 Ill. Adm. Code
732.606(hh).
BURDEN OF PROOF
Section 105.112(a) provides the burden of proof is on the petitioner. 35 Ill. Adm. Code
105.112(a). The burden is on the petitioner for reimbursement to demonstrate that the costs
incurred are related to corrective action, properly accounted for, and reasonable. Beverly
Malkey, as Executor of the Estate of Roger Malkey d/b/a Malkey’s Mufflers v. IEPA, PCB 02-
104 slip op. at 9 (Apr. 17, 2003). When requesting reimbursement from the fund, the owner or
operator must provide an accounting of all costs associated with the implementation and
completion of the corrective action plan.
Id
.; 415 ILCS 5/57.7(b)(3).
STANDARD OF REVIEW
The standard of review under Section 40 of the Act is whether the application, as
submitted to the Agency, would not violate the Act and Board regulations. Ted Harrison Oil Co.
v. IEPA, PCB 99-127, slip op. at 5 (July 24, 2003);
citing
Browning Ferris Industries of Illinois
v. PCB, 179 Ill. App. 3d 598, 534 N.E.2d 616 (2nd Dist. 1989). The Board will not consider
new information not before the Agency prior to its final determination regarding the issues on
appeal. Kathe’s Auto Service Center v. IEPA, PCB 95-43, slip op. at 14 (May 18, 1995). The
Agency’s denial letter frames the issues on appeal. Pulitzer Community Newspapers, Inc. v.
EPA, PCB 90-142 (Dec. 20, 1990).
DISCUSSION
Todd’s challenges the Agency’s June 7, 2002 decision to deny a total of $4,427.50 of
Todd’s high priority corrective action plan budget amendment for personnel costs it deemed
unreasonable. Todd’s appeals deductions the Agency made relating to both hourly rates and the
number of hours of work performed. Specifically, the Agency approval reduced the number of
hours for the following personnel: (1) senior project manager; (2) environmental hydrogeologist;
(3) senior environmental manager; (4) professional engineer; (5) principal; and (6) project
manager. The Agency approved reduced hourly rates for the environmental hydrogeologist, the
senior environmental manager, and the professional geologist. As discussed below, the Board
affirms the Agency’s modification of Todd’s budget amendment.
5
Todd’s Arguments
Todd’s contends that it spent the entire requested $7,483.58 on personnel time that was
spent on the project. Todd’s asserts that both the hourly rates and the number of hours were
reasonable and necessary for completion of the project and site closure. Pet. at 3. Todd’s further
asserts the additional work performed was pre-approved by the Agency.
Todd’s argues the Agency has no established standard for reviewing budgets. Todd’s
contends that if the Agency had a standard, the deferential arbitrary and capricious standard
might apply to the Agency’s decision denying $4,677.50 of the budget amendment. Pet. Br. at 8;
citing
Town of Sugar Loaf v. IEPA, 305 Ill.App.3d 483, 712 N.E.2d 393, 238 Ill.Dec.671 (5th
Dist. 1999). However, Todd’s argues that because the Agency’s review is purely subjective, an
arbitrary and capricious standard should not apply. Todd’s moves the Board to reverse the
Agency’s final determination and allow the additional reimbursement in the amount of
$4,677.50. Pet. Br. at 9.
Agency’s Arguments
The Agency argues that the personnel hours and rates of the budget that the Agency
denied are excessive and not reasonably necessary for the work described. Resp. at 2-3. The
Agency contends that Todd’s claims the additional work was orally approved by the Agency.
However, the Agency notes that the budget amendment was submitted after Todd’s performed
the work itself. The Agency argues that the conversations between Midwest and the Agency do
not constitute Agency approval of the hours of work done or the rates charged for the respective
personnel. Resp. at 3.
The Agency asserts that it properly reduced the hourly rates in the approved amended
budget. Resp. at 6. The Agency approved reduced rates for the hydrogeological engineer, the
senior environmental manager, and the professional geologist. The Agency contends that Todd’s
did not meet its burden of proving that the requested rates were reasonable. For example, the
Agency argues, Todd’s provided no information that defined how it arrived at the hourly rates, or
how the rates were calculated. Resp. at 7. Accordingly, the Agency asks the Board to affirm the
Agency’s decision to approve reduced hourly rates. Resp. at 8.
The Agency asserts that the Act and Board regulations clearly define the standard of
review the Agency applies in reviewing budgets. Section 57.7(c)(4)(C)
1
of the Act provides that
the Agency must determine that the costs associated with the budget are reasonable, will be
incurred in performing corrective action, and will not be used for activities in excess of those
required to meet the minimum requirements of Title XVI of the Act. The Agency notes that
Section 732.505 of the Board’s regulations provides the same standard of review that is found in
1
This citation was provided by the Agency in its final decision regarding the budget amendment
and references the applicable section of the Act in effect at the time of the Agency’s final
decision. 415 ILCS 5/57.7(c)(4)(C) (2000).
6
the Act. 35 Ill. Adm. Code 732.505(c). In addition, the Agency contends, Section 732.606 lists
costs that are ineligible for payment from the UST Fund. 35 Ill. Adm. Code 732.606.
The Agency contends it also properly reduced the hours of work at issue. The Agency
approved reduced hours of work for work performed by a Senior Project Manager,
Environmental Hydrogeologist, Senior Environmental Manager, Professional Engineer, Principal
and Project Manager. AR, at 80. The Agency argues that except for a line item task description,
Midwest did not breakdown how many hours were attributable to each of the listed tasks in the
budget amendment. The Agency asserts the budget amendment contains no explanation of how
the figures were calculated, how many hours were spent on each activity, or what specific
actions were included in the tasks. The Agency contends that in reducing the number of hours,
Mr. Chappel considered three factors: (1) his experience in reviewing submittals for similar
tasks; (2) experience from having personally done those tasks; (3) the specific information
provided in the application by the applicant. Resp. at 9; Tr. at 79.
Mr. Chappel also stated there were certain tasks in the budget amendment that the
Agency had already approved or referenced in part in the original budget. For example, Todd’s
asserts there were difficulties in obtaining the HAAs for the site. However, the Agency argues
there was no information or documentation within the proposed amended budget that described
any of the difficulties claimed by Midwest. Resp. at 11.
In conclusion, the Agency argues that given the lack of information that Midwest
provided, its final decision is correct. Resp. at 11. The Agency argues it acted in accordance
with its statutory and regulatory obligations and guidelines. Accordingly, the Agency asks the
Board to affirm the June 7, 2002 reimbursement determination.
BOARD ANALYSIS
After careful review of the record in this proceeding, the Board is persuaded that the
Agency correctly denied reimbursement for certain amounts of, and rates regarding, personnel
time in Todd’s budget amendment. The Board has held that the purposes of the UST Fund are
narrow. Rantoul Township High School Dist. No. 193 v. IEPA, PCB 03-42, slip op. at 13
(Apr. 17, 2003);
citing
Strube v. PCB, 242 Ill. App. 3d 822, 610 N.E.2d 717, 851 (3rd Dist.
1993). The Act establishing the UST Fund limits reimbursement for high priority sites to
corrective action that mitigates any threat to human health, human safety or the environment
resulting from a UST release. 415 ILCS 5.57.7(b)(2) (2002).
The standard the Agency must apply when reviewing budgets is found in the Act and
Board rules. In reviewing a corrective action plan budget, the Agency must consider whether the
costs are reasonable and not incurred for corrective action in excess of that which is necessary to
meet the minimum requirements of the Act and Board regulations. 415 ILCS 57.7(c)(4)(C); 35
Ill. Adm. Code 732.505(c).
The Agency claims the personnel costs denied are not reasonable. Pet. Exh. D. The
Agency also provided that Todd’s could submit additional information and/or supporting
documentation to demonstrate that the costs submitted are reasonable. While approximately
7
$250 of the reduction relates to a reduction in hourly rates, most of the controversy revolves
around the number of hours authorized for the budget amendment. Tr. at 9-10.
Regarding the hourly rates, the Board finds no explanation in either the budget
amendment or hearing testimony of how Midwest calculated personnel rates or why they are
reasonable. In approving Todd’s original corrective action plan budget in 2000, the Agency
similarly reduced the approved rate for the environmental hydrogeologist from $98 to $85.
Todd’s did not appeal the Agency’s decision at that time.
The Board also finds the Agency properly approved a limited number of hours of work
for certain Midwest personnel that performed corrective action at the Todd’s site. Resp. at 8;
Resp. Exh. 1. Todd’s argues that the hours accounted for in the budget amendment were actually
spent on the tasks indicated. However, the hours actually spent on the tasks indicated is
irrelevant to whether the number of hours expended are reasonable. Resp. at 10.
The Board finds the record supports the Agency’s approval of reduced rates and number
of hours of Todd’s amended budget. Line item descriptions of the work performed by each
professional do not provide enough information for the Agency to determine whether the number
of hours and rates charged are appropriate and reasonable. A more specific breakdown of the
tasks performed and how many hours were spent on each task is necessary for the Agency to
make this determination. Also, Todd’s did not present any testimony at hearing explaining how
the Agency record demonstrates that the costs are reasonable.
The Agency’s June 7, 2002 letter approves $2,806.08 in personnel costs. However, as
discussed above, at hearing the Agency modified this total due to an error in calculating the
approved hours and rates for the professional engineer. The Agency testified that the amount
approved should total $3,056.08. Accordingly, the Board affirms the Agency’s June 7, 2002
approval of a reduced number of hours and rates as modified, totaling $3,056.08.
This opinion constitutes the Board’s findings of fact and conclusions of law.
ORDER
The Board affirms the Agency’s June 7, 2002 determination, as modified.
IT IS SO ORDERED.
Section 41(a) of the Environmental Protection Act provides that final Board orders may
be appealed directly to the Illinois Appellate Court within 35 days after the Board serves the
order. 415 ILCS 5/41(a) (2002);
see also
35 Ill. Adm. Code 101.300(d)(2), 101.906, 102.706.
Illinois Supreme Court Rule 335 establishes filing requirements that apply when the Illinois
Appellate Court, by statute, directly reviews administrative orders. 172 Ill. 2d R. 335. The
Board’s procedural rules provide that motions for the Board to reconsider or modify its final
orders may be filed with the Board within 35 days after the order is received. 35 Ill. Adm. Code
101.520;
see also
35 Ill. Adm. Code 101.902, 102.700, 102.702.
8
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above opinion and order on January 22, 2004, by a vote of 5-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board