On July 11, 2003, the Office of the Attorney General, on behalf of the People of the State
of Illinois (People), filed a complaint against Valley Run Stone, a Division of Avery Gravel Co.,
Inc. (Valley Run Stone).
See
415 ILCS 5/31(c)(1) (2002); 35 Ill. Adm. Code 103.204. The
People allege that Valley Run Stone violated Sections 9(b), 9.1(d), and 39.5(6)(b) of the
Environmental Protection Act (Act), Sections 201.142 and 201.143 of the Board’s regulations,
and several federal regulations implementing the federal Clean Air Act, which are enforceable
under the Section 9.1(d) of the Act. 415 ILCS 5/9(b), 9.1(d), and 39.5(6)(b) (2002); 35 Ill. Adm.
Code 201.142 and 201.143; 40 C.F.R. 52.21(i)(l), (k), (m), and (n). The People further allege
that Valley Run Stone violated these provisions by failing to obtain a construction permit, failing
to comply with preconstruction prevention of significant deterioration standards, failure to obtain
an operating permit, and failing to obtain a Clean Air Act permit. The complaint concerns
Valley Run Stone’s construction of a natural gas-fired power generation engine at its quarry
located in Lisbon, Kendall County.
On October 14, 2003, the People and Valley Run Stone filed a stipulation and proposed
settlement, accompanied by a request for relief from the hearing requirement of Section 31(c)(1)
of the Act (415 ILCS 5/31(c)(1) (2002)). This filing is authorized by Section 31(c)(2) of the Act
(415 ILCS 5/31(c)(2) (2002)).
See
35 Ill. Adm. Code 103.300(a). Under the proposed
stipulation, Valley Run Stone neither admits nor denies the alleged violations and agrees to pay a
civil penalty of $24,500.
Unless the Board determines that a hearing is needed, the Board must cause notice of the
stipulation, proposed settlement, and request for relief from the hearing requirement. Any person
may file a written demand for hearing within 21 days after receiving the notice. If anyone timely
files a written demand for hearing, the Board will deny the parties’ request for relief and hold a
hearing. 415 ILCS 5/31(c)(2) (2002); 35 Ill. Adm. Code 103.300(b), (c). The Board directs the
Clerk of the Board to provide the required notice.
IT IS SO ORDERED.
2
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above order on November 6, 2003, by a vote of 6-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board