ILLINOIS POLLUTION CONTROL BOARD
November 16, 2000
PEOPLE OF THE STATE OF ILLINOIS,
Complainant,
v.
NESTLE USA, INC.,
Respondent.
)
)
)
)
)
)
)
)
)
PCB 01-80
(Enforcement – Water)
ORDER OF THE BOARD (by C.A. Manning):
On November 9, 2000, the People of the State of Illinois filed a three-count complaint
against Nestle USA, Inc. (Nestle), a pumpkin processor. The complaint alleges Nestle caused or
allowed a water pollution hazard, offensive discharges, and water quality violations at its facility
located near Morton, Tazewell County, Illinois. These activities were in alleged violation of
Sections 12(a) and (d) of the Environmental Protection Act (Act) (415 ILCS 5/12(a), (d) (1998))
and the Board’s water pollution regulations at 35 Ill. Adm. Code 302.203, 302.204, 302.206, and
304.106. The Board accepts this matter for hearing.
The Board directs that this matter proceed to hearing as expeditiously as practicable. The
assigned hearing officer must set the matter for hearing in accordance with the requirements of
the Act and the Board’s procedural rules. Accordingly, this matter must be set for hearing within
90 days after the filing of the complaint unless the hearing officer, after appropriate consultation
with the parties, determines that a later date is appropriate and that no undue delay or material
prejudice in the resolution of this matter would result. See 35 Ill. Adm. Code 103.125(a). In any
event, it is the responsibility of the hearing officer to guide the parties toward prompt resolution
or adjudication of this matter, through whatever status calls and hearing officer orders he or she
determines are necessary and appropriate.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the
above order was adopted on the 16th day of November 2000 by a vote of 7-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board