ORDER OF THE BOARD
(By J
Yi):
On March
14,
1996,
the Illinois Environmental Protection
Agency (Agenoy)
filed a “Motion to Postpone Filing an Answer and Record”.
The Agency requests an
extension until July 29,
1996 to
file its answer.
The deadline in this matter has been
waived through September 30,
1996.
The parties are presently
involved in discussions
towards resolution of the issues on appeal.
The Agency contends that the ffling of the
answer is not necessary at this time.
The Agency believes that filing of the answer by
July 29,
1996 will allow sufficient time for notice,
briefing and decision by the Board.
The Agency indicates that petitioner has no objection to
the extension.
As of the date
of this order THF Belleville, L.P.,
has not filed a response.
The Board encourages negotiated settlements of permit appeals, and does not
object to
the grant of an extension of time for filing
the Agency’s answer.
The Board,
however, also encourages expeditious
resolution of cases before it.
Granting an
extension for filing an answer may provide excessive delay if the parties become aware
that negotiations are not going
to lead to a workable settlement.
The Board
therefore grants the Agency’s motion for an extension of time to file
its answer. However, due to the statutory decision deadline and the time necessary to
schedule a hearing
in this matter we will only grant the Agency’s request until June 28,
1996.
The Agency must file its answer on
Or before June 28,
1996.
IT IS
SO ORDERED.
2
I, Dorothy M. Gunn, Clerk of the Illinois Pollution
Control Board,
hereby
certify
that the above order was adopted on
the
~2/~’
day of/~‘~?~2~
~L’
,
1996,
byavoteofltO.
Dorothy M’~f3unn,Clerk
Illinois Pdlfution
Control Board