ILLINOIS POLLUTION CONTROL BOARD
    October
    19,
    1995
    ROBERT SCHWAKE STONE COMPANY,
    )
    INC.,
    )
    Petitioner,
    )
    v.
    )
    PCB 94—137
    (UST Fund)
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    ORDER OF THE BOARD
    (by M. McFawn):
    This matter is before the Board on a stipulation of
    settlement and dismissal,
    filed jointly by petitioner Robert
    Schwake Stone Company,
    Inc.
    (Schwake) and respondent Illinois
    Environmental Protection Agency
    (Agency)
    on October 10,
    1995.
    The parties stipulate that the Agency will approve reimbursement
    to Schwake from the Underground Storage Tank Fund for the
    following costs:
    1)
    $11,378.31 for costs previously denied as
    lacking supporting documentation;
    2)
    $2,728.46 for costs
    previously denied as costs associated with a tank ineligible for
    reimbursement; and 3)
    $295.00 for cost previously denied as costs
    not demonstrated to be reasonable.
    The Agency has agreed to
    reimburse these costs based on Schwake’s submittal of additional
    documentation and clarification of costs.
    All other costs for
    which reimbursement was denied in the invoice voucher dated March
    8,
    1994 shall not be reimbursed.
    Based upon this agreement,
    Schwake withdraws and dismisses its petition in this matter.
    This matter is dismissed and this docket is closed.
    IT IS SO ORDERED.
    Board Member 3. Theodore Meyer concurred.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certif~ythat the above order was adopted on the
    /
    ~
    day of
    __________________,
    1995, by a vote of
    7
    C
    Control Board

    Back to top