ILLINOIS POLLUTION CONTROL BOARD
June 28,
1973
MISSISSIPPI LIME COMPANY,
Petitioner,
vs.
)
PCB 73—12
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
ENVIRONMENTAL PROTECTION AGENCY,
Complainant,
vs.
)
PCB 73—35
MISSISSIPPI LIME COMPANY,
a
Missouri Corporation and
INTERNATIONAL GREAT LAKES SHIPPING)
COMPANY,
an Ohio Corporation,
Respondents.
Michael
A.
Snyder, Attorney for Mississippi Lime Company and
International Great Lakes Shipping Company
Kenneth Gun-ibiner, Assistant Attorney General for the EPA
OPINION AND ORDER OF THE BOARD
(by Mr. Henss)
Mississippi Lime Company operates a facility at 12200 South
Stony Island Avenue, Chicago for the transfer of lime from barges
to storage bins and thence to trucks.
The Company filed a request
for variance stating that the facility in two specific respects
fails to meet emission standards contained in Chapter
2 of the
Regulations of the Illinois Pollution Control Board and in the
Regulations Governing the Control of Air Pollution.
The Company
stated that it was installing control equipment and expected to
be in compliance with the Regulations by late September 1973.
Two weeks after the filing of the variance request, the EPA
filed an enforcement action alleging that Mississippi Lime had
discharged particulate matter,
i.e.
limestone dust,
into the
atmosphere
in
excess
of
amounts
allowed under Rule 3—3.111 of the
8
—
395
—2—
Rules and Regulations Governing the Control of Air Pollution and
had installed equipment capable of contributing
to or preventing
air pollution without first obtaining
a permit from the EPA.
International Great Lakes Shipping Company, which is said to
be the operator of a bucket and crane for unloading pebble lime
from barges, was also prosecuted for its discharge of particulate
matter.
The variance and prosecution cases were consolidated for
hearing.
When the cases were called for hearing, the parties submitted
a Stipulation of Facts.
In essence, the Respondents admitted the
alleged violations although Mississippi Lime denied that the violations
were as frequent as claimed by the EPA.
Testimony by R.
W. Woodcock, Vice-President
-
Traffic,
indicated
that the facility is primarily a transfer point for limestone
products produced at Respondent’s
St. Genevieve, Missouri processing
plant.
Traffic through the facility in 1972 consisted of about 320
barges unloaded and about 20,000 trucks loaded out.
Woodcock
estimated that the annual throughput was about 465,000 tons.
The
facility is located in a highly industrialized area on Lake Calumet
Harbor at a point over
1 mile from the nearest residential area.
One of the chief sources of emissions is the barge unloading
area.
Here
a clamshell bucket owned by International removes the
pebble lime from barges and transfer it to a large receiving hopper
on Mississippi Lime property.
From the receiving hopper, the lime
is moved to an inclined belt conveyor which feeds an elevator-
bucket system which discharges
to
a diversion storage bin which
ultimately feeds
4 storage bins.
Each bin has a capacity of 500
tons.
The control equipment for this source will consist of a
fabric dust collector
(baghouse)
to collect limedust at the emission
points.
The second major source of emissions is at the discharge spouts
where lime
is unloaded from the
4 storage bins into trucks.
Murney
testified that
a similar but smaller dust collection control system
would be installed at these sources.
Respondent estimates that upon
completion of the control systems, emissions will be about
5 lbs.
per hour.
Agency calculations show that the allowable emission rate
at this facility is about 53 lbs.
per hour.
At least 228 lbs. per
hour are now discharged.
Respondents seek variance from Chapter
2, Air Pollution Control
Regulations,
Rules 203(a),
203(b)
,
203 (f) (1)
,
203(f) (2)
,
203 (f) (4),
and Rule 3-3.111 of the Rules and Regulations Governing the Control
of Air Pollution.
We agree that Respondent’s operation is
a
“process” within the meaning of those Rules and that the Rules are
8
—
396
—3—
applicable here.
However,
Respondent does not require
variance
from Rules 203 (a)
and 203 (b).
As provided in Rule 203(1) (2),
Respondent’s operation is currently governed by Rule 3-3.111
until December 31,
1973,
at which time Respondent must come
into compliance with Rule 203 (a).
Since Respondent has requested
variance only until October
31,
1973, we believe the requested
variance from Rule 203(a)
is moot at this
time.
We note that the Agency’s estimated emission rate of 228
lbs. per hour did not include emissions from stockpiles, unpaved
roadways and truckloading spouts.
If such emissions were included
the total emission rate would be considerably higher.
However,
we were not provided an estimate of what the higher figure would
be.
Agency personnel operated a hi-vol sampler near the facility
from July 5,
1972
to July 13,
1972.
This surveillance revealed
that suspended particulates near Respondent’s facility ranged
from a high of 1,367 micrograms per cubic meter to a low of
205
micrograms per cubic meter.
Five of the eight daily readings
exceeded 700 micrograms per cubic meter.
Mississippi Lime is installing over $200,000 in abatement
equipment,
and in addition has undertaken the blacktopping of
the entire area in an effort to reduce emissions from windblown or
traffic-induced fugitive dust emissions.
The company is currently
operating under
a variance from the Appeal Board for the City of
Chicago.
This variance requires the following timetable:
Modification of Receiving Hopper
—
Mid-February 1973
Dust Collection System --end of April 1973
Phototype Chut
--
late February 1973
Completion of Dust collecting system at loading chute
——
late September 1973
The Agency recommends that we deny
a variance on the ground
that Respondent had not been timely in implementing its control
program and that Respondent’s hardship was self-induced.
The record
does not support that Agency claim.
Although the possibility
exists that some phases of Respondent’s control program could
have been expedited somewhat, we are satisfied that Respondent has
honestly attempted to satisfy both the State and the City of Chicago
by investigating and then selecting equipment equal to the task at
hand.
Respondents contend that a denial of the variance would cause
layoff of personnel at the Chicago facility,
that 4 major area steel
producers would be denied a vital
source of lime required for their
process, that numerous northern Illinois and Indiana water companies
would be denied this source of lime necessary for water purification,
8—397
—4—
and, about 200 workers at the St. Genevieve, Missouri processing
plant would be layed off.
Since Respondent is within
5 months of completion of the
control program, we believe it is reasonable to allow the variance.
The large expenditure for control equipment
is a mitigating factor
in our assessment of a monetary penalty.
The emissions in this
case,
however, were heavy and the violation should not go un-
punished.
The Board believes that a monetary penalty in the amount
of $5,000 is appropriate under all of the circumstances.
ORDER
It is the Order of the Pollution Control Board
that:
1.
Petitioners Mississippi Lime Company and International
Great Lakes Shipping Company are granted
a variance
from Rules 203 (f) (1),
203 (f) (2)
,
203 (f) (4)
of
the
Air Pollution Control Regulations and Rule 3-3.111 of
the Rules and Regulations Governing the Control of
Air Pollution until October
31, 1973 for the install-
ation of control equipment pursuant to the schedule
contained in this Opinion.
2.
The variance is conditioned upon the submission of
monthly progress reports commencing July 1,
1973 to
the Agency describ!ng the status of construction and
installation of the control equipment and upon
a
showing of satisfactory progress in the installation.
3.
Petitioner shall,
by July 23,
1973, post a bond in
the amount of $50,000 for the period of one year in
a form acceptable
to the Environmental Protection
Agency, such bond to be forfeited in the event
Petitioner fails to install and operate the equipment
listed in the Stipulation of Facts presented in this
case.
The bond shall be mailed to Fiscal Services
Division, Illinois EPA,
2200 Churchill Road,
Springfield,
Illinois 62706.
4.
Mississippi Lime Company and International Great Lakes
Shipping Company shall, after October 31,
1973,
cease
and desist from their violations
of the Regulations
governing the emission of particulates.
5.
Respondent shall pay to the State of Illinois by
July 23, 1973 the sum of $5,000 as
a penalty for the
violations found in this proceeding.
Penalty payment
by certified check or money order payable to the State
of Illinois shall be made to:
Fiscal Services Division,
Illinois EPA,
2200 Churchill Road,
Springfield, Illinois
62706.
8
—
398
—5—
I,
Christan
L. Moffott, Clerk of the Illinois Pollution Control Board
hereby certify the above Opinion and Order was adopted this
28th
day of June,
1973 by
a vote of
4
toO.
8— 399