ILLINOIS POLLUTION CONTROL BOARD
    April 11, 1991
    ESG WATTS, INC.,
    Petitioner,
    )
    v.
    )
    ILLINOIS ENVIRONMENTAL
    )
    PCB 90-144
    PROTECTION AGENCY,
    )
    (Permit Appeal)
    )
    Respondent,
    )
    and
    PEOPLE OF THE STATE
    )
    OF ILLINOIS,
    )
    Intervenors.
    KEVIN
    T.
    NcCLAIN,
    of
    IMMEL,
    ZELLE,
    OGREN,
    NcCLAIN,
    &
    COSTELLO,
    APPEARED ON BEHALF OF PETITIONER;
    MARK V. GURNIK APPEARED ON BEHALF OF RESPONDENT; and
    KELLY
    A. O’CONNOR, ASSISTANT ATTORNEY GENERAL, APPEARED ON BEHALF
    OF INTERVENORS.
    OPINION AND ORDER OF THE BOARD
    (by J. Theodore Meyer):
    This matter
    is before the Board on a permit appeal filed by
    petitioner ESG Watts,
    Inc.
    (Watts)
    on August 1,
    1990.
    Watts asks
    this
    Board
    to
    review
    respondent
    the
    Illinois
    Environmental
    Protection Agency’s
    (Agency) June 29, 1990 decision denying Watts’
    application for a RCRA Part B permit for its proposed industrial
    waste treatment facility in Rock Island,
    Illinois.
    A RCRA permit
    is required by Section
    21(f)
    of the Environmental Protection Act
    (Act)
    (Ill.Rev.Stat.1989,
    ch.
    ill
    1/2,
    par.
    1021(f))
    and
    35
    Ill.Adm.Code
    703.121.
    At
    hearing
    on
    December
    10,
    1990,
    the
    Attorney General moved to intervene on behalf of the People of the
    State of Illinois.
    The hearing officer granted that motion,
    over
    Watts’
    objection,
    on December
    31,
    1990.
    All three parties filed
    briefs.
    For
    the
    reasons
    stated
    below,
    the Board
    affirms
    the
    Agency’s denial of the requested permit.
    Background
    This appeal is the continuation of a long history of dispute
    121—29

    2
    and
    litigation
    over
    Watts’
    proposed
    industrial
    waste
    treatment
    complex
    (complex
    or
    facility).
    Watts
    seeks
    to
    construct
    and
    operate this facility at 602 First Street in Rock Island, Illinois.
    The proposed
    facility would
    store
    and treat
    hazardous
    wastes,
    handling only water—based or
    aqueous waste.
    The facility would
    have eight treatment and receiving tanks and five tanks for storage
    of product chemicals, treated water,
    and waste oil for recycling.
    The complex is designed to treat and discharge 100,000 gallons of
    wastewater per day, with a daily maximum of 120,000 gallons.
    (P.
    at 30_38.)1
    The City
    of Rock Island originally denied site approval for
    the facility.
    On appeal, this Board found that the City’s decision
    was against
    the manifest weight
    of
    the evidence,
    and therefore
    reversed the denial.
    (Watts Trucking v. City of Rock Island, PCB
    83-167
    (March 8,
    1984).)
    The appellate court affirmed the Board’s
    decision (Braet v. Pollution Control Board, Nos.
    3-84—0193 and
    3-
    84-0221
    (unpublished decision, August 23, 1985)), and the Supreme
    Court
    of
    Illinois subsequently
    denied
    appellant’s
    petition
    for
    leave to appeal.
    (No. 62414, denied December 4, 1985.)
    Therefore,
    the site of the facility was approved and Watts proceeded to apply
    for construction and operation permits.
    On February
    10,
    1987,
    Watts submitted its application for a
    RCRA
    Part
    B
    permit
    for
    the
    construction
    and
    operation
    of
    the
    proposed
    facility.
    The
    application
    indicated
    that the
    treated
    wastewater
    was
    to
    be
    discharged
    into
    the
    City’s
    storm
    sewer,
    eventually
    being
    discharged
    into
    the Mississippi
    River
    under
    a
    NPDES permit.2
    (R. at 38-39.)
    The Agency sent Watts three notices
    of
    deficiency
    (March
    9,
    1987,
    August
    26,
    1987,
    and
    February
    8,
    1988),
    and Watts responded to those notices.
    On August 12,
    1988,
    the Agency
    issued
    a draft RCRA permit,
    tentatively deciding
    to
    issue the permit.
    (R.
    at
    323—324.)
    The Agency held
    a public
    hearing
    on
    the draft
    permit on December
    13,
    1988.
    (R.
    at
    586-
    788.)
    On November
    1,
    1988, Watts’ consulting engineer informed the
    Agency that Watts had changed the proposed routing of the treated
    1
    “P.”
    denotes the Agency’s record,
    filed with the Board
    on
    August 21,
    1990.
    2 Watts applied for an NPDES permit for the proposed facility
    on
    February
    11,
    1987.
    That permit was denied by the Agency on
    March
    30,
    1990.
    Watts appealed that decision to this Board,
    and
    the Board today decided that appeal in a separate proceeding.
    (PCB
    90—95)
    121—30

    3
    wastewater.3
    The engineer indicated that the original method
    of
    disposal
    (into the City’s storm sewer) was impossible because the
    storm sewer
    system is directly tied to the City’s sanitary sewer
    system.
    Therefore, Watts proposed to route the discharge directly
    to the Mississippi through construction of a private pipeline.
    (R.
    at 467.)
    This method would require an easement from the City to
    extend the pipeline under a city street.
    Watts notified the City
    of
    the change
    in plans
    on November
    3,
    1988.
    (R.
    at
    468.)
    On
    September
    6,
    1989,
    the Agency asked Watts whether
    it wished to
    continue pursuing the RCRA Part B permit, and
    if
    so,
    how it was
    planning to dispose of the treated wastewater.
    (R. at 513.)
    After
    obtaining two extensions
    of time to answer the Agency’s inquiry,
    on December 29,
    1989 Watts replied that it had been “dragging its
    feet” but that it wished to pursue the Part B permit.
    Watts stated
    that it hoped to be issued a permit “that would allow us to truck
    the water from the facility or use direct discharge,
    leaving both
    options open to us.”
    (R. at 517.)
    On
    February
    9,
    1990,
    the Agency
    formally
    asked
    Watts
    to
    provide information
    on the
    final
    disposition
    of the wastewater
    generated by the treatment facility.
    (P. at 519.)
    Watts supplied
    written responses on March
    9 and March 30,
    1990.
    Watts explained
    its difficulties in making arrangements for the disposal
    of the
    wastewater.
    Watts had not yet been able to obtain an easement from
    the City, nor had
    it been able to arrange for the use of a point
    along the Mississippi to which the wastewater.could be trucked.
    On
    March
    29,
    1990,
    Watts
    formally
    petitioned
    the
    City
    for
    an
    easement.
    That request was denied by the City.
    (Pet.
    Br. at 4.)
    On June 29,
    1990,
    the Agency denied the requested Part B permit.
    (P.
    at 1037-1041.)
    The denial stated:
    The permit
    is denied because the application has been
    deemed
    to
    be
    incomplete,
    on
    the
    grounds
    that
    the
    applicant has not demonstrated there
    is
    an acceptable
    means to dispose of the treatment plant wastewater.
    The
    disposition
    of the treated wastewater has significant
    potential to cause environmental damage
    if disposed of
    improperly
    and
    is
    an
    integral
    part
    of
    being
    able to
    provide
    a
    service
    as
    a
    hazardous
    waste
    treatment
    facility.
    The Agency does not feel that issuance of
    a
    permit without a feasible discharge point is protective
    of the environment.
    Without a feasible discharge point,
    the facility operations could result in the indefinite
    storage of wastes at the site if the company was unable
    to resolve its problem.
    (P.
    at 1041.)
    The November 1, 1988 letter states that Watts had indicated
    during an October
    4,
    1988 meeting with the Agency that the route
    of disposal had changed.
    12 1—31

    4
    The Agency cited 35 Ill.Adm.Code 705.123
    in support of its denial
    on
    grounds
    of
    failure to correct the deficiency.
    That section
    reads in part:
    If an applicant fails or refuses to correct deficiencies
    in the application, the permit may either be denied or
    issued
    on
    the
    basis
    of
    information
    available
    to
    the
    Agency...
    The Agency stated in its denial letter that it had concluded that
    the missing information “is of such vital importance to the permit
    decision
    that
    issuance
    of
    a
    Part
    B permit
    with
    a
    compliance
    schedule or some
    other mechanism for obtaining information would
    not
    be
    feasible.”
    (R.
    at
    1038.)
    Watts filed
    its petition for
    review of the Agency’s decision with the Board on August
    1,
    1990.
    Issue Presented
    When reviewing a permit decision made by the Agency, the issue
    before the Board
    is whether the permit application,
    as submitted
    to
    the Agency,
    demonstrates that the issuance
    of the requested
    permit
    will
    not
    violate
    the
    Act
    or
    the
    Board’s
    regulations.
    (Joliet Sand
    & Gravel v. Illinois Pollution Control Board
    (3d Dist.
    1987),
    163
    Ill.App.3d
    830,
    516 N.E.2d
    955,
    958.)
    In
    order
    to
    reverse a permit denial, the petitioner must demonstrate that its
    permit application met that standard:
    that no violation of the Act
    or Board regulations will occur
    if the permit is granted.
    (Waste
    Management,
    Inc.
    v.
    Illinois Environmental Protection Agency,
    PCB
    84—45,84—61,
    and 84—68
    (Cons.)
    (November 26, 1984); aff’d sub
    noin.
    Illinois Environmental Protection Agency v. Pollution Control Board
    (3d Dist.
    1985),
    138 Ill.App.3d
    550,
    486 N.E.2d
    293,
    93 Ill.Dec.
    192, aff’d 115 Ill.2d 65, 503 N.E.2d 343, 104 Ill.Dec. 786 (1986).)
    Thus,
    in this case Watts must demonstrate that the grant
    of
    the
    permit
    without
    a
    specific
    method
    of
    disposal
    of
    the
    treated
    wastewater will not violate the Act or rules.
    Discussion
    Watts raises several arguments in support of its position that
    the RCRA Part B permit
    should be
    issued.
    First,
    Watts contends
    that
    the
    Agency
    is
    estopped
    from
    asserting
    that
    the
    permit
    application
    is
    incomplete.
    Watts
    maintains
    that
    the
    Agency’s
    February
    9,
    1990 letter requesting
    information on the method
    of
    disposal
    did
    not
    state
    that
    the
    information was
    necessary
    to
    correct a deficiency,
    although several earlier deficiency letters
    had been issued to Watts.
    Watts also states that the Agency had
    previously determined
    that the application was .complete,
    before
    deciding to issue the 1988 draft permit.
    Therefore, Watts asserts
    that the Agency
    is estopped from contending that the application
    is incomplete when it had already determined,
    at an earlier time,
    that the application was
    complete.
    Watts also contends that the
    121—32

    5
    Agency waived
    its
    right
    to
    determine that
    the application
    was
    incomplete when it failed to raise that point “on a timely basis”
    prior to the issuance of the denial.
    In response,
    the Agency points out that although the Agency
    did at one time determine that the application was complete, that
    early determination was made well before Watts informed the Agency
    that it was having difficulties securing a discharge point for the
    treated wastewater.
    The Attorney General also argues that Watts’
    claim
    of estoppel
    is
    inappropriate.
    The Attorney General notes
    that the application was found incomplete only after Watts changed
    its application
    to
    omit
    the specific
    point
    of
    discharge.
    The
    Attorney
    General
    maintains
    that
    the
    Agency
    did
    not
    make
    any
    misrepresentations or conceal any material
    fact,
    and that Watts
    could not reasonably rely on the Agency’s early determination of
    completeness after Watts modified the application, since Watts knew
    of that modification.
    Therefore, the Attorney General argues that
    Watts cannot avail itself of the doctrine of estoppel because none
    of the necessary elements
    of estoppel are present
    in this
    case.
    (See City of Mendota v. Pollution Control Board
    (3d Dist.
    1987),
    16 Ill.App.3d 203,
    514 N.E.2d 218,
    222.)
    The Board agrees with the Agency and the Attorney General that
    the doctrine of estoppel is not applicable to this case.
    Although
    the Agency
    did,
    at one time,
    determine that the application was
    complete, the Board believes that the Agency was not bound by that
    determination after Watts modified its application to reflect the
    uncertainty of the method of discharge.
    The method of discharge
    of treated wastewater is certainly not a minor modification. This
    is especially true where, as here, the application was changed to
    show uncertainty, rather than simply reflecting a definite change
    in the disposal method.
    After such a change,
    the Agency
    is free
    to
    find
    that
    it does
    not
    have
    enough
    information
    to
    make
    an
    informed decision on the permit.
    Additionally,
    as the Attorney
    General
    points
    out,
    the
    necessary elements
    of
    estoppel
    are not
    present in this situation.
    Watts
    does not even allege that the
    Agency made any misrepresentations or concealed any material fact.
    The Board finds that the Agency
    is not estopped from determining
    that Watts’
    application was incomplete.4
    Second, Watts contends that the Agency’s denial of its permit
    is
    not well-founded.
    Watts
    maintains
    that the Agency
    did
    not
    The
    Board
    notes
    that
    Watts
    implies
    that
    the
    Agency’s
    February
    9,
    1990
    letter
    formally requesting
    information on
    the
    method
    of discharge did not rise to the
    level
    of
    a
    deficiency
    letter.
    Although it might have been better practice for the Agency
    to
    issue
    a
    formal deficiency
    letter,
    as
    it had previously,
    the
    Board finds that the text of the letter should have put Watts on
    notice that the Agency felt that more information on the discharge
    method was essential to its determination.
    121—33

    6
    produce any evidence to show that the facility,
    if the permit was
    granted, would create environmental harm or “be in violation of any
    statute
    or regulation promulgated by the Agency.”
    (Pet.
    Br.
    at
    12.)
    Watts
    argues that the RCRA Part B permit application was
    submitted
    for
    the
    purpose
    of
    constructing
    a
    hazardous
    waste
    facility, not
    for the purpose of disposing of hazardous or
    non-
    hazardous waste.
    Watts
    further alleges that it
    is “uncontested”
    that the construction and operation of the facility would conform
    to
    federal
    and
    state
    guidelines
    for
    RCRA
    operation
    and
    construction.
    Watts contends that the City of Rock Island’s denial
    of its petition for easement merely delayed the planned method of
    discharge,
    and that the problems with the City
    should have
    no
    bearing on the
    RCRA
    Part B permit.
    Finally, Watts maintains that
    the Agency should not deny a permit because .the proposed method of
    disposal
    is
    subject to
    a local
    zoning ordinance.
    In support of
    this last claim,
    Watts cites County of Lake v. Pollution Control
    Board
    (2d Dist.
    1983)
    ,
    120 Ill.App.3d 88,
    457 N.E.2d 1309,
    1316,
    and Carlson
    v. Village of Worth
    (1975),
    62 Ill.2d 402,
    343 N.E.2d
    493.
    The
    Agency
    contends
    that,
    contrary
    to
    Watts’
    claims,
    the
    Agency must be concerned with Watts’
    ability to dispose of
    the
    wastewater.
    The Agency states that the wastewater
    is regulated
    under
    the
    RCRA
    program
    until
    it
    is
    discharged,
    when the NPDES
    program
    takes
    control.
    35
    Ill.Adm.Code
    721.104(a) (2)
    and
    corresponding
    Board
    note.
    The
    Agency
    notes
    that the
    proposed
    facility
    will
    have
    one
    20,000
    gallon tank
    for
    the
    storage
    of
    treated wastewater,
    but that the facility
    is expected to have an
    average daily
    flow of
    100,000
    gallons.
    Thus,
    the Agency argues
    that
    if
    the
    facility were to
    begin
    operation without
    means
    for
    wastewater disposal, the facility would almost immediately become
    an
    indefinite storage facility and would be
    in violation of
    its
    permit.
    The Agency notes that there may be alternative methods for
    wastewater disposal, but points out that Watts never gave it (the
    Agency)
    any specific or concrete information on Watts’
    ability to
    pursue those alternatives.5
    The Agency also contends that this
    permit
    appeal does not involve the propriety
    or
    impropriety of
    struggles between the facility and the local government.
    Finally,
    The Agency also points out that even if Watts can obtain the
    easement
    for construction of
    its pipeline or
    obtain the use
    of
    discharge point to which the wastewater
    could
    be trucked,
    those
    discharge points would have to have their own
    RCRA
    Part B permit.
    This is because the wastewater would still be regulated under PCRA
    and the discharge point would be accepting hazardous waste
    for
    disposal.
    35 Ill.Adm.Code 703.122(b).
    In its reply brief,
    Watts
    challenges the citation to this section, stating-that the section
    refers to owners
    or operators
    of publicly owned treatment works
    (POTW) and thus does not apply to Watts.
    The Board points out to
    Watts
    that
    only
    a
    portion
    of
    Section
    703.122(b)
    is
    limited
    to
    POTWs.
    12 1—34

    7
    the
    Agency
    maintains
    that
    this
    case
    does
    not
    involve
    the
    application of a local zoning ordinance, because an easement is not
    a zoning ordinance.
    After reviewing the arguments presented by Watts, the Agency,
    and
    the
    Attorney
    General,
    the
    Board
    concludes
    that
    Watts’
    application did not demonstrate that the grant
    of the requested
    permit,
    without
    a
    specific method of discharge
    for the treated
    wastewater, would not violate the Act or the rules.
    The Agency is
    correct in its belief that the method of discharge of the treated
    wastewater
    is an integral part of the operation of the proposed
    facility.
    A hazardous waste remains subject to RCRA regulation
    until that waste is discharged pursuant to an NPDES permit.
    35
    Ill.Adin.Code 72l.104(a)(2).
    Without knowing what will happen to
    the wastewater between the time that it is treated and when it is
    disposed
    of,
    the Agency
    cannot
    know
    if the wastewater will
    be
    handled properly.
    Therefore,
    it
    is
    impossible for the Agency to
    determine whether granting the permit would result in a violation
    of the Act or Board regulations.
    The Board notes that,
    contrary
    to Watts’ claim, the Agency need not produce evidence to show that
    the facility would cause environmental harm or violate the Act or
    Board
    (not Agency)
    regulations.
    That burden is on Watts.
    Watts’
    contention
    that
    caselaw
    prevents
    the
    Agency
    from
    denying
    a
    permit
    because
    of
    local
    zoning
    ordinances
    is
    not
    applicable here.
    This case involves
    a
    request for an easement,
    which is not a zoning issue.
    The issue presented in this case
    is
    Watts’ failure to identify a discharge point or method of discharge
    for the treated wastewater, not whether Watts is able to ultimately
    obtain an easement from the City.
    Watts’
    problems with the City
    of Rock Island are not at
    issue
    in this appeal.
    The only
    issue
    before the Board is whether Watts’ has demonstrated that the grant
    of the permit, without an identified disposal method, would violate
    the Act or the regulations.
    The Board finds that Watts has not
    made that showing.
    Therefore,
    the Agency’s denial of the permit
    on grounds of incompleteness is affirmed.
    This opinion constitutes
    the Board’s
    findings
    of
    fact and
    conclusions of law.
    ORDER
    The Agency’s June 29,
    1990 denial of ESG Watts’ RCRA Part
    B
    permit application for a hazardous waste treatment facility in Rock
    Island,
    Illinois, on grounds that the application was incomplete,
    is affirmed.
    IT IS SO ORDERED.
    12
    1—35

    8
    I, Dorothy N.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the a)ove 9pinion and Order was adopted
    on
    the
    //~7_~day
    of
    _______________,
    1991,
    by
    a
    vote
    of
    7-ô.
    Dorothy N.4unn,
    lérk
    Illinois P~,1lutionControl Board•
    12 1—36

    Back to top