1. penalty. See Wasteland, Inc., (Case No. 33, Standard Scrap
      2. Metal, Case No. 36).
      3. 3. Other Considerations
      4. a. Aiding Enforcement by Deterring Others
      5. b. Economic Benefit From Non—Compliance
      6. 111—47
      7. factor to non—governmental entities.
      8. Consideration of the economic benefits of non—compliance
      9. became part of the statutory factors listed in Section 33(c) when
      10. Sec.tion 33(c)(5) was added in 1987. That Section now requires
      11. the Board to consider “any economic benefits accrued by a non-
      12. 111—48
      13. Id., 491 N.E.2d at 1257
      14. 11 1—4”
      15. $1,125,000. This is about half of what USEPA highlighted for
      16. penalties against non—municipalities for RCRA and Clean Water Act
      17. d. Cessation and Duration of Violation
      18. * Any subsequent compliance. Section33(c) (6).
      19. significant:
      20. 111—55
      21. 111—5’)
      22. total Kjeldahl nitrogen (“TKN”) (nitrogen compound) violations,
      23. were multiplied by the days of violations and tallied to arrive
      24. at a final penalty. Briefly summarized, the compone’nts were as
      25. follows (the Board notes that the figures in “B” are taken
      26. directly from the court’s Appendix B; however, there appea.rs to
      27. be $1,000 discrepancy in the court’s addition):
      28. A. Chlorination viclations
      29. —gravity corrpcnent
      30. winter ‘81—82:
      31. $166,050—further adjustrr~nts:
      32.  
      33. C. Other Federal Decisions
      34. 11 1—65
      35. ii 1—66
      36. 111—67
      37. 111—69
      38. Economic benefit from noncompliance S 8,000
      39. Recalcitrance or indifference re:Compliance Schedule ($750 x 714 days) $ 535,500
      40. Subtotal S 577,650
      41. illegal activity;
      42. (d) cause of the discharge or violation;
      43. It 1—74
      44. RCRAjudicial $96,479 $209,791 $1,100,000administrative 9,440 17,576 150,000
      45. figure
      46. judicialadministrative
      47. $78,000 $96,218 $ 280,00012,500 15,620 60,000
      48. Table 5: Illinois Civil Penalties Reviewed by Supreme Court
      49. 1975 Southern Illinois Asphalt $ 5,000(2 cases consolidated) $11,000
      50. Petitioner Board
      51. 19751975
      52. 19761976
      53. 250—0—
      54. $25,000—0—
      55. 111—77
      56. 1989 Perkinson/Porkville
      57. Remanded
      58. 19801983
      59. Ii 1—78
      60. Petitioner
      61. Permit Cases (Air/Water/Land)
      62. Board AppellateCourt
      63. 197519751976
      64. 19771981197819821983197319861989
      65. 19841990
      66. $10,000
      67. —0—S 1,000
      68. —0—$ 1,000
      69. 3. Recent Stipulated Penalties
      70. Highlake PoultryFreeman Coal Mining (air)Hindman
      71. 280,000
      72. Clean Water Act 139,834 13,545RCRA 209,791 ~7,576
      73. Section 33(c)(5)
      74. 3. Suitability/Unsuitability of Pollution Source to ItsLocale
      75. 5. Economic Benefits of Non—Compliance
      76. Board Member Joan Anderson concurred.
      77. Dorothy M. ~inn, Clerk
      78. Illinois Po~lutionControl Board
      79. Exhibit A
      80. CWA Penalty Summary Worksheet
      81. (7) Litigation Considerations

ILLINOIS POLLUTION CONTROL BOARD
May
10,
1990
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Complainant,
v.
)
PCB 88—71
(Enforcement)
ALLEN BARRY,
individually and
ALLEN
BARRY,
d/b/a
ALLEN
BARRY
LIVESTOCK,
Respondent.
MS.
PAM
CIARROCCHI,
ASSISTANT
ATTORNEY
GENERAL,
APPEARED
ON
BEHALF
OF
THE
COMPLAINANT;
AND
MR.
DONALD
A.
MANZULLO,
P.C.,
APPEARED
ON
BEHALF
OF
THE
RESPONDENT.
OPINION AND ORDER OF THE BOARD
(by
B.
Forcade):
This matter comes before the Board
on the April
19,
l98~8
complaint of
the Attorney General,
filed on behalf of
the
Illinois Environmental Protection Agency
(‘Agency”).
The
complaint alleges
that respondent, Allen Barry,
individually and
d/b/a Allen Barry Livestock
(“Allen Barry”)
violated Sections
12(a),
~d) ano
(f)
of the Illinois Env~rornenral Protect~o~-’Act
(“Act”)
tne
~ater cuality standaras
in
35
111
?o~ Coca
02
203
and
302 212
tr-e
eff1ue~itsta~carcsof
35
Ill
~cn
Coca
304
lOS
and the oDerational
rules and oermit
recuirements
for acricuiture
related oollutjon
in 35111.
Adm.
Code 301.403(a), 50l.404(b)(l)
and 502.104.
The Acencv comDlalr.t details
the vIolations
in
itur
counts described below.
A Stipulation and Proposal
for
Settlement
was
filed
April
12,
1989,
leaving the issue of
a
penalty
for the Board’s decision here.
Procedural
History
Hearinc
is mandatory pursuant
to Section
33
of
the Act and
the case was acceDted
for hearinc
at
the Aori!
21,
1988 Board
meetinc.
Hearing was held
on January
10,
1989, and continued
to
March
14,
1989.
No
member
of
the oublic was
in attendance.
The
parties
rii~ed tne executec
Stipulation
and
Proposat
tor
Settlement
on Aoril
12,
1989.
The Agency’s Dost-hearlnc brief
support of
a penalty
was
filed May
1,
1989.
Alien Barry’s brief
in oPposition
to a penalty was filed May
22, l~89.
111-11

The Facility
Allen Barry owns and operates
a livestock operation,
known
as
Allen Barry Livestock
in Ogle County,
Illinois.
The
confinement operation handles more than
300 brood cows and
slaughter
or
feeder cattle on an ongoing
basis.
The facility
includes feedlots and
at
least one manure storage pile.
A man-
made drainage ditch collects runoff
from these.
Rufloff,
via a
man—made drainage ditch and
in part via direct drainage,
to an
unnamed tributary
to Mill Creek
in Ogle County
is
the subject of
this enforcement action.
Comolaint:
Counts
I
through Count
IV
Count
I alleges
that
on or about July
27,
1982,
and
continuing intermittently through April,
1988,
Allen Barry
violated Section
12(a)
and
(d)
of
the Act.
Those subsections
govern the discharge
or demosit
of
contaminants
which
cause
or
Leno
to
cause
water
collut~on
or
wnicn
create
a
water
pollution
hazard.
Allen
Barrys
operations
allegedly
discharged
contaminants, livestock waste and feedlot
runoff
into the unnamed
tributary of Mill Creek.
Agency personnel witnessed
this
discharge
on July
27,
1982, November
5,
1985,
April
22,
1987,
and
February
18,
1988.
The discharge allegedly altered the chemical
and
biological
nature
of
the
water
resulting
in
harmful
or
injurious conditions
for fish
or
aquatic
life
and
harmful
conditions
for public health.
Count
II alleges
that Allen Barry has confined more than 300
brood cows and cattle
in
its ongoing operation while at
no
time
possessing
a National Pollutant Discharge Elimination System
(“NPDES”)
permit
for
the
related discharges.
This
is an alleged
violation of Section
12(f)
of
the Act,
which requires an NPDES
permit
for point source discharges.
On or about July
27,
1982
through April,
1988,
Allen
Barry also allegedly violated
33
Ill.
Adm. Code 501.403(a),
50l.404(b)(l), and 502.104.
These sections
recuire
that livestock
facilities maintain diversion dikes, wails
or curbs
to control surface waters and contain runoff;
that
manure
stacks
be
managed
to
prevent
runoff
and
leachate
from
entering state waters; anc that NPDES permits
oe ontatnec
for
facilities of
a ce~teins~ze~n~cn disc-~argeDolute-~ts into
navigable waters directly or
through man—made devices.
Count
III alleges
that Allen Barry violated the ;~ater
Quality Standard regulating unnatural
sludge as found
in
35
Ill.
Adm.
Code
302.203 and the effluent standard stated
in
35
Ill.
Adm. Code
304.103 regulating effluents wnich cause
a violation of
water quality standards.
The Agency alleges that
on or
about
July
27,
1982 and continuing through April,
1988,
Allen Barry’s
oDerations
caused
or
contr:buted
to
murky,
brownish,
or
turbid
water and manure odors
in
the unnamed tributary.
These
conditions
were specifically noted by the Agency on July
27,
1982,
November
5,
1983,
and April
22,
1987.
Allen
Barry thereby
allegedly violated Section
12(a)
of
the Act and
35
Ill.
Adm. Code
302.203
and
304.103.
111-12

Count
IV alleges
that Allen Barry violated Section
12(a)
of
the Act and
33
Ill. Adm. Code 304.105 also noted
in Count
III and
the particular
water quality standard for ammonia nitrogen.
Pursuant
to
35
Ill. Adm. Code
302.212, ammonia nitrogen may not
exceed
15 mg/l
(milligrams per liter).
On November
15,
1985 and
on February
18,
1988,
levels of
59.0 mg/l and 18.5 mg/l were
recorded.
The Agency alleges
that on
or about July’27,
1982
through April,
1988,
Allen Barry therefore was
in violation of
Section
12(a)
of
the Act and 35
Ill. Adm.
Code 302.212 and
304.105
including,
but
not limited
to,
the two particular dates
above.
The Agency alleces
that the violations described
in Counts
I
through
IV
above
were continuing violations
from July
27,
1982
through the April,
1988 complaint date and that they
will
continue unless halted by
the Board.
The relief
recuested
is
that
the Board direct Allen Barry
to cease and desist from
further
vtolations,
that
the
Board
assess
a
penalty
not
to
exceed
$10,000
for Count
I violations and $1,000 per
each day during
which
the violations continued.
StiDulation
The Stipulation and Proposal for Settlement
(with
Exhibits
A
through
F) was executed in March of
1989 and filed with the ~oard
on April
12,
1989.
It
sets
forth
facts noted
in the facility
description above and acknowledges
that pursuant
to Section
31(d)
of the Act,
notice of apparent violations was given
to Allen
Barry by letters dated October
15,
1982 and December
18,
l98~5.
(Exhibits A and B.)
The following additional
facts are
stioulated
by
the
carties.
Allen Barry’s livestock operation,
a sole ~roorietorship,
discharged
runoff from
its feedlots.
Those discharges requ:re
a
NPDES permit.
At
no time has Allen Barry possessed,
nor has the
Agency
issued,
an
NPDES
permit
for
those
discharges.
Alien
Barry
caused,
threatened
or allowed contaminants,
livestock waste
and
feedlot
runoff,
to be discharged upon
the land and
into
the
unnamed tributary of Mill Creek,
a water
of
the State
of
Illinois,
so as
to cause or
tend
to cause water pollution
in
Illinois.
These
discharges
were
observed
on
or
about
July
27,
1982,
November
5,
1985,
Aoril
22,
1987,
and February
18,
1988,
by
Acenc~’oerso~ e
~o
.t~’essect’~eo~ect ctsc~a~geof l~esrock
waste
and
feeclot
runo:f
~n:o
me
unnarnec
trtoutary wnich
intersects
and
runs
through
Responcent’s
property
:rcm
sou:n
to
north and empties
into Mill Creek.
(Ex.
C).
On July
27,
1982;
November
5,
1983;
April
22,
1987;
and
February
18,
1988, water samples were taken at and around Allen
Barry’s
facility.
These samples showed violations
of water
quality
standards
contained
in
the
Board
regulations
for
unnatural
sludge
and
ammonia
nitrogen.
(Ex.
D).
111-13

The Terms of Settlement
provide that
it shall
be
a
full
settlement of
the action filed by
the Agency and Allen Barry’s
liability for all violations
alleged
•in the complaint.
The
Agency contends,
and Allen
Barry admits,
that
the facts
as set
out
in the Complaint constitute
the following violations of the
Act and Board Regulations:
Count
I:
Section
12(a)
and
12(d)
of
the
Act
as
these sections relate to livestock waste;
Count
II:
Section
12(f)
of
the Act and 35
Ill.
Adm.
Code 501.403(a)
and 502.104;
Count
III:
Section
12(a)
of
the Act and
35
Ill.
Adrn.
Code 302.203 and 304.103;
Count
IV:
Section
12(a)
of
the Act and
35
Ill.
Adm.
Code 302.212 and 304.103.
Allen Barry does
not admit
the violation of
33
Ill.
Adm.
Code
501.404(b)(l)
alleged
in Count
II.
That section
regulates
handling and storage of livestock waste
in temporary manure
stacks
to prevent
runoff and leachate problems.
Allen Barry agrees
to cease
and desist from any and all
violations
of the Act and Board
regulations.
As
a remedial
course of action, Allen Barry agrees to submit
to the Agency by
April
25,
1989 specifications
for the construction of
a livestock
waste handling
facility,
in accordance with the Act and Board
regulations,
Such construction must be implemented by Allen
Barry within
180 days after Agency approval and must
be completed
in accordance with Agency approved specifications no
later
than
August
1,
1990.
Allen Barry agrees
to apply
for and obtain an NPDES permit
concurrent
with
the start of
construction of
its livestock waste
handling
facility.
With respe~t to the unnamed
tributary
on
the
eastern portion of his property, within 180 days of approval of
this settlement, Allen
Barry agrees
to do the
following:
1.
place
a
fence
25
feet
from each
side
of
the tributary;
2.
plant
dense
vegetation
within
this
25—
foot
area;
3.
maintain
one
area
for
crossing
this
tributary;
and
4.
maintain a vegetative cover
on pasture.
Allen Barry agrees
to act
in accordance with all terms
and
conditions of all permits
issued
by the Agency.
11 1-~1~

The parties have notstipulated
to
a civil penalty
to be
paid by Allen Barry for violations
of
the Act and regulations.
The Agency recuests a penalty of u~to $10,000 and Exhibits A
through E
in support
of
a penalty.
Allen Barry argues that
no
penalty
is necessary and provided Exhibit
F
in support of
that
position.
Exhibits A through
F amount to about
78 pages of
various documents,
including correspondence since
1982 and
inspection
reports.
Statutory Penalty Authority
As
part of
a final order
in an enforcement case,
Section
33(b)
empowers the Board
to impose civil penalties
in accordance
with Section
42 penalty provisions.
Generally,
Section 42(a)
and
(b)
of
the Act provides
for ootential civil cenalties
of
UD
to
$10,000 per violation and up
to $1,000
per day.
Ho~ever,certain
violations,
such as
of Section 12(f),
carry a $10,000
per day
penalty.
Subsections
42(a)
and
(b)
provide
in pertir.ent
part:
a.
Except
as
provided
in
this
Section,
any
person
that
violates
any
provisions
of
this Act or any regulation adopted by
the
Board,
or any permit or term or condition
thereof,
or
that
violates
any
determi-
nation
or
order
of
the Board pursuant
to
this
Act,
shall
be
liable
to
a
civil
penalty of
not
to exceed $10,000
for
said
violation and an additional civil penalty
of
not
to
exceed
$1,000
for
etch
day
during which violation continues;
b.
Notwithstanding
the
provisions
of
subsection
(a)
of this Section:
1.
Any
person
that
violates
Sectton
12(f)
of
this
Ac:
or
any
NPDES
permit
or
term
or
condition
thereof,
or
any
filing
requirement,
regula-
tion
or
order
relating
to
the
NPDES
permit
program
shall
be
liable
to
a
civil
penalty
of
not
to
exceed
$10,000 per day
of violation;
.
.
Ill.
Rev.
Stat.
ch. ll1~, par.
1042.
In an enforcement action Section
31(c)
of
the Act places the
burden of proof on the Agency or other
complainant
to
show
either
1
Effective January
1,
1990 penalty amounts increased
to S50,000
per violation and S10,000 per day,
but
these amounts are not
aoolicable
to the violations here,
which
are
from
the earlier
1982—1988
time period.
111-1S

that the respondent has caused or threatened
to cause air
or
water pollution or
that the respondent has violated or threatens
to violate any provision of
(thel
Act
or any rule or provision of
the Board.
If such proof
has been made,
the burden shall be on
the respondent
to show that compliance with the Board’s
regulations would impose an arbitrary or unreasonable hardship.
How this burden of proof
is carried was explained by
the
Illinois Supreme Court
in Incinerator,
Inc.
v.
Pollution Control
Board,
59
Ill.2d
290,
319
N.E.2d
794,
799
(1974).
There,
the
court
stated that
“the EPA had the burden of proving all
essential elements of
the type of
air pollution violation
charge~d, and the Board must
then assess
the sufficiency of
such
proof
by
reference
to the
Section. 33(c)
criteria,
basing thereon
its findings and orders.”
The Suoreme Court
later clarified this
in Processing
&
Books,
Inc.
v.
Pollution Control
Board,
64 Ill.2d
68,
351 N.E.2d 865
(1976).
In
that
case,
the court stated
that
the
Incinerator
Inc.
case
was
not
intended
to
place
on
the
Agency
“the burden of proving,
by evidence which
it offered,
the
unreasonableness of the respondents’
conduct
in terms of each of
the four
criteria mentioned
in Section
33(c).”
That
interpretation would “frustrate the purpose of
the Act” and “also
render redundant
or contradict
the allocation of
the burdens of
proof
in Section
31(c).
Processing
&
Books,
351 N.E.2d at 869
(emphasis added).
As
to the Board’s responsibility
to evaluate the evidence
offered,
the Illinois Supreme Court
requires that unreason-
ableness of the alleged pollution must be determined with
reference
to the criteria stated
in Section
33(c).
Wells
Manufacturing Company
v.
Pollution Control Board,
73
Ill.2d
226,
383 N.E.2d~148
(1078),
citing Mvstik TaDe
v. Pollution Control
Board,
60 Ill.2d
330,
328 N.E.2d
5
(1975),
Incinerator,
Inc.,
59
Ill.2d 290
(1974) and Citvcf Monmouth
v. ?ollut~onControl
Board,
57
Ill.2d 482,
313 N.E.2d 161
(1974).
However,
this does
not require
that the Board find against
the respondent with
respect
to each of
the Section
33(c)
criteria.
Nor does
it mean,
“that
the Board
is ~rec1uded
from considering additional
relevant:
factors.”
Wells
Manuf~~rin~ç2moanv,
383
N.E.2d at
151.
See
also,
Southern Illinois Asohalt Comoany,
Inc.
‘1.
Pollution
Control Board,
60
Ill.2d
204,
326 N.E.2d
406,
408
(1975)
directing the Board
to consider all the facts and
circumstances.
As noted below,
Section
33(c)
specifically
directs
the Board
to consider all facts and
circumstances
in
enforcement cases.
Section
33(c)
provides:
c.
In
making
its orders and determinations,
the
Board
shall
take
into
consideration
all
the
facts
and
circumstances
bearing
upon
the reasonableness of
the emissions,
discharges,
or
deposits
involved includ-
ing, but not
limited
to:
Ill-i
(~

1.
the
character
and
degree
of
injury
to,
or
interference
with
the
protection
of
the
health,
general
welfare and physical property of
the
people;
2.
the social and economic value
of the
pollution source;
3.
the suitability
or
unsuitability
of
the pollution
source
to
the area
in
which
it
is
located,
including
the
cuestion
of
oriority
of
location
in
the area involved;
4.
the
technical
practicability
and
economic
reasonableness
of
reducing
or
eliminating
the
emissions,
discharges
or
deposits
resulting
from such pollution source;
5.
any
economic
benefits
accrued
by
a
non—complying
pollution
source
because
of
its
delay
in
compliance
with pollution control
requirements;
and
6.
any subsequent compliance.
Section
33(a)
of the Act requires that
the determinations
which the Board makes pursuant to Section
33(c) above must
be
in
a written opinion describing
the facts and reasons
for the
decision.
The Board’s findings are subject
to
review pursuant to
Section
41
of the Act.
The standard of
review of
the Board’s
decisions
is the manifest weight of
the evidence.
This means
that,
in carrying out its quasi—judicial function
in enforcement
cases,
the Board’s decision will be upheld unless contrary to the
manifest weight of the evidence.
Wells Manufacturinc Comoany,
383 N.E.2d
at
151.
Some enforcement
cases
result
in settlements.
The Board’s
regulations set forth procedures
for settlement of enforcement
cases at
35
Ill. Adm.
Code 103.180.
In
a
1986 air pollution case
involving
a $20,000 stipulated penalty,
the Fifth District
decided that
“the Board has
the statutory authority
to accept
settlement
agreements
in enforcement cases where
findings of
violation are precluded by
the terms of
the stipulation and
proposal but where
the respondent
is ordered
to
pay a stipulated
penalty and
to timely perform agreed upon compliance
activities.”
Chemetco,
Inc.
v.
Illinois Pollution Control
Board,
140 Ill.Ap~.3d 283,
488 N.E.2d 639,
643
(5th Dist.
1986).
The
court noted
that
consistent with the primary goal of enhancing
the environment,
“settlements
that
do not
contain
a finding
of
violation but do impose
a oenaltv and a compliance
plan may more
ii 1-17

expeditiously facilitate
this enhancement.”
Id.
(emphasis
added).
This same conclusion was also
reached by the Third
District
in Archer Daniels Midland
v.
Pollution Control Board,
140 Ill.App.3d
823, 489 N.E.2d 887
(3d Dist.
1986), where
the
parties stipulated
to a penalty but not
to a
finding of
violation.
Although the cases discussed below involve contested
penalties,
the Chemetco case does present encouragement for
settlements involving penalty
issues,
which,
in general,
the
Board
favors.
The Allen Barry case
involves a Stipulation and
Proposal
for Settlement
as
to the violations
only,
and leaves
open the issue of
a penalty.
Discussion
of Penalty Determination
The Board believes
that,
in order
to properly address
the
penalty
issue
in
this
case,
a broad overview of Illinois,
federal
and some other
states’
penalty determinations
is necessary
to
guide the Board
in this,
and future decisions.
The following
discussion
is intended to articulate
the Illinois approach
to
penalties since
the Board has
at times
been faced with conflicts
among
the reviewing courts,
and the Illinois Supreme Court
has
not addressed the Board’s imposition
of civil penalties since
1978.
To summarize and clarify the current framework
for the
Board’s penalty decisions,
a comprehensive analysis will follow,
concluding with
a discussion
of how the
law applies
to
the facts
of
the Allen Barry
case.
This discussion will proceed
in
accordance with
the Table of Contents below.
These discussions
are intended only
to briefly summarize
the case law, and not
to
provide holdings or new interpretations of
those cases.
Table of Contents
I.
OVERVIEW OF ILLINOIS LAW ON CIVIL PENALTIES
A.
Illinois Supreme Court Cases
10
B.
Illinois
Appellate
Court Cases
15
1.
Air
Pollution
Cases
15
2.
Water
Pollution
Cases
21
3.
Permit
Violation
Cases
24
4.
Local
Government
Cases
31
C.
Penalty Factors Derived from Illinois Case Law
34
1.
Statutory Factors
35
2.
Good Faith
5
3.
Other Considerations
36
a.
Aiding Enforcement by Deterring Others.. .36
b.
Economic Benefit
from Noncompliance
37
c.
Ability
to Pay
38
d.
Cessation and Duration of Violation
40
D.
Summary Outline of Illinois Statutory and
Judicial Considerations
41
B.
Illinois Legislative
Intent
42
111—is

II. OVERVIEW OF FEDERAL LAW ON CIVIL PENALTIES
43
A.
Federal Statutory Considerations
43
B.
U.S.
Supreme Court Cases:
The Tull and Gwaltney Decisions
46
1.
The
Tull
Case
46
2.
The
Gwaltney
Case
48
a.
The
Gwaltney
Penalty
Calculation
49
b.
The Gwaltney Implication of a
Mandatory Penalty
52
C.
Other
Federal
Decisions
53
III.
PENALTY CONSIDERATIONS
IN OTHER STATES
59
IV. STATISTICAL DATA ON PENALTIES
63
A.
USEPA Statistical Data on Penalties
63
a.
Table
No.
1
64
Total USEPA Penalties
for 1989
b.
Table
No.
2
65
Selected
USEPA
Penalties
for
1988
All Regions
c.
Table
No.
3
65
Selected USEPA Penalties
for 1988
Region V Only
B.
Illinois Statistical Data on Penalties
66
1.
Pollution Control Board
a.
Table
No.
4
Summary of Penalties Assessed by
Illinois Pollution Control Board
2.
Illinois Court Decisions
67
a.
Table
No.
5
67
Illinois Civil Penalties
Reviewed by Supreme Court
b.
Table No.
6
68
Illinois Civil Penalties
Reviewed by Appellate
Court
3.
Recent Stipulated Penalties
69
a.
Table
No.
7
70
Recent Stipulated
Penalties
C.
Comparison of Federal and State Penalties
70
a.
Table
No.
8
71
Comparison of Federal and
State Penalties
b.
Table
Nc.
9
72
Comparison
of Federal and State
Average Penalties
V.
CONCLUSION:
RELEVANT FACTORS FOR BOARD
DETERMINATION OF THE CIVIL PENALTIES
IN THIS CASE
A.
Calculating
the Maximum Penalty
72
B.
Statutory Factors Which Must
be Considered
73
C.
Other
Factors
73
11 1-1~

—in—
71
PENALTY DETERMINATION FOR ALLEN BARRY
74
A.
The Maximum Penalty
74
B.
Consideration of Statutory Factors
75
1.
Character and Degree of Harm
75
2.
Social and Economic Value
75
3.
Suitability/Unsuitability of
Pollution Source to Its Locale
76
4.
Technical Practicability and EcOnomic’
Reasonableness of Pollution Control
76
5.
Economic Benefits of Non—Compliance
77
6.
Any Subsequent Compliance
78
C.
Other Factors
78
D.
Penalty Calculation
80
I.
OVERVIEW OF ILLINOIS LAW ON CIVIL PENALTIES
To provide
a framework
for appellate
review of
the Board’s
penalty decisions,
a summary of
a comprehensive list of
Illinois
Supreme Court and Appellate Court
cases follows.
A total of
42
cases are briefly discussed
in two sections:
(A)
Illinois
Supreme Court cases
and
(B)
Illinois Appellate Court
cases.
Each
case will be
referred to by
a numbering system,
(1
through
42J,
and the summary of each case will be captioned with
a heading
for
the case name.
The summary of each case
is intended as
a
reference point
for the Board’s discussion of P~na1tyFactors,
which begins on page
35 herein.
This survey of Illinois Cases
begins with a 1974 Illinois Supreme Court decision and continues
through early
1990 decisions.
The outcomes
in
a number of these
decisions would have been impacted by subsequent
statutory
amendments
to Sections
33 and
42
of the Act.
However,
the cases
are presented
from
a historical perspective and not
in
terms of
precedent
for the Board’s decisions.
The new legislative
directives
to the Board are discussed separately
in the section
labeled “Illinois Legislative Intent.”
Cases which predate
the
amendments,
therefore,
must be viewed
in
the time frame
in which
the courts
issued those opinions.
A.
Illinois Supreme Court Cases
(1
The City of Waukegan Case
The Illinois Supreme Court
first acknowledged the Board’s
authority
to impose monetary penalties
in
1974.
See City of
Waukegan
v.
Pollution Control Board,
57
Ill.2d
170,
311 N.E.2d
146
(1974)
affirming
fines
of
$1,000,
$250 and $250.
In
that
refuse disposal
case,
the court determined
that penalties are
constitutional and consistent with
the state goal
to preserve and
improve
the environment,
and that Section
33(c) provides protec-
tion against arbitrariness and serves
to guide
the Board
in
imposing penalties.
However,
the Illinois Supreme Court
later
noted
that,
“(obviouslv
the General Assembly did not
intend
that
the Pollution Control
Board should moose
a monetary fine
in
111—20

every case of
a violation of
the Act or
regulations.”
Southern
Illinois Asphalt Co.
v.
Pollution Control
Board,
160
Ill.2d 204,
326
N.E.2d
406,
408
(1975)
(described
in detail
infra)
(Case No.
4.
(2
The City of Monrnouth Case
The guiding ~principle articulated by the Illindis Supreme
Court
is that civil penalties should aid enforcement
of
the Act
and
that “punitive considerations were secondary.”
City of
Monmouth
v.
Pollution Control Board,
57 Ill.2d
482,
313 N.E.2d
161,
166
(1974).
In
this
1974 air pollution case involving
emissions from the City of~Monmouth’s sewerage lagoon system,
the
Supreme Court
of Illinois
found that
a $2,000 penalty could
not
aid enforcement where
the city cooperated with
the Agency and no
technological netr~oc .ias aia.~aoe to effect~ve~ic.~-et~e
problem.
Various attempts were made,
but none resolved the
violation until after enforcement proceedings
began.
The Supreme
Court concluded
that since
“the City,
at substantial expense,
cooperated
in
the implementation of every proposal,
and that
through the City’s efforts
the problem appears
to have been
solved,
we hold that
the Board erred
in imposing the
fine.”
City
of Monmouth
v.
Pollution Control Board,
313 N.E.2d at
166.
(3
The Incinerator,
Inc. Case
In the case of
Incinerator,
Inc.
v.
Pollution Control Board,
59
Ill.2d 290,
319 N.E.2d 794
(1974),
the Illinois Supreme Court
upheld civil penalties of $25,000
for air pollution violations
resulting from refuse
incinerator operations.
Substantial
amounts
of flyash, heavy
smoke emissions and foul odors
unreasonably
interfered
with
the enjoyment
of
life and property
in the area,
in violation of
the Act and rules and regulations.
Corrective measures were not technically impracticable or
economically
unreasonable.
The Board was
found
to have properly
evaluated the unreasonableness of
the interference
in
licht of
Section
33(c)
ractors,
altnougn,
in
tne
tuture,
tne Boarc was
instructed
to be more specific
in making written findings as
to
the criteria
in Section
33(c)
of the Act.
The Incinerator court referred
to the Board’s review
of key
facts
relevant
to Section
33(c)
factors
in
its decision
to upnoid
the Board’s assessing
a S20,000 penalty.
The harm
to
the public
was found
to
be
a
substantial
interference
with
the
enjoyment
of
life and property over an extended period
of
time.
The social
and economic value of
the pollution source was evaluated
in terms
of
alternative available incinerators and disposal facilities,
the time
required
to obtain and install
pollution control
equipment,
and the
impact of
a close down on
the
23 employees
affected.
Regarding
the suitability or unsuitability of the
pollution source
to
its locale, evidence on zoning,
uses of
prooertv
in
the area,
and the nature of
nearby industries was
considered.
The Board also heard testimony on
the number
of
111-21

—12—
homes and buildings which predated the facilities,
as well as
those constructed later.
Another
important factor was
the
availability
of technically practicable,
although not
fully
perfected,
devices
to eliminate the air pollution problem and a
clear ability
to pay for
this
equipment.
The Supreme Court was
not persuaded by appellant’s arguments that
the pollution control
systems were either technically impracticable or economically
unreasonable.
The Board’s consideration of
these’ factors
amounted
to substantial compliance with the Act’s requirement
that Section
33(c)
criteria be analyzed
in Board determinations
in enforcement cases.
An additional
$3,000 penalty for failing
to file
a
required plan
for reducing emissions
was
affirmed
as
being neither arbitrary or excessive.
4~
The Southern :llinois Asphalt Company Case
In Southern Illinois Asphalt Co.
v.
PCB,
60
Ill.2d
204,
326
N.E.2d
406
(1975)
(two cases consolidated),
the :llinois Supreme
Court held
the penalties
inappropriate as abuses of
the 2oards
discretion.
The court
found
that the penalties would not aid
enforcement,
but were punitive.
In
the
first case
ir.volving
a
$5,000
fine for violation of air pollution permit requirements,
the appellant had ceased its asphalt plant operations prior
to
the Agency’s filing of
the complaint.
Furthermore, when
it d~d
operate, although lacking a permit,
the plant operated within the
Board’s emission standards.
The failure
to obtain
a permit was
inadvertent and
in good faith reliance that
the
installer
of
its
pollution control equipment had applied for and obtained a
permit.
In the second case,
involving
a $11,000 penalty
for water
pollution from cyanide discharges
from
an. auto parts
manu-’
facturer,
the court
found that
the violations ceased
five months
prior
to
the filing of
the comolaint.
Furthermore,
the company
“had been diligently trying
to bring
its operations
into
conformity... and was not dilatory or
recalcitrant.”
The penalty
was
held
“purely punitive’
under these circumstances.
Southern
Illinois Asphalt,
326 N.E.2d at
412.
The court concluded as
to both cases
that
‘the General
Assembly intended
to vest
the Board with broad discretionary
powers
in
the imposttion
or
civiL penaltIes
;
nowever,
the
recorc
showed
“substantial mIt~gat:ngcircumstances” wn~cn requtrec tcat
no penalty be imposed.
Southern
Illinois Asohalt,
326 N.E.2d
at
409.
Both cases
involved occoerative efforts and violaticns
which ended well before
the filing of
tne complaints.
The court
found,
therefore,
that
the penalties could not aid enforcement
of
the Act.
While acknowledging that
the Board has discretionary
authority
to levy civil penalties
in enforcement cases,
the
Supreme Court offered
a
note of caution.
‘Implicit
in
the grant
of
the discretionary authority
to impose monetary c~vi1penalties
in varying amounts
is
the
reouirement
that
the sever itv of
the
11 1—22

penalty should bear
some relationship to
the seriousness
of the
infraction or conduct.”
Southern Illinois AsDhalt,
326 N.E.2d at
408.
This directs
the Board
to consider
the overall significance
of
the violation as part of
a penalty determination.
(5
The Mystik Tape Case
In Mystik Tape,
Division of
Borden.,
Inc.
v.
Pollution
Control Board,
60
I11.2d 330,
328 N.E. 2d
5
(1973),
an
air
pollution
(odor) case,
a $3,500 cenalty was uoheld by
the
Illinois Supreme Court.
Mystik was found
to have violated
the
Act and rules and regulations by installing certain equipment
after
it had
beer. denied permits
for doing
so.
The ~erm:t
violation warranted
a penalty since
tne
facts were un1~ke those
of Southern Illinois Asphalt
(Case
No. 4,
where one company
showed good faith and
its failure
to obtain a permit was purely
inadvertent.
Also,
Mystik’s behavior was not analogous
to
that
of the other company
in Southern Ill:n.ois Asphalt,
Case
No.
4,
whose conduct was not dilatory or
recalcitrant.
Although
the
case was remanded to the Board
for reconsideration of
the alleged
air pollution violation based on the
factors set
forth
in Section
33(c),
the penalty was upheld
for the clear violation of the
relevant permit requirements.
Citing
to Incinerator,
Inc.
Case
No.
3,
the court
found that
the penalty was not arbitrary ~r
oppressive.
The court also reaffirmed
“the power
of the Board
to
impose civil
penalties primarily as
a method
to aid enforcer~ent
of the Act,” citing Southern Illinois Asphalt,
Case
No. 4L
and
City of Monmouth,
(Case
No.
2.
Mystic Taoe,
328 N.E.2d at
10.
Without
a detailed discussion
as
to how the penalty would
aid enforcement
or
how each factor
of Section
33(o)
applies~to
the failure
to obtain oerm~ts, the Mvstik Taoe court affirmed the
penalty
for the permit violation.
The
Mvst:~
?aoe court
noted
that Mystik applied for permits
for:
(I) odor—ccun:eracr.ant
devices and
(2)
a spreader.
The Agency denied
the permits
because
the former
equipment was believed
to only mas-~. tre odors
and
the
latter
equipment
was
considered
a
potential
source
of
pollution needing pollution control devices.
The penalt
issue
in
this case
thus seems
to relate
in part
to whether
there
is an
aooarent risk
of oresent or future air collution.
Tnis
is
in
contrast
to
the mere technical comoliance
with oCrm~t
requirements sought
by
the Agency
in
the case of Southern
Illinois .Asohalt,
Case
Nc.
4,
where
air
oollution
was
not
an
issue.
Mvstik
:nstalled
tne ecu~omentdesotte
the per—~~~it
denIals
and,
therefore,
the
fine was not arbitrary
or oppressive
since
the permit violation was knowing,
and not
an.
inadvertent failure
to meet
a technical
recuirement.
6
The Metropolitan Sanitary District Case
The Illino:s Suoreme Court reiterated
the theme
of aiding
enforcement of
the Act
in another
1975 case.
In
that
case,
the
111—23

_1
,1~_
Metropolitan Sanitary District of Greater Chicago independently
initiated plans
to construct compliant facilities
to cure water
pollution problems.
The district had not been “dilatory
or
recalcitrant.”
It “fell victim to inter—agency conflicts
(i.e.,
extensive negotiations with
the Northeastern Illinois Planning
Commission and the Sanitary District of Elgin)
resulting
in
delays which made
it impossible.. .to prevent
the violations...”
Under
these circumstances,
the penalties totaling $~,000were
found to
be “purely punitive” and not
an aid
in enforcement
of
the Act.
Metropolitan Sanitary District v.
Polluti~onControl
Board,
62 Ill.2d 38,
338 N.E.2d 392,
397
(1975).
(7
The Processing
&
Books,
Inc.
Case
The Illinois Supreme Court upheld
a $3,000 penalty
in
a 1976
case involving air oollution from odors emitted
from an egg and
poultry
rarm.
Processing
&
Books,
Inc.
v.
Pollution
Control
Board,
64 Ill.2d 68,
351 N.E.2d 865
(1976).
The court
found
that
the Board decision predated
the court’s decision
in Incinerator,
Inc.,
(Case No.
3,
and,
therefore, although
the Board did not
make specific findings on each of the
(then
four)
fdctors
in
Section
33(c)
of
the Act,
this did not warrant reversal since
the
Board’s order made clear
that each factor was considered.
The
court found that,
for more than one mile outside the farm,
“respondents seriously interfered with the enjoyment of life and
property
in ways which could have been prevented.”
~
Books,
Inc.,
351 N.E.2d at 870.
The court
noted
that
the
operation had substantial social and economic value.
However,
the great increase
in
the size of
the operation,
the related
negative impact on the area,
and the availability of corrective
measures
(which
respondents did not begin
until after
the
complaint was
filed),
supported the Board’s finding that
a
penalty was apDropriate.
(8
The Wells Manufacturing Company Case
The 1978
case of Wells Manufacturinc Comoanv,
73
Ill.2d
226,
383 N.E.2d
148
(1978),
involved a S9,000 penalty for alleged
odor—related
air pollution emitted from an
iron foundry.
In
a
detailed analysis of Section 33(c)
factors,
the Illinois Supreme
Court reversed
the Board’s decision as being against
the manifest
weight of the evidence.
‘The court described
the task of
eva1uat~ng a Section
9(a)
air pollution case
in
terms of
a
balancing
test.
“The Board must balance
the costs and beneftts
of abatement
in
an effort
to distinguish the
trifling
inconvenience,
petty annoyance or minor discomfort
fror~ia
substantial interference with the
enjoyment
of
life and
property.”
Wells Manufacturing Comoanv,
383 N.E.2d at
150,
citing Processing
& Books
Inc.,
Case
No.
7.
Section
33(c)
must
be used
to guide
the Board
in
this determination.
111—24

The Supreme Court
found
that much evidence had been
developed below concerning
the character
and extent of
the harm
pursuant
to Section 33(c)(i).
The Board focused on citizen
testimony and concluded
that
the “odors
‘unreasonably interfered
with the enjoyment of life and property’
.“
Wells Manufacturing
Company,
383 N.E.2d at
152.
Regarding Section
33(c)(ii),
the
company indisputably was making
a major
social and economic
contribution by employing approximately 500 persons ‘and supplying
parts
to numerous industries.
Section
33(c)(iii),
involving the
appropriateness
of the pollution source
to its locale raised
several areas of dispute.
Although the Supreme Court agreed that
the company’s “priority of
location does not achieve the
level of
an absolute defense,”
i~t was “impressed with
its significance’
here.
Wells Manufacturinc Comoanv,
383 N.E.2d at
152.
The
nearby residential area and
hign. school were develcoed
later with
notice that the adjacent area was zoned
for heavy—industrial
use.
The hiçh school was even built on
land accuired from
the
foundry.
Expansions
to
the
foundry
were
made
after
the
school
was
constructed
and after
some homes were built.
The court held
that this weighs against
the priority of location argument but
that the proof
that emissions had increased
was insufficient
to
meet the Agency’s burden on
this point.
The final criteria
in
Section
33(c)(iv)
regarding
the technical practicability and
economic
reasonableness of pollution controls ultimately Favored
the company.
Financial considerations were not at
Issue.
Hbwever~ the court held
that
the Agency had the burden
“to come
forward with evidence
that emission reduction
is practicable
Wells Manufacturing Company,
383 N.E.2d at
153,
and conflicting
expert testimony on three methods
of abatement and
•an inadequate
record on
a fourth method defeated Agency assertions
of
tech~’nical
practicability.
The court concluded that
these
factors,
tak~en
together,
did not establish
the unreasonableness
of
the odocs.
Hence,
no violations
had occurred and the penalties were
inapproor iate.
B.
Illinois Appellate
Court Cases
1.
Air Pollution Cases
Air pollution violations
involving Section
9 of
the Act have
been
the subject
of many contested penalty cases.
These case~
may be subdivided somewhat
into the
two types of violations
covered
by Section
9(a) based on
the
alternative
definitions
of
air pollution offered
in Section 3.02.
That section defines
air
pollution
both
in
terms
of
injury
and
in
terms
of
inteçference
with life
or property as follows:
“AIR
POLLUTION”
is
the
presence
in
the
atmosphere
of
one
or
more
contaminants
in
sufficient
quantities
and
of
such character-
istics
and
duration
as
to
be
in,~urious to
human,
plant,
or animal
life,
to health,
or
to
property,
or
to
unreasonably
interfere
with
the enjoyme~ of
life or property.
111-2S

—,
Section
3.02
of the Act
(emphasis added).
(9
The Allied Metal Company Case
Allied Metal Co.
v.
Illinois Pollution Control Board,
22
Ill.App.3d
823,
318 N.E.2d 257
fIst Dist.
1974) was an early air
pollution case where
a $2,500 penalty was appealed.
The fine had
been imposed for violations
of Section
9(a)
of the Act,
particulate emission regulations and permit recuirements.
The
court reversed the Board’s decision finding Section 9(a) and
emission violations
as being against
the manifest weight
of
the
evidence.
Furthermore,
the Board had failed
to consider the
“reasonableness’
factors
of Section
33(c), which
thts
court held
to
be mandatory
to estabiish:ng these violations.
The permit
violation
for
construction
of
a
potential
emission
source
was
upheld and on that issue
the court remanded
for
redetermination
of
the penalty.
For
tne permit violation
alone,
the Board
reassessed
the penalty at
$750 upon remand.
(101 The Sangamo Construction Company Case
In Sancamo Construction Company
v.
Pollution Control Board,
27
Ill.App.3d 949,328
N.E.2d 571
(4th Dist.
1975),
the court
affirmed the finding of
a violation of Section 9(a)
for odors and
dust emanating
from petitioner’s asphalt and concrete plants and
for operating without
a permit.
The Fourth District extended the
Supreme Court’s rationale
in.
Incinerator
Inc.,
(Case
No.
3,
which held
that air
pollution causing interference must be
considered
in light of Section 33(c)
factors before
a violation
is established.
The district court held
that both
tvoes of
air
pollution violation must
be proved through an analysis of Section
33(c)
factors.
Sanca:mo Construction,
328 N.E.2d
at
575.
The
court stated that the Board correctly found
a Section
9(a)
violation,
but finding
that only one plant had operated without
a
permit,
remanded for
reimposition
of
the
fine.
A $5,000
fine had
been imposed
for
the three violations, and on remand
to the
Board,
the fine was reduced
to S4,000.
The Sangamo case approaches Section
33(c)
as part
of
the
proof
of
a Section 9(a)
violation.
However,
as discussed below,
in
the Aluminum Coil Anodizinc case,
40
Ill.Aoo.3d
785,
31S
N.E.2d
612,
615
(2d D~st. 1976)
Case
No.
111,
some courts have
found
that Section
33(c)
is
part
of
the penal:’; determination and
not part
of
the proof of
a Section
9(a)
air polluticn vLolation
where harm
or
injury occurred.
11
The Aluminum Coil Anodizing Corooration Case
In a 1976 odor
case,
involving
the first
type of
Section
9(a) air pollution violation,
the Second District upheld
a $1,500
penalty against
an anodizing pant.
The court observed
tnat
th:s
1 11
20

violation, which was injurious
in
its effect,
involves
a
different burden of proof
than air pollution which intrudes on or
interferes with
life.
“By
its terms proof of
the essential
elements of air pollution of
the first
type set forth
by section
3(b) does not
require any showing
by the complainant of
the
unreasonableness of
the emissions
involved,
in contradistinction
to air pollution of the second type set forth
in section
3(b)
Aluminum Coil Anodizing Corporation
v.
Pollution Corftrol Board,
40 Il1.App.3d
785,
315 N.E.2d
612,
615
(2d Dist.
1976).
In this
case,
the company’s
emissions were associated with
foul odors,
various health ailments,
and property damage.
Air pollution of
the first type was established based
or. testimony regarding its
injurious effects including instances
of breath:ng difficulties,
headaches,
couching,
and eye Irritations;
spotting
on. aluminum
doors and plants
in
the area;
and deterioration of
a nearby
roof.
The court
found
that
the Board’s opinion
reflected due
consideration of Section 33(c)
factors.
The court
noted
that
the
company’s not having
received complaints might
be
a m:ticatin.g
factor.
However,
the record also showed no good faith efforts
to
achieve compliance between
the date of
the complaint and
the
closing
of
the plant
over one year later,
despite available
technology
to control
the odors.
The penalty, therefore,
was
appropriate,
and not excessive and would “serve
to aid
in the
enforcement
of
the Act by working to secure voluntary compliance
with
the
Ac,t
in other
cases,
especially
by ACA at
its new
facility.”
Aluminum Coil Anodizing,
315 N.E.2d at 619
(emphasis
added)
12
The Lloyd
A. Fry Roofing Company Case
In
1974,
the First District affirmed the finding of
a
violation.
in the nature of
the second type of
air pollution,
that
is, unreasonable interference with
life and property
in
a case
involving smoke and odors
from an asphalt
roofing plant.
Lloyd
A.
Fry Roofing Comoanv
v.
Pollution Control
Board,
20
Ill.App.3d
301,
314 N.E.2d 350
(1st
Dist.
1374).
Headaches,
nausea,
and eye
and throat
irritations were associated with
the emissions.
The
court
found
that evidence regarding Section
33(c)
factors was
sufficient
to supPort
the Board’s
findings.
Besides
the
impact
above,
the Board heard evidence on
the operation of
the plant,
the presence of other pollut:on sources
in
the area,
and,
notably,
the availabilit
of pollut:on control devices
to asphalt
plants
in general and their
usage at petitioner’s other
plants.
The court affirmed the
Section 9(a)
violation,
but
the case was
remanded
for reconsideration
of
tn.e S50,000 ocralty since
the
court
reversed
tne Board
s
f:n.c:ng or
a v:olaticn or
the
~oaro
s
rules and regulations.
On
reconsideration,
the Board assessed
a
reduced penalty of $10,000.
111-27

l33 The Bresler
Ice Cream Company Case
In contrast with
the Lloyd
A.
Fry Roofing case
(Case No.
12,
a number of cases involving the second type of
Section 9(a)
violation
(i.e.,
interference) were decided by the appellate
courts with
the conclusion
that civil penalties should not
be
sustained.
In Bresler
Ice Cream Company
v.
Illinois Pollution
Control Board,
21 Ill.App.3d
560,
315 N.E.2d 619
(lit Dist.
1974),
the court
found
that an air pollution violation
in
the
naçure of unreasonable interference with the enjoyment
of life or
property resulted from the release
of
flyash and odors
from
Detitioner’s incinerator.
However,
the record did not suoport
the $1,500 penalty since petitioner ultimately carried
the burden
of proof
as
to mitigating circumstances.
Notably,
the company
showed good faith
in.
volun.taril’i attemotinc
to abate
the
pollution.
in terminatinc use of
the incinerator orior
to
the
corola_-’t
bc_np
i_ec, a~o
ac~ee~gto
re:~ar~
:ron futur:
use.
The violation was held
to
be
“de minimus,”
with
no impact
on health.
The
facts stipulated
to by
the parties
“evince
a
sincere desire
...
to cooperate...
This attitude should have
been noted and encouraged
by
the Board.”
Bresler Ice Cream,
315
N.E.2d at
621.
As
a further
note,
the court compared
the subject
penalty
to a $1,000 penalty levied
in another
case
for solid
waste dumping violations which posed health
risks.
It concluded
that petitioner’s case was a
far less serious situation
for which
the Board
imposed
a disproportionate penalty.
The court gave
a
clear
signal to
the Board to
look
for violator’s good
faith
conduct and for consistency
in
its disposition of
penalty cases.
(14
The Chicago Magnesium Casting Company Case
The First District reached
the same conclus:on
in. anotner
197~air pollution
case. involving
a $1,000
fine
for ocors
generated by a
foundry.
The court
found
that
the company had
worked with
the county agency, conducted studies, attempted
to
mask the odors, and then abandoned the offending chemical six
months before the complaint was filed.
Although a Section
9(a)
violation was found,
the court
held that
a oenaltv would not aid
enforcement of the Ac: given tne coooerat~veetforts
snown,
tn.e
lack of
reasonable means
to control odors
prior
to the company’s
use of
a new cnemical,
and the
fact
that compliance was acnieved
six months prior
to the complaint.
Chicago Macnesiun Cast:nc
Comoany
v.
Illinois
Pollution. Control Board,
22
ll.Apu.3d
489,
317 N.E.2d
689 (lstD:st.
1974).
2
The court
noted,
however,
that “economic reasonableness and
technical practicability are but two factors
to be considered
by
the Board
in determining whether
or
not the Act has
been
violated.”
Chicaco Macnesium Castinc,
317
N..E.2d at
632.
These
do
not
rise
to
the
level of
a coriolete defense.
111—28

(15
The CPC International,
Inc. Case
CPC International,
Inc.
v.
Illinois Pollution Control Board,
24
Ill.App.3d
203,
321 N.E.2d
58
(3d Dist.
1975)
represents
another Section
9(a) air pollution
case,
this
time involving
regulatory standards
for particulate
levels.
In
this
case,
the
Third District found
that
a viol~tionoccurred, but ‘the $15,000
penalty assessed by
the Board was vacated.
As
in Bresler
Ice
Cream,
(Case No.
13,
and Chicaco Magnesium Castina,
Case
No.
14,
the petitioner acted promptly
to correct
the problem.
The
violations were minor
and were remedied before
the Board’s
decision.
The penalty was arbitrary and excessive wnen compared
to three prior
Board decisions
imposin.9 fines of $3,000
to
$10,000
“for
violations
whicn
were
deliberate
and
long—term.”
CPC International,
Inc.
321 N.E.2d at
61.
The court
also
observed
that three adjacent industrial plants had received
variances and emitted higher levels
of particulates
than
the
petitioner,
and that
this should be
a major consideration in
a
penalty determination.
This,
too,
bears on
the court’s
evaluation of the Board’s even—handedness
in penalty
cases.
(161 The Arnold
N.
May and Hillview Farms,
Inc.
Case
In a 1976 case involving odors
from the application of
sludge and feedlot wastes
to farmland,
a penalty was again
vacated on appeal.
In Arnold
N. May and Hillview Farms, Inc.v.
Pollution Control
Board,
35 Ill.Apo.3d 930,
342 N.E.2d 784
(2d
Dist.
1976),
the Board’s findings
of violations of both types of
Section
9(a) air pollution and Section
12(b)
water pollution
permitting requirements were upheld.
However,
the S2,500 penalty
was vacated as
being against
the manifest weight of the evidence
and not an aid
in enforcement
of the Act.
The court disagreed
with the conclusion
which
the Board drew from
its analysis of
Section
33(c)
factors.
The court
noted
that
the Board
found
minimal impact
on health and the environment.
Furthermore,
the
court
found
that
the Board’s emphasis on
“discomfort and
inconvenience caused to neighbors over
a
long period
of
time”
from the offensive odors
could not support
a penalty when
the
remaining three of
the four Section
33(c)
factors
favored the
petitioners.
(171
The Draper and Kramer,
Incorporated Case
In
the case of Draper and Kramer,
Incoroorated
v.
Illinois
Pollution Control
Board,
40
fll.Aop.3d
918,
353 N.E.2d
106
(1st
Dist.
1976),
the court reversed both
the violation.
of Section
9(a) and the $1,000 penalty
for the alleged discharge of
a
toxic
mist from petitioner’s cooling
tower.
The emissions were said
to
result
in
eve,
ear,
nose,
throat and skin irritations.
However,
the court
round
that
the cescr~oedinter:erence w~tnl~:ecouid
not
be attributed conclusively
to petitioner’s equipment.
The
111-2

court
noted
that use of
the chemical purportedly responsible was
discontinued,
but the physical complaints continued
for almost
nine more months.
Petitioner also
took prompt and cooperative
action to prevent any further
release of
the spray upon learning
at hearing
that
the sPray itself, and not just
the chemical, was
objectionable.
Neither
the record nor
the complaint had
previously focused the violation on other than
the one
chemical.
The court concluded that,
under
these cir’cumstances,
the penalty could not aid enforcement
of
the Act.
181
The Marblehead Lime Company Case
Contrasting with the above cases,
a penalty of $20,000 was
affirmed
in a
1976 case
for a Section 9(a)
air oolluticn
violation ;h~o~unreasonably ~nterferec
~_th life a~’corooerty
In
Marblehead
Lime
Comoanv
v.
Pollution
Control
Boaro,
42
Ill.App.3d
116,
355 N.E.2d 607
(1st
Dist.
1976), petitioner’s
lime manufacturing plant subjected area residents
to constant
fallout of dust which blanketed nearby property indoors and
outdoors and caused skin,
eye and throat irritations and
breathing problems.
The court concurred with the Board’s
evaluation
of Section
33(c)
factors,
noting several mitigating
factors.
In finding no abuse
of the Board’s discretion
to impose
a penalty,
the court highlighted the extent
of
the negative
impact of
the pollution and the availability of
“housekeeping and
maintenance”
alternatives
to control
it.
“The penalty was
imposed after extensive hearings which indicated that petitioner,
for
a long period of time,
had i~terferedwith the enjoyment of
life and property
in ways
that reasonably could have been
avoided.”
Marblehead Lime,
355 N.E.2d at 612,
613.
Thus,
as. in
Lloyd A. Fry
?.oofinc,
(Case No.
12,
the accessibility of
pollution control procedures or equipment weighs heavily
in favor
of
a penalty.
(19
The Hillside Stone Corporation Case
In another
case’ involving
the second type
of air pollution,
the First District reduced
a penalty from $10,000
to S2,000.
In
Hillside Stone Corporation v.
Illinois Pollution Control Board,
43
Ill.App.3d 158,
356 N.E.2d
1098
(1st Dist.
1976),
the
unreasonable
interference with
life and property due
to heavy
dust emission from the limestone quarry was much
like
that
in
Marblehead
Lime,
(Case
No.
18.
After affirming
the finding
of
the violation based
on sufficient evidence on
the Section
33(c)
criteria,
the court agreec with
tne pet1t~oner tnat
tne fine was
excessive.
Evidence that oetitioner
nad taken substantial steps
to control
emission, had spent S600,000
to control pollution, and
had already
paid
a $10,000
fine as
a result of
a suit
by the Cook
County Department of Environmental Control persuaded
the court
to
reduce the
fine
to S2,000.
This amount was considered “adequate
to
aid
enforcement
of
the
Act
and
as
a
warning
to
Hillside
of
the
necessity properly
to maintain its equipment and to avoid delay
11 i—3~

in the filing of a corporate approved plant
for compliance.”
Hillside Stone,
356 N.E.2d
at
1102.
20
The Joliet Railway Equipment Company Case
In
a
1982 case involving air pollution and open burning
in
violation of Section’ 9(a) and
(c),
the Third Distridt court
upheld
a $10,000 penalty assessed,
not by the Board, but
by the
Circuit Court of Will County.
P~oole of
the State of
Illinois v.
Joliet Railway Ecuioment Co.,
108 Ill.App.3d
197,
483 N.E.2d 1205
(3d Dist.
1982).
Although
the case was remanded with respect
to
injunctive
relief granted~ the lower court’s penalty was affirmed
as being supported
by
the evidence.
The record included
testimony of dizziness,
vomiting,
r.ausea,
headaches,
and tearing
of
the eyes
in conne~tionwith
a fire at petitioner’s salvage
yard.
The reaular coerations resulted in reoeated instances of
fires and of toxic
fumes
emissions.
2.
Water Pollution Cases
(21
The Meadowlark Farms,
Inc.
Case
In a .1974 water pollution case,
the Board assessed
a minor
$141.66 penalty against
the owner of surface
rights
in land on
which coal mining refuse piles produced seepage containing acid
mine drainage.
Meadowlark
Farms,
Inc.
v.
Illinois Pollution
Control
Board,
17 Ill.App.3d
851,
308 N.E.2d
829
(5th Dist.
1974).
The seepage entered
a tributary of
a larger stream,
resulting
in periodic fish kills
from the contaminated
flow.
The
$141.66 penalty was assessed
for the value of
the fish kill,
and
not unde,r
the Board’s discretionary powers
to assess penalties
of
up to $10,000
per violation and $1,000 per day.
However,
the
court determined an imoortant enforcement
issue,
finding
that the
owner of
the water pollution source need
not
be shown
to have
created the hazard nor
to have had knowledge of
the discharge.
“The Environmental Protection. Act
is malum prchibitum~ no proof
of guilty knowledge or mens
rea
is necessary
to
a finding
of
guilt.”
“(Kinowledge
is not an element of
a violation of Section
12(a)
and lack
of knowledge
is
no defense.”
Meadowlark
Farms,
308 N.E.2d at
837.
22
The Freeman Coal Mining Corporation Case
Citing Meadowlark
Farms,
(Case
No.
21,
the Fifth District
again found
a water poll~itionviolation where
a mine refuse pile
on petitioner’s
land produced acidic runoff
in
the case of
Freeman Coal
Mmmc
Corooration
v.
Illinois Pollution Control
Board,
21
Ill’.Aop.3d
137,
313 N.E.2d 616
(5th Dist~ 1974).
The
court held
that the water pollution threatened
the health and
welfare
of
the surrounding
residents, may have made nearby crop
land unproductive, and seriously impacted the fish and insect
111-31

po~ulationof
the stream and adjacent vegetation.
The totality
of circumstances,
however, did not
support the
$5,000. penalty
assessed by
the Board.
The court reduced the penalty
to $500
based on numerous mitigating circumstances,
including
petitioner’s efforts and expenses to control
the pollution
through a water treatment system,
the Board’s use of a
performance bond
to ensure compliance, and the disproportionate
size of the penalty compared
to the less
than $200 penalty
in
Meadowlark Farms,
Case
No.
21.
23
The Allaert Rendering,
Inc. Case
Water pollution violations and
related permit violations
were
the subject of an appeal
in Allaert Renderin~ Inc.
v.
Illinois Pollution Control
Board,
91 Ill.ApP.3d
153,
414 N.E.2d
492
(3dDist.
1980).
The Board assessed
a S3,000 penalty
in
Connection with
the wastewater treatment system of petitioner’s
rendering plant.
Petitioner’s highly contaminated lagoons
created
a hazard of water pollution
to surface waters
from.
flooding.
The court
held
that
it was not necessary
to show
actual pollution had already occurred since Section 12(a)
of
the
Act prohibits
the threat of contamination.
Flooding,
which was
shown
to have previously occurred,
could reoccur.
The court also
found that
the lagoons were
illegally constructed and operated
without permits.
Given
the environmental risks and the five—year
history of delayed compliance with the Act and regulations,
the
court approved
the penalty
in
a cursory statement,
noting
that
“(the
Board stated
that
it
found
the amount of
the
fines
to be
‘...
the minimum necessary
to ensure future compliance...’”
Allaert Renderinc,
414
N.E. 2d
at
497.
The court affirme.d
the
penalty, T~tding
no abuse of discretion
in either
its imposition
or amount.
(24
The Archer Daniels Midland Case
In Archer Daniels_Midland
v.
Illinois Pollution_Control
Board,
119 I1l.A~o.3d 428,
456 N.E.2d 914 (4thDist.
1953)
Case
No.
24a,
petitioner aooealed a sizable $40,000 oenalty imposed
for water
pollution and NPDES permit violations, which resulted
in fish kills and oily scum problems at
a nearby
lake.
Contami-
nation resulted from storm water discharges carrying organic
material from petitioner’s
soybean and corn germ extraction
plants and vegetable oil
refinery.
The Board assessed a $40,000
penalty after
hearing evidence on
the environmental
impact
on
violations occurring from
1976 through
1981,
on petitioner’s
efforts and $4,500,000
in expenditures
for pollution control,
on
an Agency calculation of possible savings
from non—compliance
ranging from about
S53,000
to $108,000,
and on other factors such
as
the social and economic value of
the pollution source and its
suitability
to
the area.
On appeal,
the court
remanded the case
for
redetermination
of
the penalty.
The court
found that’the
Board erroneously
relied on evidence of
the savings
to
111-32

petitioner,
which the court believed was based on spurious
assumptions and lacked adequate foundation.
At hearing,
the
Agency’s witness
testified
that he used computer generated
calculations, based on USEPA’s “Noncompliance Penalty Formulae,”
which ultimately were too complicated to explain.
Also,
in
response
to theBoard’s assertion
that $40,000 was
de minimus
given petitioner’s financial strength,
the court
stated:
We are
not
aware
of any authority which
makes
the
ability
to
pay
the
proper
basis
for
a
civil
oenalt’, and
in
the case
of
a multiolant
corooration,
it
ignores
any
internal
accounting
system wh~cn mignt
attr~oute tne
entire penalty
to one profit center.
Archer Daniels Midland,
456 N.E.2d at
99.
The court
then distinguished Wasteland
Inc.,
118 I11.Aop.3d
1041,
456 N.E.2d 964
(3d Dist.
1983),
Case
No.
34,
which gave support
to
a penalty which reflected savings from noncompliance.
That
case focused more on
the violator’s “continuing blatant
disregard”
of environmental
laws,
which
this court believed
contrasted substantially from the.facts
here.
The court went on
to emphasize
that
the Board inadequately considered the major
efforts and $4,500,000
in expenditures
already made and the
willingness of petitioner
to spend another $1,000,000
if that
would remedy
the problem.
On
remand,
the Board
imposed
a $32,500 penalty, after
rejecting
a $15,000 settlement proposed by
the Agency and
petitioner.
That decision was appealed, and
in Archer Daniels
Midland
v.
Pollution Control Board,
149 Ill.App.3d
301,
500
N.E.2d 580
(4th Dist.
1986)
(Case
No.
24b,
the court
reduced the
penalty
to $i5,000~
The court based
this decision on
the
substantial mitigating
factors,
including
the large sums spent,
and
to be spent,
towards compliance, good faith
in
reporting the
violations,
and value to
the community.
The court believed
“$15,000
is adequate to aid
in enforcement of
the Act and
to
serve
as
a
deterrent
to
ADM
against
future
violations.”
Archer
Daniels Midland,
500 N.E.2d at
584
(4th Dist.
1986)
Case
No.
24b
(emphasis
added).
Noticeably,
the
court
limited
the
scope
of the deterren.t
effect
to
this petitioner only,
and concluded
that
a much smaller penalty
than
the Board assessed would achieve
that
end.
(25
The Russell Perkinson, d/bia Porkville Case
In
a case involving
the discharge of
liquid swine waste
into
a stream,
the Third District upheld a SlO,000 penalty as well
as
an additional
$10,376
for the value of 101,219
fish killed.
Russell
Perkinson., d~b/aPorkville
v.
Illinois Pollution Control
Board,
135
Ill.Dec.
333,
543
N.E.2d
901
(3d
Dist.
1989).
In. 1983
and
1984 petitioner’s swine
farm,
which
had experienced prior
Ii 1—33

—.J
seepage problems with its waste lagoons,
discharged waste
to an
adjacent field where drain
tiles connected
to a discharge pipe
carried
the waste
into
a stream.
The Board assessed respective
fines of $10,000 and $1,000
for 1983 and 1984 violations
of the
Act,
rules and regulations and NPDES permit conditions requiring
notification of any discharge.
Costs assessed
for the 1983 and
1984 fish kills were $10,376.84 and $443.26.
Petitioner appealed
the 1933 fines and costs as an abuse
of the Board’s ‘discretion.
In affirming the Board’s decision,
the court
found
that
the
violations did not require proof of knowledge or intent regarding
the discharges.
See
Russell
Perkin.son,
543
NLE.2d at
903,
citing Meadowlark
Farms,
Case
No.
21;
Hindman,
(Case
No.
28;
Freeman
Coal Mmmc,
Case
No.
22;
and Bath
Inc.,
10 Ill.Aoo.3d
507,
294 N.~.2o7i8 (~~tnD:st.
l9i3)
Case
No.
34.
Furthermore,
the court observed that although petitioner claimed
that
a trench
constructed by vandals caused
the 1983 violations,
the court
found
no evidence that
petitioner
tried
to prevent vandalism or
lacked the caoability
to control
the source of pollution.
The case before
us
is controlled
by
the
long
line of precedent
in Illinois which holds
that
the
owner
of
the
source
of
the
pollution
causes
or
allows
the
pollution
within
the
meaning
of
the statute and
is
responsible
for
that
pollution
unless
the
facts
establish
the
owner
either
lacked
the capability
to
control
the
source,
as
in
Phillips
Petroleum
or
had
undertaken
extensive
precautions
to
prevent
vandalism
or
other
intervening
causes,
as
in
Union Petroleum.
Russell
Perkinson,
543
N.E. 2d
at
903,
citing
Phillios
Petroleum
Co.
v.
Illinois
Environ-
mental
Protection
Acencv,
72
Ill.Apo.3d
217,
390
N.E.2d
620
(2d
Dist.
1979)
and
Union
Petroleum
Core.
v.
United
States,
651
F.2d
734,
(Ct.
Cl.,
1981).
Furthermore,
the
continuing
seepage
from
the
lagoon
also
supported
the Board’s order.
The court pointed out that
the
$10,000 penalty assessed
was
less
than
the Agency had requested
and referred
to
the violation.
as
a “major pollution event.”
3.
Permit Violation Cases
26
The Highlake Poultry
Inc.
Case
Penalties assessed
for violations
of various permitting
requirements have been
the basis of
a number
of reversals of
Board decisions.
In
the case of Hichlake Poultry Inc.
v.
Pollution Control Board,
25 Ill.Apo.3d
956,
323 N.E.2d 512
(2d
Dist.
1975),
the petitioner
began construction of
a sewage
ill
-

—25-
treatment plant without a permit.
The court reversed penalties
totalling $2,500 upon
a showing
that
the Agency contributed
to
delays
in securing
a permit, and the petitioner had been
cooperative and had achieved substantial compliance.
Showing
little tolerance for
this particular enforcement action the court
stated:
It
appears,
further,
that
in
this
case
a
relatively
small
business
was
being
put
to
considerable
trouble
and
expense,
was
trying
to
cooperate
with
the
various
governmental
bodies which seemed
to
be aligned against
it,
and
was
ultimately
penalized
for
being
too
early
rather
than
too
late
in making improve-
ments
to
its
sewage
treatment
system,
on
the
instigation
of
an
agency
responsible
in
some
measure
for the company’s oredicament.
~ih1ake
Poultry,
323 N.E.2d at
615.
(27
The Freeman Coal Mining Case
Other
cases
reinforce the Second District’s implication
in
H~~ake’Poultry, Case
No.
26,
that permit violations
in
the
face of good faith efforts and substantial compliance
expenditures present
a weak case
for
a penalty finding.
The case
of
Freeman Coal Minin~v.
Illinois Pollution Control Board,
29
Il1.App.3d
441,
330. 1~T~72d524
(5th
Dist.
1975)
demonstrates
that
the
appellate
courts
are
not
always
impressed
with
the
seriousness of permit violations, which may appear
to be more
form than substance when genuine efforts toward compliance have
been made.
The Freeman
Coal Mining case
involved violations
of both
permit
requirements and
regulatory standards
for air pollution
(density
of
smoke)
established
by
the
Board’s predecessor agency,
the Air Pollution Control
Board.
The court
remanded
the decision
to the Board on
the basis
that only two of
three alleged
violations could be sustained.
It directed
the Board
to
reevaluate
the $1,500 penalty
in light of
the
reduced number
of
violations and mitigating
factors.
‘The court
specifically noted
that with
respect
to
the petitioner’s failure
to secure permits
on
a timely basis,
“in determining the penalty for such
violation.,
the Board should
take
into consideration that the
installation of
the rnulticlones was cart
of
the acoroved ACERP’
(Air Contaminant Emission Reduction Program).
Freeman Coal
Mining,
380 N.E.2d at
529.
On remand
the penalty was
reduced
to
$850.
111-33

—~rz
-
281
The Hindman Case
In Hindman
v.
Environmental Protection Agency,
42
Ill.App.3d
776,
356 N.E.2d
669,
(5th Dist.
1976),
the court reduced
penalties
for open burning of
refuse at
a landfill and for permit
violations by
60,
on finding some mitigating circumstances and
good faith efforts
at compliance.
The court reduced the arguably
nominal penalties
from $250 and $500
to $100 and
$20’O.
In
dropping the open burning
fine
to $100,
the court stated that
“the
fine
of $250 could not prevent
the recurrence of
fires for
which he was not fully responsible.”
As
to the permit violation,
the court added
that
“a fine of
$200 would have accomplished what
the $500
fine sought
to accomplish and would have been more
closely related
to the
nature
of
the violation
involved.”
Hindman,
356 N.E.2d at
672.
This case illustrates
a reluctance
of the court
to imoose fines and the difficulty
faced by
the
Board
in setting amounts which might
encourage
compliance
in
similar circumstances.
(29
The Harris—Hub Company,
Inc.
Case
In another permit violation case,
the First District found
that
the. good faith,
inadvertent failure
to obtain
a permit
in
the absence of
a pQllution violation could not support
a
$500
penalty.
In Harris—Hub Company,
Inc.
v. Pollution Control Board,
50 Ill.App.3d
608, 365 N.E.2d 1071
(1st Dist.
1977),
the court
found that the company’s good faith was shown by changing
the
plant’s heating
system,
installing
an afterburner,
ceasing
to
burn refuse entirely,
and beginning
a plan
to convert forklift
trucks and tractors from gas
or diesel
to electric power.
The
comPany had a good faith belief
that
no permit was required and
was not recalcitrant.
It had also begun
the permit application
process before the complaint was filed,
and the record did not
reveal any economic advantage gained from
its
failure
to obtain
a
permit.
In
a forceful commentary on seeking
a penalty
for permit
violations,
the court
stated:
Here,
however,
‘it
is
apparent
that
the
resources
of
the
EPA
and
the
PCB
would
have
been
better
served
by obtaining
compliance
by
polluters
rather than by seeking the sanctions
of
a
civil
penalty
for
a
technical
noncom-
pliance
by Harris.
Harris—Hub,
365
N. E.2d
at
1073
(emphasis
added)
(30
The Darrel Slager,
d/b/a Rapid Liquid Waste Case
Darrel Slaaer,
d/b/a Rapid
Licuid Waste and Rubbish Removal
v.
Illinois
Pollution
Control
Board,
96
Ill.Aop.3d
332,
421
N.E.2d 929,
(1st Dist.
1981)
presents the kind
of case
in which
111—30

the courts
readily uphold a penalty
for
a permit violation.
Here
a $1,000 penalty was affirmed where petitioner
showed “conscious
disregard”
of an Agency warning and the liquid wastes posed
“an
especially
great hazard
to the environment because of their
tendency
to spread quickly and react with other wastes.”
Darrel
Slager,
421 N.E.2d at 934.
Giving
a measure of support
for
the
function of permits,
the court noted
that,
“one of
the reasons
for
the permit requir~men’tis
to enable the Agency
t’o supervise
economically safe disposal methods for such substances.”
Penalties,
therefore, may be most appropriate where safety
hazards and the Agency’s
need
to regulate those
risks
are at
issue.
See
also:
R.E. Joos Excavating Co.
v.
Environmental
Protection
Agenca,
58 Ill.Aop.3d
309’,
374 N.E.2d 486
(3d Dist.
1978)
Case
No.
31,
affirminc $1,500 oenaltv for ooeratinc
a
refuse disoosal
site without
a oermjt;
?ielet Bros. Tradinc,
Inc.
v. Pollution Control
Board,
110
Il1.App.3d 752,
442 N.E.2d 1373
(5th Dist.
1982)
Case
No.
32,
affirmin.g
$7,500
penalty
for
operating
a solid waste management
site without
a permit and
other violations
for on-site practices and open burning
on
a
80
acre
automobile
shredding
and
junk
site.
(33
The Wasteland,
Inc.
Case
In
a
1983 case also involving
a solid waste landfill
site,
a
$75,000 penalty was upheld
for numerous violations of the Act and
regulations where operations were
far beyond
the scope of
the
permit.
Wasteland,
Inc.
v.
Illinois Pollution Control
Board,
118
Ill.App.3d
1041,
456 N.E.2d 964
(3d Dist.
1983).
Among other
violations,
the firm accepted unpermitted
refuse, carried on
salvage operations,
failed
to properly cover
the waste,
caused
leachate
problems,
and
handled
almost
three
times
the
amount of
waste estimated
in
its permit application.
The court summarized
the facts
as
“a
case of.continuinc blatant disregard
for
requirements and procedures designed
to protect
the environment
while permitting useful operations.”
Wasteland,
Inc.,
456
N..E.2d
at 976.
The court
found
that
real
dartqers were oresent with
these extensive violations,
and this gave support
to
the
“severity
oi
the punishment.”
Id.
The court
noted
that
the civil pena1t~was not
in excess of
the maximum $10,000 per violation and S1,000
per day,
given
that
violations were committed
for over
a year.
The court also found
it was within
the Board’s discretion
to assess this oenalty
in
light of
the Board’s finding
that Wasteland
had saved Sl7,000
to
$25,000
by burying unpermitted wastes and saved $45,000 due
to
violations
occurring
at
a paper
recovery site.
This penalty was
found
by
the
court
to
a~o enrorcement
or
the
Act,
for
tnrough
penalties
upon
those who blatantly disregard applicable
rules and
regulation,
others who might consider cutting corners at
the
expense of
the environment,
are deterred.”
Id.
Here, where
the
court did not
find good faith efforts
at comoliance,
and the
violators benefited at the clear expense of
the environment,
the
court favored
a high penalty which might deter others
as well
as
ii 1-37

the violators.
(For an early case involving violations of
landfill
rules and regulations for spreading,
compaction, ‘cover,
salvage, and for underground burning,
see Bath,
Inc.
v. Pollution
Control Board,
10
Ill.App.3d 507,
294 N.E.2d 778
(4th Dist.
1973)
(Case No.
34.
The case did not involve permit violations,
but
did support
a $2,000 penalty
for illegal landfill
practices,
including burning, which the court held did not require proof of
knowledge,
intent,
or
sc’ienter.)
35
The Citizens Utility Company of
Illinois
Case
Another example of
the courts
general reluctance
to impose
penalties
for permit violations absent
a showing of actual
pollution or harm
is
found
in Citizens Utilities Company of
Illinois
v.
Illinois
Pollution
Control
Board,
127
Ill.Apo.3d
504,
468 N.E.2d
992
(3d
Dist.
1984).
In
this
case,
the N?DES permit
for operation of,
and discharges
from,
a sewage
treatment plant
was allegedly violated due
to inadequate operation and
maintenance practices.
The court reversed the $1,000 penalty,
finding
that no adverse environmental impact had occurred.
36
The
Standard
Scrap
Metal Company Case
In Standard Scrap Metal Company
v.
Pollution Control
Board,
142 Ill.App.3d
655,
491 N.E.2d 1251,
1259
(First District,
1986),
the court
found
that
the company’s operation of
a furnace and
incinerator
for nine years and the associated air pollution
“exhibited
a blatant disregard
for the
rules and procedures
designed
to
protect
the environment.”
Affirming
a $30,000
penalty,
the court held
that petitioner had acted
in bad faith
and
that the permit violation had been accompanied
by heavy smoke
emissions which “endangered
the public health and safety,”
“created a safety hazard” on
the nearby highway, and caused
nearby workers
to become
ill.
Standard Scrap Metal,
491 N.E.2d
at
1255.
The court
found support
for the amount of the penalty
in the
Board’s
consideration of Section
33(c)
factors as well as the
savings derived
from noncompliance and the company’s history of
profits
spent
for officers’
compensation
instead of pollution
controls.
The
court
cited
Wasteland,
Inc.,
Case
No.
33,
where
the violations
had also involved “dangers
to
the environment” and
the “petitioner was a private party who reaped an economic
benefit
from violations.”
Standard Scrap Metal,
391
N.E.2d at
1257,
1258.
(But
see also:
Archer Daniels Midland
(1983),
Case
No.
24a,
where
the Fourth District rejected the savings evidence
and assertion of financial
ability
to
pay.)
The court likewise
adopted
the Wasteland,
Inc.,
(Case No.
33,
reasoning
that
the
fine would
aid enforcement of
the Act
by deterring others.
The
court noted
with favor
that
the Board considered Standard
Scrap’s
financial condition as
a
mitigating
factor.
However,
the court
also allowed
the Board
to take
judicial notice of petitioner’s
ii 1-38

noncompliance with an earlier Board order,
requiring
the
installation of pollution control devices,
as
a matter
in
aggravation.
The court. noted that
it was inconsequential that
the petitioner was a different legal entity than
that
in the
earlier order,
finding
that petitioner was the successor—in—
interest to the first entity.
Standard Scrap Metal,
491 N.E.2d
at
1258.
Ascribing more significance to permit violations
than some
other court opinions have,
the First District stated:
Contrary
to
Standard
Scrap’s
contention,
violation
of
the Act’s
permit
requirements
is
not
a
mere
“oaoer”
or
“minor”
violation.
Rather,
the
violation
of
a
permit
requirement
goes
directly
to
the
heart
of
the
state’s
enforcement
program
and
ability
to
protect
against
environmental
camage.
The
permit
program
is
a method through which
the State of
Illinois
can control
emitters
of
contaminants
into the atmosphere,
as well
as emissions
that
may
result
in
the presence
of contaminants
in
the environment....
(The
Act provides
that
where
a
permit
requirement
imposes
an
arbitrary
or
unreasonable
hardship,
a
party
can seek and obtain
a variance from the permit
requirement.
Standard
Scrap
Metal,
491
N.E.2d
at
1256
(emphasis added).
The court went
‘on
to note
that despite Agency efforts, Standard
Scrap did not comply with peririit requirements and did not appeal
its permit denials or
seek
a variance.
The court seemed
to
be
addressing
these points
in
the context
of lack of good faith,
but
it should be noted that
failure to seek
a variance was held by
the Second District
in 1990
to be an
inappropriate element
in
a
consideration of Section
33(c)
factors.
See Modmn.e
Manufacturinq,
193 Ill.P.pp.3d
643,
549 N.E.2d
1379
(2d Dist.
1990).
(Case No.
381
below.
37
The Trilla Steel Drum Corporation Case
A 1989 appeal involving
a $10,000 penalty
for the
failure
to
secure an operating permit
for manufacturing operations which
resulted
in ~iO~1em:ssions endec
in
reversal ann remana on
the
issue
of
the
penalty.
Trilla
Steel
Drum
Corooration
v.
Pollution
Control Board,
180 Il1.App.3d
1010,
536 N.E.2d
788
(1st Dist.
1989).
The penalty was based on the lack
of
a permit and
not on
any finding of
violation of emission regulations or
of bad
faith.
Standing alone,
then,
the permit violation was
found
to
he an
inadequate basis
for what
the court
labele.d “the maximum
penalty of $10,000.”
Id.,
536 N.E.2d at
791
(emphasis added).
I 11—30

The court did not explain how
it calculated
that $10,000 would
be
the maximum penalty for a violation of
the Act for
a period
in
excess of
15 months.
In
the court’s
view,
the
record showed that
the violation lacked the requisite seriousness
to warrant
this
penalty.
This was found
to be especially
true since an expired
permit and a variance application pending at
the time of the
complaint put Trilla within “the regulatory awareness of the
Agency.”
“The Board has not shown
that Trilla’s omrssion has
harmed
in a serious manner either
the information gathering or
oversight
roles of
the Agency.”
Trilla Steel Drum,
536 N.E.2d at
790.
Discouraging
the use of
a penalty
as
a general deterrent
to
violations,
the court advised that
“the
Board should not
attempt
to make an example of Trilla since
such
a practice has
been expressly disapproved
of by this court...”
Id.,
at 791
citing Southern Illinois Asphalt
Case
No.
4
and City of Chicago
v.
Illinois Pollution Control Board,
57
Ill.App.3d
517,
373
N.E.2d
512
(1st Dist.
1978)
Case
No.
39.
This case
illustrates
how, absent proof of actual or threatened
harm,
most
large
penalties
for permit violations have not been affirmed by
the
courts.
(38
The Modine Manufacturing Company Case
Modine Manufacturing Company
v.
Pollution Control
Board,
193
Ill.App.3d
643,
549 N.E.2d 1379
(2d Dist.
1990), was an appeal of
a $10,000 civil penalty
imposed by the Board on remand after
an
earlier appeal.
The $10,000 penalty was imposed
for operating
without a permit
in violation of Section 9(b)
of
the Act.
The
1990 court ocinion noted
that beginning
in late
1981,
Modine’s emission levels were found by
the Agency to exceed
regulatory
limits.
Despite efforts made by Modine,
emissions
remained excessive and the renewal
of
‘its operating permit was
denied
in
1983.
Contact with the Agency and corrective efforts
continued,
with Modine also spending $22,000
in
1984 and $310,000
in early
1985
to achieve compliance.
At
a June
1985 pre—
enforcement meeting,
the parties agreed that Modine
would
replace
its pollution control process with one based on
technology
it
purchased at
the $310,000 cost above,
and that
the Agency would
refrain from bringing an enforcement action
for emission.
violations.
The Agency brought an enforcement action
in
February,
1986 and the Board
imposed
a $10,000
fine
for operating
without
a permit since October,
1983 and for violations
of
particulate emission limitations.
In
the original appeal,
the
court
found
that
the Agency could
not pursue
the emissions
violation and remanded to
the Board on the sole issue of
the
appropriate penalty
for the permit violation.
Id.,
549 N.E.2d at
1381,
citing Modine Manufacturing Company
v.
Pollution Control
Board,
176 Ill.App.3d
1172,
549 N.E.2d
359
(1988).
On
remand,
the Board
imposed
a SlO,000 penalty
for the permit violation
alone.
Modine appealed
the Board’s decision and the court
reduced
the fine
to $1,000.
111—40

The Second District rejected appellant’s argument
that
a
penalty could
not aid enforcement since
the violation had ended
before the complaint was filed.
“(We
decline
to hold
categorically that penalties may not ~e imposed
for wholly past
violations.”
Modine Manufacturing,
549 N.E.2d at
1382,
citing
City of East Moline
v.
Pol1uti~onControl
Board,
136 Ill.App.3d
687,
693,
483 N.E.2d 642
(3d Dist.
1985)
(Case No.
41.
However,
when the court reviewed the
Board’s decision,
the cdurt
found
that although some penalty could be sustained,
the amount was
influenced
by
not only Section
33(c)
factors,
but Modine’s good
faith,
candor,
cooperation,
sincere efforts and exper.diture
of
substantial amounts of money
to remedy
the problem.
Modine
Manufacturing,
549 N.E.2d
at
1384.
The court
found
that $1,000,
and not $10,000, was
in keeping with the Supreme Court’s ruling
in Southern Illinois Asphalt,
Case
No.
4,
that all
the facts
and
circumstances
bearing
on
the reasonableness of the complained
of
conduct
and
the seriousness
of
the infraction must
be
considered
in
a penalty determination.
Citing Trilla Steel
Drum,,
C~se
No. 3~,
the court
found that Modine had become a part
of
the
regulatory
program
and,
therefore,
the
Board’s
estimate
of
the
seriousness
of
the
failure
to secure
a permit was
of
diminished importance.
Interestingly,
the court also found
that
Modine’s failure
to seek
a variance was not relevant
to the
Board’s ev~luationof
technical practicality
or economic
feasibility.
This was a
“procedural consideration”
only, which
the court
found excusable.
Modine Manufacturing,
549 N.E.2d at
1383.
Again,
a permit violation without attendant harm or bad
faith did not support
a
lar’ge penalty, much
less
the statutory
fine of up to $10,000
per violation, which
the court
here
referred
to as
the “maximum penalty of $10,000,” while noting
that
the Board had argued that
the statute also provides
for
a
$1,000 per day additional penalty.
Id.,
549 N.E.2d at
138$
(emphasis added).
As
in Trilla Steel
Drum,
Case
No.
37,
the
court did not explain how
it calculated
that $10,000 would
be the
maximum
penalty
for
several
years
of non—compliance with the
permit
requirements.
4.
Local Government
Cases
Penalty
cases involving local governments reflect
a certain
deference
to
the needs and workings
of those governir.g bodies.
The courts seem
to recognize
the nature of
the economic impact
of
a civil oenaltv on
the community.
Comoliance alternatives are
pernaps more l:m:tea
for
a public coc~consicering
tne
range or
public services which oust
be delivered consistently
to
the
public.
Among other services,
water,
sewer, and garbage
collection are imoortant health services orovided by
local
governments.
Their
costs are borne
by
the oublic and the ability
to finance
them involves
a variety of
issues,
such as
the health
of
the local
economy,
the availability
of bond
financing and the
oossibilities of state or
federal
aid.
Pollution control
measures
ann
any
penaities
tor
v~o1ations
a~so
ratse
tnese
questions.
Loo~z1ng to these
facts,
the courts seem
to allow
less
latitude
to
the
Board
where
th~
Board
has
attempted
to
impose
111-41

penalties
for violations of environmental laws.
The appellate
case law therefore shows
a pattern of frequently
reduced or
vacated penalties.
39
The City of Chicago Case
In 1978,
the First District
reversed a $10,000 penalty
for
operation of
a municipal
incinerator without
a permit
in
violation of Section 9(b)
of the Act, and for air pollution and
particulate emissions which violated Section 9(c).
The court
found that
“first,
petitioner demonstrated
a sincere desire
to
eliminate,
or
at
least
reduce,
stack emissions....
Secondly,
the
Board’s Order failed
to consider economic and technological
factors.”
City of Chicago
v.
Illinois Pollution Control
Board,
57
Ill.App.3d
517,
373 N.E.2d
512
(1st
Dist.
1978).
The court
was favorably
impressed by petitioner’s studies and efforts
to
minimize air pollution with respect
to all its facilities, and
not just
the one involved here.
Furthermore,
to modify
the
incinerator
in question would require
a two
year
shutdown
or
inordinate expense, given that
the City had ‘decided to abandon
it
and develop a new plant.
The court
found
that
the Board had
assessed
a large penalty despite mitigating circumstances and the
failure of
the Agency
to request
a penalty.
“Consequently, we
believe
the Board’s primary purpose was
to make an example out of
petitioner.
Such a purpose
is
improper and in this case violates
the requirement
that the penalty bear some relationship
to the
seriousness of
the infraction.”
City of Chicago,
373 N.E.2d at
516.
One more caveat was delivered
by
the court.
That was a
caution
to
the Board
in cases involving local government.
“Many
of
the considerations facing petitioner directly involved the
public sector.
The public would be
the ultimate loser
if
petitioner were
to shutdown operations.”
City of Chicago, 373
N.E.2d at
516
(emphasis added).
(40
The City of Moline Case
In The City of Moline
v.
Pollution Control
Board, 133
Ill.App.3d 431,
478 N.E.2d 906
(3d Dist.
1985),
the court vacated
a $90,000
fine
imposed
by the Board
for water pollution
violations associated with
the city’s sewage treatment plant.
Tne court agreed that
tne city had v~o~atedthe Act,
recunations,
and
its NPDES permit.
However,
the court
found
that
the serious
pollution problems were substantially cured before
the complaint
was
filed.
The court concluded,
therefore,
that
the penalty
could not aid enforcement
of the Act.
It reversed the penalty,
highlighting
two facts:
111-42

Two
significant
facts
dictate
against
the
imposition
,of
any
mandatory
penalty
by
the
Board.
First,
the
ends
sought
did
‘not
necessarily
require
the
bringing
of
the
instant complaint.
In working with Moline
to
solve
its
problems,
the
LEPA
chose
an
effective
and
appropriate
course
of
action.
Instead
of
jumping
the gun
in September
r980
and
bringing
an
action
against
an
obvious
polluter,
the
IEPA
took
the
prudent
course
of
seeking
alternative
means
to
assure
com-
pliance.
The
main.taining
of
this
course
produced,
if’ not with any great
immediacy,
the
initially
desired
result.
This
was
parti-
cularly
aoorooriate
in
that
the
IEPA
was
dealinq
with
neither
a
wilful
and
callous
oillaqer
of
the
environment
nor
a
orivate
party
for
whom
delayed
compliance
would
translate
into
oersonal
gain.
Second,
one
must
consider
the
identity
of
the
respon-
dent.
The burden
of
the
fine
would
be
borne
by
the
taxeavers
of
Moline.
While
the
Board
points out
that
the under—assessment
of
these
taxpayers
was
a
contributing
reason
for
Moline’s
noncompliance,
it
would
serve
no
useful purpose
to punish
them
further
for
the
violations
charged.
It
should
also
be
noted
that
an
increase
by
165
in sewer
assessments
was
necessary
to
finance
the
measures
instituted
by Moline.
City
of
Moline,
478
N..E.2d
at
908,
909
(emphasis added).
The court seemed
to be distinguishing municipalities which
make some efforts at compliance
from private parties who might
personally profit from noncompliance.
Economic gain from
noncompliance might
be relevant
in assessing
a penalty,
but
the
court implied
that this factor
is not
as meaningful
for a
munici~ality,
since
the
benefit
is
not
personal
in.
nature.
The
court
reached this conclusion despite
the Board’s
finding
that
Moline’s
delayed
compliance
resulted
in
savings
in
excess
of
$1.3
million.
(See
IE?A
v.
City of Moline,
60 PCB 01,
17,
PCB 82—154,
Sept.
6,
1984.)
‘The court also observed
that the burden of
a
penalty would be borne by
the taxoayers who ultimately pay for
the
municipality’s
environmental
programs.
The
court
seemed
sympathetic
to Moline’s situation,
and,
therefore,
reversed
the
$90,000
fine completely,
even though the Board had calculated
the
maximum penalty at $43,697,000.
11-
~‘.
3

_,
~1
(41) The City of East Moline Case
The
case
of
City
of
East
Moline
v.
Pollution
Control
Board,
136 Ill.App.3d
687,
483 N.E.2d 642
(3d Dist.
1985)
involved
violations of
permits and of various
regulations governing
the
city’s sanitary landfill,
such as clay cover
requirements,
control of leachate and vectors
(animals/insects), and dumping
practices.
The court
reduced the penalty from $30,dOO
to
$10,000,
finding that many of
the violations
had ended before
enforcement proceedings began
(including ~some of which were cured
by the issuance of permits).
It also held
that the Agency’s
conduct
from the early 1970’s until
1980
“represent(ed
an
accommodation
to and an acceptance of
an
inappropriate level of
compliance which can not now be characterized
as bad faith.”
City of East Moline,
483 N.E.2d at
648.
The court was willing
to
impose
a penalty
for violations which were related
to “conditions
existing
at the time
the enforcement proceedings were
instituted,” which
...“might well promote compliance
with
the
violated sections of the regulations.”
Id.
at
648.
A penalty
might
then help bring
about
a municioaliE~s compliance
if
enforcement
relates
to violations
of
a current
nature.
42
The City of Freeport Case
In a 1989 decision,
the Second District showed much
less
deference where
a City’.s sanitary sewer backed up and overflowed
into homeowners’
yards and flooded basements over
a 20-year
period.
In City of Freeport
v. Pollution Control Board,
135
Ill.Dec.
644,
544 N.E.2d
1
(2d Dist.
1989)
a $10,000 penalty was
affirmed based on the court’s concurrence with
the Board’s
evaluation of Section
33(c)
factors.
The court
noted
that
the
long—standing violations
imposed “an extreme inconvenience on
homeowners as well as health risks.”
City of
Freeport’,
544
N.E.2d at
4.
The Board
found
that the solutions were neither
technically impracticable or
economically unreasonable.
Firmly
supporting
the Board’s decision,
the court also noted
that
the
Board had authority
to impose
a fine of $1,000
per day,
but did
not.
C.
Penalty Factors Derived From Illinois Case Law
The courts have reviewed
the Board’s penalty decisions
by
balancing statutory and other
factors relevant to
the reason-
ableness of
the pollution offense.
The statutory guidelines are
delineated
in Section
33(c)(l)
through
(6).
The other consider-
ations are discussed
in the cases under
the Section 33(c)
directive
to consider all the
facts and circumstances.
Some
,of
these factors addressed
in
the body of case
law are good faith,
any deterrent effect
of
a penalty, economic benefits of non-
compliance,
ability
to pay,
and cessation and duration
of
a
violation.
Court-enunciated principles
on
these factors are
discussed
below.
I,
I.
i
j’+—~

~
1.
Statutory Factors
The
six
statutory
criteria
of
Section
33(c)
to
be
considered
in
enforcement
cases provide only the starting point
in a penalty
determination.
The statute specifically states that
“the Board
shall
take into consideration all the
facts and circumstances
bearing upon the reasonableness of
the emissions,
discharges,
or
deposits involved including,
but not limited to”
th4 six
criteria.
See
also
Modine
Manufacturing,
(Case No.
38,
and
Southern Illinois Asphalt,
(Case No.
4.
Those enumerated
factors may
be characterized as
(1)
harm,
(2)
social and
economics value,
(3)
acorooriateness
of
location of the oollution
source,
(4)
technic-al practicability and economic reasonableness
of pollution control,
(5)
economic benefits
of
noncompliance,
an.d
(6)
any
subsequent
compliance.
The
courts
have
not
weighted
these factors
in terms
of relative importance.
However,
in
keeping with the Supreme Court’s emphasis
in Southern
Illinois
Asohalt,
(Case
No.
4,
on the seriousness of
the offense or
infr~Eion, physical ailments or serious health risks have
generally warranted imoosing penalties.
See Marblehead
Lime,
Case
No.
18
Darrel Slacer,
(Case No.
30,
Wasteland,
Inc.,
Case
No.
33.
On the other
hand,
permit violations,
absent bad
faith or
harm,
generally have not been sufficient
to support
a
penalty.
See Southern Illinois Asphalt,
(Case No.
4,
Harris-
Hub,
Case
No.
29.
Another
key fact,
the availability of
control technology that
is not prohibitively costly,
has
generally justified
a penalty.
See Aluminum Coil Anodiz~,
Case
No.
11;
Lloyd
A.
Fry Roofing,
(Case No. .121;
Standard
Scrap Metal,
Case
No.
36).
However,
no formulae exist,
and
essentiaIT~, the Board must make
a case—by—case determination.
2.
Good Faith
The courts have found evidence of
the presence or absence of
good faith
to be
a very significant determinant
of
a penalty.
Good faith has not been found
to be
a matter of
intent, since
intent
or guilty knowledge
is not a necessary element
to finding
a violation.
Rather,
good. faith has been inferred from behavior
which reflects diligence and which
is reasonably directed
towards
the goal of achieving compliance.
The acceptable efforts have
included hiring engineers
to find
a cure for pollution,
attempting
to secure permits, installing pollution control
equipment
at considerable expense, and abandoning offensive
practices all together.
See,
e.g., Citvof
Chicaao,
Case
No.
39), Harris—Hub,
Case
No.
291,
Archer
Daniels
Midland,
Case
No.
24), Modine Manufacturinc,
(Case No.
38.
The quantum of goon fa~tneffort
to achieve success may nave
fallen short
of successful pollution abatement,
and yet the court
has found
that
no penalty was justified,
even though some
violation had been found.
Bresler
Ice Cream,
(Case
No.
13,
Chicago Magnesium Castinc,
Case
No.
14),
CPC
nternational,
(Case
No.
15,
Arnold
N.
May,
16.
Bad faith
or
clatan.t
disregard of en~ironmental laws, however, stroncly supports
a
111-$5

penalty.
See Wasteland,
Inc.,
(Case No.
33,
Standard Scrap
Metal,
Case
No.
36).
3.
Other Considerations
a.
Aiding Enforcement
by Deterring Others
Some conflict exists over whether deterring others from
violating environmental laws
is an appropriate element
in
assessing
civil penalt-ies.
In the 1976 case, Aluminum Coil
Anodizing,
Case
No.
11,
the court
explained
that
a $1,500
penalty would aid enforcement
“by working
to secure voluntary
compliance with the Act
in other cases,
especially
by ACA at its
new facility.
Id.,
315 N.E.2d at 619
(emphasis added).
Here,
the company had made no good faith efforts at curing an odor
problem for over one year after
the complaint was filed.
In the
absence of further explanation from the court,
the penalty might
be considered as generally deterring similar bad faith
in others,
and thereby, indirectly
fostering compliance.
Similarly,
in 1983 the court
in Wasteland,
Inc.,
Case
No.
33,
held
that
the $75,000 penalty
for blatant disregard of
landfill rules and regulations would aid enforcement since
“others, who might consider cutting corners at
the expense of the
environment, are deterred.”
Id.,
456 N.E.2d at 976.
This
position was specifically adopted
in 1986 by the First District
in Standard Scrap,
Case
No.
36.
That court
found that
a
$30,000 penalty
for the bad faith violation of air pollution laws
would aid enforcement
of the Act by deterring others.
However,
in 1989 the First District admonished the Board not
“to make an example” of
a company against whom the Board assessed
a $10,000 penalty
for failure
to secure an operating permit.
Trilla Steel
Drum,
536 N.E.2d at 791.
In this case neither harm
in the form of excessive emissions
nor bad faith was proved.
The
court relied on the Supreme Court decision
in Southern Illinois
Asphalt,
(Case No.
4,
and
its
own
decision
in City of Chicago,
Case
No.
39,
both of which involved permit violations.
In both
of these early cases,
the courts found
that
in light
of all the
facts and circumstances,
the violations were
not sufficiently
serious
to justify the penalties, and the primary purpose of
a
penalty
is
to aid enforcement of the Act.
In
the City
of
~
(Case No.
39,
the First District reversed a $10,000
penalty since
it believed
that despite
the City’s substantial
efforts,
the Board’s primary purpose
“was
to make an example out
of petitioner.
Such
a purpose
is improper...”
Id.,
373 N.E.2d
at
516.
Thus, while
the Board has some appellate
court
support
for assessing penalties which might deter others, some Illinois
decisions suggest
that
this
cannot be
the Board’s primary purpose
in assessing penalties, although
higher penalties may be
warranted
for relatively more serious violations or
those
evidencing
bad faith.
111—00

b.
Economic Benefit From Non—Compliance
Independent. of the 1987 statutory amendment requiring
consideration of economic benefits,
some appellate courts have
acknowledged that the Board may consider whether
a violator has
gained an economic benefit or cost savings from delayed
compliance as part of
a penalty determination.
In Wasteland,
Inc.,
Case
No.
33,
total cost savings
of $62,000
to
$70,000
were considered
in affirming
a $75,000 penalty
for blatant
violations
of landfill requirements.
Similarly,
in Standard
Scrap Metal,
(Case No.
361,
the court noted
that
“in Wasteland,
as
in this case,
the petitioner was a private party who reaped an
economic benefit-from violations.”
Id.,
491 N.E.2d at
1258.
In
affirming
a $30,000 penalty
for
nine years of
blatant violations,
the court
supported
the Board’s reliance on an Agency estimate of
cost savings of approximately $104,500.
The court
found
that the
evidence showed
“a substantial economic savings by Standard Scrap
at the expense of the public health and welfare,” which was
properly considered by
the Board.
Id.,
491 N.E.2d at
1259.
The cost savings was found
to be estimated conservatively
and was based on the following evidence:
James Levis,
economist employed by the Agency,
testified
that
Standard
Scrap
saved
approx-
imately
$104,500
by
failing
to
install
the
afterburner
required
by
the
1974 order.
This
figure
was
arrived
at
based
on
a
computer
progtam adopted
by
the United States Environ-
mental
Protection
Agency
(USEPA).
Levis
testified
that
the
computer
program
utilizes
the following
data:
the estimated cost of the
afterburner
at
the
time
that
it was
initially
to
be
installed;
the
prevailing
rate
of
inflation
for
the
relevant
time
period;
the
discount
rate,
based
on
Standard
Scrap’s
average
return
on
stockholders’
equity;
the
interest
rate
on
Standard
Scrap’s
long
term
debt;
Standard
Scrap’s
marginal
income
tax
rate;
the investment
tax credit
rate;
Standard
Scrap’s
capital
structure;
and
the
depreciation
life
of
the
afterburner
equipment.
Id.,
491 N.E.2d at 1255
These
two cases relied on
cost savings by
a violator
who was
found to have acted
in bad faith.
Other
cases suggest
that
the
cost savings may carry less weight when good faith efforts have
been shown.
In Harris-Hub,
(Case
No.
29,
for
example,
the court
reversed
a
$500 penalty based on good faith and inadvertence
in
failing
to obtain
a permit.
Further
support
for vacating
the
penalty was the absence of apparent benefit
from non-
compliance.
“Tihe
record
fails
to disclose that
Harris was
111—47

gaining any economic
advantage over
its business competitors
considering
the expense incurred
in controlling possible
pollution
in its manufacturing procedures.”
Id.,
365 N.E.2d at
1075.
Good faith was of primary importance, but economic benefit
was nonetheless relevant.
In Archer Daniels Midland,
Case
No.
24a,
the court
focused
more particularly on the relative importance
o’f good faith and
cost savings from non—compliance.
Here,
the court
rejected the
savings data,
finding that
the purported savings couldnot
be
calculated and the penalty had been based on improper and
incompetent evidence of savings.
The court distinguished
Wasteland,
Inc.,
(Case No.
33,
holding
that Wasteland’-s
continuing blatant disregard was of greater significance than the
violator’s
savings.
The court
implied
that multi—million dollar
environmental expenditures might outwiech cost savings even
if
adequately proved.
Yet the court
did not
reject savings as
a
penalty factor per
Se.
In vacating
the penalty against
the city in The City of
Moline,
Case
No.
40,
the court relied
in part
on
the contrast
between
the city and a
“private party for whom delayed compliance
would translate
into personal gain.”
Id.,
478 N.E.2d at
908,
909.
Clearly,
this reflects the relevance of possible econ,omic
benefits due
to non-compliance
,
but would limit
the savings
factor
to non—governmental entities.
Consideration of
the economic benefits of non—compliance
became part of
the statutory factors listed in Section
33(c)
when
Sec.tion 33(c)(5) was added in 1987.
That Section now requires
the Board
to consider “any economic benefits accrued by
a non-
complying pollution source because of
its delay
in compliance
with pollution control
requirements.”
Section 33(c)(5).
c.
Ability
to Pay
In Standard Scrap Metal,
Case
No.
36,
(1986)
the court
considered evidence
of
five years financial history in deciding
that petitioner
could have installed pollution control
equipment
many years prior
to the filing of
the complaints
Rejecting
arguments of current inability
to pay,
the court
found that
the
hardship was self—imposed, even
if
the economic viability of the
business was endangered.
If
Standard
Scrap
does
not
now
have
funds
to
cover
both
penalty
and
compliance
costs,
as
well
as
cease
and
desist
operations
until
compliance
is achieved,
that hardship
is self—
imposed.
The
company
should
have
taken
the
necessary
steps
to
bring
its
facility
into
compliance
when
firstS notified
by
the
Agency
and
at
a
time
when
sufficient
funds
were
available
to do
so.
Standard Scrap cannot now
be
allowed
to
pass
off
a
necessary
cost
of
111—48

doing
business
in
this
state,
and
one
borne
equally
by
competitors,
by
arguing
that
compliance with environmental laws will put
it
out
of
business.
If
that
were
the
case,
no
business would ever
be inclined
to comply with
Illinois’ environmental requirements.
Id.,
491 N.E.2d at
1257
This was considered
in
the court’s discussion of technical
practicality and economic reasonableness under
33(c).
That this
petitioner
could have afforded to control pollution weighed
in
favor
of imposing
a penalty.
The court distinguished the City
of
Moline,
Case
No.
40,
since Standard Scrap’s violations were
wilful, ongoing,
of longer duration,
and not involving
a
governmental
entity.
A separate issue
is whether petitioner
could afford
to pay a
penalty of $30,000.
Here,
the court noted
that
“the Board,
in
determining
the amount of
the fine,
took
into account Standard
Scrap’s financial condition as
a mitigating factor.”
Id.,
491
N.E.2d at 1258 (emphasis added).
The court also observed that
the Board indicated that an extended payment plan thight be
possible,
otherwise payment would
be due within
90 days.
The
court
thus supported an inability
to pay as
a factor which
rttight
warrant
a smaller penalty or modified payment plan.
The converse of
this principle may not be .true.
Financial
strength may not warrant
a larger penalty than would
be imposed
solely on the basis
of the seriousness
of
the violations.
In
fact,
the Fourth District in Archer Daniels Midland,
Case
No.
24a,
rejected the Board’s argument that $40,000 was a de minimus
penalty for
a large financially strong petitioner.
The court
stated,
“We are not aware
off
~nv authority which makes
the
ability to pay the proper basis
for a civil penalty.”
Id.,
456
N.E.2d
at
99.
Thus,
the Board may not approach penalties like a
progressive tax, growing
in proportion
to net worth and income.
Yet this
is not
to say
that
economic reasonableness pursuant
to
section
33(c)
is any less relevant
or that
the Board may
not
consider
ability
to pay
in
mitigating
the penalty.
(See also
pages 45—46
herein for applicability of ability
to pay
in federal
penalty decisions.)
The City of
Moline
case,
Case
No.
40,
suggests that
the
consideration of ability’to pay differs
in
the case of
local
governments as compared with private parties.
Since
a local
government’s expenses must
be
borne
by
its
taxpayers,
a penalty
may be more punitive
that
it
is an aid
to enforcement.
A
municipality’s limited ability
to pay,
therefore, may be
considered
in mitigation of
a penalty, although
it certainly does
not wholly negate the possibility
of
a penalty.
(See,
e.g.,
City
of Freeport,
(Case No.
42,
upholding $10,000 penalty.)
11 1—4”

As the earlier discussion
of Illinois Supreme Court
and
~ppel1ate
Court decisions
reveals,
the courts have reversed a
high percentage
of the Board’s penalties against
nunicipalities.
(See footnote
7
at page
58 and Tables ‘Nos.
5 and
6,
at page
68,
69.)
The theme that compliance
by municipalities
involves unique circumstances
is often stated
in state and
federal court decisions.
At
the
federal
level,
for example,
this
is reflected
in the USEPA’s highlighting
in
its l98~report
that
it had just secured
its highest penalty against
a municipality
$1,125,000.
This
is about half of what USEPA highlighted for
penalties against non—municipalities for RCRA and Clean Water Act
violations.
(See discussion herein at page
63.)
Similarly,
for
Illinois,
the highest penalty against a municipality was the
$10,000
penalty,
noted above,
assessed against
the City of
Freeport.
The status of
a violator as
a
unit of
local government
thus seems
to be
relevant in a penalty case,
and appears closely
related
to
issues’ such as who re,ally pays
the penalty.
Although
the Board would not quantify or predict
the degree
to which
municipal status may affect
a penalty decision,
this
is part of
the totality of facts and circumstances
to be considered.
d.
Cessation and Duration of Violation
In the City of East Moline,
Case
No.
41,
the Third
District reviewed other decisions on the subject of whether
a
penalty can aid enforcement of the Act
if
the violation has
ended.
That court drew the following conclusion:
If
compliance
with
proper
environmental
practices
is
the primary purpose
for
imposing
civil penalties
then prohibited practices long
discontinued are not an appropriate
basis
for
the assessment
of civil penalties.
This does
not
mean
that
cessation
of
the
violation
before
the
enforcement
proceeding
commences
should bar the assessment of
a pena~~if such
penalty
is related
to compliance with
the Act.
Where
previous
conduct
constituting
environmental
violations
has
been
discon-
tinued,
penalties
assessed
by
the
Board
have
been
reversed
in
such
cases
as
Southern
Illinois
Asphalt
Co.,
Inc.
v.
Pollution
Control
Board
60
Ill.2d
204,
326
N.E.2d
406
(1975);
Bresler
Ice
Cream
Co.
v.
Pollution
Control
Board
21
Ill.App.3d
560,
315
N.E.2d
619
(1974),
Chicago
Magnesium
Casting
v.
Pollution Control Board
22
Ill.App.3d 489,
317
N.E.2d 689
(1974);
CPC International,
Inc.
v.
Pollution Control Board
24 Ill.App.3d
203,
321
N.E.2d
58
(1974).
A
review
of
the
afore-
mentioned
cases
reveals
a
pattern
indicating
the relationship of
the enforcement proceeding
1,11—50

and
the discontinuance
of
the
violation.
The
longer
the
time
period,
the
lapse
between
cessation of the violation and commencement
of
the
enforcement
proceeding,
the
more
likely
such
enforcement
proceeding
is
apt
to
be
considered punitive only having
no relation
to
securing compliance with
the Act.
City
of
East
Moline,
483
N.E.2d
at
647,
648.
See
also
City
of
Moline,
Case
No.
40)
(emphasis added).
The absence of
a continuing violation has persuaded the
courts
to
vacate
or
reduce
penalties,
as
in.the case of Citvof
East Moline where
the fine was reduced because
some violations
had long since been cured.
However,
in
1988
the Act was amended
to
add
to
Section
33(a)
that
“(it
shall
not
be
a
defense
to
findings of violation.
.
.
or
a bar
to the assessment of civil
penalties
that
the
person
has
come
into
compliance
subsequent
to
the violation.”
This fact was noted
in the 1989 case, Modine
Manufacturing,
Case
No.
38,
where
the Second District stated
that
“we decline
to hold categorically that penalties may not
be
imposed for wholly past violations.”
Modine Manufacturing,
549
N..E.2d at
1382.
The court reaffirmed the Illinois Supreme
Court’s ruling
in Southern Illinois Asphalt,
Case
No.
4,
that
all the relevant
facts and circumstances must be examined
in
a
penalty determination.
Section
33(c) was also amended
in
1988,
and now Section 33(c)(6) provides
that the Board shall consider
“any subsequent compliance”.
This
is now to be considered
in any
penalty determination but neither negates
nor mandates a penalty.
D.
Summary Outline of
Illinois Statutory and Judicial
Penalty Considerations
The statutory factors which
the Board must consider are
summarized
as
follows:
*
All the
facts and circumstances,
Section
33(c).
*
Character
and
degree
of
injury
or
interference.
Section 33(c)(l).
*
Social and economic value.
33(c)(2).
*
Suitability/unsuitability
of
pollution
source
to
its
locale.
Section
33(c)(3).
*
Technical
practicability
and
economic
reasonableness
of
pollution
abatement.
Section 33(c)(4).
*
Economic
benefits
of
non-compliance.
Section
33(c)(5).
111-51

*
Any
subsequent
compliance.
Section
33(c) (6).
In addition
to these statutory factors, according
to the
Illinois courts,
several other considerations appear
to be
significant:
*
Conduct
suggesting
the
presence
or
absence of good faith.
*
Whether
the
penalty will aid enforcement
of
the Act by deterring non—compliance.
*
Ability
to
pay.
(Including
governmental
or private party status).
*
Duration of the violation.
*
Cessation
of
the
violation
prior
to
commencement of enforcement proceedings.
E.
Illinois Legislative Intent
The Illinois Legislature has responded to’the need
for the
effective use of penalties
in enforcement cases by revising both
Section
33 and Section
42 of
the Act.
As previously discussed,
Section
33 provides
for
the Board’s issuance of
final orders and
determinations
in enforcement cases and authorizes
cease and
desist orders and penalties.
The Board
is
required to consider
various factors.including,
but not limited
to,
those specified
in
Section 33(c)(l)
through
(6).
Penalty amounts are governed by
Section 42.
Section
33(a) was amended
in response to various Illinois
court decisions
wher’e
the penalties were held inappropriate since
compliance had been achieved before the Board made its findings
and assessment
of penalties.
One particular
court decision which
spurred
this legislative initiative was the Moline case,
(Case
No.
40,
In IEPA v.
City of Moline,
60
PCB 01,
PCB 82—154,
Sept.
6,
1984,
the Board imposed
a $90,000 penalty
for many years of
violation,
but the court
reversed the penalty, primarily due
to
Moline’s eventual compliance.
City of Moline
v.
PCB,
133
Ill.App.3d
431,
478 N.E.2d
908
(3d Dist.
1985).
The following
sentence was added
to Sect’ion 33(a)
in
1988, and addresses this
kind of fact situation:
It
shall
not
be
a
defense
to
findings
of
violations
of
the
provisions
of
the
Act
or
Board
regulations
or
a
bar
to
the assessment
of
civil
penalties
that
the
person
has
come
111—52

into
compliance
subsequent
to
the
violation,
except
where
such
action
is
barred
by
any
applicable
State
or
federal
statute
of
limitation.
This section essentially fortified the Board’s enforcement
authority.
A reviewing court could no longer predicate reversal
of a Board decision on the mere
fact of subsequent
c’ompliance.
Last minute or delayed compliance
thus could not be used
to
shield
a violator
fr,om enforcement and possible penalties.
Section 33(c)(5) was added
in
1987 and requires the
consideration of
“an-y’economic benefits accrued by
a non-
complying pollution source because of
its delay
in compliance
with pollution control requirements.”
Thus,
the Legislature
authorized
the
Board
to
recapture
the
gain
derived
from
polluting,
thereby removing the incentive to defer compliance.
Although this
is one of several Section
33(c)
factors,
this added
section mandates that
the Board consider whether
a pollution
source has profited frOm its violations.
Section 33(c)(6) was added
in 1988
and, requires
the Board
to
consider
“any subsequent compliance.”
Later compliance,
then,
is
but one of many factors
to be considered by the Board.
This
factor
is
to be evaluated as
part of
the totality of
facts and
circumstances.
Other factors remain significant
in the Board’s
determination,
even
if subsequent compliance
has been achieved.
Section
42(a) was amended in
1989
to increase the maximum
statutory penalty
from $10,000 per violation
to ‘$50,000 per
violation.
The additional
penalty of $1,000
for each added day
of violation
was
increased
to $10,000 per day of continuing
violation.
The effective date of
this
increased statutory
penalty was January
1,
1990.
The higher Illinois penalties are
now more consistent with federal enforcement penalties.
Overall,
the Board must conclude that legislative amendments
since 1970 have almost all been
in the direction of
increasing
the amount
of civil penalty which would be recovered from a
violator.
II.
OVERVIEW OF FEDERAL LAW ON CIVIL PENALTIES
A.
Federal Statutory Considerations
Various
federal statutes mandate
that
Illinois conform
its
regulatory
and enforcement activities with federally established
requirements.
As an example,
the 1965 Amendments
to
the Federal
Water
Pollution Control Act required that every state
adopt water
quality standards subject to
federal approval.
Later amendments
to this Act also established National Pollutant Discharge
Elimination System (NPDES)
permit requirements by which the state
Agency issues permits and
is charged with continuing enforcement
duties
(See
33 U.S.C.
1342
and Section
39
of
the Illinois Act).
111—53

Similarly
the Clean Air Act requires state adoption and
enforcement of state implementation plans
(SIP’s)
to achieve
national goals
for ambient
air quality.
For this
reason federal
statutes, case
law,
and policy pronouncements should help
to
guide enforcement actions,
including penalty determinations,
at
the state level.
As one example,
the Federal
Water Pollution Codtrol Act,
commonly known as the Clean Water Act,
includes an enforcement
scheme that contemplates primary enforcement by the state and,
alternatively, enforcement
by
the Administrator of
the United
States Environmental Protection Agency (“USEPA”).
Section
309(a),
33 USC 1319(a).
The Administrator has authority
to seek
injunctive
relief, criminal penalties,
and civil penalties
(Section
309(b),
(c),
,(d),
respectively).
Section 309(d)
provides for civil penalties of up
to $25,000 per day for each
violation and requires the court to evaluate various factors,
just
as Section 33(c)
of the
Illinois Act requires consideration
of certain factors.
In
determining
the
amount
of
a
civil
penalty
the
court
shall
consider
the
seriousness
of
the
violation
or
violations,
the
economic
benefit
(if any)
resulting from the violation,
any history of such violations, any good-faith
efforts
to comply with the applicable require-
ments,
the
economic
impact
of
the penalty
on
the
violator,
and
such
other
matters
as
justice
may
require.
For
purposes
of
this
subsection,
a
single
operational
upset
which
leads
to simultaneous violations
of more
than
one pollutant
parameter
shall
be treated
as
a
single violation.
Section
309(d)
of
the
Clean
Water
Act,
33
U.S.C.
1251 et
seq.
Section
309(g) provides
a more expeditious alternative
to
judicial enforcement.
It creates
a system for administrative
penalties, which are assessed, after consultation with
the state,
in dollar amounts which are less
than
the $25,000 per day
for
judicial enforcement provided under Section
309(d)
above.
Administrative penalties are grouped under
class
I
or class
II
civil penalties.
A class
I civil penalty
“may not
exceed $10,000
per violation,
except
that the maximum amount of any class
I
civil penalty...shall
not exceed $25,000.”
Sec.
309(g)(2).
This
carries
a
right
to a limited-hearing
to “provide a
reasonable
opportunity
to be heard and
to present evidence.”
Section
309(g)(2)(A).
A class
II civil penalty has the same $10,000 per
day maximum, but the
total assessed shall
not exceed $125,000 and
the right
to a hearing
is
in accordance with section 554
of title
5,
United States Code.”
Section 309(g)(2)(3).
Section
309(g)(3)
provides guide1ine~similar
to the
5 factors
off Section’309(d)
above’:
111—54

—.*~—
In
determining
the
amount
of
any
penalty
assessed
under
this
subsection,’
the
Administrator
or
the
Secretary,
as
the
case
may
be
,
shall
take
into
account
the
nature,
circumstances,
extent
and
gravity
of
the
violation,
or
violations,
and
,
with
respect
to
the
violator,
ability
to
pay,
any
pr’ior
history
of
such
violations,
the
degree
of
culpability,
economic
benefit
or
savings
(if
any)
resulting
from
the
violation,
and
such
other
matters
as
justice
may
require.
For
purposes
of
this
subsection,
a
single
operational
upset
which
leads
to
simultaneous
violations
of
more
than
one
pollutant
parameter
shall
be
treated
as
a
single
violation.
Section
309(g)(3)
of
the
Clean
Air
Act,
33
U.S.C.
1251 et
seq.
Obviously,
these federal statutory factors, which must be
considered
in
setting
the amount of
the penalty, are similar
to
the Illinois statutory directives
in Section
33(c).
Noticeably
different,
however,
is the federal focus on the history of past
violations,
the degree of culpability,
and the economic impact
of
the penalty on the violator or
the ability
to pay.
Of these
considerations,
only the federal acceptance
of .the relevance of
ability to pay seems at odds with at least one Illinois Appellate
Court decision.
In the ‘1983 Archer Daniels Midland decision,
Case
No.
24a,
the court was “not aware of any authority which
makes the ability
to pay the proper basis, for
a civil penalty.”
Id.,
456 N.E.2d at
99.
Certainly
the 1987 Clean
Water
Act
Amendments
in Sections 309(d)
and
(g) now provide at
least
conceptual authority on this
issue.
Furthermore,
the legislative history of the Clean Water Act
indicates
that certain
factors,
including
the economic impdct of
the ‘penalty on
the violator,
have
long been held relevant
to
a
penalty determination.
In
1977 at
the time of
the enactment
of
amendments
to the Clean Water Act, Senator Muskie cited
the
USEPA’s
penalty calculation policy with
favor.
123 Cong.
Rec.
39193
(1977).
The penalty policy was used
in settlement
negotiations with violators.
Factors
to be considered
in
negotiations
were
the seriousness of
the offense,
prior
violations,
good faith efforts
toward compliance and the economic
impact of
the penalty.
(For detailed discussion
of legislative
history,
see:
W. Andreen,
“Beyond Words of Exhortation:
The
Congressional Prescription for Vigorous Federal
Enforcement
off
the Clean water Act.”
55
Ceo.
Wash.
L.
Rev.
202
(1987).
See
also:
M.
Brown,
D.
Cerger,
C.
Harris,
The Water Quality Act
of
1987:
Expansion of
the Government’s Criminal, Civil and
Administrative Enforcement Authority.
144 PLI/Lit
95
(1987);
Tuilv.U.S.,
below)
111—55

B.
U.S.
Supreme Court Cases: The Tull and Gwalney Decisions
1.
The Tull Case
A 1987
U.S.
Supreme Court case also sheds
light on the
nature of penalty determinations
in environmental cases.
In Tull
v. U.S.,
481 U.S.
412
,107
S.Ct.
1831
(1987),
the p4titioner
appealed the district court’s findings of violations of
the
dredge
a,nd fill
res-trictions of
the Clean Water
Act which
resulted
in a $325,000
civi,l penalty.
The Supreme Court remanded
the case,
concluding ,that the Seventh Amendment entitled
petitioner
to a
jury
trial
to determ~nehis liability,
but not
to
determine
the amount of any penalty.~
In this case
the government had sought the maximum civil
penalty of $22,890,000 and the district court assessed a S325,000
penalty.
The Supreme Court
found
that the penalty determination
was within the district court’s discretion and that calculating
the amount did not warrant
a
jury trial.
The Court held
that
Congress has the authority
to set civil penalties and
it may
delegate the penalty determination to trial
judges.
The Court
found that this was Congress’
intent based on the legislative
history.
The legislative history of
the 1977 Amendments
to
the
Clean
Water
Act
shows,
however,
that
Congress
intended
that
trial
judges. perform
the
highly
discretionary
calculations
necessary
to
award
civil
penalties
after
liability
is
found.
123
Cong.
Rec.
39190—
39191
(1977)
(remarks
of
Sen.
Muskie
citing
letter
from
EPA
Assistant
Administrators
of
Enforcement
of. Dec.
14,
1977).
(“Penalties
assessed
by
judges
should
be
sufficiently
higher
than
penalties
to
which
the
Agency
would
have
agreed
in
settlement
to
encourage
violators
to settle”.)
Id., 481 U.S.
at 425.
Most importantly
for today’s discussion of civil penalties,
the Supreme Court
found that
the civil penalty was,
by
its very
nature,
punitive.
“The more
important characteristic of the
The Court noted also that
it has “considered
the practical
limitations of
a
jury
trial and its functional compatibility with
proceedings outside of traditional courts of law in holding
that
the Seventh Amendment
is not applicable
to administrative proce-
edings”.
Tull
v.
U.S.,
$81
U.S.
at
$18 citing Atlas Roofing Co.
v.
Occupational
Safety and Health Review Coram’n,
430 U.S.
$42,
454
(1977);
Pernell
v.
Southall Realty,
416 U.S.
363,
365
(1974).
111—50

remedy of civil penalties
is
that
it exacts punishment
a kind
of
remedy available only
in courts of
law.
Thus,, the remedy of
civil penalties
is similar
to the remedy of punitive damages.”
This
U.S.
Supreme
Court holding seems clearly to diverge from
some
earlier
Illinois case law.
The Supreme Court
then looked at
the legislative history of the Clean Water Act concerning USEPA
penalty policy and concluded
that Congress clearly intended that
the maximum penalty of $10,000 per ‘day’ of violation ‘should serve
to punish violators and not just equitably
recover
profits’ gained
from violations.
The
legislative
history
of
the
Act
reveals
that
Congress
wanted
the
district
court
to
consider
the
need
for
retribution
and deter-
rence,
in
addition
to
restitution
when
it
imposed civil
penalties.
123’ Cong.
Rec.
39191
(1977)
(Sen.
Muskie
citing
EPA
memorandum
outlining
enforcement
policy).
(Footnote
omitted.)
A court
can require retribution
for
wrongful
conduct
based
on
the
seriousness
of
the
violations,
the
number
of
prior
viola-
tions,
and
the
lack
of good—faith
efforts
to
comply
with
the
relevant
requirements.
Ibid.
It
may
also
seek
to
deter
future
violations
by
basing
the
penalty
on
its
economic
impact.
Ibid.’
Subsection l3l9(d)’s
authorization
of
punishment
to
further
retribution
and
deterrence
clearly
evidences
that
this
subsection
reflects
more
than
a
concern
to
provide
equitable
relief.
In
the
present case,
for instance,
the District Court
acknowledged
that
the
petitioner
received
no
profits
from
filling
in
properties
in
Mire
Pond
and
Eel,
Creek,
but
still
imposed
a
$35,000
fine.
‘App.
to
Pet.
for
Cert.
60a.
Thus,
the
District
Court
intended
not
simply
to
disgorge
profits
but
also
to
impose
p,~nishment.
Id.,
$81 U.S.
at
422,
423 (emphasis added).
This federal concern with punishing environmental violations
contrasts with dicta
in one
15 year old Illinois Supreme Court
decision,
which vacated oen~ltieswhere
the court
labeled
the
civil penalty “punitive.”
Southern Illinois Asonalt,
Luase No.
4.
As the Tull decision makes
clear, punishment
is
an essential
element
in
federal environmental enforcement actions, and many
factors must be considered
in determining the amount
of
a civil
penalty.
To uniformly implement national environmental
laws
which also impact the state,
Illinois must strive for consistency
with federal penalty considerations even
if
Illinois penalties
remain less
in dollar amounts
than those imposed under
Federal
law.
111—57

2.
The Gwaltney Case
Not only may the federal government
or state agency bring
environmental enforcement
actions, but citizens may also bring
civil enforcement suits
for penalties and injunctive relief.~*
Citizens suits have particularly arisen under
the Clean Water
Act.
One such case,
the subject of several appeals, reached the
U.S.
Supreme Court
in Gwaltney
of Smithfield
v. Chesapeake
Bay
Foundation,
484 U.S.
49,
108 S.Ct.
376,
26 ERC 1857
(1987).
In
the Gwaltney case
the Supreme Court
resolved a conflict between
three circuits over the statutory interpretation of citizens’
rights
to, bring
suit
against any person “alleged to be
in
violation of”’effluent
provisions
or related orders under
the
Clean Water
Act.
Section 505(a)(l),
33 U.S.C.
1365(a)(l).
Essentially,
the
issue was whether citizens could sue for
injunctive relief and/or
civil penalties
for wholly past
violations.
The Supreme Court concluded
that with respect
to
citizens suits only the remedy was prospective,
that
is, geared
toward achieving ptesent
or
future compliance.
Section 505
“confers jurisdiction over citizen
suits when
the citizen—
plantiffs make
a good—faith allegation of continuous
or
intermittent violation”, and does not extend
to wholly past
violations.
Gwaltney,
484 U.S.
at
64
(emphasis added).
In contrast,
the state or federal government
is
not
so
limited in bringing enforcement actions.
It
is
little
questioned
that
the
Admin-
istrator
may
bring
enforcement
actions
to
recover
civil
penalties
for
wholly
past
violations
.
*
*
*
A comparison
of
(section)
309
and
(Section)
505
thus
supports
rather
than
refutes
our
conclusion
that
citizens,
unlike
the
Admin-
istrator,
may
seek
civil
penalties
only
in
a
suit
brought
to
enjoin
or
otherwise
abate
an
ongoing violation.
Gwaltnev,
484
U.S.
at
58,
59.
See,
e.g.,
the Clean Air Act Section
304,
42 U.S.C.
§7604;
Federal Water
Pollution Control Act,
Section 505,
33 U.S.C.
§
1365;
Comprehensive Environmental Response, Compensation, and
Liability Act
(“CERCLA”)
Section
310,42 U.S.C.
§
9659;
Resource
Conservation and Recovery Act
(“RCRA”)
Section 7002,
42 U.S.C.
§6872;
Safe Drinking Water
Act Section
1449,
42 U.S.C.
§
300j—8;
and
Toxic Substances
Control Act Section
20,
15 U.S.C.
§
2619.
11 1—5S

Drawing on
the Supreme Court’s statutory interpretation of
Section
309 of the Clean Water
Act,
it seems clear
that,
at
the
federal level, penalties
for wholly past violations were thought
by Congress
to serve
the Clean Water Act’s goals.
Those goals
expressed
in Section 101(a)
are “to restore and maintain the
chemical, physical, and biological
integrity of the Nations’
waters.”
It likewise seems an inescapable conclusion
that
penalties for wholly past violations of Illinois’
environmental
statutes and regulations may further state environmental goals.
Thus, although some
Illinois Appellate Court decisions have,
in
dicta, minimized
the effectiveness of penalties
for past
violations,
the Board
will consider
the U.S. Supreme ,Court
decision
in Gwaltnev as
suPporting
the imposition
of penalties
in
state
initiated action even when violations
have ended.
This
is
particularly appropriate
since
the Supreme
Court
in Gwaltnev
pointed to the federal government’s reliance on
the State
to
enforce federal environmental laws,
with citizens’
suits being
a
final
resort.
The
bar
on
citizen
suits
when
governmental
enforcement
action
is
underway
suggests
that
the citizen suit
is meant
to supplement rather
than
to
supplant
governmental
action.
The
legislative history of the Act reinforces
this
view
of
the
role of citizen
suit.
The Senate
Report noted
that
“the
Committee intends the
great
volume
of
enforcement
actions
(to
be
brouaht
by the
State,”
and that citizen suits
are
proper
only
“if
the
Federal,
State,
and
local agencies
fail
to exercise their enforce-
ment
responsibility.”
S.
Rep.
No.
92-414,
p.
64
(1971),
reprinted
in
2A Legislative History
of
the Water
Pollution Control
Act Amendments
of
1972,
p.
1482
(1973)
(hereinafter
2
Leg.
Hist.
Gwaltnev,
484 U.S.
at
60.
a.
The Gwaltney Penalty Calculation
The Gwaltnev legacy
is also
rich
in
that
the 1985 district
court decision provided an extensive analysis of penalty
calculation considerations.
Chesapeake Bay Foundation
v.
Gwaltney of Smithfield,
611
F.
Supp.
1542,
22 ERC 2121
(1985).
In
the initial
suit
in district court,
plaintiffs sought the
maximum penalty of $3,300,000
for violations of pollution limits
in Gwaltney’s
NPDES
permit.
In
a detailed analysis based on
USEPA’s
penalty policy (cited as
Env’t Rec.
(BNA)
41:2991 June
1,
1984),
the District court
imposed
a $1,283,322 penalty, which
took
into account:
(1)
economic benefit,
(2)
a gravity component
111—5’)

and
(3)
adjustments.
A rate of
return,
reflecting
the time value
of money
for the period of delayed compliance, was used to
calculate the economic benefit
of delaying expenditures
for
pollution control.
Varying per diem amounts, such
as $4,000 per
day of fecal
c’oliform violations and $250
$1,000 per day for
total Kjeldahl nitrogen (“TKN”)
(nitrogen compound)
violations,
were multiplied by the days of violations and tallied
to arrive
at a final penalty.
Briefly summarized,
the compone’nts were as
follows
(the Board notes
that
the figures
in
“B” are taken
directly from the court’s Appendix
B;
however,
there appea.rs
to
be $1,000 discrepancy
in the court’s addition):
111—60

—51—
A.
Chlorination viclations
—econorric benefit:
$
1,500
—gravity—fecal coliform
($4,000 x 213 days of violaticn)
$852,000
—gravity-chlorine
($1,000 x 17 days of violation
of
iraxirrurr hint):
$ 17,000
—adjustrr.ent
for
delay
($1,000
x 125 days of delay):
125,000
$
995,5C0
B.
Biological Treatrrer.t System Violations
—eccnorric benefit:
$
54,C22
—gravity corrpcnent
—pre—start—up
TKN
violations
winter
‘81—82:
(90 x days
x
$250/day—)
22,500
sururer
‘82:
(30 days
x $1,000/day=)
30,C00
winter
‘83:
(151 days
x $25C/day-)
37,750
sumner
‘83:
(61 days
x $1,000/day-)
61,0CC
—start—up violations:
(including dowrr~ard
adjust.rr’ent. because
start—up is involved)
296 days
(199 days T~,
+
61 days TES,
+
33 days
fecal
cohiforrr,
+
3 days
oil
&
grease)
x $50/day-
14,800
$166,050
—further adjustrr~nts:
delay: 283 days x $250/day-
70,750
$
289,622
Total
111-61

—32—
Though certainly not the only approach or
a required
approach
to penalty calculation,
this methodology was approved by
the Fourth Circuit
in
1986
as that court
noted
in
its 1989
Gwaltney opinion.
See:
Chesapeake Bay Foundation,
Inc.
v.
Gwaltney of Smithfield, Ltd.,
890 F.2d
690,
692,
30 ERC 1593
(4th
Cir.
1989)
citing Chesapeake Bay Foundation
Inc.
v.
Gwaltney of
Smithfield,
Ltd.,
791 F.
2d
304,
24 ERC 1417
(4th Cir.
1986).
The $1,285,322 penalty was reduced to $289,822 in the 1989
decision since
the chlorination violations were found
to have
been wholly past’ violations which
the ~citizens could no~prove
to
be ongoing or likely
to continue at
the time
the citizens brought
suit.
b.
The Gwaltney Implication of
a Mandatory
Penalty
In
the 1989 Cwaltney decision,
the Fourth Circuit observed
that
the
Supreme
Court’s
Gwaltnev decision “effectively approved
the assessment of penalties based on past violations
(the only
possible basis
for assessing
a penalty)”.
CheasaDeake~,~1
Foundation,
Inc.
v. Gwaltnev of Smithfield,
Ltd.,
890 F.2d 690,
696,
697,
30 ERC 1593
(4th Cir.
1989),
(emphasis added).
Besides emphasizing the need
to look
to t~epast
to assess
a
penalty,
the court also looked at whether
the Court
has the
discretion
to not assess
a penalty.
The court decided
that the
penalty was virtually mandated.
At
the time
of assessment
of penalties
in
the
case,
the
statute
stated,
“Any
person
who
violates
...
any
permit
condition
or
limitation
...
shall
be
sub.ject
to
a
civil
penalty
not
to
exceed $10,000
per day of
such
violation.”
33 U.S.C.
§1319(d).
The statute
has
been
amended
to
allow
up
to
$25,000
per
day.
Id.,
890 F.2d at
696, Note
6.
6
*
*
*
hf
the plaintifffs.prove
an ongoing violation
at
trial,
the
violations
are
related
to
present
wrongdoing.
Section
1319(d)
of
the
Act
states
that
any
person’ who
violates
a
permit
condition
shall
be
subject
to
a
civil
penalty.
This
language coupled
with
§1365(a)
indicates
that,
once
an
ongoing
violation
is
shown,
the
court
is
virtually
obligated
to
assess
penalties.
Stoddard
v.
Western
Carolina Renional Sewer
Auth.,
784
F.2d
1200,
1208
(23 ERC 2105
(4th Cir.
1986).
Id.,
890 F.2d
at
697 (emphasis added)
111—62

The “shall
be subject” language of
the federal statute
is
quite similar
to
the “shall
be liable” penalty language of
Section 42 of the Illinois Act.
The, federal court’s presumption,
then,
would seem to favor imposing penalty of some amount,
even
if nominal, where violations are established.
One can argue that
any Illinois case which finds a violation,
but sets no penalty,
should have
a minimal penalty.
C.
Other Federal Decisions
Work
v. Tyson Foods,
Inc.,
720 F.Supp.
132,
30 ERC 1580
(W.D.Ark.
1989), was a citizen suit brought
in connection with
tort claims and with Clean Water Act violations by Tyson,
a
food
processor.
In
a
jury
trial
Tyson
was
found
to
have
caused
violations
of NPDES permit requirements
on
43 separate
occasions.
The court
found
a reasonable
likelihood of
recurrence,
relying on the Gwaltnev decisions, despite over
$1,000,000
in expenditures alleged
to have cured
the problem.
Tyson was held liable
for damages
to real property and other
compensatory damages with respect
to 40 plaintiffs.
Besides
damages,
the court assessed a $43,000 civil penalty
($1000 for
each of
43 separate days of violations),
refraining
from imposing
what
it viewed as
a maximum penalty of
$430,000.
The court
noted that
the EPA had drawn the court’s attention
to
two
documents,
the EPA “Policy on Civil Penalties” and
“A
Framework
for Statute—Specific Approaches
to Penalty Assess-
ments.”
The court also considered
recent Consent Judgments
in
Arkansas covering civil penalties.
The court specifically
identified ability to pay and litigation considerations as
factors
to be reviewed
in setting
a
just and equitable penalty.
(The court observed earlier
that Tyson had been involved in many
pollution controversies and litigation since
the 1970’s).
Without
further explanation
the court held
that the maximum
penalty would be “unnecessary,” and based on the facts before
it,
set the penalty at
10
of
the maximum penalty.
Work
v. TysOn,
720 F.Su~p. at
139.
Following on the heels
of
the Tyson decision,
the U.S.
District Court
for
New
Jersey issued a vociferous opinion and
imposed
a $3,200,000
penalty for
11 ‘years of NPDES permit
violations.
Public Interest Research Group
v.
Powell Duffryn
Terminals,
Inc.,
720 F.Supo.
1158,
30 ERC 1201,
(D.N.J.
1989).
That
court
introduced
its
opinion
as
follows:
The
case
before
this
Court
presents
another
chapter
in
the
never
ending
American
tragedy.
A
recalcitrant
company
in
the
private
sector
‘of
the
economy
combined
with
the
lethargic
enforcement
of
the
applicable
statutes
and
regulations
by
the
New
Jersey
Department of Environmental Protection and the
Federal
Environmental
Protection
Agency,
has
caused
a continuing,
if
not
constant,
11
year
111—63

contribution
to
the pollution
of
the Kill Van
?(ull.
It
is
indeed
sad
that
none
of
the
participants
cared
sufficiently
about
the
public
trust
the
environment
to
take
meaningful
steps
to
avert
the
tragedy.
This
Court
will
not
stand
idly
by
to
either,
explicitly
or
tacitly,
condone
such
inaction.
For
the
reasons
hereafter
set
forth,
significant
monetary
penalties
are
necessary.
Id.,
720 F.Su~p. at
1159.
In choosing
a penalty of $3,200,000, and rejecting
plaintiff’s
request
for the maximum statutory penalty of
$4,205,000
for
386 violations,
the
court gave separate
consideration
to several
factors described
in
the Clean Water
Act,
33 U.S.C.
1319(d).
These included seriousness
of
defendant’s violations;
the economic benefit resulting from
the
violations; defendant’s history of violations; defendant’s good
faith efforts
to comply with
its permit;
and the economic impact
of the penalty on the violator.
Powell Duffryn’s bulk chemical storage and transfer facility
caused violations
of eleven different effluent limitations.
The
court
found
this
to be very serious since
the effluent concen-
trations were
100
to 1000
in excess of permit limitations;
two
pollutants were toxic; and the number of violations was great.
The defendant benefitted from these violations, saving an amount
far
in excess of the statutory maximum penalty, which would
“compel”
a higher or maximum penalty. Id.,
720 F.Supp.
at
1163.
The violations persisted
for
11 years,
during which time
the,
defendant procrastinated and the state and federal agencies made
sporadic and minimal attempts
to enforce
the permit’s terms.
The
court also declined
to infer defendant’s good faith,
but the weak
governmental
efforts did not favor
a maximum penalty.
The court
found
that
defendant
had
“failed
to
demonstrate
that assessing
a
severe penalty would
jeopardize defendant’s continued operation.”
Id.,
720 F.Supp.
at
1166,
citing, Gwaltn~y, 611
F.
Supo.
1542.
In setting the penalty amount
the Court
relied on USEPA’s
penalty policy.
In explaining
this,
the court cited
its earlier
1989 opinion
in SPIRG
v.
Hercules,
Inc.,
29 ERC 1317,
1418
(D.
N.J.
1989), which
stated:
(Although
the
EPA
penalty
policy
does
not
have
the
force
of
law,
it
is
consistent
with
the Congressional policy behind
the Act.
*
*
*
The
1987 amendments, while
not incorporating
the
language
and
detail
expressed
in
the
EPA
penalty
policy,
serve
as
a
reasonable
summary
of
that policy.
111-64

The court
then held
that since
“civil penalties seek
to
deter pollution by discouraging
future violations,”
the amount
must be sufficiently high so
that
a profit maximizing
firm cannot
choose to absorb the penalty as
a cost
of doing business which
would be less than the compliance cost.
Powell Duffryn,
30 ERC
at
1207,
citing SPIRG
v. Hercules,
29 ERC 1417
(D.N.J.
1989),
SPIRG v.
A.T.
&
T.
Bell Laboratories,
Inc.,
617
F. S~pp. 1190,
23
EP.C 1201
(D.N.J.
1985)
and EVA,
“Policy on Civil
Penalties”
(February 16,
1984)
at
p. 3.~ The court concluded
that,
unfortunately,
it could not achieve this goal since economic
savings exceeded
the maximum statutory penalty.
The court
found
that a $1 million reduction
from the maximum $3,205,000 penalty
would be appropriate since
the government’s
lack
of diligence
prolonged
the violations.
The court rejected defendant’s
assertion
that
the waterway was already heavily polluted.
Even
if the harm could
not
be measured,
defendant’s NPDES violations
meant
that
“the restoration and enhancement of the river’s water
quality was inhibited and therefore,
the objective of the Act was
frustrated.”
Powell Duffrvn,
720 F.SuDp.
at
1167.
The sizable $3.2 million penalty certainly gave
a loud
warning
to others.
The court offered little hope of
a smaller
penalty unless
it would put the company out of business.
(But see
also the Illinois case,
Standard Scrap Metal,
Case
No.
36,
rejecting this kind of argument).
The NPDES violations were
quite serious for
this
federal court sitting
in New Jersey,
and
should be viewed with equal gravity
in Illinois.
As with
this
federal court which assumed the role of protecting
the
environment,
the Board has a responsibility
to set penalties
which will deter noncompliance.
U.S.
v.
Key West Towers,
Inc.,
720 F.Suop.
963,
30 ERC 1635,
(S.D.Fla.
1989)
was another decision,
in which
the District Court
in Florida systematically discussed the penalty factors of
the
~
For other federal decisions,
see also U.S.
v.
Shaffer Muffler
Shops,
Inc.,
No.
C—86—240,
30 ERG 1658,
(S.D.Tex.
Feb.
28,
1989),
($36,750
Clean Air Act);
U.S.
v. Phelps Dodge Industries,
Inc.,
589 F.Supp 1340
(S.D.N.Y. 1984);
U.S.
v.
Danube Carpet Mills,
Inc.,
540 F.Supp.
507
(N.D.Ga.
1982) aff’d 737 F.2d 988
(11th
Cir.
1984); U.S.
v. Cumberland Farms,
Inc.,
No. 85—0846—1,
25 ERG
1077,
(D.Mass.
Sept.
25 and Oct.
16,
1986),
($530,000
Clean
Water Act;
$390,000 would be refunded
if wetlands restored);
U.S.
V.
Mac’s Muffler
Shops,
Inc.,
No. C85—138R,
25 ERG 1369,
(N.D.Ga.
Nov.
4,
1986),
($21,000
Clean Air Act);
U.S.
v.
Environmental
Waste Control,
Inc.,
710 F.Suoo.
1172,
29 ERC 1757,
(N.D.Ind.
March
29,
1989),
($2,778,000— RCRA); Student
Public Interest
Research Group
off New Jersey,
Inc.
v.
Monsanto Co.,
29 ERG 1078,
(D.N.J. Mar.
30,
1988),
($240,000— Clean Water Act);
Student
Public Interest Research Group
off New Jersey,
Inc.
v. Hercules,
Inc.,
29 ERG 1417,
(D.N.J.
1989),
($1,680,000— Clean Water Act).
11 1—65

Clean Water Act,
33 U.S.C. l3l9(~).
In
this
case the District
Court imposed a $250,000 penalty
for filling approximately 2.7
acres of wetlands
in violation of the Clean Water Act,
33 U.S.C.
1311.
Although
the government sought only
a $250,000 penalty,
the Court communicated’in a footnote that the maximum penalty
would have approximated $25,000,000.
The Court imposed the
requested penalty largely due to the seriousness of
the
offense.
“Any destruction of these rare and fragile’ natural
resources
requires a
substantial penalty.”
Id.,
30 ERG at
1637.
(emphasis added).
The lack of good faith efforts also strongly
compelled the Court’s imposing a substantial penalty.
Together,
the five factors indicated
that
“a $250,000 fine would promote
the soeciffic and general deterrence
theories behind
a civil
penalty”.
Id.,
citing Tull,
481 U.S.
412
(emphasis added).
In
Illinois,
NPDES
permit violations by
the City of Joliet
were the subject of
a
federal enforcement action brought
in 1988
in the District
Court
for
the
Northern
District
of
Illinois
by
the U.S.
Attorney General, on behalf of
the USEPA.
U.S.
v. The
City
of
Joliet,
No.
88—5661,
(N.D.Ill.
1988).
The
action
was
for
injunctive
relief and civil penalties under
the Clean Water Act
for violations of
the state—issued NPDES permit for Joliet’s
sewage treatment facility.
Joliet discharged pollutants
in
excess of
permitted levels
for biochemical oxygen demand (“BOD”),
total, suspended solids,
and fecal coliform bacteria.
USEPA
requested permanent injunctive
relief as
to future violations;
that Joliet comply with
its permit;
and that Joliet pay civil
penalties
up to $10,000 per day for violations prior
to February
4,
1987 and $25,000 per day of violation after
that date,
in
accordande wi’th
the upward revision
in
the Clean Water Act’s
penalties.
A consent decree was entered
in 1988 requiring remedial
action to achieve and maintain compliance with
the NPDES permit;
payment
of
a $160,000 penalty; and stipulated penalties
for any
subsequent violation of
the decree.
Corrective
action
included
upgrading
facilities; constructing
a new nitrification facility;
and operating
and maintenance
requirements.
Stipulated
penalties,
which would not limit other
remedies or sanctions,
included $250
to $750
for each day of violation,
increasing
to
$1,000 per day
if compliance was
not achieved by June
1,
1991;
$250
to $1,000
for daily, weekly,
or monthly violations of
effluent limitations;
and $300
per day for reporting or other
violations.
Quite obviously,
the NPDES violations involved
6
Alternatively,
the Court
felt
that
the direction
of
33 U.S.C.
1319(d),
to consider “such other matters as justice may require”
enabled
the court
to allow defendant
the option of deeding
a
1.9
acre pond
involved here
to
a charitable
group
to serve as
a
nature
reserve.
ii 1—66

significant penalties,
and federal
enforcement against
the
municipality entailed much stiffer penalties
than
those upheld
against
local governments by Illinois state courts.
Just as NPDES permits under
the Clean Water Act tie the
state to a federal water pollution enforcement program,
so,
too,
does the Clean Air Act’s
requirement of
a state implementation
plan
(“SIP”)
commit the state
to achieve national
ai’r quality
standards.
Section 110
of
the Clean Air Act,
42 U.S.C.
7410,
requires Illinois,
and every
state,
to adopt
“a plan which
provides
for implementation,
maintenance, and enforcement”
of
national ambient air quality standards.
To meet
this
requirement
the Board has adopted various emissions r~gulations which are
subject
to federal approval.
Upon approval,
the various aspects
of
the comprehensive plan are federally enforceable.
The vast
majority of Board air pollution regulations have been federally
approved, and enforcement actions under
state law may thus
be
brought
in federal district court.
Similar federal enforcement
of state environmental laws occurs with respect
to other federal
environmental laws such as
the Safe Drinking Water
Act,
42 U.S.C.
300,
et seq. and RCRA,
42 U.S.C.
6901,
et.
seq.
These federal
statutes continue to be the basis
for. state promulgation
off laws
derived from and intended
to implement federal
laws and policies.
In 1988
a federal action was brought
to enforce Illinois’
emission limitations pursuant to the Clean Air Act,
42 U.S.C.
7410, inthe case of U.S.
v. General Electric Company, No.
88 C
2564
(N.D.Ill.
1989).
The U.S. Attorney General, on behalf of
the USEPA, sought injunctive
relief and
civil penalties from
General Electric Company
(“G.E.”)
for excessive emissions of
volatile organic compounds
(“VOGs”).
Pursuant to Section 113(b)
of
the Clean Air Act,
42 U.S.C.
7413(b), notice
off the federal
action was given to the state agency,
the Illinois Environmental
Protection Agency (“IEPA”).
G.E.’s paint coating operation
for large appliances
in
Cicero,
Illinois released VOGs
in excess of
the limitations
established by
the Board
in Rule 205(n)(l)(H).
35
Ill. Adm.
Code
205(n)(l)(H).
This rule was adopted as part of the federally
required Illinois SIP.
The rule’s VOC limitation, which has been
federally approved,
is part of the SIP’s means
to achieve
the
National Ambient Air Quality Standard for ozone.
Because
violations posed
a threat
to
the public health and welfare,
the
U.S.
Attorney General sought
to halt operations,
to require that
the facility be brought
into compliance, and to obtain penalties
of up to $25,000 per day of violation.
7’
See Illinois cases discussed herein,
City of Waukegan;
City
of
Monmouth; Municioal Sanitary District of Greater Chicago; City
of
Chicaqo; City
off Moline; City
off East Moline
and City of
Freeport.
The highest penalty upheld by
the state courts was
$10,000.
111—67

This suit culminated
in the lodging of a Joint Stipulation
with the District Court, and the issuance of
a consent decree by
the court
in
1989.
The decree required that G.E. systematically
reduce emissions based on daily ozone
forecasts;
close
the
coating operations permanently by June
30, 1990;
post
a
$3,000,000 bond
to assure compliance; pay a $150,000 civil
penalty; and pay additional
penalties of $5,000 to $25,000 per
day
for
various
unexcused
violations
of
the
decree.
This
extensive relief was based on Illinois air rules and rendered in
a federal
forum.
On January
8,
1990
the Federal District Court
for
the
Northern District
of Illinois a,ddressed
important penalty issues
in assessing
a $100,000 civil penalty
for RCRA violations
in the
case
of
U.S.
v.
Maiorano,
No.
87 G
4491
(N.D.Ill.
Jan.
8,
1990).
Defendants’
violations grew out of
the storage and
disposal of hazardous wastes generated by
their electroplating
business.
Defendants
h’ad failed
to respond
to USEPA’s
information requests and failed
to timely submit initial and
revised closure plans as ordered.
For these violations
the
government sought penalties for 909 days
of violations
(some of
which were
for different violations on
the same days).
Based on
the $25,000
fine per violation provided
in Section
3008(g)
of
RCRA,
42 U.S.C.
6928(g),
the maximum penalty was calculated
at
$22,725,000.
The court agreed with the government
that
a substantial
penalty was “warranted for
reasons of deterrence.”
slip op.
at
5,
citing U.S.
v.
T
&
S
Brass and Bronze Works,
Inc.,
681 F.Supp
314,
322
(D.S.C.
1988)
aff’d
in relevant part
at
28 ERG 1649
(4th
Cir.,
1988)
and U.S.
v.
Environmental Waste Control,
Inc.,
710
F.Supp.
1172,
1244
(N.D.Ind. 1989).
The court
found
that
the
violations were serious and
that
defendants
showed
complete
disregard
of the law and USEPA and judicial orders.
“To impose. a
perfunctory or
token penalty would send
a message
to similarly
situated persons
that
they may flout
the
law without
consequence.”
slip op.
at
6.
Delays allegedly caused
by
IE?A
would
not excuse defendants’
conduct.
The court also
acknowledged that defendants’
alleged inability
to pay was not
proved and,
nonetheless, would be unpersuasive given defendants
intransigence.
The court granted
the government’s request
for
a
$100,000 penalty, noting
that while
it was a small percentage of
the maximum penalty,
it
wa’s substantial
and would achieve the
deterrence purposes of
the RCRA penalty provision.
Both
Illinois and federal law are intended
to achieve
consistency
in setting comparable civil
penalty amounts
for
violations.
Federal law requires
that state enforcement programs
be quite similar
to the
federal program.
See 40 CFR 123.27
(1989), or equivalent
to the
federal program.
See Section
3006
of RCRA.
11 1-6~

r
-J
III.
PENALTY CONSIDERATIONS
IN OTHER STATES
State courts outside
Illinois have reiterated
the same
principles articulated
in federal and Illinois penalty
decisions.
Many states look
to factors such as the seriousness
and duration of the offense and good faith.
Some states rely
more heavily on USEPA’s penalty policy.
Others address statutory
cons~derationssimilar
to those
in Section 33(c)
of ‘the Illinois
Act.
Sometimes,
however, other states conclude that much higher
penalties should be imposed than ‘Illinois has typically seen
in
its state court decisions.
As one example,
in 1982 the Supreme Court of Ohio, addressed
the civil penalty
issue in State,
ex.
rel.
Brown
v.
Dayton
Malleable,
Inc.,
1 Ohio St.
3d 151,
38 N.E.
2d 120
(1982).
The
case involved a $493,500 civil penalty
for the NPDES permit
violations of an
iron foundry.
Noting
that
the parties had
agreed to the application of
LJSEPA civil penalty,
the Supreme
Court approved the trial court’s use of
that policy statement
as
a proper approach to penalty calculation.
The Ohio Supreme Court recited the various components
of
the
trial court’s
1978 calculations.
These included an amount
for
not complying with the permit’s schedule of compliance.
The
Supreme Court held that such
a schedule
is a permit
term or
condition, and that,
under USEPA policy,
a penalty could be
assessed
for recalcitrance or indifference with respect to
meeting
the schedule.
This was,
in fact,
the largest element of
the penalty calculation, which
the Ohio Supreme Court summarized
as follows:
8 See Selmi,
“Enforcing Environmental Laws:
A Lqok at
the State
Civil Penalty Statutes”,
19
Loy.
L.A.L.
Rev.
1279
(1986).
111—69

-
Harm or
risk
of harm
($50
x 683 days)
$
34,150
Economic benefit from noncompliance
S
8,000
Recalcitrance or indifference
re:
Compliance Schedule ($750
x 714 days)
$
535,500
Subtotal
S
577,650
Mitigating
factors
Delays due
t.o strike
$500
x 98 days
(5 49,000)
Delays due
to exceptional weather
$250
x
52 days
(S
13,000)
Delays
in equipment delivery
$250
x
90 days
(5
22,500)
Subtotal
($ 84,500)
Total Penalty
$
493,150
A second significant issue was the Ohio Supreme Court’s
review of the trial court’s consideration of the defendant’s
financial condition.
The court found
that
the information was
used,
not
to increase the penalty, but
“merely to insure that
the
penalty
...
would not
be so large as
to send DM1 into bankruptcy
but would be large enough to deter
future violations.”
Id.,
438
N.E.
2d at
125.
The court
noted,
too, several
federal decisions
and other support for
the principle
that civil penalties should
deter further violations and be lar~eenough
to remove
the
financial benefit of noncomp1iance.~
Id.
Hence, ability
to pay
is relevant
to whether
a penalty.may achieve
the desired
deterrent effect’and eliminate any financial
incentive
to violate
the
law.
A third factor favoring
the appropriateness
of
the
trial
court’s penalty assessment was
that
the
amount
was
less
than
10
of
the maximum of about
$7,000,000.
According
to expert
testimony,
the penalty was also
in the lower one third of
the
range
in which
it would have
a “material effect”.
Id.
As
a
general
rule,
the Supreme Court stated that
as
long as the amount
was
less than the statutory maximum, “discretion
to fix
that
amount
lies
in
the
trial
court.”
Id.,
citing
United
States
v.
Ancorp National Services,
Inc.,
516 F.2d
198,
202
(C.A.
2d,
1975)
and United States
v.
J.B. Williams Co.,
Inc.,
354 F.Supp.
521,
For another
state decision considering the need
to remove
the
economic benefit of
noncompliance,
see State
v.
Schmitt,
145 Wis.
2d 724,
429 N.W.
2d.
518
(Wis.
App.,
1988),
supporting
trial
court’s imposition
of $232,939 forfeiture; see also
State
ex rd.
Brown
v. Howard,
3 Ohio App.3d 189,
43 N.E.2d
469
(1981).
Ii 1-70

548.
The Ohio Supreme Court
thus
found
no abuse of discretion
when
it compared the maximum allowable penalty and the one
actually imposed under USEPA guidelines.
A 1988 state administrative decision
from Tennesse provides
another
example
of how other
states also use a
multi—faceted
framework for penalty determinations.
An enforcement action,
referred
to as
In the Matter of:
J.
C.
McCanless,
Sr’., Case No.
87—3198
(Feb.
26,
1988),
involved water pollution from feedlot
runoff.
Although only
$808.75
in damages
was assessed for
enforcement efforts and the value of fish killed,
the
Administrator of
the Tennessee Department
of Health and
Environment explained
in his Order
that the following factors
were considered
in that decision:
(a)
the facts alleged herein;
(b)
whether
the civil penalty
imposed will be
a
substantial
economic deterrent
to
the
illegal activity;
(c)
damages
to
the
state,
including
compensation
for
loss
or
destruction
of
wildlife,
fish,
and
other
aquatic
life,
resulting
from
the violation,
as well as
expenses
involved
in
enforcing
this
section
and
the
costs
involved
in
rectifying any damage;
(d)
cause of the discharge or violation;
(e)
the
severity
of
the
discharge
and
its
effect
upon
the quality
and quantity
of
the receiving waters;
(f)
effectiveness
of
action
taken
by
the
violator to cease
the violation;
(g)
the technical
and economic reasonableness
of
reducing or eliminating
the discharge;
(h)
the
social
and
economic
value
of
the
discharge source; and
(i)
the
economic
benefit
gained
by
the
violator.
Id.,
p. XVI
Quite obviously,
these considerations closely parallel
the
factors
found
in Section
33(c)
of the Illinois
Act.
This
is one
example of how the manner
in which
the Illinois Board approaches
penalty determinations
seems consistent with considerations which
have been discussed
in other
states.
111—71

In their
1989 treatise,
“State Environmental
Law”,
Professors
Selmi and Manaster observed
that the body of state
case law is relatively
limited on
the issue of civil
penalties
for environmental violations.
They noted
that Illinois cases
represent the b~k of state decisions discussing penalty
determinations.
Their analysis pointed to good faith as the
most critical decision factor, with recalcitrance being most
important
in deciding whether a large penalty
is impbsed.
Proof
of economic benefit from non—compliance was found
to be very
helpful
to success
in having
the penalty sustained on
review.
The review process
is not generally predictable,
however,
Selmi and Manaster note
that
the degree
off deference given
to
agency penalty assessments can vary widely.
They cited
Fee Plan,
Inc.
v. Dept.
of
Envtl. Conservation,
118 A.D.2d 855,
500
N.Y.S.2d
344,
345
(1986)
for the New York Court’s position that
the courts
will
not overturn an Agency’s penalty unless
“so
disproportionate
to
the
offense
as
to
shock
one’s
sense
of
fairness”.
They
noted
in
contrast
that
Illinois
courts
have
engaged
in some intensive reviews of Board decisions based on the
Illinois Supreme Court’s holdings
in Southern Illinois Asphalt,,
Case
No.
4,
and City of Monmou.th,
(Case No.
2,
that
the
penalties should primarily
“aid
in
the enforcement of
the Act”
and that “punitive considerations”
are secondary.
The authors
observed this consequence of
the
review process
in
Illinois:
This
standard
has
allowed
the
lower
courts
considerable
freedom
in
their
review
——
freedom
that
in some instances plainly amounts
to
a
de
novo
review
of
the agency’s
penalty
assessment.
The
result
has
been
a
series
of
decisions
in
which
the
Pollution
Control
Board’s
assessments
have
been
overturned
by
reviewing courts which have concluded
that
the
assessments will
not aid
in
the enforcement of
the
Act.
At
the
same
time,
however,
the
opinions
in
that
state
on
this
issue
have
an
ad hoc aualitv
to
them and Drovide
the oenaltv
decisionmaker
with
very
little
cuidanceon
whether
a oenaltv assessment will
be upheld
on
review.
Selmi
and Manaster,
at
16—69
(emphasis added).
The Board’s own extensive review
in this case suggests
that
while
the aiding—enforcement-versus-punishing
princtole has been
less helpful
than
the courts
intended,
Illinois decisions which
have more fully explored Section
33(c)
factors do provide some
guidance.
The
heart
of
the
penalty
decision
must
be
review
of
10
See,
D.
Selmi
and
K.
Manaster,
“State
Environmental
Law”,
Clark Boardm-~nCompany, Ltd.,
N.Y.,
N.Y.,
1989
pp.
16—63
16—74.
111—72

“all the facts and circumstances”,
both
in aggravation and
mitigation.
State and federal decisions now typically address
many factors, whether
from statutory guidelines
or USEPA policy
statements.
Illinois decisions are generally consistent
with
those from these other
forums.
However, some inconsistencies
do
exist, and the Board has indeed struggled at times
to find
guidance
in court opinions reviewing the Board’s penalty
assessments.
IV.
STATISTICAL DATA ON PENALTIES
A.
USEPA Statistical Data on Penalties
Information on federally
imposed penalties can provide
a
useful background
for a state approach to assessing civil
penalties.
Two USEPA reports,
“Enforcement Accomplishments
Report:
Fl
1989”
(Feb.
1990)
and “Overview of EPA Federal Penalty
Practices
Fl 1988”
(May 1989),
reveal important penalty data.
From its inception through 1989,
USEPA
assessed $185.9 million
in
civil penalties.
Of
this amount, approximately 19
or
$34.9
million was assessed
in
1989 and approximately 20
or $36.8
million was assessed
in
1988
(the record high year
for total
penalties).
These annual figures compare with amounts totalling
less
than
ss
million per year
imposed
in
the late 1970’s.
Sjnce
1985
the total annual penalties have been consistently much
larger.
The 1988 report,
referenced above, attributes
that year’s
higher penalties
to new enforcement initiatives,
increased
penalties
in established programs, and more cases
in
traditionally higher dollar amount genre, e.g.,
the Clean Water
Act program.
Interestingly,
“penalties were levied
in
92
percent
of the cases concluded
in Fl 1988.”
See 1988 report,
supra,
at
p.
1.
And
it was Region
V, where Illinois
is located, which
in
1988 had the highest number
of cases with penalties
(228).
Suora,
at
p.
2.
Federal cases certainly seem
to suggest
a
general policy of
imposing penalties where violations are found.
For
1989 the various federal programs were the basis of
the
following assessments of
total civil penalties:
111—73

_u4
-
Table
1:
Total USEPA Penalties
for 1989
Clean Air Act
$64.8 million
35
Clean Water Act
64.3
35
Toxic Substances Control Act
28.5
15
RCRA
24.0
13
Federal Insecticide,
Fungicide,
and Rodenticide Act
2.4
1
Safe Drinking Water
Act
1.5
1
Superfund
.4
Total
$185.9 million
100
Certain of these programs,
the Clean Air Act,
the Clean
Water Act,
and RCRA are the principal subject
of similar
enforcement efforts at the state level.
Federal penalties
for
these programs will,
therefore,
be discussed
in greater detail
below.
The 1989
report highlights
a number
of large civil penalties
assessed for
1989,
some of which set new records.
These are
relevant to show an upward trend
in penalty amounts and may be
useful as
the upper
limit
in state penalty determinations.
For
example,
a
1989 cons~entdecree imposed the highest Clean Water
Act civil penalty ever imposed against
a municipality.
That
$1,125,000 penalty was against
the Metropolitan Denver Sewage
District
No.
1,
the Denver Water
Board, and others.
See 1989
report,
suora,
at
o.
6.
This
report also notes
that
a civil
penalty of $2,778,000 was entered against Environmental Waste
Control,
Inc.
This penalty was the largest ever
imposed by
a
court
for RCRA violations.
Suora at
p.
8.
Another
case,
involving
the removal of cat~~icconverters
from vehicles,
resulted
in the highest civil penalty per violation
($1,750) for
such tampering under
the Glean Air Act.
Supra at
p.
24.
A
$2,200,000
fine was imposed
for Clean Water
Act violations by
Koch Refining Company.
This was one of
the
largest ever
assessed
against
a single discharger
at
a single facility.
Su~j~at
p.
24.
Numerous other
cases are referred to
in
the 1989
report
under
the section labeled,
“Major Enforcement Litigation and Key
Legal Precedents”,
suora, pp.21-47.
Compared to
the broad brush approach
off
the available
1989
report,
the
1988 report issued
in May of
1989 offers more detail
on the scope
of penalty assessments.
Since comparable data
for
Fl
1989
is
not yet available,
the statistical
information
for
1988 will
be summarized
below.
While
these penalty
figures would
probably
be higher
than most comparable state figures,
they mc’
It 1—74

—6’S—
provide
some framework
for
future state penalty determinations.
Only Clean Air Act, Clean Water Act,
and RCRA data will
be
reviewed as these programs involve enforcement actions most
analogous
to state actions.
The chart below presents the median,
average, and highest penalties assessed
for these programs.
Table
2:
Selected USEPA Penalties
for 1988
All Regions
Median**
Average***
Highest
Clean Air Act*
judicial
$30,000
$125,555
$1,750,000
administrative
39,397
37,028
61,500
Clean Water Act
judicial
$37,500
$139,834
$2,000,000
administrative
8,500
13,545
60,000
RCRA
judicial
$96,479
$209,791
$1,100,000
administrative
9,440
17,576
150,000
*
Stationary Source Air violations only
**
Median
Equal
number
of penalties above and below this
figure
~
Average
=
Arithmetic average.
(Total dollars divided by
total number
of penalty cases.)
Of particular
interest for Illinois,
Region V,
in which
Illinois
is
located, assessed the following median,
average, and
highest penalties
for 1988.
Table
3:
Selected USEPA Penalties for
1988
Region V Only
Median
Average
Highest
Clean Air Act
judicial
$27,500
$133,041
$1,750,000
administrative
50,273
50,273
61,500
Clean Water Act
judicial
$40,000
$61,700
$
60,000
administrative
20,900
20,900
34,000
111—75

B.
Illinois Statistical Data on Penalties
Some statistical
information
is available
to provide
a broad
overview of historical
figures
in Illinois penalty decisions.
Table
4 below
is derived solely from IE?A reports
labeled “State
of Illinois Environmental Protection Agency Summary Penalties
Assessed by Pollution Control Board.”
These reports were
available through July
31,
1988,
and are presumed by the Board
to
be reasonably
accurate.
Average penalties were calculated by
dividing
the reported total
amounts
by reported number
of
penalties.
As can be
seen,
the average penalties are quite
modest,
predominately
in
the $2,000
5,000
range.
These amounts
obviously are significantly less
than the federal administrative
penalties
for Region V refferrred
to
in
the preceding
table.
More
specific data
is summarized below based on the earlier discussion
of Board decisions which were appealed.
I.
Pollution Control Board
Table
4:
Summary of Penalties Assessed
by
Illinois Pollution Control
Board
RCRA
judicial
administrative
$78,000
$96,218
$
280,000
12,500
15,620
60,000
Fiscal Year
Total
Number
of
Average
Ending On
Amounts
Penalties
Penalty
6/30/71
$
96,950
18
$5,386
6/30/72
422,862
7’S
5,638
6/30/73
374,381
148
2,530
6/30/74
226,082
94
2,405
6/30/75
239,374
92
2,602
6/30/76
275,350
135
2,040
6/30/77
221,722
84
2,640
6/30/78
106,475
59
1,805
6/30/79
164,118
104
1,578
6/30/80
198,812
77
2,582
6/30/81
262,392
87
3,016
6/30/82
196,273
72
2,726
6/30/83
222,758
36
6,188
6/30/84
37,423
11
3,402
6/30/85
175,700
14
12,550*
6/30/86
61,008
13
4,693
6/30/87
13,200
6
2,200
6/30/88
37,500
3
9,375**
111 --7~

*
Noticeably higher due
to one $75,000 penalty
**
Noticeably higher due to one $25,000 penalty
2.
Illinois Court Decisions
The Illinois Appellate and Supreme Court opinions discussed
earlier represent virtually all Illinois Court pronouncements
on
Board assessed civil penalties for environmental violations.
They provide more meaningful
information than
the above table of
penalties assessed by
the Board.
Court decisions summarized
below indicate
that penalties of
as little as $100 and as much as
$75,000 may be upheld on appeal.
Penalties
off less than $3,000
predominate,
but nine decisions upheld penalties of $7,500
to
$75,000.
Notably,
in 1989 and early
1990,
two penalties were
upheld for
$10,000 against Perkinson/Porkville and against
the
City of Freeport;
one $10,000 penalty was reduced to $1,000
in
the case of Modine Manufacturing;
and another SlO,000 penalty was
remanded
to the Board
in
the case of Trilla Steel
Drum.
Table
5:
Illinois Civil Penalties Reviewed by Supreme Court
_____
_____________
_______
I~l1inoi
S
Supreme
City of Waukegan
5 1,000
(a municipality)
250
250
1974
City of Monmouth
$
2,000
(a municipality)
1974
Incinerator,
Inc.
$25,000
1975
Southern Illinois Asphalt
$
5,000
(2 cases consolidated)
$11,000
Mystik Tape
Metropolitan Sanitary Dist.
(a unit of
local government)
Processing
& Books
$ 3,000
$ 3,000
Wells Manufacturing
$
9,000
—0—
The appellate courts have reviewed a
far greater
number
of
cases regarding civil penalties.
This allows the decisions
to be
Year
1974
Petitioner
Board
1975
1975
1976
1976
$ 1,000
250
250
—0—
$25,000
—0—
—0—
$ 3,500
—0—
$ 3,500
$ 6,000
111—77

broken down
into categories
for comparison.
The following Table
6 groups the decisions
into
those where
the court was primarily
discussing
issues
relating
to violation of air pollution
requirements, water pollution requirements, and cases where
the
primary
issue was failure to have a permit for certain
activities.
For clarity,
cases involving
a local government
defendant are grouped separately.
Table
6:
Illin’ois Civil Penalties Reviewed by ADoellate Court
Water_Gases
1974
Meadowlark
Farms
Inc.
(Value of fish kill)
Allaert Rendering
Inc.
Archer Daniels Midland
1989
Perkinson/Porkville
1975
Freeman Goal Mining
Air
Petitioner
Board
Appellate
Cases
Court
1974
Allied Metal
On remand
$ 2,500
5
750
Remanded
1975
Sangamo Construction
On remand
$ 5,000
$ 5,000
Remanded
1976
Aluminum Coil Anodizing
$ 1,500
$
1,500
1974
Lloyd A.
Fry Roofing
On remand
$50,000
$10,000
Remanded
1974
Bresler
Ice Cream Co.
$ 1,500
—0—
1974
Chicago Magnesium Casting
$
1,000
—0—
1975
CPC International Inc.
$15,000
—0—
1976
May/Hillview Farms
$
2,500
—0—
1976
Draper
& Kramer
$
1,000
—0—
1976
Marblehead Lime
$20,000
$20,000
1976
Hillside Stone
$10,000
$ 2,000
1980
1983
$
141.66
$
131.66
On remand
$ 3,000
$40,000
$32,500
$10 ,000
SlO,376 .84
$ 5,000
$ 3,000
Remanded
$,1 5,000
$10,000
$10,376.84
$
500
Ii 1—78

r,
-~—
Petitioner
Permit Cases
(Air/Water/Land)
Board
Appellate
Court
1975
1975
1976
1977
1981
1978
1982
1983
1973
1986
1989
1984
1990
$
2,500
$
1,500
$
250
$
500
$
500
$ 1,000
$ 1,500
$ 7,500
$75,000
$ 2,000
$30,000
$10,000
No decision
$
1,000
$10,000
—0—
$
850
$
100
$
200
—0—
S 1,000
$ 1,500
$ 7,500
$75,000
$
2,000
$30,000
Remanded
—0—
$ 1,000
Municipalities
(See also Supreme Court Cases Above)
Petitioner
Board
Appellate
Court
1978
City of Chicago
$10,000
0
1985
City of Moline
$90,000
0
1985
City of
East Moline
$30,000
$10,000
1989
City of Freeport
$10,000
$10,000
3.
Recent Stipulated Penalties
Examples of other penalties recently imposed by
the Board
are listed below.
(These do not include penalties
imposed under
the Administrative Citation program established under Section
31.1 of
the Act.)
These penalties were assessed pursuant
to
settlement and stipulation agreements between
the parties:
Highlake Poultry
Freeman Coal Mining
(air)
Hindman
Harris—Hub
Slager/Rapid Liquid Waste
Joos Excavating Go
Pielet
Bros.
Waste Land Inc.
Bath Inc.
Standard Scrap Metal
Trilla Steel Drum
Citizen Utilities
Modine
Mfg.
yet
111—70

Table
7:
Recent Stioulated Penalties
As summarized below,
federal
judicial decisions
typically
imposed
the highest single penalties and
largest average
penalties,
followed by federal administrative penalties.
Penalties
imposed by administrative and judicial processes
in
Illinois generally,
but not always, will
be
less than
similar
federally
imposed penalties.
Date
Case
Penalty
3/22/90
3/8/90
3/8/90
2/8/90
12/6/89
11/20/89
8/10/89
8/10/89
7/13/89
PCB
PCB
PCB
PCB
PCB
PCB
PCB
PCB
PCB
89—192
89—161
89—160
89—65
89—69
88—36
89—18
89—67
88—201
$10,000
$
3,000
$ 1,500
S
600
5 1,000
$12,500
$
1,000
$ 2,500
$11,000
(1st
(?lus S3,000
reimbursement
$
1,000
(2nd
Respondent)
)
Respondent)
Date
Case
Penalty
6/22/89
6/8/89
4/27/89
4/6/89
2/23/89
2/2/89
1/19/89
1/13/89
1/13/89
PCB
PCB
PCB
PCB
PGB
PCB
PCB
PCB
PCB
89—24
88—200
89—2
84—92
88—177
87—104
88—135
86—104
88—124
SlO,000
$
1,000
5 1,000
‘5
6,500
$12,000
5 6,500
$ 5,000
5 7,500
$11,250
C.
Comoarison
-~
Federal and State Penalties
111—Sn

Table
8:
Comparison of Federal and State Highest
Penalties
Federal
Judicial
Administrat ive
All Federal
(1988)
Clean Air Act
Clean Water Act
RGRA
$1,750,000
2,000,000
1,100,000
$
61,500
60,000
150,000
Federal—Region V
(l9’88)
Clean Air Act
Glean Water Act
RCRA
$1,750,000
160,000
280,000
5
61,500
34,000
60,000
Illinois
Penalty Determinations After
1973
Judicial
Review
Board
Deci sion
Non—Municipality
Municipality
$
75,000
10,000
$ 75,000 Upheld
90,000 Reversed
1989 Board Decisions
(Stipulations)
(From Table
7)
$ 12,500
Table
8 above draws comparisons regarding maximum penalties
assessed
in the Federal system and the State of
Illinois.
The
Illinois penalties are
further divided
into those maximum dollar
amounts supported by the courts
in reviewing Board decisions and
maximum set
by
the Board
in any case
(prior
to any review).
The
maximum based on a stipulated penalty
is
listed separately.
Table
9 below provides the same information,
but based
on the
average
(arithmetic mean)
rather
than maximum penalty amount.
the
111—81

—-~
-:‘~~
I’-
Table
9:
Comparison of Federal and State Average Penalties
Federal
Judicial
Administrative
All Federal
(1988)
Clean Air Act
$ 125,555
$ 37,028
Clean Water Act
139,834
13,545
RCRA
209,791
~7,576
Federal—Region V (1988)
Clean Air Act
$ 134,041
$ 50,273
Clean Water Act
61,700
20,900
RCRA
96,218
15,620
Illinois
Penalty Determinations After
1973
Judicial
Board
Review
Decision
Non_Municipality*
$5,975
$ 13,639
Municipality*
3,000
21,285
1989 Board Decisions
(Stipulations)
$
5,983
(From Table
7)
*Derived from tables
5 and
6 detailing
Illinois court decisions,
using initial Board-imposed penalty and final
court
determination of penalty amount.
V.
CONCLUSION:
RELEVANT FACTORS FOR BOARD DETERMINATION
OF CIVIL PENALTIES IN THIS CASE
A.
Calculating
the Maximum Penalty
In this case,
the Board will begin
the penalty determination
process by considering
the maximum civil penalty
under
the statute
where such information
is available.
This
is
a natural or logical
benchmark from which
to begin considering factors
in aggravation and
mitigation
of
the penalty amounts.
This
is consistent with
the
discussions
in
the
U.S.
Supreme Court Tull and Gwaltnev decisions,
with
U.S.
EPA Penalty Policy; and with Illinois decisions discussing
a maximum penalty.
As discussed earlier,
the Illinois statute
now
provides
for
a penalty of up
to $50,000 per violation and an
additional $10,000
for each day of violation.
Section 42(a)
of
the
Act.
In deriving
a range
off appropriate penalties,
the Board may
also consider the penalties
for similar offenses which have been
imposed
in other forums (federal and other states).
The Board may
also consider
relevant any penalties imposed
by Illinois courts or
the Board
in similar
circumstances.
ii 1—82

A final consideration as
to the range of appropriate penalties,
though not necessarily binding on
the Board
in all circumstances,
is
whether
the parties have stipulated
to
a maximum penalty or whether
the complaint requests a maximum penalty which
is less than the
amount permitted by statute.
B.
Statutory Factors Which Must be Considered,
Section 33(c)
factors provide the minimum factors which must be
considered in fine tuning
a penalty assessment.
These will be
considered by the Board
in each penalty determination
to the extent
relevant evidence exists.
These factors affect the calculation of
the penalty by increasing or decreasing
the penalty amount depending
on whether
the statutory factor,
when evaluated by the Board,
weighs
in favor of
a larger or
smaller penalty within the range of
penalties derived pursuant
to the first
part
of
the penalty
evaluation.
The statutory penalty criteria
are:
*
All the facts and circumstances.
Section
33(c)
*
Character
and degree
of
injury
or inter-
ference.
Sedtion 33(c)(l)
*
Social and economic value.
33(c)(2)
*
Suitability/unsuitability
of
pollution
source
to its locale.
Section 33(c)(3)
*
Technical
practicability
and
economic
reasonableness
of
pollution
abatement.
Section 33(c)(5)
*
Economic
benefits
of
non-compliance.
Section 33(c)(5)
*
Any
subsequent
compliance.
Section
33(c) (6)
C.
Other Factors
In this case,
viewing
all the facts and circumstances
pursuant
to Section 33(c)
and
in keeping with state and federal
court decisions,
the
Board
will
evaluate
other
factors,
notably:
*
the presence or
lack of good faith;
*
whether
the
penalty
may
aid enforcement
by
deterring
future
non—compliance
by
this violator
and others;
111—83

*
the economic impact of
the penalty on
the
violator
in
terms
of
the
violator’s
ability
to
pay.
(Note,
however,
the
Board
is
not
bound
to
maintain
a
violator’s
economic
viability,
but
may
consider
this.)
*
totality of circumstances surrounding
the
violation,
including,
but not limited
to,
the
duration
of
the
violation,
any
cessation,
and
any
prior
history
of
violations.
Like the Section
33(c)
factors,
these other
factors aid the
Board
in weighing the gravity of the harm and the conduct, in
removing the economic incentive
to violate
the
law,
and
in
assigning appropriate dollar amounts
in
a penalty calculation.
An example of how this process
takes place
in
federal Glean Water
Act settlements
is attached as Exhibit A for illustration
purposes only.
VI.
PENALTY DETERMINATION FOR ALLEN BARRY
A.
The Maximum Penalty
The stipulation between
the parties
sets forth
four separate
days in
1982,
1985,
1987 and 1988 where violations of Section
12(a),
12(d)
and 12(f)
of the
Act and Sections .501.403(a),
502.104,
302.203,
304.105, and 302.212 of
the Regulations have
been admitted.
The Board views
these violations,
under
the
particular
facts of this case,
as constituting
five separate
violations encompassing
four days
of violations.
(Note,
in
the
four counts described earlier, Count
II describes
two separate
violations,
i.e., NPDES.oermitting
requirements and livestock
facility and waste handling requirements.)
Clearly,
the
violations persisted
for
a period of
up to nearly six years
for
some or all of
the violations.
However,
in the absence
of
an
allegation and proof
by
the Agency that the violations were
continuing,
the Board chooses not
to engage
in an assessment
of
the number of
days on which
each
off
the violations continued.
For the purposes of calculating
the maximum penalty the Board
will view the five violations as occurring on
each of
four
days.
This results
in
a maximum penalty of $65,000
(($10,000
x
5)
+
($1,000
x
3d
x
5).
The Agency has agreed
in
the Stipulation and Proposal
for
Settlement
to seek
a penalty
not greater than $10,000.
The Board
will abide by
the stipulation
in
limiting its penalty
inquiry
in
the range of
$0
$10,000, while recognizing
that
its evaluation
would otherwise cover
a much broader penalty
range
in
the absence
of such settlement
by
the parties.
Other Illinois decisions are
in keeping with
the
$0
$10,000
range agreed
to above.
The Perkinson/Porkville case,
111-84

(1989)
Case
No.
25,
affirmed
a Board—imposed penalty of
$10,000
for swine waste discharges.
A stipulated penalty of
$600
in the
case of IEPA
v. Russell
G.
Wake,
PGB 84—79,
62
PCB 503 (Feb.
7,
1985)
represents a slightly dated penalty assessment
also
involving swine waste discharges.
These decisions support
the
stipulated maximum of $10,000 and suggest
that
the respondent’s
request
that
no penalty be imposed would not
be
in keeping with
Illinois precedents.
B.
Consideration of Statutory Factors
1.
Character and Degree
off Harm
The livestock waste runoff from Allen Barry’s operation has
had a deleterious
impact on the chemical and biological nature of
the receiving stream.
Essentially,
the elevated ammonia nitrogen
levels, unnatural
sludge, and murky,
turbid conditions, and foul
odors create a hostile environment
for aquatic
life and harmful
conditions
for public health.
The Board
finds
that
this kind of
harm to state waters flowing
through the Barry property and
further downstream
is serious
in nature both
in
terms
of
immediate and long—term environmental impact.
These violations
date back
to
1982 and run through
1988,
further
indicating
environmental harm that spans many years.
The injuries here are
more pervasive
than the violations
from 1982—1983 which were
stipulated
to in the Russel
G. Wake case noted above.
The Board
finds
that the violations
are indeed serious;
this
is a situation which calls
for imposing
a $10,000 penalty.
2.
Social and Economic Value
The Board acknowledges
that Allen Barry’s livestock
operation makes
a social and economic contribution
to the
community and the state.
However,
that value was diminished
by
Allen Barry’s failure
to contain
livestock waste
runoff,
as
required,
and to secure and comply with an NPDES permit
intended
to regulate any such discharges.
The Agency has been required to
engage
in efforts since
1982
to secure compliance with the
Act
and regulations.
This,
too,
reduces the social ,and economic
value of Allen Barry’s business for the state.
Businesses which
comply with
the state’s enviromental
regulatory scheme do,
however, make a sizable contribution socially and economically.
As Allen Barry has agreed to take remedial action
to achieve
compliance,
his facility will
be of benefit
to
the community and
state.
However,
the value of
this operation does
not
in the Board’s
opinion justify a significant
reduction
in
the penalty amount.
This
is not an enterprise which
is critically linked to the
social and economic lifeblood
of
a community.
The record does
not establish,
for example,
that Allen Barry
is
a major employer
or
a key supplier of goods.
If
that were
the case,
the Board
could evaluate whether
enforcement and
a penalty would have
a
111—85

—76—
far—reaching negative impact on the community,
such as
if the
remedy caused a major employer
to go out of business.
The Board
finds, therefore,
that this
is not a
factor which warrants
imposing a minimal penalty, but rather suggests a penalty
in the
middle ground.
3.
Suitability/Unsuitability
of Pollution Source to
Its
Locale
The record does not disclose any significant conflict
between
the livestock operation and its locale.
The area appears
to
be primarily
rural and the business,
therefore,
seems
to be
reasonably adapted
t~the locale.
This
rather neutral
f’acto.r
would not here have
a noticeable impact on the amount of penalty.
The Board
finds
that
the penalty’ should not be increased,
as
in the case of an offending industry
in perhaps
a primarily
residential area.
A moderate penalty would
thus seem
appropriate.
4.
Technical Prac.ticability and Economic Reasonableness
of
Pollution Control
The availability of means
to control livestock waste runoff
is not at issue
here.
The feasibility of maintaining curbs,
dikes, walls or similar means of containing
runoff as the
regulations require
is not controverted.
The respondent did make
some efforts
to control runoff
in 1982,
bu’t
these efforts were
not successful
in resolving the problem.
Since receiving
the
Agency’s Pre—Enforcement Conference
letter dated October
15,
1982, Allen Barry was on notice of violations, which could have
been eliminated
by readily anticipated or discoverable methods.
The Board is persuaded
that
remediation was within
Respondent’s means despite
letters from Allen Barry’s counsel
which requested
a state agency—designed plan.
Polluters cannot
thrust the burden of compliance back on
the state and win delayed
compliance with impunity.
The State
has no obligatio.n to
formulate conceptual and/or engineering plans
for the thousands
of enterprises within
the State which must comply with the Act
and regulations.
It
remained within Allen
Barry’s responsibility
to control
runoff
in a
timely manner.
Although the Agency’s
letter of December
18,
1985,
recommended
that he engage
a
consulting engineer,
Allen Barry did not hire an engineer until
early 1989
(R.
48).
Respondent’s contacting
the Illinois Soil
and Conservation Service ultimately resulted
in
a November,
1987
preliminary plan, which has yet
to be implemented by
Respondent.
These “efforts”
at compliance are well—papered but
quite ineffective
in bringing about technically practical
pollution control.
An eight point
recommendation of needed
remedial measures was made
in
the Agency’s letter of December
18,
1985.
A reminder that
the responsibility
for the solution was
Respondent’s, not the Agency’s, was made
in a June
17,
1986
letter
from the Agency.
Thus,
the availability of means
to solve
11 l—S6

the problem weighs heavily against Allen Barry and the State
should not be
faulted for attempting
to help him to achieve
compliance.
This
is not a case where technology was unavailable
to cure pollution.
Similarly,
economic reasonableness
is not really at
issue.
The costs of walls, curbs, and dikes
to contain runoff or of such
remedial measures
as fencing and maintaining vegetat!ive cover are
not alleged
to be prohibitively expensive
in relation
to the kind
of
industry involved here.
The Board
finds
no support
for
a
proposition that
the pollution control methodology was
economically unreasonable
for livestock operations such as
conducted here.
Such expenses would appear
to be reasonable
for
commercial livestock facilities
in general, and perhaps more
so
here, where many years’
operations are involved.
Although
respondent’s brief alludes
to these costs as being expensive
for
his situation,
these costs are not inordinate,
but are to be
reasonably expected by those engaging
in this industry.
The Board
finds
that
the considerations of
technical
practicability and economic reasonableness of
reducing and
eliminating
the water pollution from Allen Barry’s operations
warrants imposing
a higher penalty
than would be appropriate
where technological and economic considerations make pollution
control
less accessible or disproportionately expensive.
5.
Economic Benefits of Non—Compliance
The cost savings of delayed compliance
take
into account
the
time—value of money.
This
is to say that by postponing capital
improvements or operating and maintenance costs
for pollution
control,
those
funds are available for other uses
or investments
or
to reduce
the, need
to borrow, creating
a better position
relative
to competitorswho
voluntarily comply.
Some
rate of
return
(an interest rate factor) can be used
to calculate an
economic savings or benefit
from not expending capital and
operating
funds
at an earlier point
in
time.
In the case of Allen Barry,
some economic benefit probably
dates back
at
least
to 1982 when he was notified
in writing of
violations.
A November
25,
1987
letter from the U.S.
Department
of Agriculture,
attached to the Stipulation as
part
of
Respondent’s Exhibit
F,
indicates that costs of $29,710 would be
incurred
for capital improvements
to eradicate
the
runoff
problem.
Another
cost figure of approximately $40,000
is noted
in Respondent’s
brief
(page
9).
This estimate
is more
fully
developed
in Exhibit
3
to
the March
14,
1989 hearing
111-37

transcript.
That document
is Respondent’s February,
1989
preliminary co~ estimate,
which total
$42,500.
At only a
6
rate of
return~-’-, cost savings
in the range of $1,783
to $2,550
could be expected each year,
based
on $29,710
to $42,500 in
capital expenditures.
Since
the 1982 written notice of
violation,
Allen Barry would have reaped at least
7 years of
savings from deferred compliance.
Without compounding
the
savings,
a simple calculation indicates
that
total ~avings
could
be
in the range of $12,481
to $17,850, clearly
in excess of the
maximum penalty sought
by the Agency.
The savings would,
of
course,
be greater
if annual maintenance charges were included.
However,
such information on economic benefit
is not adequately
presented to the Board.
This factor requires the Board
to
look
to the middle
to upper
range
of penalties
to eliminate the
economic incentive
to avoid compliance.
6.
Any Subsequent Compliance
The issue
of subsequent
compliance
is
not before
the
Board.
Where
the courts and the Board have considered
this
factor the respondent
had complied with the Act and regulations
either before the complaint was filed or
at least before the
Board’s decision.
Compliance by Allen Barry
is still prospective based on the
record before
the Board.
The injunctive relief sought
by the
Agency describes acts yet
to be performed to achieve
full
compliance.
For this reason,
the penalty calculation will not be
reduced since
this
is not a situation where
the respondent’s
independent acts,
rather than enforcement, has brought about
compliance.
C.
Other Factors
The presence or absence of good faith must be gleaned
frcm
respondent’s conduct over
the many years of this protracted
enforcement process.
According
to an IEPA report dated July
27,
1982,
to gain access
to
the Barry property an administrative
inspection warrant
had
to be obtained by the Agency.
At
that
time,
the runoff conditions
were found
to be basically
the same
as conditions
found at the time
of
an October
16,
1979 Agency
inspection.
A Pre—Enforcernent Conference Letter was mailed
October 15,
1982, which stated
that,
“(the
Agency has previously
informed you of aooarent non—comoliance,”
and gave notice of
the
Agency’s intention
to
file
a
:ormai complaint.
~nese cocuments
In the absence of
a calculation by
the Agency,
the Board here
will estimate
the economic benefit based on cost data
from the
record before
it.
The
6
interest rate
is used here as
a modest
attempt
to reflect an annual savings from deferring payment, much
as the courts use a 9
statutory
rate of
interest for
judgments.
Ill.
Rev.
Stat.
1987,
ch.
110,
par.
2—1303.
111—SO

-~
a
•.1
suggest
that early cooperation
was certainly lacking and that
ultimate compliance has required Agency efforts which span
a
decade.
More disturbing
than the longstanding compliance problem,
the nature
of respondent’s conduct
in 1979
and 1980 warrants the
Board’s comment.
A May 19, 1980
report describes that
an initial
visit on October
16,
1979 was met with belligerence’from Allen
Barry.
A July 22,
1980 memorandum notes
that
a personal visit
to
explain
the Agency’s
role and need for water samples ended
in
Allen Barry becoming angry,
yelling, and ordering the Agency’s
representative
to leave and not return.
A September
23,
1980
inspection
report describes how Allen Barry attempted
to grab an
Agency inspector’s camera and followed after
him yelling.
Three
Agency inspectors were involved
in
the incident which included a
man not from
the Agency jumping
on and
riding on the hood of the
car and Allen Barry grasping
the arm of
a woman from
the Agency
who
was attempting
to close the car door
to
leave.
A police
report was
filed.
On November
26,
1980
a memorandum reported that on November
19,
1980,
inspectors
twice drove by the facility and observed
several thousand beef cattle on open dirt
lots
near
the stream.
The report notes
that runoff was probably entering the stream,
but the Agency was deterred from making closer
inspection due to
the previous hostile actions of Allen Barry.
This recalcitrance and threatening behavior
is clearly an
extreme example of bad faith.
The Board
finds
that
this factor,
if considered alone, would
justify imposing
the maximum penalty.
Slightly offsetting this egregious conduct
is
later evidence
in
a December
18,
1985 letter
of
a cooperative visit
on November
5,
1985.
In that
letter, details of needed remedial action were
outlined.
However,
a June 11,
1987
report notes that contact
with Allen Barry was again harsh and very uncooperative.
(See
also transcript
pp.
61-63.)
Far
too much of
the Agency’s
resources appear
to have been spent
to accomplish eventual
compliance.
From 1979, Agency efforts were thwarted by hostile
behavior and numerous delays.
The Board acknowledges
that some efforts, including
blacktopping
an area and installing
tile,
a dike and holding
basin were made
in
1982.
And in
1988, Allen
Barry straightened
the receiving stream.
Yet Allen Barry
remains
in violation,
never
having made enough effort
to cure the problem.
Some delays might
be excusable due
to
intervening
illnesses
of Allen Barry
in 1983 and his attorney
in
1987.
However,
the
trail of correspondence
from
1982 through
1988 does not support
a
finding of reasonable delays but rather pays
“lip service”
to
the
notion of
cooperation.
The heart of whether action was really
forthcoming
can be seen
in
the letter
of June
8,
1988 from Allen
Barry’s attorney.
ill—SO

20.
On
February
18,
1988,
we
sent
you
a
letter showing
we were having
independent lab
tests made
and
in
the
last
paragraph
of
that
letter
I stated,
“If Mr. Barry sees on his own
tests
that
he
is
in
violation,
then
we
can
work
from
there.”
It
appears
that
his
own
tests
pushed
the
limit
on
the
COD
and
go0~
(emphasis added)
Contrary to the assertions
by
respondent’s attorney
in the
June
8,
1988 letter,
the Board does not
find
“past and continuing
cooperation” and “good
faith effort.”
An Agency report of
a June
11,
1987 visit with Allen Barry notes
that
he expressed his
unwillingness
to change any part
off his operation as
a
result of
Agency action.
Thus, despite numerous attempts
to work
with
Allen Barry over the years,
the Agency ultimately had
to file its
complaint
to accomplish
its enforcement goals.
The Board views
the lack
of good faith over many years
as supporting
a penalty
in
the higher range.
Failure
to come into compliance
is an
aggravating factor here.
In’ such a case of recalcitrance and bad faith,
the need
to
aid compliance
by deterring this violator,
as well as others,
becomes very important.
The state’s environmental goals could
never
be met
if similar
responses
to enforcement were
tolerated.
This factor,
too,
suggests a penalty in a higher
range.
Very little information
is available
to inform the Board of
the economic impact of
the penalty on the violator.
The Board
will
therefore approach this factor as
relatively neutral, with
any consideration of respondent’s ability
to pay favoring a
smaller penalty
to Allen Barry’s benefit.
D.
Penalty Calculation
Integrating the various elements which
suggest
a higher or
lower penalty amount,
the Board concludes that,
separate and
distinct
from recouping
the economic benefit
from noncompliance,
a penalty should be imposed
in
the amount of $1,000 each
for
violations
of Sections
12(a)
and
(d)
of the Act and for
violations
of ammonia nitrogen and unnatural sludge standards and
livestock management and waste handling
regulations.
35
Ill.
Adm. Gode
302.212,
302.203,
304.105 and
501.403.
Besides
this
$4,000
penalty,
an added $100 per day for
each violation’s
additional
3 days of
violation, causes
the penalty
to be
increased
by $1,200.
For
the violation of N?DES permit
rquirements under
35
Ill.
Adm.
Code 502.104
a
fine of
$500,
plus
$50 per day for each
of
3 additional
days of violations,
shall
be
imposed.
‘The minimum penalty,
therefore,
is
$5,850, which
is
well within the
range defined earlier,
and significantly
less
than the amount
imposed
in
the Perkinson/Porkville case.
11 1—flO

However,
as the Agency alleged
(but did not specificially
calculate),
an economic benefit accrued to Allen Barry from not
expending funds
to achieve compliance.
The Board has calculated
this benefit as being not less than $12,481.
The total penalty,
therefore,
to aid enforcement of the Act and to recapture the
profit or gain from non—compliance should be at
a level near
$18,331
($5,850
+
at least
$12,481).
Since
the Board
is willing
to limit
the penalty
to not more than $10,000,
the ~oard
finds
that Allen Barry
is liable
for
a SlO,000 civil penalty.
ORDER
It
is the Order
of the Illinois Pollution Control
Board
that:
1.
The Respondent,
Allen Barry,
has violated Sections
12(a),
12(d) and 12(f)
of
the Illinois Environmental
Protection Act and
35
Ill.
Adm.
Code 501.403(a),
502.104,
302.203,
304.105, and 302.212.
2.
Within
30 days of the date of
this Order,
the Respondent
shall,
by certified check or money order payable to the
State of Illinois, pay the penalty of $10,000, which
is
to be sent
to:
Illinois Environmental Protection Agency
Fiscal Services Division
2200 Churchill Road
Springfield,
Illinois 61706
Allen Barry shall
also state
its
Federal Employer
Identification number upon the certified check
or money
order.
3.
The Respondent
shall comply
with
all
the
terms and
conditions of the Stipulation and Proposal
for
Settlement
filed on April
12,
1989, which
is
incorporated
by reference as
if fully set forth herein.
Section 41 of the Environmental Protection Act,
Ill.
Rev.
Stat.
1987,
oh. 111—1/2, par.
1041,
provides
for appeal of
final
Orders of
the Board within
35 days.
The Rules of the Supreme
Court of Illinois establish filing requirements.
IT
IS SO ORDERED.
Board Member Joan Anderson concurred.
111—91

I,
Dorothy M.
Gunn, Clerk of
the Illinois Pollution Control
Board, hereby certifj’ that
the above Opinion and Order was
adopted on
the
~
day of
f..~
,
1990,
by
a
vote of
~7—O
.
~
~.
Dorothy
M. ~inn,
Clerk
Illinois Po~lutionControl Board
111—92

Exhibit A
CLEAN WATER ACT
PENALTY POLICY FOR CIVIL SETTLEMENT NEGOTIATIONS
CWA Penalty Summary Worksheet
(1)
No.
of Violations
________
x
$10,000
stat.
max.
S________
(2)
Economic Benefit
(“BEN”)
(period covered/
months)
=
_____
$
(3)
Total
of Monthly Gravity
Components
$
(4)
Benefit
+
Gravity TOTAL
S
(5)
Recalcitrance Factor
_____
(0—150)
x Total
(Line
4)
=
$_________
(6)
Preliminary
TOTAL
(Line
4
+
Line
5)
$
ADJUSTMENTS
(7)
Litigation Considerations
(Amount
off
reduction)
$
(8)
Ability to Pay
(Amount of
reduction)
$
(9)
SETTLEMENT
PENALTY
TOTAL
$
Name and Location
___________
_____________
of Facility
Date of Calculation
____________________________
UNITED STATES
ENVIRONMENTAL
PROTECTION
F.GENCY
EFFECTIVE DATE:
FEB 11 1986
11 1-°3

Back to top