ILLINOIS POLLUTION CONTROL BOARD
April
26, 1990
WILLIAM
E. BRAINERD,
Complainant,
V.
)
PCB 88—171
(Enforcement)
DONNA HAGAN,
DAVID BROMAGHIM,
and PHIL ROBBINS,
d/b/a THE
GABLES RESTAURANT,
Respondent.
ORDER OF THE BOARD
(by R.
C.
Flemal):
This matter comes before the Board
on its own motion to
close
tnis docket.
On April
27,
1989 the Board
found,
inter
alia,
that Respondents violated
35
Ill. Adm.
Code 900.102
of the
Board’s noise regulations and ordered Respondents
to cease and
desist
from violations
of the Act and Board’s
regulations
(paragraphs
I and
2,
respectively).
Paragraph three of
that
Order also included
a June
27,
1989 deadline date
for the
installation and operation of noise abatement devices.
That
deadline date was extended to September
27,
1989
by Order
of
the
Board dated July
13,
1989.
In its April
27,
1989 Order,
the Board ordered Respondents
to notify Complainant and the Board as
to whether
it has complied
with paragraphs
2 and
3
of
the Board’s April
27,
1989 Order.
On
August
7,
1989,
the Board received
a letter
from Respondents
stating
that
the installation of
a noise abatement device
is
complete and that Respondent
hoped to obtain
a “release”
from
Complainant or
the Illinois Environmental Protection Agency
(“Agency”)
that the installation of the noise abatement device
meets
their approval.
A copy of that letter was also sent
to
Complainant ‘s attorney.
To date,
the Board has received nothing further from either
party or the Agency in this matter.
The Board
therefore finds
that all pending Orders have
been satisfied
in this matter and
hereby closes this docket.
IT
IS SO ORDERED.
110—343
—2--
I, Dorothy
M.
Gunn, Clerk
of the Illinois Pollution Control
Board, hereby certify. that the above Order was adopted on the
~
day of
_______________
,
1990,
by
a vote of
?
/&
/
7
1),
~
Illinois P6llution Control Board
110—344