ILLINOIS POLLUTION CONTROL BOARD
    April
    8,
    1976
    CATERPILLAR TRACTOR COMPANY,
    Petitioner,
    )
    V.
    )
    PCB 75—499
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent,.
    OPINION OF THE BOARD
    (by Mr. Dumelle):
    This Opinion is
    in
    support of an order entered March 25,
    1976 which dismissed the petition for variance.
    This matter comes before the Board on a petition for
    variance filed December
    23,
    1975 by Caterpillar Tractor
    Company
    (Caterpillar),
    seeking relief from Rules
    404,
    408(a),
    602(c) (2)
    and 602(d)
    (3)
    of Chapter
    3:
    Water
    Pollution,
    of the Board’s Rules and Regulations.
    A
    Recommendation from the Environmental Protection Agency
    (Agency) was filed on February 19, 1976.
    Petitioner manufactures heavy equipment and employs
    18,500 people at its East Peoria, Illinois facility,
    Peti-
    tioner’s facility has
    a combined storm and wastewater treat-
    merit
    system capable of retaining all dry weather flows
    and
    additional flows up to three times the average dry weather
    flow.
    Caterpillar’s combined storm and wastewater sewer
    system has
    14 overflow discharge points.
    During heavy
    rainstorms the combined storm and industrial wastewater
    bypasses the existing interceptor sewer and waste treatment
    plant,
    and is discharged through the
    14 outfalls into four
    waterways, all of which are tributary to the Illinois River.
    Caterpillar’s petition,
    in summary,
    asks the Board to
    find the arbitrary and unreasonable hardship required for
    a grant of variance on the basis
    of the following five
    allegations; quotations from the petition are underlined,
    followed by the Board’s comments:
    First,
    Caterpillar has
    been diligently working
    on
    a method ~3meet
    the requirements of
    Rule__602.

    —2—
    The implementation date for Rule 602 was December 31,
    1975;
    this petition was filed December 23,
    1975, one week
    before compliance was due and proposed
    a delay of three years
    in compliance.
    Rule 602 was adopted March
    7,
    1972 and became
    effective April 16,
    1972.
    The petition indicates that during
    the period from the effective date of the regulations until
    some unspecified date after the third calendar quarter of
    1974,
    a period of longer than
    2 years,
    some $1,000 of engineering
    time and $23,100 had been expended to equip one building with
    a trial roof runoff and flume
    system.
    Approximately one yar
    after the trial system was found wanting,
    an engineering con-
    sultant was engaged on November
    4,
    1975,
    less than
    60 days
    prior to the compliance date, to produce a preliminary design
    for submission to the Agency by July
    1,
    1976, six months after
    the compliance date had passed.
    While we have no doubt that the Caterpillar personnel
    involved worked diligently on their assignment, the facts
    as set forth in the petition could support a logical conclusion
    that compliance with Rule 602 by December 31, 1975 was far
    from a high priority concern on the top management agenda.
    An examination of Petitioner’s schedule now proposed for
    bringing the facility into compliance indicates that the
    Board’s implementation date as originally promulgated was
    capable of achievement by Petitioner had he initiated,
    on the
    effective date of Rule 602, the compliance progrant he now
    proposes.
    Second, The requirement for a variance until
    December
    31,
    1978 is a reasonable term
    for design, installation and testing
    of the holding lagoons.
    As discussed just above, were the required implementation
    date December
    31,
    1978, the schedule may indeed be reasonable,
    given a November
    4,
    1975 employment date for a design con-
    sultant.
    However, there is absolutely no preliminary design
    information in the petition concerning the proposed project
    which would allow either the Board or the Agency to verify that
    the time schedule proposed represents
    a reasonable time within
    which the constructions inherent in such a project should be
    completed.
    We are supplied
    a small
    scale
    (1”
    =
    1000’) plot plan with
    four lagoons approximately located thereon with an admonition
    in the text of the petition that the exact number and location
    of the lagoons may change as the design phase continues.
    Similarly we are told that the lagoons will be designed to
    21
    106

    —3—
    handle at least
    10 times the average dry weather flow but
    nowhere
    is the amount of dry weather flow given.
    No cost
    estimate of any nature
    is
    f~urnishedand the schedule proposed
    is conditioned to
    include
    possible further delays necessitated
    by design and procurement of materials,
    labor disputes,
    acts
    of God or occurrences beyond the control of Caterpillar.
    Addi-
    tionally, no cost or schedule comparisons of any alternative
    methods of compliance are set forth in the petition.
    The petition is devoid of any proof that the schedule
    proposed is reasonable;
    nor
    are sufficient facts presented
    from which the Board might draw such an
    inference.
    Third, During
    the
    period for which the variance
    is sought,
    there will not be any significant
    environmental harm due to the fact that
    bypasses can be expected to occur quite
    infrequently,
    i.e., at an estimated rate of
    only
    12 times per year.
    The petition contains no estimate of the quantity and
    nature of
    the overflows except to
    state that oils and suspended
    solids are the only pollutants expected to be discharged.
    Agency grab—samples of effluent from Petitioner’s treatment
    works establish
    the
    presence of chromium, phenol,
    iron,
    zinc
    and cyanide
    and lead to
    the inescapable conclusion that they
    are present in the combined sewer system in addition to the
    oil and grease and suspended solids and all are subject to by-
    passing.
    No estimates of the quantity and nature of the
    discharge from the overflow points were given to us because
    Petitioner “feels that any such estimate would be of highly
    questionable validity.”
    While
    we
    can appreciate the factors
    mitigating against precision
    in
    such an estimate, the following
    information, readily available,
    could be evaluated to assist
    in a determination of the possible environmental impact of
    the discharges:
    (a)
    Measured dry weather flow to the existing
    treatment
    works;
    (b)
    Identification
    of
    contaminants
    present
    in
    treatment
    works
    influent
    (c)
    Average
    concentration
    of
    contaminants
    present
    :Ln
    treatment
    works
    influent;
    (d)
    Measured
    dry
    weather
    flow
    in
    the
    collection
    system compared to design average dry weather
    flow;
    (e)
    Stream flow data, biologic status and water
    quality sampling of those water courses
    receiving the combined sewer overflows from
    Petitioner’s pLant
    site.
    21
    flj7

    —4—
    Since none of the above information appears in the petition,
    the Board
    is simply unable to make any conclusion regarding
    the environmental impact of Petitioner’s discharges on the
    receiving stream and can make no estimate of the benefit
    to the public by Petitioner’s immediate compliance with Rule 602.
    Fourth,
    Without
    a variance, Caterpillar may
    be subject to an enforcement
    case
    ~~E~o~ldjeopardize
    its
    operation
    and affect the
    livelihood of its
    18,500 employees at the East Peoria
    Fifth,
    Caterpillar contributes to the tax
    base of
    the
    community and the State of
    Illinois, and contributes substantially
    to
    the
    gross income of the community by
    amplay
    ing 18, 500 pars
    ons
    at
    the
    Eas
    Peoria facility,
    It
    is clear
    from the petition that the
    cost
    of
    compliance
    with
    the
    regulation
    is not
    in issue
    here and that the hardship
    complained of is solely of
    the
    need for a delay during which
    compliance
    can
    be
    achieved,
    The two preceding allegations
    would
    be
    useful
    in ascertaining the
    social
    and
    economic
    value
    of
    the
    pollution
    source
    under
    Section
    33(c)
    of
    the
    Act.
    The
    Board
    is
    required
    by
    Section 33(c)
    of
    the
    Act
    to
    consider,
    in
    an
    enforcement
    action,, the
    social
    and
    economic
    value
    of
    a
    pollution source,
    as well
    as
    other factors,
    in determining
    the reasonableness
    of a
    discharge which
    is found to have vio-
    lated the Act.
    However, consideration
    of the particular
    criteria established by Sections 33(b)
    and
    (c)
    of the Act,
    including
    the
    social
    and
    economic
    value
    of
    the pollution source,
    are applicable to
    enforcement
    cases
    arid
    then
    by
    way
    of
    mitigation;
    other forms of
    action before the Board such as variance, permit
    denial appeal and
    regulatory proceedings are
    controlled by different
    provisions of the statute, aLthough some of the same factors may be
    involved.
    The scope of a variance order
    is limited by the provisions
    of Sections
    35 and
    :36 of
    the
    Act and the order of the Board
    disposing
    of
    a
    variance petition can only:
    (a)
    Dismiss the petition; or,
    (b)
    Grant the requested variance;
    or,
    (c)
    Grant a variance subject to conditions
    imposed by the Board, however, such a
    conditioned variance would not be binding
    until accepted by the Petitioner
    (Citizens
    Utilities Co.
    v,
    PCB,
    289 NE
    2d 642,
    646—
    648
    (2 Dist,
    1972)).
    21—108

    —5—
    Simply
    stated,
    Petitioner
    is not faced with a shutdown
    order in this proceeding.
    As
    the
    Board
    has
    previously
    held,
    denial of
    a
    variance is not a shutdown
    order
    (Norfolk and
    Western
    ~
    I PCB 281,
    284
    (1971)).
    An order denying
    a variance, liowever,
    is
    a refusal by
    the
    Board to provide the
    Petitioner with
    the defense of a
    variance to a subsequent
    enforcement action,
    In
    Norfolk,
    supra,
    the
    Board
    stated,
    at
    282:
    We
    recognize
    the
    importance
    of
    railway
    operations
    to
    the
    general welfare
    and
    economy
    of
    the
    region..,
    But. Section
    37
    of the Environmental
    Protection
    Act
    makes
    plain that Petitioner must
    prove
    that
    the
    pollution caused
    :by its continued violation
    is
    not
    so
    great
    as
    to justify the
    hardship
    that immediate
    compliance
    would produce.
    In the
    instant
    petition the Petitioner has
    completely
    failed
    to
    meet
    its
    burden of proof.
    We have not
    been provided
    any
    cost
    or
    schedule comparison
    of
    alternative
    methods of
    compliance;
    to
    the contrary we have been provided no
    estimate
    of
    the
    cost
    of
    compliance by any method,
    We have
    absolutely
    nothing
    before
    us
    from
    which we can
    adequately
    assess
    the
    pollution resulting
    from the
    overflows
    from
    the
    combined
    sewer
    system as they now exist,
    Without
    sufficient
    facts
    regarding
    both,
    it would
    not
    be
    poss:Lble
    to
    determine
    if
    there
    is an
    arbitrary
    and
    unreasonable hardship imposed upon the Petitioner
    by
    compliance
    with the regulation
    even
    if
    we were able to
    satisfy
    ourselves
    from PetitionerTs proof that the hardship
    was
    not
    self
    imposed,
    which we cannot.
    The
    Board’s
    denial
    of
    a
    variance
    is
    not
    an
    order
    shutting
    down
    all
    or
    any
    part
    of
    the
    Petitioner’s
    operations;
    in
    fact,
    we
    would
    be
    pleased to consider a new
    petition
    for
    variance
    which
    furnishes
    the information which
    does
    not
    appear
    in
    the
    record
    now
    before
    us in this matter.
    This Opinion
    constitutes the
    Board’s findings of fact and
    conclusions of
    law.
    Mr. Young
    Concurs.
    I, Christan L.Moffett,
    Clerk of the Illinois Pollution
    ontrol
    Board, hereby
    certify the above Opinion
    was adopted on the _________day
    of April,
    1976 by a vote
    of
    21
    —109

    Back to top