ILLINOIS POLLUTION CONTROL BOARD
    May 24,
    1979
    INTERLAKE,
    INC.,
    Petitioner,
    v.
    )
    PCB 79—55
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD
    (by Mr. Goodman):
    On May
    8,
    1979,
    Interlake,
    Inc.,
    filed a Motion to Con-
    solidate this permit appeal with a variance proceeding it
    initiated, docketed PCB 79—104.
    In the alternative,
    Interlake
    moves for the appointment
    of the same hearing officer in both
    proceedings and for a continuance of the hearing scheduled by
    the Hearing Officer
    in PCB 79-55 from May 30,
    1979,
    to a date
    which allows the hearing
    in PCB 79-55 and the hearing on PCB
    79—104 to be scheduled consecutively,
    either on the same day
    or on successive
    days.
    The Board has recently stated that consolidation of a per-
    mit appeal and a variance proceeding
    is inappropriate because
    of the different types of proof and issues involved in these
    two types
    of cases.
    Interlake,
    Inc.
    v.
    EPA, PCB 79—38
    (Order
    of the Board, dated April
    26, 1979);
    Beker Industries Corp
    v.
    EPA,
    PCB 79—9
    (Order of the Board, dated January 18,
    1979).
    The Motion to Consolidate
    is hereby denied.
    However,
    the
    Board finds that the request for consecutive hearings by the
    same hearing officer is reasonable.
    We will grant the request
    and order that consecutive hearings
    in PCB 79—55 and PCB 79—104
    be held within
    45 days of the date
    of this Order.
    IT
    IS SO ORDERED.
    I, Christan L. Moffett, Clerk
    of the Illinois Pollution
    Control Board, hereby certify the above Order was adopte~on
    the
    ~
    day of
    ______________,
    1979 by a vote of
    ~
    ~L~L
    Christan L. Moff
    ,
    Clerk
    Illinois Pollutio
    ontrol Board
    33—605

    Back to top