ILLINOIS POLLUTION CONTROL BORD
November
17,
1988
CITY OF ROCKFORD,
)
Petitioner,
)
v.
)
PCB 88—107
)
WINNEBAGO COUNTY BOARD,
)
)
Respondent.
)
SUPPLEMENTAL STATEMENT (by B.
Forcade,
J.D. Dumelle
&
R.
Flemal):
The majority opinion expresses the views of
a majority of
the Board.
In addition, we have reached
an agreement as
to what
would constitute an appropriate outcome for the “need” criterion.
The Act provides
in significant part
as follows:
The
county
board
of
the
county
...
shall
approve the site location suitability of
a
new
regional
pollution
control
facility
only
if
the facility meets
the following criteria:
1.
the
facility
is necessary
to accommodate
the
waste
needs
of
the
area
it
is
intended
to serve
Ill. Rev. Stat.
ch.
1039.2(a)
(1988)
P. facility
is
“necessary”
if
it is “reasonably required by the
waste needs of
the area intended to be served,
taking into
consideration the waste production of the area and the waste
disposal capabilities,
along with any other relevant factors.”
Waste Management of Illinois,
Inc.
v.
PCB, 122 Ill. App. 3d 639,
645,
461 N.E.2d
542, 546
(3d Dist.
1984);
see Waste Management of
Illinois, 123
Ill.
App.
3d at
1084,
463 N.E.2d at 976;
E
&
E
Hauling,
Inc.
v.
PCB,
116 Ill.
App.
3d
586,
609,
451 N.E.2d 555,
573
(2d Dist.
1983), aff~d, 107 Ill.
2d
33,
481 N.E.2d
664
(1985).
“Need”
is largely contingent on the remaining life of
existing landfill capacity
in relation to the time necessary to
develop new capacity.
We cannot substitute our judgment
as
to which existing
landfill life and additional capacity deve1o~menttimes
are most
reasonable;
the sole
issue
is whether
Rockford has shown that the
Winnebago County Board’s determination that existing capacity
is
sufficient
to meet local need
is not supported by the “clearly
evident, plain and indisputable weight of
the evidence”
in the
93—443
—2—
Winnebago County record.
We conclude that the Winnebago County
record could reasonably support
a range
of conclusions with
regard
to the existing landfill life available to receive
Winnebago County wastes and the time necessary to open additional
capacity to receive those wastes.
The county record could support
a conclusion that anywhere
from about six to twelve years of life remain for existing
landfills
in the area.
One Rockford witness, Clarence D. Beatty,
of Camp, Dresser
& McKee, concluded that
10 to
12 years
of
landfill capacity existed
in four landfills as of February
1983.
Rockford Ex.
2,
p.
1—5; County
R.
50—51.
Another Rockford
witness, William A. McCann,
a real—estate appraiser,
concluded
that the sole operating landfill
in Winnebago County,* Pagel Pit,
had
art estimated remaining life of only one to three years
as of
January,
1986,
but two landfills located outside the county had
remaining lives
of up to
10 years.
The Browning—Ferris
Industries
(“SF1”) landfill
in Ogle County had
a remaining life
of
10 years,
and the AM Disposal Landfill
(i.e., the Bonus Land-
fill)
in Boone County had
a remaining life
of two years and
an
available expansion area that could extend
its life by
10
years.
Rockford Ex.
38,
p.
14; County R.
499—500.
In Mr.
McCann’s estimation,
this
10 year capacity was
insufficient.
Rockford Ex.
38,
p.
15; County
R.
501—02.
Another Rockford
witness,
Robert M. Robinson of Burns
& McDonnell,
testified that
about six to eight years of capacity existed
in the Pagel Pit,
the SF1, and Bonus landfills
for disposal of area wastes.
County
R.
202—03.
Lower
or higher estimates of remaining capacity are
possible.
The record indicates that Pagel Pit could continue
in
operation for anywhere from one
to five years.
Rockford
Ex.
3
(five years); Rockford Ex.
16,
p.
1—3
(five years); Rockford Ex.
38,
p.
13
(one
to three years);
County R.
30
&
203
(five years);
County
R.
964 (three
to five years
if extended, otherwise until
1987);
R.
1088—89
&
93
(four
to five years with
a newly—opened
cell,
for an estimated closure time of Summer,
1991).
Rockford
wastes currently go to Pagel Pit.
County R.
81
& 1092.
In the
absence
of
a new landfill, Rockford and Winnebago County wastes
would necessarily go to existing landfills outside the county.
The estimates
for the continued life of the BFI
landfill
in Ogle
County vary like those for Pagel Pit, between six and 15
years.
Rockford Ex.
3
(15 plus years,
or 12 years
if accepting all
Winnebago County wastes); Rockford Ex.
16,
p.
1—2
(12 years at
*
Two landfills exist
in Winnebago County,
but one,
the South
Main landfill
in Rockford,
accepts only non—putrescible,
dry
wastes,
such
as construction rubble,
debris,
etc.
Rockford Ex.
38,
p.
11; County
R.
30
&
962.
This
landfill is not considered
as existing capacity
for
the purposes of this proceeding.
93—444
—3—
current rate of fill);
Rockford Ex.
38
(10 years);
Rockford Ex.
75,
pp. W—ll
& R—l8
(19 years from 1981); County R.
963—64
(10
to
15 years
at current rate of
fill, but
6 years
if accepting all
area wastes).
The estimated remaining life of the Bonus Landfill
ranges up
to about
15 years with
a permitted expansion.
Rockford
Ex.
3; County R./ 31
& 34;
see Rockford Ex.
16,
p.
1—2
(two
years,
with an available area
for expansion by
10 years); County
R. 963 & 965—66
(a vertical expansion adds one or two years).
The estimates did not consider the County Farm Landfill
in Boone
County, which had an anticipated
life of over six years,
because
it accepts only about 25 percent of its wastes from outside Boone
County, only a portion of which is from Winnebago County.
County
R.
1151
& 1154;
see Rockford Ex.
77; County
R.
54.
Need
is also largely contingent on the time necessary to
bring additional capacity into existence.
Mr. McCann testified
that
10 years
is
a short time for landfill planning,
but the
record
is unclear what activities he considered
in this
estimate.
County
R.
499—500
&
502.
He testified that
it takes
two to three years
to begin operations after siting and
permitting activities are complete.*
County R.
502—03.
Other
estimates indicate that the time necessary to
site,
design,
permit,
and commence operations is between four and six years.
Rockford Ex.
77 (five years); County
R.
203
(four
to six years);
County R.
282
(five to six years).
Thus,
the time necessary to
develop new landfill capacity could
lie between four and six
years based on this record
We conclude that although the low—end estimates
of existing
capacity are very close to the high—end estimates of the time
necessary to add capacity,
Rockford has failed
to prove
these are
the necessary conclusions from the county record.
The Winnebago
*
The Section 39.2 county board site approval process requires
a
minimum 14—day pre—request public notice and provides
for
a 180—
day deadline for
a final county board determination.
Ill. Rev.
Stat.
ch.
ill
1/2, par.
1039.2(b)
&
(e)
(1988).
The Section 39.3
permitting process requires
a preliminary Agency determination
within
90 days,
a public hearing within
180 days
of the
preliminary determination,
and a final determination within 60
days
of completion of the public hearing.
Section l039.3(c)(l),
(e)
&
(fl.
The administrative siting
and permitting process
could therefore reasonably require about one and
a half years.
The maximum time for this process
is about
three and
a half years
if no appeals occur.
See Section 1039.2(f).
Appeals of county
board decisions to this Board add about four to five months.
See
Section 1040.1(a).
Similar appeals of Agency permit decisions
require
a similar
time.
See Section 1040(a)
&
(c).
There
is
no
similar
time limitation on subsequent appeals
to the appellate
courts.
See Section 1041(a).
93—445
—4—
County record could also support
a conclusion that existing
capacity
is sufficient for
12 years and only four years are
necessary
to bring additional capacity into operation.
It is
immaterial whether
or not we would adopt low—end estimates
of
capacity and high—end estimates of the time needed
for adding
capacity.
The Winnebago County decision as
to need
is not
against the manifest weight of the evidence.
Further, prior
cases have held that
an existing landfill capacity of ten years
supports a conclusion that a determination that there is no need
is not against the manifest weight of the evidence.
See Waste
Management of Illinois,
123 Ill. App.
3d at 1086—88,
463 N.E.2d
at 977—979; Waste Management of Illinois,
122 Ill.
App.
3d at
644—45
& 461 N.E.2d at 544—45;
E
&
E HaiQing,
116 Il1~~P.pp.3d at
608—09; 451 N,E.2d at 572—73.
r
~
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certif~ythat the above Supplemental Statement was
submitted on the
J’~-”
day
of ________________________,
1988.
~
~7.
,~,,J
Dorothy M/Gunn,
Clerk
Illinois Pollution Control Board
93—446