ILLINOIS POLLUTION CONTROL BOARD
    June 28,
    1973
    JOHNS-MANVILLE PERLITE CORPORATION,
    ROCKDALE PLANT
    #73—60
    v.
    ENVIRONMENTAL PROTECTION AGENCY
    ROBERT JOYCE, APPEARED ON BEHALF OF PETITIONER
    STEVEN G. BONAGUIDI, ASSISTANT ATTORNEY GENERAL, APPEARED ON BEHALF
    OF ENVIRONMENTAL PROTECTION AGENCY
    OPINION
    AND
    ORDER OF THE BOARD
    (BY SAMUEL T.
    LAWTON,
    JR.):
    Petition filed by Johns-Manville Perlite Corporation seeks
    variance from the provisions
    of Rules
    203(b),205(f)
    and 206(a)
    of
    Chapter
    2: Air Pollution,
    •of the Illinois Pollution Control Board
    Rules and Regulations, until September
    28,
    1973.
    The foregoing
    Rules are not presently in effect nor will they be by September 28,
    1973.
    Accordingly, we construe the foregoing petition as one seeking
    relief from the requirements
    of Rule 3—3.111 of the Rules and Regula-
    tions Governing the Control of Air Pollution, which presently limit
    the amount of particulates that may be emitted into the air.
    The
    difficulty with the present application for variance is that petition-
    er makes no representation that it will be in compliance by Septem-
    ber 28,
    1973, but only that it will submit
    a compliance program by
    June 30,
    1973, which will delineate a program as yet unascertained
    that will,
    at some unspecified date, bring the operation into comp1ianc~
    Petitioner represents that prior to June
    30, 1973,
    it will sub-
    mit an application for extension of variance should this appear
    necessary in light of its compliance program.
    As of the date of
    this opinion,
    no compliance program nor application for extension of
    variance has been received.
    We further note that while the hearing on the amended petition
    was held on April 26,
    1973, the transcript was not received by the
    Board until May 31,
    1973.
    Petitioner’s plant
    is located south of Joliet and is engaged
    in the manufacture of mineral-type roof insulation board, decorative
    ceiling tile and ground perlite filter aids.
    Its 1973 sales are
    anticipated in the amount of $13,000,000.
    The plant employs approx-
    imately 276 personnel in production,
    administration and sales.
    The specific variance petition relates to the Fesco roofing board
    insulation department.
    Fesco is a mineral type fire~Lresistantroof
    insulation which is applied to dead level roofs in industrial and
    8—401

    commercial construction.
    The Fesco production process is described
    as
    follows:
    perlite ore is received in bulk rail cars.
    The ore
    is unloaded and transferred to nine perlite expanders where the
    ore is expanded to useable form.
    Waste newspaper is recycled by
    returning the waste paper to pulp form through the use of a hydro-
    pulper.
    Bags of starch are mixed with water to form
    a starch slurry.
    The expanded perlite, news pulp, starch slurry and asphalt water emul-
    sion are wet mixed in
    a series of headboxes and deposited on a four-
    drinier wire where the product
    is
    formed, pressed to desired thickness
    and partially dewatered.
    The board
    is then cut into large sheets and
    loaded into
    a five zone,
    eight deck Coe dryer, where the water re-
    maining in the product is driven off.
    The board is then trimmed to
    final size and packaged for shipment.
    Stack tests conducted by an independent testing laboratory
    disclose that the dryer stacks were emitting particulates that con-
    ceivably would violate the existing regulations.
    While the original
    computation indicated emissions in the amount of 73.4 pounds per hour
    of particulates based on
    a process weight rate of 93,000 pounds per
    hour,
    subsequent analysis indicates emissions of only 49.6 pounds
    per hour against an allowable emission rate of
    47.2 pounds per hour.
    While part of this difficulty
    is attributable to what the Company
    construes to be non-particulate emissions,
    it is noted that the difference
    between the permissible limits and the computed limits
    is not particu-
    larly great and we will assume for purposes of this proceeding that
    the 49.6 pounds per hour is,
    in fact,
    a particulate emission rate.
    In the event it is determined that the particulate emission rate is
    not exceeded then, of course,
    no variance would be needed or appropriate.
    The original measurements likewise reflected emissions of con-
    taminants in addition to particulates,
    as follows:
    CO
    221.74 lb/hr
    SO2
    .07 lb/hr
    N02
    17.6
    lb/hr
    CH4
    35.2
    lb/hr
    The foregoing emissions were attributed to incomplete combustion at the
    time the stack tests were conducted, which the Company
    felt could be
    eliminated by adjustment and re-balancing of the dryer.
    To further
    explore, the dryer was removed from servicr between December
    4 and
    December 14,
    1972, and a task team creat:~ito study the problem.
    During the shut—down new burners were installed in
    zones
    1 and 2,
    whdch are believed to have lessened the emissions both in
    zones
    1 and
    2 and zones
    3,
    4 and 5 because of interaction between the zones.
    Other
    correction work was made during the shut—down,
    including the installa-
    tion of new burner parts in zone
    3 and the installation
    of new baffles
    in zones 1 and 2.
    New stack tests were conducted on all dryer zones
    during the week of February 12, 1973.
    —2—
    8—402

    While at the hearing, the Company represented that the most
    recent stack tests indicated a situation of possible compliance
    with the particulate regulations,
    it still is desirous of taking
    all necessary steps to assure that compliance has been met.
    There
    is a possibility that the emissions may 3till be in violation, despite
    the corrective action taken.
    The Company proposes to conduct a pilot test program with a
    high energy air filter system known as HEAF, which has been developed
    and marketed by the Company for control of air contaminants.
    A
    pilot installation will be made on one of the five dryer stacks
    to estimate
    if the HEAF system will be able to conform with the
    regulations.
    Although the petition indicates that this testing would
    be done in March,
    at the April
    26, 1973 hearing it appears that this
    testing has not been finalized so that as of the date of the hearing,
    we are not informed whether the HEAF
    system would be adequate and
    must assume,
    for the purpose of this variance, that other systems
    must be explored.
    These include
    a wet-electrostatic precipitator,
    a high energy scrubber and a cloth collector.
    While these presumably
    will be conducted simultaneously with the I~AFpilot test,
    it
    is
    estimated that
    a minimum of 2-1/2 months will be needed to complete
    the technical feasibility studies described.
    Based
    upon
    the
    foregoing
    tests,
    the
    Company
    anticipates
    that
    it
    will
    conclude
    by
    June
    30,
    1973,
    its
    determination
    as
    to
    what
    system
    will be the most appropriate and will
    file such further petitions
    as are necessary to enable an extension of variance to provide ade-
    quate time for the installation of the abatement program selected
    to achieve
    full compliance.
    Following completion of the studies,
    the abatement system will be selected, lay-outs prepared, specifica-
    tions drawn up and ordered and the variance petition submitted.
    The variance request to September 28, 1973 is in contemplation of
    a further extension being submitted no later than June 30,
    1973,
    which would be acted on within 90 days pursuant to statutory require-
    ment or before September
    28,
    1973, which would eliminate any gap
    in the protective shield granted by a variance in the event the emis-
    sions do,
    in fact, violate the relevant regulations.
    While we are
    not normally disposed to grant a variance in the absence of a defini-
    tive plan of compliance, we believe that the relatively small amount
    of particulate emissions in excess of the applicable limits, justi-
    fies the allowance,
    in consideration of the Company’s represented
    program for developing and installing
    an abatement system.
    The hard-
    ship imposed on the community in the event the variance is granted
    does not appear significant,
    as compared to the hardship on the Com-
    pany in the event the variance is denied, requiring
    either the
    imposition of
    a penalty or the curtailment of production.
    We grant petitioner variance until September
    28, 1973,
    from
    the provisions of Rule 3-3.111 of the Rules and Regulations Governing
    the Control of Air Pollution.
    —3—
    8
    403

    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    IT IS THE ORDER of the Pollution Control Board that:
    1.
    Petitioner,
    Johns-Manville Perlite Corporation,
    be granted
    a variance from the provisions
    of Rule
    3—3.111 of the Rules and Regulations Governing the
    Control of Air Pollution until September 28, 1973, to
    enable petitioner to submit to the Board and the
    Agency
    a definitive plan
    for the installation of
    abatement equipment to bring its operation into com-
    pliance with the relevant regulations.
    2.
    The Board retains jurisdiction of this matter for
    such other and further order as may be appropriate
    based on submissions made by petitioner.
    I, Christan Moffett, Clerk of the Pollution Control Board, certify
    that the above Opinion and Order was adopted on the
    ~
    day of
    June,
    1973, by a vote of
    ,3
    to
    o
    —4—
    8—
    404

    Back to top