ILLINOIS POLLUTION CONTROL BOARD
    June
    27, 1974
    DEERE AND COMPANY,
    Petitioner,
    vs.
    )
    PCB 74—119
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr. Henss):
    Deere and Company requests variance for a period of one year
    from Rules 103
    (permits),
    104
    (compliance programs)
    and 203(a)
    (particulate emissions)
    of the Illinois Air Pollution Control
    Regulations
    for operation of its malleable iron foundry at
    Hoopeston,
    Illinois.
    The facility in question is a 60 year old
    foundry which uses two air furnaces for melting.
    In PCB 73-88
    Petitioner was granted a variance until December 31, 1973 for the
    purpose of modifying the two furnaces so as to achieve compliance
    with the particulate regulations.
    In that proceeding the Board
    ordered that:
    “a) Petitioner shall operate only one of the two
    furnaces at a time;
    b)
    one furnace shall be converted to utilize
    #2 fuel oil and be equipped with an afterburner by September 15,
    1973;
    c) a stack test shall be conducted on the converted furnace
    by September 30,
    1973;
    d)
    if
    the stack test proves compliance
    with Rule 203(a)
    Petitioner shall convert the second furnace to
    oil firing by December 31,
    1973.
    If
    the stack test fails to
    prove compliance Petitioner shall apply for a variance indicating
    what control methods will be used and the time schedule for
    bringing the air furnaces into compliance”.
    Petitioner converted one furnace to oil
    and
    then performed
    two stack tests on the furnace during the same batch cycle.
    The
    tests showed emission rates of 4.69 lbs./hr. and 1.59 lbs./hr.
    Deere submitted the stack test results to the Agency, believing
    they would be averaged to show emissions of 3.14 lbs./hr.,
    comfortably under the allowable emission rate of
    3.7 lbs./hr.
    Conversion of the second furnace was then scheduled so as to be
    completed by December 31,
    1973.
    The Agency denied an operating permit for the first converted
    furnace on the gráund that the first test
    (4.69
    lbs./hr.)
    failed
    12
    —637

    —2—
    to demonstrate compliance with the Regulations.
    Deere resub-
    mitted its application for permit in February 1974 arguing that
    the Agency had made an error in calculating the allowable
    emission rate.
    The operating permit was again denied and this
    variance proceeding
    followed.
    The Agency asserts
    that the issues raised in this variance
    proceeding can only be adjudicated in an appeal from permit
    denial “if at all”.
    For the purpose of deciding this variance
    case,
    the Agency states,
    “the Board must accept the Agency’s
    interpretation regarding the stack tests and the computation
    of the applicable emission rate”.
    We do not accept the Agency’s limited view of our function..
    Petitioner has raised two important issues in conformance with
    Rule 401(a) (v) of the Procedural Rules.
    We shall decide those
    issues.
    A determination of the allowable emission rate and the
    actual rate of emission is
    a basic part of a variance proceeding,
    as it is
    a permit proceeding.
    In filing a petition for variance,
    rather than an appeal from permit denial, Deere states that
    regardless
    of its dispute with the Agency over the averaging of
    stack tests and determining the cycle
    time of the process,
    the
    matters
    “can be resolved more expeditiously by further control
    efforts than by litigating the permit denial”.
    Operation of an air furnace on a batch cycle requires that
    the furnace be charged with raw materials which are melted,
    adjusted for metallurgical content and then discharged from the
    furnace.
    The Agency contends and the stack tests clearly show
    that particulate emissions from the batch cycle are heaviest
    during the earlier stages of the melt cycl~. For this reason
    the Agency proposes that Petitioner be required to conduct one
    test run of the stack test during “the first hour of the cycle,
    excluding any warm up period during which no metal is in the
    furnace”.
    On the record provided,
    the Board finds
    that stack tests
    conducted at different stages of
    a cyclical process, where emission
    rates are known to differ during the process,
    cannot be averagect hi
    determining whether compliance has been achieved with applicable
    regulations.
    If results of one test exceed the applicable emission
    rate standard then the cyclical process
    is being operated in violation
    of that standard regardless of what the other tes~smay show.
    Where
    such excessive emissions occur during a process start—up, the start—up
    emissions may be permitted under the provisions of Rule 105 of the
    Regulations.
    The Agency,
    in its Response to Board Request for Supplemental
    Information,
    states that the parties are in agreement on the

    —3—
    following facts:
    a)
    the charge rate is 64,000
    lbs. per cycle;
    b)
    the melt cycle time of
    16 hours yields
    a process weight rate
    of 4,000 lbs,/hr.;
    c)
    the allowable particulate emission rate
    is 3.7 lbs./hr.
    These figures and rates are in substantial
    agreement with the information provided by Deere in its Comment
    filed June
    7,
    1974.
    It appears, therefore,
    that
    the
    dispute
    over the method of computing the allowable emission rate can
    be resolved, and the rate of 3.7 lbs./hr.
    coincides with our
    findings
    in
    PCB
    73-88.
    Because of the delay in bringing the first furnace into
    compliance, conversion of the second furnace to oil firing has
    not occurred. Petitioner ceased operating the second furnace on
    coal and this forced the converted furnace to be in constant
    operation.
    This has taken its toll on the converted furnace
    and Petitioner must either proceed with conversion of the second
    furnace or periodically shut down the converted furnace for
    repairs.
    Petitioner contends that the degree of particulate
    control demonstrated
    in the first furnace should be convincing
    enough to justify conversion of the second furnace pending
    experimental modifications on the firstS furnace.
    Experimental modifications contemplated by Deere to further
    reduce its emissions include the placing of an inverted brick
    bung behind the choke bung and a wall of brick on the stack
    floor at one end of the arch area.
    It is believed that some
    variation in arrangement of these baffles will cause particle
    impingement to the degree necessary to reduce emissions by an
    additional
    20,
    the reduction required to achieve compliance.
    Cost of the entire experimental project is not expected to
    exceed $10,000.
    The Agency believes that the untested control
    scheme might work,
    in view of the small degree of control
    required to achieve compliance, and would effect a substantial
    economic savings to Deere.
    Petitioner
    requests
    that
    it
    be
    permitted
    to
    convert
    the
    second
    air
    furnace
    to
    #2
    fuel
    oil,
    install
    an
    afterburner
    and
    then
    operate
    the
    second
    converted
    furnace
    for
    “one
    week
    periods
    only when the first air furnace is undergoing
    repairs
    and
    maintenance
    or
    when
    the
    baffles
    are
    being
    installed
    or
    modified”.
    All
    equipment
    and
    parts
    are
    on
    site and conversion
    of the second
    furnace
    will
    be
    completed
    within
    one
    month after receipt of our
    Order
    allowing
    the
    conversion.
    Petitioner
    has
    argued
    convincingly
    that considerable heat loss would occur if
    #2 furnace were
    operated for less than a full week at a time.
    The Agency no
    longer objects to the company’s proposed schedule for operating
    the furnaces.
    The EPA recommends
    that Deere be required to submit a new
    variance
    petition,
    including
    a
    compliance
    plan
    and
    project
    639

    —4—
    completion
    schedule,
    in the event new stack tests
    fail to
    prove compliance.
    The Agency says such compliance plan should
    specify control equipment which “has a generally accepted per-
    centage of efficiency, and which is acceptable to the Agency”.
    Deere argues that this condition might jeopardize the Company’s
    “rights and remedies”,
    such as appeal of any permit denial, a
    variance petition for different relief,
    or
    a shut down of the
    facility.
    However,
    the Agency contends that such condition is the
    essence of Part
    6 of our prior Order.
    In addition the Agency
    points out that Petitioner
    is requesting a license to pollute
    while conducting experimental tests and therefore it
    is not
    unreasonable
    to require Petitioner to go to proven technology
    if
    the experiments fail.
    Finally, the Agency takes the position
    that the condition would not prevent Petitioner
    from seeking
    other remedies available under the Act.
    We concur with the
    Agency’s view on this matter.
    The final dispute is over length of variance.
    Petitioner
    seeks
    a December 31, 1974 expiration date, contending that its
    stack testing firm currently has a sixty day backlog and cannot
    possibly
    perform
    the
    required
    stack
    test
    before
    August
    1,
    1974.
    The
    Agency,
    on
    the
    other
    hand,
    recommends
    a
    four
    month
    variance.
    The
    issue
    does
    not
    relate
    to
    actual
    construction
    or
    arrangement
    of
    the
    baffles
    but
    to
    the
    availability
    of
    a
    test
    firm
    for
    testing
    of
    emissions
    for
    each
    baffle
    configuration.
    Petitioner claims
    that “at most,
    two or three modifications could be achieved and
    tested
    within
    four
    months”.
    Th~Agency
    presently
    has
    a
    list
    of
    37 approved independent testing firms qualified to conduct stack
    tests and seeks
    to have Petitioner schedule at least one test
    prior to July
    7,
    1974.
    The plant will shut down for 20 day
    vacation on that date.
    We cannot require that a stack test be conducted prior to
    July 7, because Petitioner would have only
    a few days to make
    the necessary arrangements after receipt of our Order in this
    case.
    However, we suggest that Deere contact other stack testers
    if that becomes necessary to avoid delay in the program.
    Deere and Company has satisfactorily shown its need for
    variance from Rule 203(a)
    and we shall grant the variance until
    December 31,
    1974.
    We think the longer period will be needed in
    order to modify the second furnace following the various experi-
    ments.
    With the grant of variance from 203(a)
    the Agency may now
    address the application for permit on the two furnaces.
    We
    will grant variance from Rules 103 and 104 for the baffle system
    in order to avoid
    a continuous shuffling of permit papers during
    the experimental period.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law.
    12—640

    —5-.
    ORDER
    It
    is the Order of the Pollution Control Board that Deere
    and Company be granted variance from Rule 203(a) of the Air
    Pollution Control Regulations until December 31, 1974 for the
    operation of two air furnaces
    at its Hoppeston foundry and from
    Rules 103 and 104 of the Air Pollution Control Regulations until
    December 31,
    1974 for the purpose of installing and testing
    furnace baffles designed to bring compliance with Rule 203 (a)
    The variance is subject to the following. conditions:
    1.
    Petitioner shall convert the second air furnace to
    #2 fuel oil and install an afterburner on it within
    45 days after receipt of this Order.
    2.
    Petitioner shall, after converting the second furnace,
    operate said furnace for periods not in excess of one
    week, but only when the first furnace
    is down for
    maintenance or repair or baffle modification.
    3.
    Petitioner shall make every reasonable effort to
    avoid delay in its stack testing program and shall
    make use of the list of stack testing firms described
    in these proceedings if it becomes necessary to avoid
    delay in the program.
    4.
    Petitioner shall notify the Agency in advance of stack
    tests and allow Agency personnel to observe such tests
    if they so desire.
    As far as possible the testing
    shall be conducted during the same period of the batch
    cycle as those tests conducted on September
    25,
    1973.
    5.
    On or before October
    31, 1974 ~Petitioner shall submit
    to
    the Agency a report on the stack test results.
    If
    the stack test proves that the first furnace has been
    brought into compliance with Rule 203(a),
    Petitioner
    shall apply for and obtain all necessary permits for
    the baffle system and
    immediately thereafter
    install
    the baffle system on the second air furnace.
    All
    details of the successful baffle system shall be
    supplied to the Agency when Petitioner makes application
    for the permits.
    6.
    If the stack test fails to prove compliance with Rule
    203 (a), Petitioner shall apply for such additional
    variance or may be needed beyond December 31,
    1974 and
    shall indicate what control methods will be used and
    the time schedule for bringing the air furnaces into
    compliance.
    641

    —6—
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certif
    the above Opinion and Order
    j.~as adopted
    this
    ~74’~
    day of
    ________,
    1974 by a vote of
    ‘5
    to
    p
    ~JJL~

    Back to top