ILLINOIS POLLUTION CONTROL BOARD
    November 15,
    1979
    AMERICAt~IHOECHST CORPORATION,
    Petitioner,
    v.
    )
    PCB 79—43
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr. Goodman):
    On April
    13,
    1979,
    Petitioner American Hoechst Corporation
    filed
    its petition for variance before the Board.
    Petitioner
    seeks a variance from Chapter
    2:
    Air Pollution Control Rule
    203(g)(1)(B),
    “for a period of sixty
    (60) days following August
    16,
    1979 or for such period as may be necessary to secure a
    permit for
    its
    Ottawa facility’s two
    (2) Babcock and Wilcox
    FF15-32 chain grate stoker coal
    fired boilers”
    (Second Amended
    Petition,
    p.1).
    Petitioner, however, believes “that
    it now
    and will hereafter be able to satisfy the formulation standards
    of Board Rule 203(G)(1)(B)
    as well
    as the requirements of the
    Illinois Environmental Protection Act” based upon the prelim-
    inary results
    of testing conducted during July 17—19,
    1979
    (Second Amended Petition,
    pp.1-2).
    Petitioner’s First Amended
    Petition alleged that immediate compliance “would impose an
    unreasonable hardship on Petitioner since Petitioner expects
    that Union Carbide Corporation
    its
    lessee
    will cease opera-
    tions at this facility by the middle of 1979,
    resulting in
    major changes
    in steam requirements
    at this facility”
    (At p.3).
    Petitioner’s estimate of the cost of compliance
    is over $300,000.
    The major issue
    in this proceeding has been whether Peti-
    tioner has proven that immediate compliance with Rule
    203(g)(1)(B) would constitute an arbitrary or unreasonable
    hardship.
    This Petitioner has not done, and for this reason,
    among other reasons,
    its request for variance will
    be denied.
    American Hoechst Corporation employs
    220 persons
    to pro-
    cess polyvinylchloride
    (PVC)
    resins and conducts blending
    and calendering operations
    to manufacture yearly 12,000,000
    pounds of PVC film
    (R.12).
    It produces PVC sheets in sheet
    and in roll
    form,
    sometimes planishing the sheet
    (R.17).
    Planishing is
    a process
    in which a PVC sheet is placed between
    two pieces of metal and inserted in a
    2 feet by
    8 feet press
    3—103

    —2—
    to change
    its characteristics by the application of heat and
    pressure
    (R.17—8).
    The steam demand of the coal—fired boilers to heat the
    building
    is a uniform one which does not upset the boilers,
    but every hour one of five planishing presses
    is run for an
    hour, which requires an almost double steam demand for the
    three to five minutes during which the press is started
    (R.19).
    This fluctuating steam demand is a source problem
    (R.20) and
    is the reason attributed to violations
    of Rule 203(g)(1)(B)
    (R.23—4,
    73—5,
    89—90,
    96—7,
    113—4).
    On September
    5,
    1979 hearing was held in this matter.
    A petition to intervene by thirty—three owners of mobile homes
    in King’s Trailer Court,
    which is located just northwest of
    the city limits of Ottawa
    in LaSalle County, was allowed by
    the hearing officer (R.10—11).
    Representative Breslin of the
    38th District on May 14, 1979 submitted petitions from
    97
    citizens opposed to granting of
    a variance.
    These were filed
    more than 21 days after the effective filing date of the peti-
    tion of April
    13,
    1979 and are therefore considered as public
    comment.
    In December of
    1977,
    Petitioner bought the facility at
    issue
    (R.20).
    A permit had been issued covering the facili-
    ties for the period 1974 through February of 1979;
    the permit
    was based on testing conducted in 1973 for Union Carbide
    Corporation
    (Union).
    Petitioner believed the results of the
    1973 tests to be valid and applied for a permit
    in June of
    1978.
    In July of 1978,
    the Illinois Environmental Protection
    Agency
    (Agency)
    requested more testing done.
    This was performed
    in October but the results indicated to Petitioner that a
    permit might not be granted to Petitioner upon the expiration
    of the previous permit.
    Petitioner then “evaluated many of
    theirl
    alternatives” and
    in February of 1979 petitioned for
    a variance “limited
    in time
    ...
    to examine the possibilities,
    to see what could be done about bringing the boilers into
    compliance”
    (R. 20—1).
    Petitioner’s boilers have not been significantly modified
    in 30 years
    (R.18),
    and are operated with no air pollution con-
    trol equipment
    (R.41).
    In June of 1979,
    Petitioner met with
    the Agency.
    It was determined that there was
    a possibility of
    complying by derating the boilers.
    Tests at lower ratings
    were performed in July of 1979,
    and Petitioner resubmitted
    its permit application and filed a Second Amended Petition
    for Variance on August
    7,
    1979
    (R.22).
    Petitioner received two complaints about
    its particulate
    emissions from neighbors
    in December of 1978.
    During the
    Summer of 1978 Intervenor
    4.
    E. Gillard called Petitioner’s
    Plant Manager Youmans,
    who visited the neighbor’s site
    (R.46-7).
    36—104

    —3—
    On June 22, July 20,
    22 and 24,
    and August 25 and 30,
    1979,
    Petitioner’s emissions were particularly bothersome to neigh-
    bors
    (R.144—5,
    160—1,
    173—5, 183).
    On June 30,
    1979 Union
    ceased its manufacturing process
    (R.42).
    During August,
    1979,
    Union removed its equipment and the facility’s steam consump-
    tion decreased
    (R.39—40).
    The problems Petitioner faces in complying include
    a high
    steam demand and a fluctuating particulate emission amount when
    its five planishing presses are in operation.
    Opacity readings
    vary with the type of coal used
    (R.23-4,
    32).
    The fluctuation
    occurs five times during 8—hour periods of the operation of the
    press
    (R.29—30).
    Fuel conversion is expensive for Petitioner
    and apparently is
    in short supply (R.24,49);
    installing clean-
    up equipment is likewise expensive
    (R.25).
    Petitioner has chosen the following course of compliance:
    reduce steam production by burning 5,000 tons or less of coal
    per year;
    limit
    the amount of
    steam to the planishing press
    to level the fluctuating steam load and to limit the draw of
    the press;
    operate the press at lower pressures to level the
    fluctuating
    steam load;
    further insulate the boilers;
    install
    smaller steam valves to reduce the size of the fluctuating
    steam
    load
    (R.25-7);
    install
    a dry sprinkler system;
    not heat
    the buildings which Union had occupied
    (R.36);
    and soot blow
    the boiler more frequently
    (R.76).
    At the hearing, Petitioner introduced no evidence regar-
    ding the environmental impact a variance would have
    (R.22).
    It has conducted no studies on environmental effects
    (R.37).
    It alleges that operating at derated levels would reduce the
    particulates emitted to an amount which would enable Petitioner
    to be
    in compliance.
    It is by virtue of this allegation that
    Petitioner renewed its application for a permit and its peti-
    tion for a variance
    (R.22).
    Regarding the fluctuating demand, testing at various fluc-
    tuating
    loads may not be possible
    (R.69,
    89—90).
    Tests results
    at steady state cannot be compared with test results under
    fluctuating demand
    (R.115).
    Petitioner alleges that tests show
    that it would be
    in compliance if
    it could use the same coal
    it has been using and could operate the boilers at less than
    25,000 pounds of
    steam per hour
    (R.33), which is the maximum
    capacity of the boilers
    (R.21).
    Petitioner plans
    to experi-
    ment with coals having 0.70,
    0.83
    and 0.87
    sulfur content
    (R. 65—6).
    The normal operating level of the boilers since June of
    1979 has been 5,000 pounds
    of steam per hour when the planish—
    ing presses are not operated, and 12,000 pounds per hour,
    for
    three
    to four minutes, when they are operated
    (R.34—5,
    61).
    Petitioner projects a “normal operation” during the winter
    months of 10,000 pounds per hour;
    no steam rate was projected
    56—105

    —4—
    for operation of the presses during the winter months
    (R.34—5).
    There are opacity problems operating at levels of less than
    10,000 pounds
    (R.35-6);
    the boilers become
    less efficient due
    to nonuniform temperatures within the boiler casings and par-
    ticulate emissions are increased
    (R.63).
    It
    is the Agency’s position that,
    since the ash content
    of the coal Petitioner is experimenting with is unknown to the
    Agency,
    it cannot ascertain whether Petitioner will violate
    the particulate emission standard.
    However,
    the Agency be-
    lieves that operating at 10,000 pounds
    of steam per hour
    under steady state conditions will not violate the standard
    (R.92,
    96—7),
    although
    it has evidence that opacity levels
    will he unacceptable
    at less than 10,000 pounds of
    steam per
    hour
    (R.93).
    The Agency
    is uncertain about violations while
    operating
    at greater than a 10,000 pound
    level
    (R.93,
    119),
    although three out of the six tests conducted at a 15,000—
    pound
    level on July 17-19, 1979 showed results which were
    in
    compliance
    (R.60,
    98).
    There are no test results
    for a 12,500—
    pound
    level
    (R.99—100).
    There
    is no evidence of violation at
    levels
    less than 10,000 pounds
    (R.100—1),
    although there are
    boiler operating difficulties at 5—6,000 pounds
    (R.71).
    The
    Agency does not recommend a variance at
    less than 10,000 pounds
    per hour
    (R.93), but does not maintain that that
    is the only
    level
    at which Petitioner can achieve compliance
    (R.115—6).
    The nature and impact of the particulate emissions from
    Petitioner’s facility were described at
    length by a first few
    of
    the intervenors,
    speaking for the rest.
    Tens of photographs
    of motor vehicles, mobile homes,
    plants and human bodies were
    admitted into evidence at the hearing
    (Intervenors’ Exhibits
    1-8).
    The particulates were described as having
    a
    “base”
    (R.173—5), as being
    like “coal
    soot with grease in it”
    (R.145).
    On at least July 22,
    1979,
    it fell
    like “black snowflakes”
    (R.129,
    150-2).
    One could
    feel the particles
    “hit you in the
    face
    in
    sic
    the arms”
    (R.180).
    It imbeds
    in everything
    (R.145,
    164, 173—5).
    It
    is impossible to wipe
    off because it
    just smears
    (R.164,
    176).
    The particulates prevent the neighbors from enjoying the
    woods
    (R.150) and even from going outside
    (R.145,
    160—1).
    It
    makes plants more susceptible to attack from varmits and weakens
    plant growth
    (R.148-9).
    One can’t hang
    a wash outside to dry
    (R.159—60).
    It gets on bare feet from being on the grass
    (R.183),
    and
    it can sift through pants,
    boots,
    to socks
    and otherwise ruin shoes and clothing
    (R.145).
    It gets on
    car handles and trailer home railings
    (R.145)
    and on auto
    upholstery (R.160—1).
    It pits cars and boats
    (R.173—5).
    It
    got on the photographer’s camera lenses on July 22, 1979
    (R.145—6,
    189).
    The mobile homes must be cleaned constantly because
    the particles sift into them
    (R.149—50).
    Air conditioners,
    36—106

    —5—
    if possessed, must be
    run constantly.
    One neighbor awoke
    in
    the morning to find that the soot had sifted through the
    screen on her bedroom window and had covered her arms and bed;
    she realized she had been breathing
    it all night
    (R.160—1).
    Another neighbor without
    an air conditioner realizes that she
    breathes it all night
    in the summer months
    (R.184).
    When
    pillow cases
    are washed,
    dark,
    greasy spots remain (R.183).
    One neighbor has constant headaches since having moved into
    the court a year ago, although she cannot state that the soot
    causes them
    (R.150—65).
    It
    is now worse than
    it was
    a year ago, and “ten times”
    as bad as when Bake—O—Lite occupied the facility
    (R.150—2).
    Apparently Plant Manager Youmans agreed in a December 19,
    1978
    letter to the Intervenors not to emit matter unless
    the wind
    velocity was at least
    6 mph and the wind direction was not
    from the South.
    Intervenors believed such action would allev-
    iate the problem
    (R.157).
    It was after this letter, and after
    Union had ceased operations, that
    in the Summer of 1979 the
    problem increased.
    In the absence of evidence to the contrary,
    the Board finds that the presence of carbonaceous particulate
    matter poses
    a breathing hazard to those forced to inhale the
    material.
    The particles are similar to that particulate matter nor-
    mally emitted from coal-fired burners and are not similar
    visually to emissions from other stacks
    in the area
    (R.187—8).
    The particles can be seen falling
    as they come from Petition-
    er’s stack
    (R.130—1,
    159—60,
    166—78); they take 30—45 seconds
    to fall
    (R.180).
    There are
    no other stacks
    in the immediate
    area and open burning
    is not allowed
    (R.130—1).
    The Board denies Petitioner a variance
    from Rule 203(g)
    (1)(B).
    Petitioner has not proven that immediate compliance
    imposes an unreasonable hardship and there
    is
    no evidence that
    a cost of compliance of $300,000 is such sum as would
    force
    Petitioner ~o cease operations or prevent
    it from leasing its
    facility.
    This
    is especially true
    in light of the dangers
    which exist and which have existed at least since July of
    1979 to the health of people and of
    all living things.
    Not
    only must people and animals breath particles which are visible
    as snowflakes are visible, but plant life must endure the
    matter.
    Not only must people choose to breathe
    it
    or to stay
    indoors with an air conditioner running, but they cannot keep
    their clothing,
    furnishings,
    vehicles, homes and other person-
    al property clean without constant, daily attention.
    Such
    destruction of property and interference with human life and
    welfare
    is what pollution regulations are adopted to prevent
    and, where
    a balancing of rights
    is
    applicable,
    to curtail.
    Although there
    is evidence that to operate Petitioner’s
    boilers at 10,000 pounds of steam per hour,
    a derating from
    25,000 pounds,
    would not violate Rule 203(g)(1)(B), there is
    36—107

    —6—
    evidence that operating at
    less than that rate
    ——
    specifically,
    between
    5 and 6,000 pounds per hour
    -—
    would violate the rule.
    Petitioner states that since June of 1979 its normal operating
    level has been 5,000 pounds per hour except when the planish—
    ing press
    is on for three or four minutes;
    in the winter it
    expects
    a normal operating level of 10,000 pounds per hour.
    In at least the summer months,
    then,
    Petitioner will be viola-
    ting Rule 203(g)(1)(B).
    But it is in the summer months when
    enjoyment of neighboring property is most affected and when
    health effects are most demonstrable.
    The Board notes that Petibioner’s boilers have no air
    pollution control equipment installed and that these boilers
    have
    not been substantially modified in 30 years.
    Looking at
    the fact that since December of 1977 Petitioner knew that the
    Union permit would expire on February 28,
    1979, the denial
    of
    a variance can present no hardship.
    This Opinion constitutes the findings of
    fact and conclu-
    sions of law of the Board in this matter.
    ORDER
    It
    is the Order of the Pollution Control Board that
    American Hoechst Corporation’s petition for variance is
    hereby denied.
    Mr. Werner abstained.
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, heç~Q~
    certify t~eabove Opinion and Order were
    adopted on the
    /~
    day of
    l)C)M1~44.i..
    ,
    1979 by
    a
    vote of
    ~-tj___
    Christan L. Moffe
    Clerk
    Illinois Pollution
    ontrol Board
    36—108

    Back to top