ILLINOIS POLLUTION CONTROL BOARD
    January
    23,
    1975
    MISSOURI PORTLAND CEMENT COMPANY,
    Petitioner,
    vs.
    )
    PCB 74—407
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    Mr.
    Henss)
    On
    January
    9,
    1975
    the
    Board
    granted
    Petitioner
    an
    Interim
    Extension
    of
    Variance
    to
    and
    including
    January
    31, 1975 so that
    Petitioner could continue operations pending receipt of the
    Agency Recommendation and Board consideration of
    the merits of
    a requested three month variance extension.
    Variance from Rules 203(b)
    and 203(d) (3) of
    the Air Pollution
    Control Regulations was originally granted Missouri Portland on
    June
    6,
    1974 in PCB 73-480.
    This variance was granted for the
    purpose of allowing Petitioner sufficient time to complete in-
    stallation and testing of an electrostatic precipitator on kiln
    ~l
    at Petitioner’s Joppa, Illinois cement manufacturing plant.
    Missouri Portland now seeks a three month extension of
    variance in order to complete the electrostatic precipitator
    project.
    Bruce Kester, Petitioner’s Vice President-Environmental
    Systems, submitted an affidavit showing that installation of the
    electrostatic precipitator has been delayed beyond the direction
    and control of Missouri Portland by the following events:
    a)
    The
    precipitator parts were not delivered until
    late July,
    1974.
    To accelerate completion, Missouri
    Portland Cement Company caused assembly to begin
    at ground level in August of
    1974, because certain
    essential structural st~elwas not delivered on
    schedule.
    b) The structural steel was not received until
    August,
    1974.
    Erection of the structure began
    immediately and is still in progress.
    c) The necessary duct work components could not
    be delivered before late December,
    1974 and
    installation, therefore,
    could not be started
    before January of 1975.
    15 —325

    —2—
    d) The fan and drive component for the precipitator
    cannot be delivered before
    February.
    This
    installation
    will,
    therefore,
    be delayed until March of 1975 with
    completion scheduled for April,
    1975.
    e)
    The dust screws for the precipitator could not be
    delivered until January,
    1975, and installation cannot
    be completed before April
    1,
    1975.
    f)
    The electrical equipment and supplies could not be
    delivered until late October or November,
    1974 and in-
    stallation cannot be completed before March,
    1975.
    Petitioner has kept the Agency advised of progress and delays
    throughout the term of the original variance.
    Kester states that
    Petitioner has taken all steps possible to accelerate installation
    compatible with the late delivery schedules.
    If no further delays
    are experienced, Petitioner will shut down kiln #1 on March
    1,
    1975
    and complete installation of the electrostatic precipitator before
    restarting kiln
    1f1.
    During proceedings on the original variance,
    a number of
    Petitioner’s neighbors complained strongly about emissions from
    the plant.
    Agency interviews
    relative tothe instant case indicate
    that conditions have not changed as far as
    these citizens are con-
    cerned.
    However,
    the Agency believes that the impact upon these
    citizens because of Petitioner’s emissions will be reduced once
    the electrostatic precipitator is in operation.
    Although the Agency recognizes that delay in completion of
    the project is beyond the control of Petitioner,
    they believe that
    the time requested by Petitioner is excessive.
    It is
    the Agency’s
    opinion that Missouri Portland should not be given any time beyond
    the March
    1,
    1975 shutdown date particularly in light of the
    citizen’s comp1aints~
    If Petitioner is actually planning to shut the kiln down on
    March
    1,
    1975 in order to complete the tie-in with the electrostatic
    precipitator systems, there would be no reason to grant the variance
    for an additional month.
    Petitioner has not indicated that in
    plans to operate this kiln on an intermittent basis while the tie-in
    is taking place and we seriously doubt whether operations
    could
    continue during March even on an interim basis.
    The Agency recommends denial of variance or in the alternative
    that variance be granted only until March 1,
    1975 subject to certain
    conditions.

    —3.-
    The record clearly shows
    that Petitioner is going to shut
    the kiln down on March
    1,
    1975
    and
    the Board
    is not inclined
    to allow the variance to extend beyond that date.
    Compliance
    with the Regulation after March
    1,.
    1975 will not cause an
    arbitrary and unreasonable hardship.
    Variance will be granted
    to and including March
    1,
    1975 on which date Missouri Portland
    will he required to cease uncontrolled operations of its kiln #1.
    This Opinion constitutes the findings
    of fact and conclusions
    of
    law
    of
    the
    Illinois
    Pollution
    Control
    Board
    with regard to the
    appLication for a three month extension of variance~
    ORDER
    It is the Order of the Pollution Control Board that Missouri
    Portland Cement Company be granted variance from Rules 203(b)
    and
    203(d) (3)
    of
    the Air Pollution Control Regulations
    to
    and in-
    cluding March
    1,
    1975.
    This variance is subject to the following
    conditions:
    1) Conditions
    1 through
    5 of our Order in PCB 73-480 shall
    remain in effect through the term of this extended
    variance.
    2)
    Within 15 days of this Order, Petitioner shall submit
    its time table for completion
    of the electrostatic
    precipitator and stack test to the Environmental Pro-
    tection Agency.
    3)
    Petitioner shall not operate kiln #1 in an uncontrolled
    manner after the expiration date of this variance
    except as may be authorized by the Environmental Pro-
    tection Agency pursuant to Rule
    105 of the Air Pollution
    Control Regulations.
    4) Petitioner shall use a continuous monitor attached to the
    electrostatic precipitator as imposed by Part 1 of the
    Board Order in PCB 73-480 throughout the term of this
    extended variance.
    The new electrostatic precipitator
    shall use said monitor in the same fashion
    as. described
    in Exhibit B of the Board Order in PCB 73-480.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Opinion and Order was adopted
    this
    ~3R~
    day
    ~
    1975 by
    a vote of ~toQ.
    15—327

    Back to top