ILLINOIS
POLLUTION
CONTROL
BOARD
August
5, 1976
LEONARD C. TRIEM,
d/b/a
TRIEM
INDUSTRIAL BUIlDING OPERATIONS,
Petitioner,
v.
)
PCB 76—32
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Zeitlin):
The original Petition for Variance in this matter was filed
on February
5, 1976 by Leonard C. Triem, doing business as Triem
Industrial Building Operations
(hereinafter
“Triem”), seeking
relief
from the permit requirement for solid waste management sites
in
Rule 202(b) of Chapter
7: Solid Waste, of the Board’s Rules and
Regulations.
Pursuant to an Interim Order of the Board entered on
February 11,
1976, finding the original Petition inadequate, an
Amended Petition was filed on March 29,
1976, dropping the Variance
request with regard to Rule 202(b), and seeking instead relief from
the final cover requirement of Rule 305(c)
of Chapter
7.
An Agency
Recommendation was filed on June
14, 1976,
to which Triem responded
on July 20,
1976.
No hearing was held in this matter.
Triern has operated a sanitary landfill site in southern Cook
County,
Illinois since 1947.
Prior to Triem’s purchase of the site
it had been used for refuse dumping by approximately 20 surrounding
communities since 1929.
Petitioner describes the site
(as
of
1947)
as a clay hole 20
to 30 feet deep surrounded by a solid clay wall
with an additional clay berm 15 feet high added by Triem.
Now 95
full, operations on the site are confined to a trench 30 feet deep
and measuring 100 feet by 600 feet.
Petitioner states that there are some areas
of the site which
have been filled, but do not have sufficient final cover.
Petitioner
alleges that
it will take about 20 months to apply approximately
90,000 cubic yards of clay cover material,
thus bringing the site
up to final grade in conformity with all applicable cover require-
ments.
The final grade and cover should be such that surface water
will not infiltrate into the site, but will run off to adjacent
natural drainage without contacting the incorporated refuse.
The
final cover will be seeded to avert runoff problems.
23
—
231
—2—
Triem also expressed a complete willingness to comply with
all closure requirements, and an intent to assure that the site
will not cause environmental damage.
Triem states that it will
perform groundwater monitoring downgrade from the site, despite
the fact that the site’s clay lining should prevent leachate flows.
Triem will also install additional methane burners
to complement
the existing one.
Based on the above factors, Triem alleges that the grant of
the requested Variance would not result in any environmental harm.
The Agency’s Recommendation agrees and states that,
“because of
the composition of the underlying soil,
the possibility of signifi-
cant groundwater pollution from leachate is small.”
Rec. at
2.
Despite its conclusions as to lack of environmental harm,
however, the Agency’s Recommendation questions whether Triem has
shown sufficient hardship to warrant the grant of
a Variance.
The
Agency notes that Petitioner has another solid waste management
site
in Beecher, Illinois,
from which cover material is now being
hauled to the site in issue
here, and questions whether the Beecher
site could be used for all of Petitioner’s operations while the site
in issue here
is closed and all required cover added.
Triem’s
response to the Agency Recommendation adequately covers this issue
by noting that in the event of such a diversion,
all cover material
at the Beecher site would be required there by virtue of the increased
operations and consequent need for additional cover.
Nor do we feel that the hardship in this case
is self-imposed.
The Amended Petition shows that Petitioner’s site was operated
as
an open dump for many years before acquisition by Petitioner,
resulting
in
a great need for cover material.
Petitioner has shown that during
the last year approximately 183,000 cubic yards of cover material
has been applied to the site, indicating
a good faith attempt to
achieve compliance.
We feel that a Variance here will allow Petitioner
to continue
those efforts, and will provide the most expeditious means toward
final, complete and proper closure of the site.
Triem has consented
to the monitoring-well condition
in the Agency Recommendation, which
should provide further assurance that there will be no environmental
harm.
This Opinion constitutes the findings of fact and conclusions
of law of the Board
in
this matter.
23
—
232
—3—
ORDER
IT
IS THE ORDER OF THE POLLUTION CONTROL BOARD that Petitioner
Leonard
C.
Triem,
d/b/a
Triem
Industrial
Building
Operations,
be
granted a Variance for one year from the date of this Order from
Rule 305(c)
of Chapter
7: Solid Waste,
subject to the following
conditions:
1.
A water monitoring well built conforming to
Illinois Environmental Protection Agency specifications
shall be installed down—gradient of Petitioner’s solid
waste management site.
2.
Petitioner shall, within twenty—eight
(28) days
of the date of this Order,
execute and forward to the
Environmental Protection Agency, Control Program Coordinator,
2200 Churchill Road, Springfield, Illinois 62706,
a
Certificate of Acceptance in the following form:
I,
(We), ____________________________ having read
the Order of the Illinois Pollution Control Board in
case No. PCB 76-32, understand and accept said Order,
realizing that such acceptance renders all terms and
conditions thereto binding and enforceable.
SIGNED
TITLE
DATE
Mr.
James
Young
dissented.
I,
Christan
L.
Moffett,
Clerk
of
the
Illinois
Pollution
Control Board, h rèby certify the ab ye Opinion
and Order we e1
adopted on the
‘~
day of
_________,
1976,
by a vote of
(
Christan
L. Moffett/,çr~rk
Illinois Pollution ~e~rol
Board
23
—
233